This solicitation is for an indefinite-delivery, indefinite-quantity multiple award construction contract to provide large general construction projects primarily in the Hampton Roads Area of Responsibility in Virginia. The Naval Facilities Engineering Command is seeking contractors to complete design-build and design-bid-build projects including new construction, renovations, and repairs. Offerors can submit proposals at any time during the five-year period of performance. Awarded contracts will have a minimum and maximum ordering value of $500,000 and $100 million respectively, and a five-year ordering period. This multiple award contract aims to reduce acquisition lead time for small to mid-sized projects in the Hampton Roads region.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO.
At the
PREPARED BY:
Architectural: Mechanical:
Civil: Electrical:
Structural:
APPROVED BY:
Specifications:
For Commander, NAVFAC:
Date:
Submitted By: Date:
UNCLASSIFIED/FOR OFFICIAL USE ONLY
Help Note All fields can be edited. If you have trouble selecting a field, either use the tab key or click "highlight fields" in Acrobat 7. Fields that are not needed can be selected and deleted. Tool tips with "additional field" can be deleted or changed. The contract number can also be deleted or changed.
LFornataro Text Box Volume I - Division 01 Volume II - Division 02 through Division 14 (Divisions 15 through 20 not used) Volume III - Division 21 through Division 46
CORROSION CONTROL AND PAINT FACILITY 21P1035
NAVAL STATION, NORFOLK, VA EPROJECTS W.O. NO.: 1614720
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 30 01.00 22 DESIGN, PROCUREMENT, AND INSTALLATION OF FURNITURE,
FIXTURES, AND EQUIPMENT
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 00.15 22 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 45 00 PRECAST ARCHITECTURAL CONCRETE
DI VI SI ON 04 - MASONRY
04 20 00 UNIT MASONRY
DI VI SI ON 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 26 23.19 22 BROWNFIELD MEMBRANE SYSTEMS
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 41 63 FABRICATED ROOF PANEL ASSEMBLIES
07 42 10 COMPOSITE FRAMING SUPPORT (CFS) SYSTEM
07 42 13 METAL WALL PANELS
07 60 00 FLASHING AND SHEET METAL
07 72 00 ROOFTOP FREESTANDING GUARDRAIL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 22 20 FIBERGLASS REINFORCED PLASTIC (FRP) DOORS AND FRAMES
08 31 00 ACCESS DOORS
08 33 23 OVERHEAD COILING DOORS
08 34 16 CORROSION CONTROL HANGAR DOORS
08 34 16.10 STEEL SLIDING HANGAR DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 60 45 TRANSLUCENT PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 87 33 DECORATIVE FILMS
08 91 00 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC TILING
09 51 00 ACOUSTICAL CEILINGS
09 54 50 METAL PANEL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 67 23.14 CHEMICAL RESISTANT RESINOUS FLOORING
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 26 HDPE SOLID PLASTIC LOCKERS
10 53 00 HANGER ROD SUPPORTED CANOPY
PROJECT TABLE OF CONTENTS Page 2
DI VI SI ON 11 - EQUI PMENT
11 01 00 ROOF MAINTENANCE FALL ARREST EQUIPMENT
11 24 29 RIGID RAIL FOR AIRCRAFT HANGAR
11 90 30.00 22 AIRCRAFT WASHING EQUIPMENT
11 90 40 PLASTIC MEDIA BLASTING (PMB) SYSTEM
11 90 50 PMB BAY VENTILATION AND EXHAUST
DI VI SI ON 12 - FURNI SHI NGS
12 24 13 ROLLER WINDOW SHADES
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DI VI SI ON 14 - CONVEYI NG EQUI PMENT
14 55 00 MECHANICAL SCISSORS LIFT SYSTEM
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 13 16.00 20 DRY-PIPE FIRE SPRINKLER SYSTEMS
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 MECHANICAL SOUND AND VIBRATION CONTROL
22 15 19.19 20 NONLUBRICATED ROTARY SCREW AIR COMPRESSORS (BREATHING
AIR, 100 HP AND LARGER)
22 15 19.20 20 LUBRICATED ROTARY SCREW AIR COMPRESSORS (SHOP AIR, 100 HP
AND LARGER)
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93.00 22 TESTING, ADJUSTING, AND BALANCING FOR MECHANICAL SYSTEMS
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 01.00 20 TESTING INDUSTRIAL VENTILATION SYSTEMS
23 09 00.00 22 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13.00 22 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 22 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 22 26.00 20 STEAM SYSTEM AND TERMINAL UNITS
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED AND CONDENSER WATER PIPING SYSTEMS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.01 CYBERSECURITY FOR ADVANCED METERING INFRASTRUCTURE (AMI)
SYSTEMS
25 05 11.02 CYBERSECURITY FOR WASTEWATER INDUSTRIAL CONTROL (ICS)
SYSTEMS
25 05 11.03 CYBERSECURITY FOR FIRE ALARM SYSTEMS
25 05 11.04 CYBERSECURITY FOR BUILDING AUTOMATION SYSTEMS (BAS)
