2.11 - Drawings 11 of 17 - 08-TN-011 to 00-TJ-028.pdf

PDF 21 MB Posted

Attached to
NOLA EHRM Infrastructure Upgrades Construction - New Orleans, LA 629-22-700
Solicitation number
36C77623B0038
Issued by

About this file

This document provides details on a federal contract opportunity for infrastructure upgrades at a Veterans Affairs facility in New Orleans, Louisiana. The solicitation number is 36C77623B0038 and is being issued by the Department of Veterans Affairs Technology Acquisition Center Austin. The opportunity is for construction services related to EHRM infrastructure upgrades at the New Orleans location. Products and services required include general construction work to upgrade existing infrastructure systems. The estimated award date is not provided but the response deadline for this solicitation is [date]. Relevant set-aside provisions or considerations for small businesses are not outlined.

View the file

Other files

File Type Posted
36C77623B0038 0007.pdf PDF
Tech Questions Tracker - NOLA - 8-25-23.pdf PDF
Brand Name JA - NOLA EHRM.pdf PDF
Tech Questions Tracker - NOLA - 8-23-23.pdf PDF
36C77623B0038 0006.pdf PDF
36C77623B0038 0005.pdf PDF
Tech Questions Tracker - NOLA - 8-9-23.pdf PDF
36C77623B0038 0004.pdf PDF
Specs and Drawings - NOLA EHRM - Addendum No 2.pdf PDF
36C77623B0038 0003.pdf PDF
Specs and Drawings - NOLA EHRM - Addendum No 1.pdf PDF
36C77623B0038 0002.pdf PDF
NOLA EHRM Site Visit Sign-In Sheet 19 July 23.pdf PDF
36C77623B0038 0001.pdf PDF
Site Visit Instructions.pdf PDF
2.12 - Drawings 12 of 17 - 00-EG-001 to 02-ED-051.pdf PDF
2.2 - Drawings 02 of 17 - 000-AJ-601 to 000-AJ-606.pdf PDF
2.4 - Drawings 04 of 17 - 01-AE-011 to 02-AE-052.pdf PDF
2.17 - Drawings 17 of 17 - 04-FP-100 to 11-FP-110.pdf PDF
1 - Specifications.pdf PDF
2.10 - Drawings 10 of 17 - 04-TD-011 to 08-TD-051.pdf PDF
2.13 - Drawings 13 of 17 - 02-EP-011 to 03-EP-071.pdf PDF
2.5 - Drawings 05 of 17 - 02-AC-011 to 03-AE-071.pdf PDF
2.16 - Drawings 16 of 17 - 00-FP-000 to 03-FP-111.pdf PDF
2.9 - Drawings 09 of 17 - 02-TN-011 to 03-TN-071.pdf PDF
IFB 36C77623B0038 - 6-29-23.pdf PDF
6 - Contractor Safety and Environmental Record.docx DOCX document
4 - DBA Wage Rates - Orleans County - 06-16-23.pdf PDF
2.1 - Drawings 01 of 17 - GI001 to GI003.pdf PDF
2.6 - Drawings 06 of 17 - 03-AC-011 to 11-AE-011.pdf PDF
2.8 - Drawings 08 of 17 - 00-TG-001 to 02-TD-052.pdf PDF
2.14 - Drawings 14 of 17 - 04-ED-011 to 10-EP-011.pdf PDF
2.15 - Drawings 15 of 17 - 01-EJ-001 to 00-EJ-026.pdf PDF
2.7 - Drawings 07 of 17 - 00-MK-001 to 10-MJ-011.pdf PDF
3 - HVAC Load Calculations.pdf PDF
5 - Limitations on Subcontracting - Construction.docx DOCX document
2.3 - Drawings 03 of 17 - 00-CG-001 to CJ-A102.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

UP

UPDN

B B

B

BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB

B B

B B

B B

B B

B B

B B

B B

B B

B

B

B

B B

B B

B B

B

B B

B

BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB

B B

B B

B B

B B

B B

B B

B B

B B

B

B B

B B

B B

B

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

OFF

SUP

1P102L

VESTIBULE

1P113

SHELL

1P113A

OFF CH

1P103E

OFF DEP

1P103A

BID OPEN

1P103B

STOR

1P106

CONF

1P105

CH LOG

1P107C

TECH

1P107A

OFF

1P102Q

OFF

1P102P

OFF

1P102N

INV

1P102M

INV

1P102K

INV

1P102J

INV

1P102H

INV

1P102G

INV

1P102F

OFF

1P101F

SUP

1P107F

ASST CH

1P107B

OFF

1P101G

OFF

1P101H

OFF

1P101J

STOR

1P101D

OFF

1P101E

INV

1P101B

INV

1P101A

RD PI

1P101N

RD PI

1P101M

CONF

1P108

TR

1P110

INV

1P102D

INV

1P102C

GROUP

1P112B

CLASS

1P112C

GROUP

1P112D

TLT

1P109

TLT

1P111

RECY

1P115A

LAB STOR

1P115B

SEC

1P100B

ELEC

1P115C

BIO MED

1P114 EMS

1P116

DOCK

1P115

REC

1P100C

COPY

1P101C

RECP + W

1P101

TECH

1P107D

CPY

1P102E

MULTI PURP

1P112

WAITING

1P100D

GROUP

1P112A

REC

1P102PSA, RN

1P102R

DATA WORK

1P101L

HK

1P104

ELEC

1P116A

RAD WST

1P115E

STOR

1P115D

COPY

1P107E

SEC WAIT

1P107

SEC

1P103

VESTIBULE

1P100A

CLER TECH

1P103D

HS CUBES

1P101K

CORR

1P-C02

CORR

1P-C06

CORR

1P-C07

CORR

1P-C01

CORR

1P-C05

CORR

1P-C03

CORR

1P-C04

ALCOVE

1F-CO4A

STAIR

STP-2

STAIR

STP-1

SHAFT UTILITY ACCESS

1P115H

ELEV

PS-02

ELEV

PS-01

SHOWER

1P109A

SHOWER

1P111A

ELEC

1P1025

BIO HAZ WST

1P115F

STORAGE

1P112G

LOBBY

1P100

LVSR

1P110A

CORR

1P-C11

SHELL

1P113A

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

08-TN-011

(E)CABLE TRAY

SEE SITE PLAN ON

SHEET 00-TS-005

FOR CONTINUATION

(4)24-STR SM (OS2)

(3)24-STR SM (OS2)

(3)24-STR SM (OS2)

4"C. UP TO 2ND FLOOR

(1)24-STR SM (OS2)(4)24-STR SM (OS2)

4"C.

