This is a Project Meetings specification document for the Route 54 Sanitary Sewer Extension Project, Contract No. WB-1, administered by the West Branch Regional Authority in Clinton Township, Lycoming County, Pennsylvania. The project consists of approximately 1,520 linear feet of gravity sanitary sewer, 11 manholes, 13 lateral connections, one duplex sewage pumping station, 404 linear feet of force main, one stream crossing, and associated surface restoration and appurtenances. Sealed bids are due online at http://pennbid.net/ by 1:00 PM local prevailing time on Monday, February 16, 2026. The specification establishes requirements for engineer-administered preconstruction, progress, and special meetings throughout the project duration. The preconstruction meeting must be scheduled within ten days after Notice to Proceed and shall include the owner's representative, engineer and consultants, resident project representative, contractor's superintendent, major subcontractors, and major suppliers. Progress and special meetings are to be held as directed by the engineer and scheduled at the contractor's field office as applicable, with attendance by the engineer, relevant subcontractors and suppliers.

The specification details comprehensive meeting administration requirements including agenda preparation, written notice distribution four days in advance, minute recording and distribution in PDF format within seven days, and coverage of critical topics such as construction schedules, work sequencing, equipment deliveries, field decision procedures, safety protocols, and schedule revisions. Prospective bidders must register as plan holders on PennBid to receive periodic updates including addenda and other relevant information. Each bid must be accompanied by a certified or bank check or bid bond in the amount of ten percent of the total bid amount as security for proper execution of the agreement. The contractor is subject to prevailing minimum project wage rates as established by the Pennsylvania Department of Labor and Industry and must comply with the Pennsylvania Steel Products Procurement Act of 1978, P.L. 6, as amended.

View the file

Other files

File Type Posted
63-REV 1.19.26 16000 Elect Gen Prov.pdf PDF
17-00700 Gen Cond.pdf PDF
31-01600 Mat and Equp.pdf PDF
4-00250 Experience Equipmt and Finan Stmt.pdf PDF
52-05900 Miscelanous Metals.pdf PDF
47-02820 Topsoil Seeding.pdf PDF
14-00660 Form Change Order No 1.pdf PDF
1-1 CD COVER.pdf PDF
36-02000 Site Wrk.pdf PDF
42-02310 Horizontal DD.pdf PDF
7-00630 Public Verification Form.pdf PDF
26-01340 Shop Draw.pdf PDF
70-REV 1.19.26 16402 Underground Construction.pdf PDF
27-01380 Construct Photos.pdf PDF
50-03200 Concrete Reinforcement.pdf PDF
11-00610 Release of Lien.pdf PDF
32-01700 Cont Close.pdf PDF
24-01090 Ref Stand.pdf PDF
8-00350 Non-Discrimination.pdf PDF
66-REV 1.19.26 16130 Boxes.pdf PDF
56-15015 NonPress PVC.pdf PDF
30-01570 Traffic Reg.pdf PDF
38-02110 Demolition.pdf PDF
69-REV 1.19.26 16161 Grounding.pdf PDF
60-15100 Basic Req Plumb Wrk.pdf PDF
10-00600 Bonding Forms.pdf PDF
34-01720 Proj Rec Doc.pdf PDF
67-REV 1.19.26 16140 Wiring Devices.pdf PDF
64-REV 1.19.26 16111 Conduit.pdf PDF
44-02600 Paving Surface.pdf PDF
53-09900 Painting.pdf PDF
48-02900 Landscaping.pdf PDF
46-02710 Chain Link Fence.pdf PDF
62-15136 Basic Pip Mat and Meth.pdf PDF
5-00300 Bid Form.pdf PDF
61-15115 Supp and Anchors.pdf PDF
35-01740 Warranty and Bonds.pdf PDF
3-00200 Instructions to Bidders.pdf PDF
51-03300 Cast in Place.pdf PDF
37-02102 Clear Grub.pdf PDF
58-2 TOC.pdf PDF
21-01000 Summ of Work.pdf PDF
18-00800 Supp Cond.pdf PDF
45-02607 Manholes.pdf PDF
55-11930 Pump Equp.pdf PDF
71-REV 1.19.26 16511 Led Exterior Lighting.pdf PDF
19-Wage Rates.pdf PDF
68-REV 1.19.26 16160 Panelboards.pdf PDF
41-02300 HDPE Pipe.pdf PDF
15-00670 Payment Application.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01200