PROJECT TABLE OF CONTENTS Page 3
25 05 11.05 CYBERSECURITY FOR COMPRESSED AIR SYSTEMS
25 05 11.06 CYBERSECURITY FOR PLASTIC MEDIA BLAST SYSTEMS
25 08 10 UTILITY MONITORING AND CONTROL SYSTEM TESTING
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END
AND INTEGRATION
DI VI SI ON 26 - ELECTRI CAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS
26 13 00 SF6/HIGH-FIREPOINT FLUIDS INSULATED PAD-MOUNTED SWITCHGEAR
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 27 14.00 20 ELECTRICITY METERING
26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS
26 32 13.00 20 SINGLE OPERATION GENERATOR SETS
26 36 23.00 20 AUTOMATIC TRANSFER SWITCHES
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 23 00.00 20 EXCAVATION AND FILL
31 31 16.13 CHEMICAL TERMITE CONTROL
31 62 13.20 PRECAST/PRESTRESSED CONCRETE PILES
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 60 02 ABOVEGROUND HEAT DISTRIBUTION SYSTEM
33 61 13 PRE-ENGINEERED UNDERGROUND HEAT DISTRIBUTION SYSTEM
33 61 13.13 PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
PROJECT TABLE OF CONTENTS Page 4
DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT
41 22 23.19 JIB CRANE HOISTS
DI VI SI ON 46 - WATER AND WASTEWATER EQUI PMENT
46 53 60 WATER TREATMENT SYSTEM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 6
SECTION 21 13 13.00 20
WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
04/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2019; Errata 19-1; Errata 19-2; TIA 19-1;
TIA 19-2; TIA 19-3; TIA 19-4; Errata 19-3) Standard for the Installation of Sprinkler Systems
NFPA 24 (2016; ERTA 2016) Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 1963 (2019) Standard for Fire Hose Connections
UNDERWRITERS LABORATORIES (UL)
UL Fire Prot Dir (2020) Fire Protection Equipment Directory
1.2 SYSTEM DESCRIPTION
Design and provide new automatic wet pipe fire extinguishing sprinkler systems for complete fire protection coverage throughout the entire building.
1.3 SPRINKLER SYSTEM DESIGN
Except as modified herein, design automatic wet pipe fire extinguishing sprinkler systems in accordance with the required and advisory provisions of NFPA 13 , including all recommendations and advisory portions, which must be considered mandatory; this includes advisory provisions listed in the appendices of such standard(s), as though the word "must" had been substituted for the word "should" wherever it appears. Design system by hydraulic calculations for uniform distribution of water over the design area. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers. Provide sprinklers and piping system layout. All Devices and equipment for fire protection service must be
SECTION 21 13 13.00 20 Page 1
UL Fire Prot Dir listed or FM APP GUIDE approved for use in wet pipe sprinkler systems.
1.3.1 Location of Sprinklers
Sprinklers in relation to the ceiling and the spacing of sprinklers must not exceed that permitted by NFPA 13 for the hazards indicated on the contract drawings. Uniformly space sprinklers on the branch piping,to the extent practical, while complying with applicable spacing requirements.
Sprinklers must provide coverage throughout 100 percent of the building.
This includes, but is not limited to, telephone rooms, electrical equipment rooms, boiler rooms, switchgear rooms, transformer rooms, and other electrical and mechanical spaces.
1.3.2 Water Distribution
Distribution must be uniform throughout the area in which the sprinklers will open. Discharge from individual sprinklers in hydraulically most remote area must be between 100 percent and 120 percent of the specified density.
1.3.3 Density of Application of Water
Size pipe to provide the specified density when the system is discharging the specified total maximum required flow. Application to horizontal surfaces below the sprinklers must be as indicated on the contract drawings.
1.3.4 Sprinkler Discharge Area
Area must be the hydraulically most remote area as indicated on the contract drawings. Area reductions and increases from NFPA 13 must not be applied to this area.
1.3.5 Outside Hose Allowances
Hydraulic calculations must include a hose allowance for outside hose streams as indicated on the contract drawings.
1.3.6 Water Supply
Base hydraulic calculations on the water supply data shown on the contract drawings at the junction with the existing water distribution piping system.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.
Partial submittals and submittals not fully complying with the requirements and recommended practices of NFPA 13 and this specification section must be returned disapproved without review. This contract stipulation is non-negotiable.