(4)24-STR SM (OS2)

(E)1P140-RK1

(E)1P140-RK2

(E)1P140-RK3

(E)1P140-RK4

TR

1P110

1P140

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

08-TN-011

OVERALL FIRST FLOOR TELECOMM PLAN -

BLDG. 08

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 08 TELECOMM OVERALL PLAN - LEVEL 1

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13. FOR ENLARGED PLAN CALLOUTS WE ANNOTATED CURRENT ROOM NUMBER. FLOOR PLAN

ROOM NUMBERS SHOW LEGACY ROOM NUMBERS.

1/4" = 1'-0"2

ENLARGED TELECOMM PLAN - TR 1P140

PLAN NOTES

1 EXISTING TR RACKS TO REMAIN. PROVIDE FIBER ENCLOSURES, UPS, AND PDU'S. SEE RACK

EQUIPMENT SCHEDULE ON THIS SHEET FOR ADDITONAL INFORMATION.

2 PROVIDE HILTI FIRESTOP SPEED SLEEVE.

3 PROVIDE RACK BONDING BUSBAR(RBB) IN EXISTING 2-POST RACK. PROVIDE BONDING AS

REQUIRED. SEE BONDING DETAILS ON SHEET TJ-007 FOR ADDITIONAL INFORMATION.

4 PROVIDE VERTICAL CABLE SUPPORTS FROM CONDUIT/SLEEVE TO COMMUNICATION RACK.

RACK EQUIPMENT SCHEDULE - EXISTING TR WITH/ (4)EXISTING RACKS

EQUIPMENT QTY TYPE PART#

UPS 4 5 KVA EATON #ZC0517708100000 OR APPROVED

EQUAL, WITH HEAVY DUTY SHELF EATON

#ZC0517708100000

FIBER ENCLOSURE NOTE 1 NOTE 1 NOTE 1

PDU 8 VERTICAL PDU APC #8861, WITH MOUNTING BRACKETS

#KIT-MB-41 OR APPROVED EQUAL

ZONE PDU 1 60 AMP HORIZONTAL

ZONE PDU

#ZPDS-208V60A-HW-6L21-20R OR

APPROVED EQUAL

NOTES: SEE RACK ELEVATIONS FOR EXACT LOCATIONS OF EACH PIECE OF EQUIPMENT.

1. SEE FIBER ONE LINE DIAGRAMS FOR ADDITIONAL INFORMATION.

Revisions: Date:

UP

DN

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

HS OFFICE

2P104C

HS OFFICE

2P104B

COPY/ STG

2P104A

HS WKSTNS

2P105

HS WKSTNS

2P106

HS WKSTNS

2P104

STAIR

STP-2

STAIR

STP-1

ELEV

PS-02

ELEV

PS-01

LVSR

2P100A

ELEC

2P169

ELEC

2P137

TC

2P139

MIC D

2P139A

TC

2P141

MIC D

2P135A

FRZ UL

2P143

REFRIG/FRZ

2P149A

ELEC MIC

2P150

TC

2P145

TC

2P147

FZ-20

2P149B

TC

2P135B

MIC D

2P135BB

PI

2P134

PI

2P132

PI

2P130

PI

2P128

PI

2P126

PI

2P124

PI

2P122

PI CONF

2P120

TC

2P151

CELL

S

2P153D

TC

2P153C

HPLC

2P153B

MIC D

2P153A

MIC D

2P157A

TC

2P157

TC

2P155

IM HIST

2P159

HK

2P161

GLASS WASH

2P163

CELL BANK

2P165

LER

2P135

LER

2P149

LER

2P153

TL

2P116

TL

2P115

LAB 1

2P138

LAB 4 & 5

2P152

LAB 6

2P162

LAB 7 & 8

2P168

CYL

2P167

LAB 2

2P142

LAB 3

2P148

CORR

2P-C04.1

CORR

2P-C02

CORR

2P-C01A

CORR

2P-C01

CORR

2P-C03A

EQUIP RM

2P163AELEC MIC

EQUIP

2P150A

LAB 7 & 8 HOODS

2P168B

LAB 7 & 8 ENTRY

2P168A LAB 7 & 8 HOODS

2P168C

LAB 6 HODDS

2P162B

LAB 1 ENTRY

2P138A

LAB 1 FUME HOOD

2P138B

LAB 2 ENTRY

2P142A

LAB 2 HOODS

2P142B

LAB 3 ENTRY

2P148A

LAB 3 HOODS

2P148B

LAB 4 & 5 HOODS

2P152B

LAB 4 & 5 ENTRY

2P152A

LAB 4 & 5 HOODS

2P152C

LAB 4 & 5 HOODS

2P152D

LAB 4 & 5 HOODS

2P152E

LAB 6 ENTRY

2P162A

STAIR

STAIR

ELEV

ELEV

CORR

2P-C04.2

WORK/COLAB

2P100B

AISLE

2P-C01B

CORR

2P-C03B

TR

2P100C

COPY/ STG

HS OFFICE

HS OFFICE

HS WKSTNS

HS WKSTNS

HS WKSTNS

PI

HS

WORK/ COLAB

PI EQ

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

08-TN-021

(E)CABLE TRAY

(E)2P120A-RK1

(E)2P120A-RK2

(E)2P120A-RK3

(E)2P120A-RK4

TR

2P100C

2P120A

(2)24-STR SM (OS2)

4"C. UP TO 3RD FLOOR

(1)24-STR SM (OS2)

3 4

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

08-TN-021

OVERALL SECOND FLOOR TELECOMM

PLAN - BLDG. 08

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 08 TELECOMM OVERALL PLAN - LEVEL 2

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13. FOR ENLARGED PLAN CALLOUTS WE ANNOTATED CURRENT ROOM NUMBER. FLOOR PLAN

ROOM NUMBERS SHOW LEGACY ROOM NUMBERS.

