This is a Public Safety specification document for the Route 54 Sanitary Sewer Extension Project, Contract No. WB-1, issued by the West Branch Regional Authority in Pennsylvania. The project involves construction of approximately 1,520 linear feet of gravity sanitary sewer, 11 manholes, 13 lateral connections, one duplex sewage pumping station, 404 linear feet of force main, one stream crossing, and all required surface restoration and appurtenances located within easements in Clinton Township, Lycoming County, Pennsylvania. Sealed bids for the project must be submitted online at http://pennbid.net/ by 1:00 PM local prevailing time on Monday, February 16, 2026. Prospective bidders are required to register as plan holders on PennBid to receive periodic updates on addenda and project information. Bid documents are available for download exclusively through PennBid, and neither the Owner nor Engineer will be responsible for documents obtained from other sources.
Each bid must be accompanied by a certified check, bank check, or bid bond equal to ten percent of the total bid amount as security for proper execution of the Agreement. The project is subject to Pennsylvania Department of Labor and Industry prevailing minimum wage rates and the Pennsylvania Steel Products Procurement Act of 1978, P.L. 6, as amended. The specification sections establish requirements for workers' personal conduct on site, schedule change approval by the Owner to ensure public safety compliance, maintenance of Material Safety Data Sheets for all products used on the project, and specific hot work safety requirements including fire tarps, fire watch assignments, and fire extinguisher availability.
View the file
Other files
Show 40 more
Latest 50 of 75 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01560
PUBLIC SAFETY DIVISION 1
West Branch Regional Authority 01560-1 January 2026 Route 54 Sanitary Sewer Extension Project Public Safety Contract No. WB-1
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Workers' Personal Conduct on the Job Site.
B. Schedule changes.
C. Compliance material for employees.
D. Hot work.
1.02 RELATED SECTIONS
A. Standard General Conditions of the Construction Contract and Supplementary Conditions.
B. Section 01000: Summary of Work and Special Requirements.
PART 2 - PRODUCTS
NOT APPLICABLE
PART 3 - EXECUTION
3.01 WORKERS' PERSONAL CONDUCT ON THE JOB SITE
A. Prior to the start of construction, the Owner and the Engineer will establish the rules to manage workers personal conduct on site, including but not limited to the following:
1. Tobacco policy.
2. Use of recreational audio equipment.
3. Dress code.
4. Use of offensive language.
3.02 SCHEDULE CHANGES
A. Any proposed changes to the construction schedule shall be reviewed by the Owner to assure that the public safety requirements of this section of the Specifications have not been reduced and that no hazard has been created by the proposed change in the schedule.
3.03 MATERIAL SAFETY DATA SHEETS (MSDS)
A. Contractor shall maintain on the job site, in a single file, a complete set of manufacturer's Material Safety Data Sheets for every product used on the project.
1. The SDS sheets shall be made available to the Owner, Engineer and Engineer's representatives upon request.
SECTION 01560
PUBLIC SAFETY DIVISION 1
West Branch Regional Authority 01560-2 January 2026 Route 54 Sanitary Sewer Extension Project Public Safety Contract No. WB-1
2. The Contractors shall provide, per MSDS, all necessary handling, worker protection, and instruction for all workers on site to prevent worker accidents and property damage.
3.04 HOT WORK (WELDING/BURNING) REQUIREMENTS
A. Contractor shall comply with the following minimum requirements for all hot work:
1. Cover adjacent areas with fire tarps.
2. Assign fire watch to the immediate area. Should fire danger exist on adjacent floor assign fire watch to that area also.
3. Assign to fire watch only personnel familiar with fire call box locations who shall have appropriate fire extinguishers.
4. Take all additional precautions to prevent fire from being caused by hot work operations.