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SECTION 21 13 13.00 20 Page 2
SD-02 Shop Drawings
Shop Drawings ; G
Prepare 24 by 36 inch detail working drawings of sprinklers and piping. Floor plans must be drawn to a scale not less than 1/8" = 1'-0" . Show data essential for proper installation of each system. Show details, plan view, elevations and sections of the systems supply and piping. Show piping schematic of systems supply, devices, valves, pipe and fittings. Show point to point electrical wiring diagrams. Provide three copies of the Sprinkler System Shop Drawings, no later than 21 days prior to the start of sprinkler system installation.
SD-03 Product Data
Pipe ; G Fittings ; G Valves , including gate, check, and globe; G Sprinklers ; G Pipe hangers and supports ; G Sprinkler Alarm Switches ; G Fire department connections ; G Mechanical couplings ; G
Annotate descriptive data to show the specific model, type, and size of each item. Catalog cuts must also indicate UL Listing/FM Approval and country of manufacture.
SD-05 Design Data
Hydraulic Calculations ; G
Submit computer program generated hydraulic calculations to substantiate compliance with hydraulic design requirements.
Calculations must be performed by computer using software intended specifically for fire protection system design.
SD-06 Test Reports request to schedule Preliminary Tests ; G
Preliminary Test Report ; G
Provide Three copies of the completed Preliminary Test Report, no later than 7 days after the completion of the Preliminary Tests.
The Preliminary Tests Report must include both the Contractor's Material and Test Certificate for Underground Piping and the Contractor's Material and Test Certificate for Aboveground Piping.
request to schedule Final Acceptance Test ; G
Final Acceptance Test Report ; G
Provide Three copies of the completed Final Acceptance Tests Reports, no later than 7 days after the completion of the Final Acceptance Tests.
SECTION 21 13 13.00 20 Page 3
SD-07 Certificates
Sprinkler System Installer ; G
Submit data showing the Sprinkler System Installer has successfully installed systems of the same type and design as specified herein, Data must include names and locations of at least two installations where the Contractor, or the subcontractor referred to above, has installed such systems. Indicate type and design of each system and certify that each system has performed satisfactorily in the manner intended for not less than 18 months. Provide NICET certification of the system technician.
Contractor must submit data along with submittal of the Fire Protection Engineer Qualifications.
SD-10 Operation and Maintenance Data
Operating and Maintenance Instructions
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA and Section 01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT INFORMATION (eOMSI) as supplemented and modifies by this specification section.
Provide six manuals in accordance with NFPA 13. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization (including address and telephone number) for each item of equipment. Each service organization submitted must be capable of providing 4 hour on-site response to a service call on an emergency basis.
SD-11 Closeout Submittals
As-built drawings
As-built shop drawings, at no later than 14 days after completion of the Final Tests. The Sprinkler System Drawings must be updated to reflect as-built conditions after all related work is completed. Provide electronic drawings in dwg or pdf format.
On-site training
1.5 QUALIFICATIONS
1.5.1 Sprinkler System Installer
The Sprinkler System Installer must be regularly engaged in the installation of the type and complexity of system specified in the Contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months. Installation drawings, shop drawings and as-built drawings must be prepared, by or under the supervision of, an system technician who is experienced with the types of works specified herein, and is currently certified by the National Institute for Certification in Engineering Technologies (NICET) as an engineering
SECTION 21 13 13.00 20 Page 4 technician with minimum Level III certification in Automatic Sprinkler System program or by a fire protection engineer.
1.6 QUALITY ASSURANCE
1.6.1 Material and Equipment Qualifications
Provide materials and equipment that are standard products of manufacturers regularly engaged in the manufacture of such products, which are of a similar material, design and workmanship. Standard products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year use must include applications of equipment and materials under similar circumstances and of similar size. The product must have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2 year period.
1.6.2 Alternative Qualifications
Products having less than a two-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturer's factory or laboratory tests, can be shown.
1.6.3 Manufacturer's Nameplate
Each item of equipment must have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.
1.6.4 Field Fabricated Nameplates
ASTM D709. Provide laminated plastic nameplates for each equipment enclosure, relay, switch, and device; as specified in the technical sections or as indicated on the drawings. Each nameplate inscription must identify the function and, when applicable, the position. Nameplates must be melamine plastic, 0.125 inch thick, white with black center core.
Surface must be matte finish. Corners must be square. Accurately align lettering and engrave into the core. Minimum size of nameplates must be one by 2.5 inches . Lettering must be a minimum of 0.25 inch high normal block style.
1.7 ACCESSIBILITY
Install all work so that parts requiring periodic inspection, operation, maintenance, and repair are readily accessible. Install concealed valves, expansion joints, controls, dampers, and equipment requiring access, in locations freely accessible through access doors.
1.8 DELIVERY, STORAGE AND HANDLING
All equipment delivered and placed in storage must be housed in a manner to preclude any damage from the weather, humidity and temperature variations, dirt and dust, or other contaminants. Additionally, all pipes must either be capped or plugged until installed.