1/4" = 1'-0"2

ENLARGED TELECOMM PLAN - TR 2P120A

PLAN NOTES

1 EXISTING TR RACKS TO REMAIN. PROVIDE FIBER ENCLOSURES, UPS, AND PDU'S. SEE RACK

EQUIPMENT SCHEDULE ON THIS SHEET FOR ADDITONAL INFORMATION.

2 PROVIDE RACK BONDING BUSBAR(RBB) IN EXISTING 2-POST RACK. PROVIDE BONDING AS

REQUIRED. SEE BONDING DETAILS ON SHEET TJ-007 FOR ADDITIONAL INFORMATION.

3 PROVIDE HILTI FIRESTOP SPEED SLEEVE.

4 PROVIDE VERTICAL CABLE SUPPORTS FROM CONDUIT/SLEEVE TO COMMUNICATION RACK.

RACK EQUIPMENT SCHEDULE - EXISTING TR WITH/ (4)EXISTING RACKS

EQUIPMENT QTY TYPE PART#

UPS 4 5 KVA EATON #ZC0517708100000 OR APPROVED

EQUAL, WITH HEAVY DUTY SHELF EATON

#ZC0517708100000

FIBER ENCLOSURE NOTE 1 NOTE 1 NOTE 1

PDU 8 VERTICAL PDU APC #8861, WITH MOUNTING BRACKETS

#KIT-MB-41 OR APPROVED EQUAL

ZONE PDU 1 60 AMP HORIZONTAL

ZONE PDU

#ZPDS-208V60A-HW-6L21-20R OR

APPROVED EQUAL

NOTES: SEE RACK ELEVATIONS FOR EXACT LOCATIONS OF EACH PIECE OF EQUIPMENT.

DN UP

UP

UP

J

J

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

HS OFFICE

3P202B

HS CONF

3P101A

COPY

3P202A

HS WKSTNS

3P202

HS OFFICE

3P202C

HS WKSTNS

3P104

HS WRKSTNS

3P101

COLLABORATION

3P202D

STAIR

STP-2

STAIR

STP-1

ELEV

PS-02

ELEV

PS-01

STAIR

STAIR

ELEV

ELEV

TC

3P139

MIC D

3P139A

ELEC

3P137

ELEC

3P173

LVSR

3P100A

PI

3P134

PI

3P132

PI

3P130

PI

3P128

PI

3P126

PI

3P124

PI

3P122

PI CONF

3P120

OFF

3P107

TL

3P105

TL

3P103

WORK/ COLAB

3P100

LER

3P135

LER

3P149

LER

3P155

TC

3P141

FRZ UL

3P143

MIC D

3P135A

COLD

3P149A

TC

3P145

TC

3P147

TC

3P153

MIC D

3P153AMIC D

3P149B

TC

3P135B

MIC D

3P135BB

TC

3P155C

TC

3P155B

EQ ROOM

3P155A

TC

3P157

CON FOC

3P159

IM HIST

3P161

HK

3P163

RAD LAB

3P165

TC

3P167

FLAM STOR

3P171

ACID STOR

3P169

LAB 11

3P148

LAB 14

3P162

LAB 10

3P142LAB 9

3P138

LAB 15

3P168

SERV

3P102

LABS 12 & 13

3P152

CORR

3P-C20

CORR

3P-C04

CORR

3P-C04A

CORR

3P-C01

CORR

3P-C03A

CORR

3P-C02

LAB 9 ENTRY

3P138A

LAB 9 HOODS

3P138B

LAB 10 ENTRY

3P142A LAB 10 HOODS

3P142B

LAB 11 ENTRY

3P148A LAB 11 HOODS

3P148B

LABS 12 & 13 HOODS

3P152B

LABS 12 & 13 ENTRY

3P152A

LABS 12 & 13 HOODS

3P152C

LABS 12 & 13 HOODS

3P152D

LABS 12 & 13 HOODS

3P152E

LAB 14 ENTRY

3P162A LAB 14 HOODS

3P162B

LAB 15 HOODS

3P168B

LAB 15 ENTRY

3P168A LAB 15 HOODS

3P168C

STAIR

STAIR

ELEV

ELEV

CORR

CP-CO3B

TR

3P100C

COLLABORATION

3P202D

HS WKSTNS

3P104

HS WKSTNS

COPY

HS OFFICE

HS OFFICE

HS WKSTNS

HS CONF

MASS SP

HS

HS

LOUNGE

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

08-TN-031

(E)CABLE TRAY

(1)24-STR SM (OS2)

4"C. UP TO 4TH FLOOR

(E)3P102A-RK1

(E)3P102A-RK2

(E)3P102A-RK3

(E)3P102A-RK4

TR

3P100C

3P102A

(E)SBB

(1)24-STR SM (OS2)

(1)24-STR SM (OS2)

4"C. UP TO 4TH FLOOR

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

08-TN-031

OVERALL THIRD FLOOR TELECOMM PLAN -

BLDG. 08

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 08 TELECOMM OVERALL PLAN - LEVEL 3

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13. FOR ENLARGED PLAN CALLOUTS WE ANNOTATED CURRENT ROOM NUMBER. FLOOR PLAN

ROOM NUMBERS SHOW LEGACY ROOM NUMBERS.

1/4" = 1'-0"2

ENLARGED TELECOMM PLAN - TR 3P102A

RACK EQUIPMENT SCHEDULE - EXISTING TR WITH/ (4)EXISTING RACKS

EQUIPMENT QTY TYPE PART#

UPS 4 5 KVA EATON #ZC0517708100000 OR APPROVED

EQUAL, WITH HEAVY DUTY SHELF EATON

#ZC0517708100000

FIBER ENCLOSURE NOTE 1 NOTE 1 NOTE 1

PDU 8 VERTICAL PDU APC #8861, WITH MOUNTING BRACKETS

#KIT-MB-41 OR APPROVED EQUAL

ZONE PDU 1 60 AMP HORIZONTAL

ZONE PDU

#ZPDS-208V60A-HW-6L21-20R OR

APPROVED EQUAL

NOTES: SEE RACK ELEVATIONS FOR EXACT LOCATIONS OF EACH PIECE OF EQUIPMENT.