PROJECT MEETINGS DIVISION 1

West Branch Regional Authority 01200-1 January 2026 Route 54 Sanitary Sewer Extension Project Project Meetings Contract No. WB-1

1.01 DESCRIPTION

A. Engineer or representative(s) thereof, shall schedule and administer preconstruction meetings, progress meetings and specially called meetings throughout the progress of the work.

1. Prepare agenda for meetings.

2. Distribute written notice of each meeting four (4) days in advance of meeting date.

3. Make physical arrangements for meetings.

4. Preside at meetings.

5. Record the minutes; include all significant proceedings and decisions.

6. Distribute minutes in pdf file format within seven (7) days after each meeting.

a. To all participants in the meeting.

b. To all parties affected by decisions made at the meeting.

B. Representatives of Contractors, Subcontractors, and Suppliers attending the meetings shall be qualified and authorized to act on behalf of the entity each represents.

C. Engineer may attend any and all meetings held in regard to the project to ascertain that work is expedited consistent with Contract Documents and the construction schedules.

D. Related requirements in other Parts of the Contract Documents:

1. Instructions to Bidders: Section 00200.

E. Related requirements specified in other Sections of these General Specifications:

1. Summary of Work and Special Requirements: Section 01000.

2. Shop Drawings, Product Data, and Samples: Section 01340.

3. Project Record Documents: Section 01720.

1.02 PRE-CONSTRUCTION MEETING

A. Will be scheduled within ten (10) days after date of Notice to Proceed.

B. Location: Project location or as designated by the Engineer/Owner.

C. Attendance:

1. Owner's Representative.

2. Engineer and his professional consultants.

3. Resident Project Representative.

4. Contractor's Superintendent.

5. Major Subcontractors.

6. Major suppliers.

7. Others as appropriate.

West Branch Regional Authority 01200-2 January 2026

D. Suggested Agenda:

1. Distribution and discussion of:

a. List of major Subcontractors and suppliers.

b. Projected construction schedules.

2. Critical Work sequencing.

3. Major equipment deliveries and priorities.

4. Project Coordination.

a. Designation of responsible personnel.

5. Procedures and processing of:

a. Field decisions.

b. Proposal requests.

c. Submittals.

d. Change Orders.

e. Applications for payment.

6. Adequacy of distribution of Contract Documents.

7. Procedures for maintaining Record Documents.

8. Use of premises:

a. Office, Work, and storage areas.

b. Owner's requirements.

9. Construction facilities, controls and construction aids.

10. Temporary utilities.

11. Safety and first-aid procedures.

12. Security procedures.

13. Housekeeping procedures.

14. Other pertinent business.

1.03 PROGRESS MEETINGS/SPECIAL MEETINGS

A. Meetings shall be scheduled, as directed by Engineer.

B. Hold called meetings as required by progress of the work.

C. Location of the meetings: The Project field office of the Contractor (if applicable).

D. Attendance:

1. Engineer, and his professional consultants as needed.

2. Subcontractors as appropriate to the Agenda.

West Branch Regional Authority 01200-3 January 2026

3. Suppliers as appropriate to the Agenda.

4. Others.

E. Suggested Agenda:

1. Review and approve minutes of previous meeting.

2. Review of work progress since previous meeting.

3. Field observations, problems, conflicts.

4. Problems which impede Construction Schedule.

5. Review of off-site fabrication, delivery schedules.

6. Corrective measures and procedures to regain projected schedule.

7. Revisions to Construction Schedule.

8. Plan progress, schedule, during succeeding work period.

9. Coordination of schedules.

10. Review submittal schedules; expedite as required.

11. Maintenance of quality standards.

12. Review proposed changes for:

a. Effect on Construction Schedule and on completion date.

b. Effect on other contracts of the Project.

13. Other pertinent business.