SECTION 21 13 13.00 20 Page 5
PART 2 PRODUCTS
2.1 UNDERGROUND PIPING COMPONENTS
2.1.1 Pipe
Pipe must comply with NFPA 24 . Minimum pipe size must be 6 inches .
Piping more than 5 feet outside the building walls must comply with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING.
2.1.2 Buried Utility Warning and Identification Tape
Provide detectable aluminum foil plastic backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an electronic detection instrument. Provide tape in rolls, 3 inches minimum width, color coded for the utility involved with warning and identification imprinted in bold block letters continuously and repeatedly over the entire tape length. Warning and identification must read "CAUTION BURIED WATER PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.
2.2 ABOVEGROUND PIPING COMPONENTS
All components of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section. Aboveground piping must be steel.
2.2.1 Steel Pipe
Pipe must be rigid black steel. Steel pipe must be Schedule 40 for sizes less than 2-1/2 inches and Schedule 10 or 40 for sizes 2-1/2 inches or larger. Fittings into which sprinklers, sprinkler riser nipples, or drop nipples are threaded must be welded, threaded, or grooved-end type.
Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe and segmented welded fittings must not be permitted. Rubber gasketed grooved-end pipe and fittings with mechanical couplings must be permitted in pipe sizes 1.5 inches and larger. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Steel piping with wall thickness less than Schedule 30 must not be threaded. Side outlet tees using rubber gasketed fittings must not be permitted. Sprinkler pipe and fittings must be metal.
2.2.2 Grooved Mechanical Joints and Fittings
Grooved couplings, fittings and grooving tools must be products of the same manufacturer.
2.2.3 Flexible Sprinkler Hose
The use of flexible sprinkler hose is not permissible.
2.2.4 Sprinklers
Provide sprinklers with minimum orifice size as indicated on the contract drawings. Sprinklers with internal O-rings must not be used. Sprinklers must be used in accordance with their listed coverage limitations.
SECTION 21 13 13.00 20 Page 6
Provide Recessed Pendent, Upright and Sidewall sprinklers. Upright sprinklers must have a brass finish. Recessed pendent sprinklers must have a white polyester finish. Sprinklers must be quick response unless noted otherwise. Temperature classification must be ordinary unless noted otherwise. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Sprinklers utilizing glass bulb fusible element technology are not permitted. Extended coverage sprinklers must not be used. Provide corrosion-resistant sprinklers and sprinkler guards as required by NFPA 13 . Deflector must not be more than 3 inches below suspended ceilings. Ceiling plates must not be more than 0.5 inch deep.
Ceiling cups must not be permitted.
2.2.5 Valves
Provide valves of types approved for fire service. Valves must open by counterclockwise rotation. Provide a butterfly valve in each riser.
Check valves must be clear opening swing-check type with inspection and access cover plate for sizes 8 inches and larger. Each control valve must be electrically supervised; minimum contact ratings must be 2.5 amps at 24 volts DC. Provide supervision against valve closure or tampering of valve.
2.2.6 Pipe Supports
Provide Pipe hangers and supports in accordance with NFPA 13 .
2.2.7 Fire Department Connections
Fire department connection must be projecting type with cast brass body, matching wall escutcheon lettered "Auto Spkr" with a polished brass finish. The connection must have two inlets with individual self-closing clappers, caps with drip drains and chains. Female inlets must have 2-1/2 inch diameter American National Fire Hose Connection Screw Threads (NH) per NFPA 1963 .
2.3 ALARM INITIATING AND SUPERVISORY DEVICES
2.3.1 Sprinkler Alarm Switches
Provide vane type flow switch(es) with circuit opener or closer for the automatic transmittal of an alarm over the facility fire alarm system.
Connection of switch must be under Section 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE. Vane type Alarm actuating devices must have mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.
2.3.2 Valve Supervisory (Tamper) Switch
Switch must be suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain one set of SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.
2.4 ACCESSORIES
2.4.1 Sprinkler Cabinet
Provide metal cabinet with extra sprinklers and sprinkler wrench adjacent to the sprinkler risers. The number and types of extra sprinklers must be
SECTION 21 13 13.00 20 Page 7 as specified in NFPA 13 .
2.4.2 Pipe Escutcheon
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
PART 3 EXECUTION
3.1 UNDERGROUND PIPING INSTALLATION
The methods of fabrication and installation of the underground piping must fully comply with the requirements and recommended practices of NFPA 13 , NFPA 24 and the contract drawings.
3.2 ABOVEGROUND PIPING INSTALLATION
The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.
3.2.1 Piping in Finished Areas
In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.
3.2.2 Pendent Sprinklers
Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend more than 1 inch below the underside of the ceiling. Pendent sprinklers in suspended ceilings must be a minimum of 6 inches from ceiling grids.
3.2.3 Reducers
Reductions in pipe sizes must be made with one-piece tapered reducing fittings. Bushings are prohibited.