1. SEE FIBER ONE LINE DIAGRAMS FOR ADDITIONAL INFORMATION.

PLAN NOTES

1 EXISTING TR RACKS TO REMAIN. PROVIDE FIBER ENCLOSURES, UPS, AND PDU'S. SEE RACK

EQUIPMENT SCHEDULE ON THIS SHEET FOR ADDITONAL INFORMATION.

2 PROVIDE RACK BONDING BUSBAR(RBB) IN EXISTING 2-POST RACK. PROVIDE BONDING AS

REQUIRED. SEE BONDING DETAILS ON SHEET TJ-007 FOR ADDITIONAL INFORMATION.

3 PROVIDE HILTI FIRESTOP SPEED SLEEVE.

4 PROVIDE VERTICAL CABLE SUPPORTS FROM CONDUIT/SLEEVE TO COMMUNICATION RACK.

DNUP

UP

DN

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

STAIR

STP-2

STAIR

STP-1

ELEV

PS-02

ELEV

PS-01

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

HS

4P102A

HS

4P105A

HS

4P101A

HS

4P103A

HOLD

4P327

TREAT

4P329

HOLD RABBIT

4P331

TREAT

4P333

HOLD RABBIT

4P335

ELEC

4P115B

HK

4P113

HOLD

4P302A

HOLD

4P323

TREAT

4P321

HOLD

4P317

HOLD

4P324

TREAT

4P322

ISO HOLDING

4P320B

ISO HOLDING

ANTE-ROOM

4P320A

HOLD

4P316

OR SUP

4P318D

OR

4P318C

GOWN PREP

4P318B

FEED & BED STOR

4P314B

CLEAN CAGE

4P314A

CLEAN CAGE WASH

4P314

SOIL CAGE WASH

4P304

WOMEN LOCKER

4P300F

VET OFF

4P300B

LOUNGE

4P300

OFF

4P300A

MEN LOCKER

4P300C

HAZ WASTE STOR

4P303

FRZ/STOR

4P305

TR

4P103

WATER SYS

4P311

CARC HOLD

4P309

NECRO

4P307

EQUIP

4P305AUNASSIGNED

4P315

ENVIRO PROC

4P313A

ENV HOLD

4P313

ELEC

4P301

TL

4P104

TL

4P102

REC + W

4P101

RECPT

4P100

X RAY

4P318A

UNASSIGNED

4P100A

HK

4P319

QUAR HOLD

4P302B

DIAG HOLD

4P302C

CORR

4P-C03

CORR

4P-C03A

CORR

4P-C03B

CORR

4P-C01

CORR

4P-C02

STAIR

STAIR

ELEV

ELEV

T/S

4P300E

T/S

4P300D

VESTIBULE

4P-C01A

VESTIBULE

4P-C03C

UNAS

4P106A

VESTIBULE

4P115A

CORR

4P-CO1B

LOBBY

4P100B

LVSR

4P103B

ACOS CONF

4P204

FILE/COPY

4P203

OFFICE

4P202E

RCO

AO

CORR

OFFICE

ACOS OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

STAIR

STAIR

ELEV

ELEV

08-TN-041

(E)CABLE TRAY

(E)4P103-RK1

(E)4P103-RK2

(E)4P103-RK3

(E)4P103-RK4

TR

4P103

4P103

(1)24-STR SM (OS2)

4"C. FROM 3RD FLOOR

3 4

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

08-TN-041

OVERALL FOURTH FLOOR TELECOMM

PLAN - BLDG. 08

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 08 TELECOMM OVERALL PLAN - LEVEL 4

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13. FOR ENLARGED PLAN CALLOUTS WE ANNOTATED CURRENT ROOM NUMBER. FLOOR PLAN

ROOM NUMBERS SHOW LEGACY ROOM NUMBERS.

1/4" = 1'-0"2

ENLARGED TELECOMM PLAN - TR 4P103

RACK EQUIPMENT SCHEDULE - EXISTING TR WITH/ (4)EXISTING RACKS

EQUIPMENT QTY TYPE PART#

UPS 4 5 KVA EATON #ZC0517708100000 OR APPROVED

EQUAL, WITH HEAVY DUTY SHELF EATON

#ZC0517708100000

FIBER ENCLOSURE NOTE 1 NOTE 1 NOTE 1

PDU 8 VERTICAL PDU APC #8861, WITH MOUNTING BRACKETS

#KIT-MB-41 OR APPROVED EQUAL

ZONE PDU 1 60 AMP HORIZONTAL

ZONE PDU

#ZPDS-208V60A-HW-6L21-20R OR

APPROVED EQUAL

NOTES: SEE RACK ELEVATIONS FOR EXACT LOCATIONS OF EACH PIECE OF EQUIPMENT.

1. SEE FIBER ONE LINE DIAGRAMS FOR ADDITIONAL INFORMATION.

PLAN NOTES

1 EXISTING TR RACKS TO REMAIN. PROVIDE FIBER ENCLOSURES, UPS, AND PDU'S. SEE RACK

EQUIPMENT SCHEDULE ON THIS SHEET FOR ADDITONAL INFORMATION.

2 PROVIDE RACK BONDING BUSBAR(RBB) IN EXISTING 2-POST RACK. PROVIDE BONDING AS

REQUIRED. SEE BONDING DETAILS ON SHEET TJ-007 FOR ADDITIONAL INFORMATION.

3 PROVIDE HILTI FIRESTOP SPEED SLEEVE.

4 PROVIDE VERTICAL CABLE SUPPORTS FROM CONDUIT/SLEEVE TO COMMUNICATION RACK.

DN UP

DN

DN

DN

DN

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

MECHANICAL

5P-CO47

UNOCCUPIED

5P-CO48

TOWER ACCESS

5P-CO49

UNOCCUPIED

5P-CO46

STAIR

STP-2

STAIR

STP-1

ELEV

PS-02

ELEV

PS-01

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

STAIR

STAIR

ELEV

ELEV

EMER ELEC

5P101

ELEC SW GEAR

5P100

MECH PENT

5P102

STAIR

STAIR

ELEV

ELEV

VEST

5P200

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

08-TN-051

OVERALL FIFTH FLOOR TELECOMM PLAN -

BLDG. 08

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 08 TELECOMM OVERALL PLAN - LEVEL 5

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13. FOR ENLARGED PLAN CALLOUTS WE ANNOTATED CURRENT ROOM NUMBER. FLOOR PLAN

ROOM NUMBERS SHOW LEGACY ROOM NUMBERS.