3.2.4 Pipe Penetrations
Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Do not core-drill precast concrete wall panels without prior approval of precast manufacturer. Each sleeve must be Schedule 40 galvanized steel, ductile iron or cast iron pipe and must extend through its respective wall or floor and be cut flush with each wall surface.
Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 . The space between the sleeve and the pipe must be firmly packed with mineral wool insulation. Where pipes penetrate fire walls, fire partitions, or floors, pipes must be fire stopped in accordance with Section 07 84 00 FIRESTOPPING. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be
SECTION 21 13 13.00 20 Page 8 sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.
3.2.5 Inspector's Test Connection
Provide test connections approximately 6 feet above the floor for each sprinkler system or portion of each sprinkler system equipped with an alarm device. Provide test connection piping to a drain location that can accept full flow where the discharge will be readily visible and where water may be discharged without property damage. Discharge to floor drains, janitor sinks or similar fixtures must not be permitted. Provide discharge orifice of same size as corresponding sprinkler orifice. The penetration of the exterior wall must be no greater than 2 feet above finished grade.
3.2.6 Drains
Main drain piping must be provided to discharge at a safe point outside the building. Auxiliary drains must be provided as required by NFPA 13 .
3.2.7 Installation of Fire Department Connection
Connection must be mounted on the exterior wall approximately 3 feet above finished grade. The piping between the connection and the check valve must be provided with an automatic drip in accordance with NFPA 13 and arranged to drain to the outside.
3.2.8 Identification Signs
Signs must be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Valve identification signs must be minimum 6 inches wide by 2 inches high with enamel baked finish on minimum 18 gauge steel or 0.024 inch aluminum with red letters on a white background or white letters on red background. Hydraulic design data nameplates must be permanently affixed to each sprinkler riser as specified in NFPA 13 .
3.3 ELECTRICAL WORK
Except as supplemented and modified herein, electric equipment and wiring must be in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.
Alarm signal wiring connected to the building fire alarm control system must be in accordance with 28 31 76 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE.
3.4 PIPE PAINTING AND COLOR CODE MARKING
Paint and color code mark sprinkler piping system as specified in Section
09 90 00 PAINTS AND COATINGS.
3.5 PRELIMINARY TESTS
The system, including the underground water mains, and the aboveground piping and system components, must be tested to assure that equipment and components function as intended. The underground and aboveground interior piping systems and attached appurtenances subjected to system working pressure must be tested in accordance with NFPA 13 and NFPA 24 .
Submit request to schedule Preliminary Tests , no later than 14 days prior
SECTION 21 13 13.00 20 Page 9 to the proposed start of the tests. Upon completion of specified tests, the Contractor must submit for approval a Preliminary Test Report .
3.5.1 Underground Piping
3.5.1.1 Flushing
Underground piping must be flushed in accordance with NFPA 24 .
3.5.1.2 Hydrostatic Testing
New underground piping must be hydrostatically tested in accordance with
NFPA 24 .
3.5.2 Aboveground Piping
3.5.2.1 Hydrostatic Testing
Aboveground piping must be hydrostatically tested in accordance with
NFPA 13 .
3.6 FINAL ACCEPTANCE TEST
Final Acceptance Test must begin only when the Preliminary Test Report has been approved. Submit request to schedule Final Acceptance Test , no later than 14 days prior to the proposed start of the tests. Notification must include a copy of the Contractor's Material & Test Certificates.
Copies of as-built drawings and certificates of tests previously conducted must be available. The Contractor must submit the Final Acceptance Test Report as specified in the Submittals paragraph.
An experienced technician regularly employed by the system installer must be present during the inspection. At this inspection, repeat any or all of the required tests as directed. Correct defects in work provided by the Contractor, and make additional tests until the systems comply with contract requirements. Furnish appliances, equipment, electricity, instruments, connecting devices, and personnel for the tests. The Government will furnish water for the tests. The MIDLANT Division, Naval Facilities Engineering Command, Fire Protection Engineer, will witness formal tests and approve systems before they are accepted.
3.7 ON-SITE TRAINING
Submit request to schedule the On-site Training, at least 14 days prior to the start of related training but prior to the final inspections and tests. The sprinkler contractor must conduct a training course for operating and maintenance personnel as designated by the Contracting Officer. Training must be provided for a period of 2 hours of normal working time and must start after the system is functionally complete and after the Final Acceptance Test. The On-Site Training must cover all of the items contained in the approved Operating and Maintenance Instructions .