THIS DRAWING WAS PRODUCED FROM ORIGINAL

AS-BUILT DRAWINGS AND FIELD OBSERVATIONS, AND

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

UP

DN

UP

DN

UP

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

UNOCCUPIED

BQ110

STAIR

UNASSIGNED

STAIRS

STAIRS

STAIRS

STAIRS

ELECT

EMERGENCY ELECT.

SUPPLIES

BQ104

EXIT PASSAGEWAY

BQ105

TEMP ELEC DSCNT

BQ114

ELEC

BQ107

ELEC

BQ108

SHAFT

SHQ02

ELEC

BQ100

EMER ELEC

BQ101

UNOCCUPIED

BQ106

CORR

BQ-C01

LOBBY

BQ103

STAIR

STAIR

STAIR

MALE SHWR

BQ112

FEMALE SHWR

BQ111

ELEV

ELEV

QP-4

ELEV

ELEV

HK

BQ138

FIRE PUMP

BQ115

SHAFT

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-0B1

OVERALL BASEMENT TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - BASEMENT

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

UP

UP

DN

UP

UP

STAIR

STAIR

STQ-2

ELEC./AV

1Q126

CONF

1Q132

CONF

1Q130

CONF

1Q135

PANTRY

1Q129

CONF

1Q137

AUDITORIUM

1Q136

MALE

1Q118

FEMALE

1Q113

SUPPLIES

1Q112

PREFUNCTION SPACE

1Q134

MANAGER

1Q105

SUPERVISOR

1Q108A

LOAN OFFICER

1Q108B

VAULT

1Q109

ATM

1Q127

LOBBY

1Q108

OFFICE

1Q115

CLASSRM

1Q116

RECEPT

1Q114A

SEATING

1Q114B

COMPUTERS

1Q114F

AV

1Q114E

CLASSROOM

1Q104

SIM LAB

1Q100

CLASSROOM

1Q102

SERVICE WINDOW

1Q110

PERIODICALS

1Q114C

ADMIN.

1Q114D

SUPPLIES

1Q119

TR

1Q140

ELEC

1Q111

EMER ELEC

1Q111A

TELECOM

DEMARCATION

1Q103

IT CLASSRM

1Q121

IT CLASSRM

1Q122

ASST./ WAITING

1Q123A

ACOS

1Q123B

IT SUPPLIES

1Q120

CAFE

1Q125

STAIR

STQ-4

STAIR

STQ-3

PREFUNCTION SPACE

1Q138

WRKSTN

1Q107

HK

1Q131

CHILLED WATER PUMP

1Q117

CHAIRS

1Q144

MALE

1Q133

FEMALE

1Q128

ELEC

16CORR

1Q-C01

LOBBY

1Q139

ELEV

QP-1 ELEV

QP-2

SHAFT

SHQ01

SHAFT

SHQ03

LIBRARY

1Q114

SHAFT

SHQ04

SHAFT

SHQ09

CORR

1Q-C06

CORR

1Q-C04

CORR

1Q-C03

ELEV

SUPPLIES

1Q106

CAFE WRKRM

1Q141

LVSR

1Q101

ELEV LOBBY

1Q139A

PREFUNCTION SPACE

1Q146

PREFUNCTION SPACE

1Q145

TELEPHONE EQUIP

1Q124

SHAFT

SHQ10

SHAFT

ELEC

SHQ12

09-TD-011

09-TD-011

(E)CABLE TRAY

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

TR

1Q140

(E)SBB

(E)1Q129A-RK1

(E)1Q129A-RK2

(E)1Q129A-RK3

(E)1Q129A-RK4

(E)1Q122-RK1

(E)SBB

(E)1Q122-RK2

(E)1Q122-RK3

TELEPHONE EQUIP

1Q124

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-011

OVERALL FIRST FLOOR TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - LEVEL 1

DEMOLITION GENERAL NOTES

1 VISIT AND EXAMINE THE SITE PRIOR TO INITIATION OF WORK TO ASCERTAIN THE

CONDITIONS AND LIMITS OF DEMOLITION AND CONSTRUCTION.

2 DISPOSE OF REMOVED EQUIPMENT UNLESS DIRECTED TO DO SO OTHERWISE BY OWNER.

3 COORDINATE EXTENT AND SCOPE OF DEMOLITION IN ALL SPACES WITH ARCHITECTURAL.

4 CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

5 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

6 CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD" OR ANY PORTS

WITHOUT AN ADDRESS IN EXISTING PATCH PANELS AND VERIFY AN OUTLET. FOR PRICING

PURPOSES ASSUME A MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

7 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

PLAN NOTES

1 EXISTING COMMUNICATIONS 2-POST RACK TO REMAIN.

1/4" = 1'-0"2

ENLARGED TELECOMM DEMO PLAN - TR 1Q129A

1/4" = 1'-0"3

ENLARGED TELECOMM DEMO PLAN - TR 1Q122

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

DN

UP UPDN

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

STAIR

STQ-1

MALE

2Q113

STAIR

WFD INSTR (6)

2Q138

VIDEO EDT

2Q127

CONFERENCE

2Q122

CONF

2Q118

SECTRY/RECEP

2Q117

ILLSTN PREP

2Q103

DEPUTY PAO

2Q104

PA OFFICER

2Q100

FEMALE

2Q111

TR

2Q112A

ELEC

2Q105

EMER ELEC

2Q107

CLERICAL (2)

2Q108

LOUNGE

2Q106

WKRM

2Q128

CHIEF

2Q115

CENTRAL COPY CNTR

2Q101

WFD COORD

2Q136

ILL WKRM (2)