-- End of Section --
SECTION 21 13 13.00 20 Page 10
SECTION 21 13 16.00 20
DRY-PIPE FIRE SPRINKLER SYSTEMS
04/06
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2019; Errata 19-1; Errata 19-2; TIA 19-1;
TIA 19-2; TIA 19-3; TIA 19-4; Errata 19-3) Standard for the Installation of Sprinkler Systems
NFPA 70 (2019; TIA 19-1; TIA 19-2; TIA 19-3; TIA
19-4; ERTA 1 2019) National Electrical Code
UNDERWRITERS LABORATORIES (UL)
UL Fire Prot Dir (2020) Fire Protection Equipment Directory
1.2 SYSTEM DESCRIPTION
Design and provide automatic dry pipe fire extinguishing sprinkler system for complete fire protection coverage of the exterior dust collectors (DC-1 and DC-2).
1.3 SPRINKLER SYSTEM DESIGN
Design automatic dry pipe fire extinguishing sprinkler systems in accordance with the required and advisory provisions of NFPA 13 , hydraulic calculations using the area/density method for uniform distribution of water over the design area for ordinary hazard occupancy. Each system must include materials, accessories, and equipment inside and outside the building to provide each system complete and ready for use. Design and provide each system to give full consideration to blind spaces, piping, electrical equipment, ducts, and other construction and equipment in accordance with detailed working drawings to be submitted for approval.
Locate sprinkler heads in a consistent pattern with ceiling grid, lights, and air supply diffusers. Devices and equipment for fire protection service must be UL Fire Prot Dir listed or FM APP GUIDE approved for use in dry pipe sprinkler systems.
1.3.1 Location of Sprinkler Heads
Spacing of sprinklers and position and orientation of sprinklers in relation to the dust collector configuration must conform to Factory
SECTION 21 13 16.00 20 Page 1
Mutual Data Sheet 07-73 "Dust Collectors and Collection Systems.".
1.3.2 Water Distribution
Distribution must be uniform throughout the area in which the sprinkler heads will open. Discharge from individual sprinklers in the hydraulically most remote area must be not less than 100 percent of the specified density.
1.3.3 Density of Application of Water
Size pipe to provide the specified density when the system is discharging the specified total maximum required flow. Application to horizontal surfaces below the sprinklers must be as indicated on contract drawings.
1.3.4 Sprinkler Design Area
Area must be the entirety of one dust collector.
1.3.5 Outside Hose Allowances
Hydraulic calculations must include an allowance for outside hose streams as indicated on contract drawings.
1.3.6 Friction Losses
Calculate losses in piping in accordance with the Hazen-Williams formula with 'C' value of 100 for steel piping, 150 for copper tubing, and 140 for cement-lined ductile-iron piping. Velocity in the sprinkler piping must be limited to a maximum of 20 ft/sec .
1.3.7 Water Supply
Base hydraulic calculations on water supply data shown on the contract drawings.
1.3.8 Detail Drawing
Prepare 24 by 36 inch detail working drawings of sprinkler heads and piping system layout in accordance with NFPA 13 , "Working Drawings (Plans)." Show data essential for proper installation of each system.
Show details, plan view, elevations, and sections of the systems supply and piping. Show piping schematic of systems supply, devices, valves, pipe, and fittings. Show point to point electrical wiring diagrams . Show location and orientation of sprinkler heads in relation to obstructions.
1.3.9 Detail Drawings
After completion, but before final acceptance, submit complete set of as-built drawings of each system for record purposes. Submit 24 by 36 inch drawings on reproducible mylar film with title block similar to full size contract drawings. Furnish the as-built (record) working drawings in addition to as-built contract drawings required by Division 1, "General Requirements."
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control
SECTION 21 13 16.00 20 Page 2 approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
The MIDLANT Division, Naval Facilities Engineering Command, Fire Protection Engineer, will review and approve all submittals in this section requiring Government approval.
SD-02 Shop Drawings
Sprinkler heads and piping system layout ; G
Electrical wiring diagrams ; G
SD-03 Product Data
Piping ; G
Valves , including gate, check, and globe; G
Sprinkler heads ; G
Pipe hangers and supports ; G
Abnormal nitrogen pressure supervisory switch ; G
Dry pipe valves ; G
Nitrogen generator ; G
Mechanical couplings ; G
Pressure Switch ; G
Annotate descriptive data to show the specific model, type, and size of each item.
SD-05 Design Data
Sprinkler system design ; G
Submit computer program generated hydraulic calculations to substantiate compliance with hydraulic design requirements.
Calculations generated by computer program must include the name, address, and telephone number of the software manufacturer.
SD-06 Test Reports
Preliminary tests on piping system; G
SD-07 Certificates
Qualifications of installer ; G
SD-10 Operation and Maintenance Data
Dry pipe valves , Data Package 3; G
SECTION 21 13 16.00 20 Page 3
Nitrogen generator , Data Package 3; G
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA and Section 01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT INFORMATION (eOMSI).