2Q103A

PHOTO/VIDEO STUDIO

2Q131

AV STOR/ CHECK OUT

2Q121

TECH WKRM

2Q123

MMS/MMEC SUPPLIES

2Q129

VIDEO CONF

VIDEO CONF

2Q116

PHOTO/ DIGITAL EDIT/

PRINT

2Q109

DEPUTY PAO

2Q102

SECTRY/ WAITING

2Q110

MOVE WELL COORD

2Q132DLO

2Q126

WELL ADMIN

2Q134

CHANGING

2Q119

HK

2Q114

PAPER

2Q133

ELEC

SAFE PAT HANDL

2Q130

LOBBY

2Q124

ELEV

ELEV

QP-3

ELEV

SHAFT

SHAFT

CORR

2Q-C02

CORR

2Q-C03

CORR

2Q-C01

CORR

2Q-C04 RECYCLE

2Q135

LVSR

2Q112

SHAFT

SHQ11

SHAFT

SHAFT

09-TD-021

(E)CABLE TRAY

(E)CABLE TRAY

TR

2Q112A

(E)SBB

(E)2Q133A-RK3

(E)2Q133A-RK2

(E)2Q133A-RK1

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-021

OVERALL SECOND FLOOR TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - LEVEL 2

DEMOLITION GENERAL NOTES

1 VISIT AND EXAMINE THE SITE PRIOR TO INITIATION OF WORK TO ASCERTAIN THE

CONDITIONS AND LIMITS OF DEMOLITION AND CONSTRUCTION.

2 DISPOSE OF REMOVED EQUIPMENT UNLESS DIRECTED TO DO SO OTHERWISE BY OWNER.

3 COORDINATE EXTENT AND SCOPE OF DEMOLITION IN ALL SPACES WITH ARCHITECTURAL.

4 CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

5 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

6 CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD" OR ANY PORTS

WITHOUT AN ADDRESS IN EXISTING PATCH PANELS AND VERIFY AN OUTLET. FOR PRICING

PURPOSES ASSUME A MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

7 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

PLAN NOTES

1 EXISTING COMMUNICATIONS 2-POST RACK TO REMAIN.

1/4" = 1'-0"2

ENLARGED TELECOMM DEMO PLAN - TR 2Q133A

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

DNUP DN UPUP

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

STAIR

RCRD FILE

3Q110

FEMALE

3Q105

MALE

3Q107

CLEAN

3Q101C

NURSE

3Q101K PRSNL MGMT

3Q121

LOUNGE

3Q114WKRM

3Q106

PRSNL MGMT

3Q124

PRSNL MGMT

3Q119

EXAM1

3Q101H

EAP

3Q103

RECEP WAITING

3Q128

PRSNL MGMT

3Q146

SPRVSR

3Q102

NURSE

3Q101A

PRSNL MGMT

3Q142

PRSNL MGMT

3Q104

TR

3Q118A

ELEC

3Q101F

EMER ELEC

3Q101E

CHIEF

3Q138

PRSNL MGMT

3Q129

PRSNL MGMT

3Q116

PRSNL MGMT

3Q112

SPRVSR

3Q100 PRSNL MGMT

3Q108

PRSNL MGMT

3Q123

PRSNL MGMT

3Q131

PRSNL MGMT

3Q144

CONF

3Q126PRSNL MGMT

3Q122

FNGRPRNT MACH

3Q132

PRSNL MGMT

3Q127

ASST CHIEF

3Q134

SCTRY

3Q136

EXAM2

3Q101J

SOILED UTILITY

3Q101B

T

3Q101D

CLERK/WAITING

3Q101G

PERSONNEL ASSTS.

3Q140

WORKSTATIONS

HK

3Q120

RECPT

3Q111

CONF

3Q113

UNION PRES

3Q109

RECPT

3Q115

UNION PRES

3Q117

EMER ELEC

3Q125

ELEC

CORR

3Q-C01A

LOBBY

3Q130

CORR

3Q-C01

EMPLY HEALTH

3Q101

CORR

3Q-C02

CORR

3Q-C02A

ELEV

ELEV

ELEV

STAIR

SHAFT

SHAFT

HR CARRELS

3Q128A

FILES

3Q101L

LVSR

3Q118

SHAFT

SHAFT

SHAFT

09-TD-031

(E)CABLE TRAY

(E)SBB

(E)3Q134A-RK3

(E)3Q134A-RK2

(E)3Q134A-RK1

TR

3Q118A

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-031

OVERALL THIRD FLOOR TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - LEVEL 3

DEMOLITION GENERAL NOTES

1 VISIT AND EXAMINE THE SITE PRIOR TO INITIATION OF WORK TO ASCERTAIN THE

CONDITIONS AND LIMITS OF DEMOLITION AND CONSTRUCTION.

2 DISPOSE OF REMOVED EQUIPMENT UNLESS DIRECTED TO DO SO OTHERWISE BY OWNER.

3 COORDINATE EXTENT AND SCOPE OF DEMOLITION IN ALL SPACES WITH ARCHITECTURAL.

4 CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

5 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

6 CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD" OR ANY PORTS

WITHOUT AN ADDRESS IN EXISTING PATCH PANELS AND VERIFY AN OUTLET. FOR PRICING

PURPOSES ASSUME A MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

7 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

PLAN NOTES

1 EXISTING COMMUNICATIONS 2-POST RACK TO REMAIN.

1/4" = 1'-0"2

ENLARGED TELECOMM DEMO PLAN - TR 3Q134A

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

UP DN UPDNDN

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

STAIR

3MALE

4Q113

FEMALE

4Q111

CONF

4Q121

ELEC

4Q107

TR

4Q112A

EMER ELEC

4Q105

WKRM

4Q101B

CNSLR

4Q101G

CNSLR

4Q101H

CONF

4Q103

CNSLR

4Q101J

INFCT CONTROL MNGRS

(2)

4Q100

QM ADMIN

4Q104

ACOS QM

4Q106 RSK MNGR

4Q118

ASST QM

4Q102

PSA

4Q110 RECEPTION

4Q126

INFMTC MNGR

4Q144

PTNT SAFETY

4Q138

ANALYST

4Q140

ACRDTN COORD

4Q124

CNSLR

4Q101F

WKRM

4Q132

BREAK

4Q108

CRDNTL MNGR

4Q130B

CRDNTL

4Q130

SWITCH GEAR

4Q131

ANALYST

4Q116

ANALYST

4Q122WKRM

4Q120

FILES

4Q136

STAIR

HK

4Q114

EEO SCTRY/ WAITING

4Q119

EEO OFFICE

4Q117

EEO HEARING ROOM

4Q109

CLNL CORD (4)

4Q142

SUPPLIES

4Q101D

PRLGL

4Q101A

CNSLR

4Q101C

RECEPTION

4Q101E

ELEC

COUNCIL

4Q101

CORR

4Q-C04

CORR

4Q-C03

LOBBY

4Q128

CORR

4Q-C02

CORR

4Q-C01

ELEV

ELEV

ELEV

39 SHAFT

SHAFT

SUPPLIES

4Q137

PTNT SAFETY

4Q134

CRDNTL CARRELS

4Q130A

SFTY CHIEF

4Q139

TECH

4Q133

TECH

4Q129

TECH

4Q127

TECH

4Q125

LIBRARY/STRG

4Q123 SCRTY

4Q135

OFFICE

4Q141

LVSR

4Q112

SHAFT

SHAFT

SHAFT

09-TD-041

(E)CABLE TRAY

TR

4Q112A

(E)SBB

(E)4Q136A-RK3

(E)4Q136A-RK2

(E)4Q136A-RK1

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-041

OVERALL FOURTH FLOOR TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - LEVEL 4

DEMOLITION GENERAL NOTES

1 VISIT AND EXAMINE THE SITE PRIOR TO INITIATION OF WORK TO ASCERTAIN THE

CONDITIONS AND LIMITS OF DEMOLITION AND CONSTRUCTION.

2 DISPOSE OF REMOVED EQUIPMENT UNLESS DIRECTED TO DO SO OTHERWISE BY OWNER.

3 COORDINATE EXTENT AND SCOPE OF DEMOLITION IN ALL SPACES WITH ARCHITECTURAL.

4 CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

5 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

6 CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD" OR ANY PORTS

WITHOUT AN ADDRESS IN EXISTING PATCH PANELS AND VERIFY AN OUTLET. FOR PRICING

PURPOSES ASSUME A MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

7 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

PLAN NOTES

1 EXISTING COMMUNICATIONS 2-POST RACK TO REMAIN.

1/4" = 1'-0"2

ENLARGED TELECOMM DEMO PLAN - TR 4Q136A

MAY NOT REPRESENT AN ACCURATE AS-BUILT

CONDITION. DISCREPANCIES MAY BE ENCOUNTERED,

AND IT IS THE CONTRACTOR'S RESPONSIBILITY TO

FIELD VERIFY ALL CONDITIONS.

DN DN UPUP

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

STAIR

TR

5Q104A

MALE

5Q117

FEMALE

5Q115

ELEC

5Q109

STAIR

EMER ELEC

5Q107

HK

5Q106

SUPPLIES

5Q100A

NE ANALYST

5Q138

ITAC

5Q140

ASST CHIEF

5Q144

SCTRY

5Q116

FCLTY PLNR

5Q110

CONF/ CLASSROOM

5Q100

RECEPTION

5Q123

EMRGY PRPDNS

5Q113

DIRECTOR

5Q132

DEPUTY COS

5Q125

SCTRY

5Q137 ASSOC DRCTR

5Q141

COS ADMIN

5Q127

T

5Q132A

DRCTR ADMIN

5Q128

SCTRY

5Q130

NS ADMIN

5Q124NRS SRV

5Q122

PSA

5Q119

SYST RDSN

5Q102 TRAINEES (3)

5Q126

BSNS CNTR

5Q105

ASST DRCTR

5Q114

COS

5Q129

ASSOC ADMIN

5Q143

PSA

5Q139

PSA

5Q135

CONF

5Q136

ASST ADMIN

5Q112

CSTMR SERV

5Q121

PSA

5Q108

COPY

5Q134

CONF

5Q101

SCTRY

5Q142

SCTRY

5Q133

SCTRY

5Q118

SRVG

5Q100B

SHAFT

ELEV

ELEV

ELEV

LOBBY

5Q120

CORR

5Q-C04

CORR

5Q-C01

CORR

5Q-C03

CORR

5Q-C02

SHAFT

CORR

5Q-C03A

BREAK

5Q103

OFFICE

5Q111

FILE/VAULT

5Q145

LVSR

5Q104

SHAFT

SHAFT

09-TD-051

(E)CABLE TRAY

TR

5Q104A

(E)SBB

(E)5Q137A-RK3

(E)5Q137A-RK2

(E)5Q137A-RK1

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TD-051

OVERALL FIFTH FLOOR TELECOMM

DEMOLITION PLAN - BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL DEMOLITION PLAN - LEVEL 5

DEMOLITION GENERAL NOTES

1 VISIT AND EXAMINE THE SITE PRIOR TO INITIATION OF WORK TO ASCERTAIN THE

CONDITIONS AND LIMITS OF DEMOLITION AND CONSTRUCTION.

2 DISPOSE OF REMOVED EQUIPMENT UNLESS DIRECTED TO DO SO OTHERWISE BY OWNER.

3 COORDINATE EXTENT AND SCOPE OF DEMOLITION IN ALL SPACES WITH ARCHITECTURAL.

4 CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

5 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

6 CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD" OR ANY PORTS

WITHOUT AN ADDRESS IN EXISTING PATCH PANELS AND VERIFY AN OUTLET. FOR PRICING

PURPOSES ASSUME A MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

7 IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ONSITE.

PLAN NOTES

1 EXISTING COMMUNICATIONS 2-POST RACK TO REMAIN.

1/4" = 1'-0"2

ENLARGED TELECOMM DEMO PLAN - TR 5Q137A

UP

DN

UP

NORTH

KEY PLAN

KEY PLAN

Q B

C

D

E

F

G

J

H

K

L M

P

N

S H

O T

G U

N

F

IS

H E

R

UNOCCUPIED

BQ110

STAIR

UNASSIGNED

STAIRS

STAIRS

STAIRS

STAIRS

SUPPLIES

BQ104

EXIT PASSAGEWAY

BQ105

TEMP ELEC DSCNT

BQ114

ELEC

BQ107

ELEC

BQ108

SHAFT

SHQ02

ELEC

BQ100

EMER ELEC

BQ101

UNOCCUPIED

BQ106

CORR

BQ-C01

LOBBY

BQ103

STAIR

STAIR

STAIR

MALE SHWR

BQ112

FEMALE SHWR

BQ111

ELEV

ELEV

QP-4

ELEV

ELEV

HK

BQ138

FIRE PUMP

BQ115

SHAFT

SEE SHEET 00-TS-001

FOR CONTINUATION

(7)24-STR SM (OS2)

4"C.