SD-11 Closeout Submittals
As-built drawings of each system ; G
1.5 QUALITY ASSURANCE
1.5.1 Qualifications of Installer
Prior to installation, submit data showing that the Contractor has successfully installed systems of the same type and design as specified herein, or that Contractor has a firm contractual agreement with a subcontractor having such required experience. Data must include names and locations of at least two installations where the Contractor, or the subcontractor referred to above, has installed such systems. Indicate type and design of each system and certify that each system has performed satisfactorily in the manner intended for not less than 18 months.
Qualifications of System Technician: Installation drawings, shop drawing and as-built drawings must be prepared, by or under the supervision of, an individual who is experienced with the types of works specified herein, and is currently certified by the National Institute for Certification in Engineering Technologies (NICET) as an engineering technician with minimum Level-III certification in automatic sprinkler system program. Contractor must submit data for approval showing the name and certification of all involved individuals with such qualifications at or prior to submittal of drawings.
PART 2 PRODUCTS
2.1 ABOVEGROUND PIPING SYSTEMS
Provide fittings for changes in direction of piping and for connections.
Make changes in piping sizes through tapered reducing pipe fittings;
bushings will not be permitted. Perform welding in the shop; field welding will not be permitted. Conceal piping in areas with suspended ceiling.
2.1.1 Sprinkler Piping
NFPA 13 , except as modified herein. Steel piping must be Schedule 40.
Fittings into which sprinkler heads, sprinkler head riser nipples, or drop nipples are threaded must be welded, threaded, or grooved-end type.
Grooved joints shall be cut-grooved; roll-grooving is not permitted.
Plain-end fittings with mechanical couplings and fittings which use steel gripping devices to bite into the pipe when pressure is applied will not be permitted. Rubber gasketed grooved-end pipe and fittings with mechanical couplings must be permitted in pipe sizes 1.5 inches and larger. Fittings must be UL Fire Prot Dir listed or FM APP GUIDE approved for use in dry pipe sprinkler systems. Fittings, mechanical couplings , and rubber gaskets must be supplied by the same manufacturer. Gaskets must be of silicon compound and approved for dry fire protection systems.
Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Steel piping with wall thickness less than Schedule
SECTION 21 13 16.00 20 Page 4
30 must not be threaded. Sprinkler pipe and fittings must be metal.
2.1.2 Sprinkler Heads
Provide nominal 0.50 inch or 0.53 inch orifice standard or quick response sprinkler heads. No o-rings will be permitted in sprinkler heads.
Release element of each head must be of the intermediate temperature rating or higher as suitable for the specific application. Sprinklers utilizing glass bulb fusible element technology are not permitted.
Provide corrosion-resistant sprinkler heads and sprinkler head guards as required by NFPA 13 . Automatic sprinklers installed in the pendent position must be of the dry-pendent type.
2.1.3 Cabinet
Provide metal cabinet with extra sprinkler heads and sprinkler head wrench adjacent to each dry pipe valve. The number and types of extra sprinkler heads must be as specified in NFPA 13 .
2.1.4 Dry Pipe Valves
Provide valve complete with accessories and appurtenances for the proper operation of the system.
2.1.5 Pressure Switch
Provide switch with circuit opener or closer for the automatic transmittal of an alarm over the facility fire alarm system. Connection of switch must be under Section 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM ADDRESSABLE. Do not install a shutoff valve in the piping between the dry pipe valve and any pressure switch.
2.1.6 Abnormal Nitrogen Pressure Supervisory Switch
Provide switch for each sprinkler system and connect to building fire alarm system to activate the system supervisory alarm when nitrogen pressure in system drops halfway from the normal pressure to the tripping point. Connection of switch must be under Section 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM ADDRESSABLE. Provide a bleeder valve in the air line ahead of the switch for testing operation of the switch.
The valve must be normally open. Closing the valve must shut off the air supply to the switch and exhaust the pressure between the switch and valve.
2.1.7 Nitrogen Generator
Provide an approved nitrogen generator including pressure switch piping and all components necessary for proper operation. Generator must have a minimum capacity capable of charging the complete sprinkler system to normal system air pressure within 30 minutes. Nitrogen generator must utilize membrane technology and be capable of delivering a minimum 98 percent nitrogen composition throughout all of the system piping within 14 days from commencement of the inerting process. Provide an approved automatic air maintenance device for each system.
2.1.8 Pipe Hangers and Supports
Provide in accordance with NFPA 13 .
SECTION 21 13 16.00 20 Page 5
2.1.9 Valves
Provide valves of types approved for fire service. Valves must open by counterclockwise rotation. Provide supervised indicating control valve beneath each dry pipe valve.
2.1.9.1 Valve Supervision
Provide supervision of each control valve against closure and tampering in accordance with NFPA 13 . Provide switch with SPDT (Form C) dry contacts for the automatic transmittal of a supervisory signal over the facility fire alarm system; minimum switch contact rating must be 2.5 amperes at 24 VDC. A supervisory signal must be initiated during the first two revolutions of the hand wheel, or during the first 1/5th of travel distance of the valve stem, from the full open position. Connection of the switch must be under Section 28 31 76 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM ADDRESSABLE.