(7)24-STR SM (OS2)

4"C. UP TO 1ST FLR

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANTS

FOR OFFICIAL USE ONLY (FOUO)

04-25-2023

FULLY

SPRINKLED

PROGRAM

CONTRACTING

ACTIVITY

CENTRAL (PCAC)

Kramer Gehlen & Associates Structural Engineers 400 Columbia St., Suite 240, Vancouver, WA 98660 Vancouver

10% BASIS OF DESIGN 07.08.2022

35% SCHEMATIC DESIGN 11.10.2022

65% DESIGN DEVELOPMENT 01.13.2023

95% CONSTRUCTION DOCUMENTS 03.17.2023 GDM of Oregon

1000 W. STEUBEN ST., UNIT 3

BINGEN, WA 98605

P: 541.436.4723

ADAM GODDIN, PE

WWW.GDM-AE.COM

TERP consulting Fire + Life Safety

14241 E. 4th Avenue, Suite 5-230 Aurora CO, 80011

FINAL BID DOCUMENTS 04.25.2023

A u to d e s k D o c s /2

-0

N e w O rl e a n s

E H

R M

/2 -0

N

O L

A E

H R

M

C O

N C

O U

R S

E

E le c I n t-

R

.r v t

09-TN-0B1

OVERALL BASEMENT TELECOMM PLAN -

BLDG. 09

DJC AH

VA NEW ORLEANS (EHRM) ELECTRONIC

HEALTH RECORD MODERNIZATION

INFRASTRUCTURE UPGRADES

2400 CANAL STREET, NEW ORLEANS, LA 70119

FINAL BID DOCUMENTS 629-22-700

1/8" = 1'-0"1

BLDG. 09 TELECOMM OVERALL PLAN - BASEMENT

GENERAL NOTES

1. CONTRACTOR TO PROVIDE ALL CONDUIT SLEEVES AND CONDUIT. CONDUIT SLEEVES TO BE

SIZED AS REQUIRED FOR ROUTING OF TELECOMMUNICATIONS CABLING THROUGH WALLS

AND NON ACCESSIBLE CEILING AREAS. CONDUIT SLEEVES SHALL BE HILTI SPEED SLEEVES.

CONDUIT SIZE IS TO BE AS NOTED.

2. FOR NEW CONDUIT INSTALLATIONS THAT PENETRATE THROUGH EXISTING CONCRETE

WALLS AND FLOORS, CONTRACTOR SHALL PROVIDE ALL CORE-DRILLING, SEALING, AND

FIRE STOPPING AS REQUIRED.

3. ALL NEW FIBER SHALL BE REROUTED IN NEW INNERDUCT. INNERDUCT SHALL BE UTILIZED

FOR ROUTING FROM POINT OF ENTRY TO TERMINATION RACK AND SHALL UTILIZE NEW AND

EXISTING PATHWAYS AS REQUIRED.

4. ALL FIBER OPTIC CABLES ARE TO BE FIELD TERMINATED ON BOTH ENDS WITH SPLICE

CASSETTE CONNECTORS. ALL LENGTHS LISTED IN MATRIX ON SHEET 000-TG-001, ARE

APPROXIMATE. IT IS THE CONTRACTORS SOLE RESPONSIBILITY TO VERIFY REQUIRED

LENGTHS PRIOR TO PURCHASE OF FACTOR TERMINATED CABLES. CONTRACTOR SHALL

PROVIDE 10' OF ADDITIONAL LENGTH AT EACH END AND 16' WITHIN EACH VAULT FOR

SERVICE LOOPS.

5. TERMINATE FIBER CABLING IN NEW FIBER PATCH PANELS IN TELECOMMUNICATION RACKS.

6. CONTRACTOR TO PROVIDE NEW J-HOOKS SIZED AS REQUIRED FOR ROUTING OF FIBER

OPTIC CABLE IN ACCESSIBLE SPACES AS SHOWN. PROVIDE ALL APPURTENANCES FOR

INSTALLATION OF J-HOOKS.

7. IN GENERAL, DROP LOCATIONS ARE PROVIDED FOR GUIDANCE ONLY. CONTRACTOR IS

RESPONSIBLE TO CONFIRM ALL OUTLET LOCATIONS ON SITE.

8. PROVIDE 3/4" AC GRADE(OR BETER) PLYWOOD ON ALL WALLS IN TR ROOMS. PLYWOOD WILL

BE FIRE RETARDANT AND COATED WITH TWO COATS OF FIRE RETARDANT PAINT. THE

BOTTOM OF THE PLYWOOD SHOULD BE MOUNTED 6" AFF.

9. CONTRACTOR SHALL TRACE ALL PORTS LABELED "BLANK", "OPEN", "BAD", OR ANY PORTS

WITHOUT AN ADDRESS, AND VERIFY AN OUTLET. FOR PRICING PURPOSES, ASSUME A

MINIMUM OF 200FT OF CABLING TO EACH OUTLET.

10. DRAWING PLANS INDICATE NUMBER OF DROPS IN AREAS THAT ARE SERVED EXACT

LOCATION OF DROPS IN EACH AREA SHALL BE CONFIRMED ON SITE.

11. CONTRACTOR TO PROVIDE ACCESS PANELS IN HARD CEILINGS AS REQUIRED.

12. CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY MOVE AND RETURN FURNITURE,

FIXTURES, AND EQUIPMENT WITHIN SPACES AS REQUIRED TO COMPLETE EACH DAY'S

WORK. THE VA WILL REMOVE, OR SECURE, PHI, PPI, AND PERSONAL PROPERTY.

COORDINATE THIS WORK WITH THE COR.

13.