2.1.10 Identification Signs
Attach properly lettered and approved metal signs to each valve and alarm device. Permanently affix hydraulic design information sign to the riser of each system.
2.1.11 Inspector's Test Connection
Provide test connections approximately 6 feet above the floor for each sprinkler system or portion of each sprinkler system equipped with an alarm device; locate at the hydraulically most remote part of each system.
Provide test connection piping to a location where the discharge will be readily visible and where water may be discharged without property damage. Provide discharge orifice of same size as corresponding sprinkler orifice. Provide a precast concrete splash block under each exterior discharge orifice.
2.1.12 Main Drains
Provide separate drain piping to discharge at safe points outside the building. The penetration of the exterior wall must be no greater than
2.0 feet above finished grade. Provide auxiliary drains as required by NFPA 13 . Provide precast concrete splash blocks under each exterior drain discharge.
2.2 ESCUTCHEON PLATES
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
PART 3 EXECUTION
3.1 INSTALLATION
Installation, workmanship, fabrication, assembly, erection, examination, inspection, and testing must be in accordance with NFPA 13 , except as modified herein. Install piping straight and true to bear evenly on hangers and supports. Do not hang piping from plaster ceilings. Keep the interior and ends of new piping and existing piping affected by
SECTION 21 13 16.00 20 Page 6
Contractor's operations thoroughly cleaned of water and foreign matter.
Keep piping systems clean during installation by means of plugs or other approved methods. When work is not in progress, securely close open ends of piping to prevent entry of water and foreign matter. Inspect piping before placing into position. Provide Teflon pipe thread paste on male threads.
3.1.1 Electrical Work
Provide electrical work associated with this section under Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Provide fire alarm system under Section
28 31 76 INTERIOR FIRE AND MASS NOTIFICATION ALARM SYSTEM., ADDRESSABLE
Provide control and fire alarm wiring, including connections to fire alarm systems, under this section in accordance with NFPA 70 . Provide wiring in rigid metal conduit or intermediate metal conduit, except electrical metallic tubing conduit may be used in dry locations not enclosed in concrete or where not subject to mechanical damage.
3.1.2 Field Painting
Clean, prime, and paint new sprinkler system piping, valves, hangers, accessories, and miscellaneous metal work as specified in Section 09 90 00 PAINTS AND COATINGS. Exercise care to avoid painting sprinkler heads and operating devices.
3.2 FIELD QUALITY CONTROL
Perform test to determine compliance with the specified requirements in the presence of the Contracting Officer. Test, inspect, and approve piping before covering or concealing.
3.2.1 Preliminary Tests
Hydrostatically test each system at 50 psig above normal system static pressure or 200 psig , whichever is greater, for a 2-hour period with no leakage or reduction in pressure. Flush piping with potable water and air test each system in accordance with NFPA 13 . Piping above suspended ceilings must be tested, inspected, and approved before installation of ceilings. Test the alarms and other devices. Test the water flow alarms by flowing water through the inspector's test connection. Water must be delivered to the system test connection in not more than 60 seconds, starting at the normal air pressure on the system and at the time of a fully opened inspection test connection. When tests have been completed and corrections made, submit a signed and dated certificate, similar to that specified in NFPA 13 .
3.2.2 Formal Tests and Inspections
Do not submit a request for formal test and inspection until the preliminary test and corrections are completed and approved. Submit a written request for formal inspection at least 15 days prior to inspection date. An experienced technician regularly employed by the system installer must be present during the inspection. At this inspection, repeat any or all of the required tests as directed. Correct defects in work provided by the Contractor, and make additional tests until the systems comply with contract requirements. Furnish appliances, equipment, water, electricity, instruments, connecting devices, and personnel for the tests. The Government will furnish water for the tests. The MIDLANT Division, Naval Facilities Engineering Command, Fire Protection Engineer, SECTION 21 13 16.00 20 Page 7 will witness formal tests and approve systems before they are accepted.
-- End of Section --
SECTION 21 13 16.00 20 Page 8
SECTION 22 00 00
PLUMBING, GENERAL PURPOSE
11/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI 1010 (2002) Self-Contained, Mechanically Refrigerated Drinking-Water Coolers
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z21.10.1/CSA 4.1 (2017) Gas Water Heaters Vol. I, Storage Water Heaters with Input Ratings of 75,000 Btu Per Hour or Less
ANSI Z21.10.3/CSA 4.3 (2017) Gas-Fired Water Heaters Vol.III, Storage Water Heaters With Input Ratings Above 75,000 Btu Per Hour, Circulating and Instantaneous
ANSI Z21.22/CSA 4.4 (2015) Relief Valves for Hot Water Supply Systems
AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)
ASSE 1001 (2016) Performance Requirements for Atmospheric Type…