21_DENA_332037_-_EVC_Rehabilitation_Amendment_0004_0004.pdf

PDF 164 KB Posted

Attached to
DENA 332037 Eielson Roof Replacement Federal contract opportunity
Solicitation number
140P2026R0087
Issued by
Department of the Interior National Park Service National Office

About this file

This is Addendum #2 to the contract documents for DENA 332037, the Eielson Visitor Center Rehabilitation project located in Denali National Park, Alaska. The addendum, issued on September 18, 2026, amends the original contract documents and must be acknowledged by bidders on the Bid Form prior to bid opening.

The addendum contains four substantive changes to the contract documents. First, the submittal list is replaced with an updated version dated 2026-07-20. Second, specification section 26 05 19, 3.2.Q is modified to explicitly prohibit multi-wire branch circuits for new circuits. Third, General Sheet Note A on drawings E201/E202 is revised to establish conditions for reusing existing branch circuiting when light fixtures and control switches are replaced on a 1-to-1 basis, requiring NEC compliance through approved handle ties for adjacent circuit breakers if existing multi-wire circuits are encountered; for fixtures and switches not replaced on a 1-to-1 basis, branch circuiting must be removed and replaced to accommodate new locations. A fourth item (AD4.5) relating to drawings is referenced in the table but contains no specified changes. All other terms and conditions of the contract documents remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to DENA 332037 Eielson Roof Replacement, newest first.
File Type Posted
Sol_140P2026R0087_Amd_0011.pdf PDF
32_Finalized_Q_and_A_amendment_011_responses_0011.pdf PDF
Sol_140P2026R0087_Amd_0010.pdf PDF
Sol_140P2026R0087_Amd_0009.pdf PDF
31_Finalized_Q___A_for_DENA_Amendment_0009_0009.pdf PDF
30_01_50_00_Temporary_Facilities_and_Controls_0008_0008.pdf PDF
Sol_140P2026R0087_Amd_0008.pdf PDF
29_Amendment_Summary_0008_0008.pdf PDF
28_DENA_332037_EVC_Rehabilitation_Addendum_2R1_0007.pdf PDF
27_Finalized_Q___A_for_DENA_Amendment_0005_0007.pdf PDF
Sol_140P2026R0087_Amd_0007.pdf PDF
25_DENA_332037_-_Pictures_0007.pdf PDF
26_DENA_332037_Submittal_List_2026-07-20_R1_0007.pdf PDF
Sol_140P2026R0087_Amd_0006.pdf PDF
D01_Amendment_0006_DENA_Roof_and_Interior_Repair_0006.pdf PDF
Sol_140P2026R0087_Amd_0005.pdf PDF
Sol_140P2026R0087_Amd_0004.pdf PDF
23_Q_A_6_Submittal_List_2026-07-20_Amendment_0004_0004.xlsx XLSX spreadsheet
22_DENA_332037_Q_A_9_18_26_Amend_0004_0004.xlsx XLSX spreadsheet
Sol_140P2026R0087_Amd_0003.pdf PDF
12_07_52_16_SBS_Modified_Bituminous_Membrane_Roofing_-_Amendment_0003_0003.pdf PDF
07_01_26_01_Contract_Modification_Procedures_Pg_7_Amendment_0003_0003.pdf PDF
06_Specification_Index_-_Amendment_0003_0003.pdf PDF
13_12_36_00_Countertops_-_Amendment_0003_0003.pdf PDF
10_02_85_00_Microbial_Remediation_-_Amendment_0003_0003.pdf PDF
14_21_13_00_Fire_Suppression_Sprinkler_System_-_Amendment_0003_0003.pdf PDF
15_26_30_00_Facility_Electrical_Power_Generating__-_Amendment_0003_0003.pdf PDF
17_32_96_13_Groundwater_Transplanting_-_Amendment_0003_0003.pdf PDF
18_Contract_Price_Schedule_(Fields_Blank)_Amendment_0003_0003.xlsx XLSX spreadsheet
08_01_27_00_Definition_of_Contract_Line_Items_Amendment_0003_0003.pdf PDF
09_02_41_19_Selective_Demolition_Pg_1-3_Amednment_0003_0003.pdf PDF
11_05_50_00_Metal_Fabrications_-_Amendment_0003_0003.pdf PDF
16_31_20_00_Earth_Moving_-_Amendment_0003_0003.pdf PDF
19_DENA_332037_-_EVC_Rehabilitation_Addendum_01_-_Amendment_0003_0003.pdf PDF
20_Eielson_Visitor_Center_-_Fire_Sprinkler_As-Builts_-_Amendment_0003_0003.pdf PDF
Sol_140P2026R0087_Amd_0002.pdf PDF
Amendment_0002_0002.pdf PDF
Sol_140P2026R0087_Amd_0001.pdf PDF
DENA_332037_Final_Construction_Documents_Amendment_1_0001.pdf PDF
Amendment_1_DENA_332037_0001.pdf PDF
DENA_332037_As_Built_Drawings_0001.pdf PDF
Drawings_56-99.pdf PDF
1-55.pdf PDF
04_WD_AK20260001_May_17_2026.pdf PDF
05__Subcontracting_Percentage_Worksheet.pdf PDF
Sol_140P2026R0087.pdf PDF
B08_FINAL_Solicitation_updated_7_31_26.pdf PDF
03__Final__Submittal_List_2026-06-12.xlsx XLSX spreadsheet
01_DENA_332037_Final_Construction_Documents_07-20-2026.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design Alaska, Inc. Page 1 of 2

September 18, 2026

DENA 332037

Eielson Visitor Center Rehabilitation Denali National Park, Alaska

Re: Addendum #2

The Contract Documents for DENA 332037 Eielson Visitor Center Rehabilitation, Denali National Park, Alaska are amended as follows; all other terms and conditions remain unchanged. Bidders are required to acknowledge this addendum on the Bid Form, before the hour and date set for the bid opening.

ADDENDA No. 2

Item No. Reference Change

GENERAL

AD4.1 Submittal List REPLACE submittal list with accompanying submittal list dated 2026-07-20

SPECIFICATIONS

AD4.2 26 05 19, 3.2.Q CHANGE Sentence two to read:

"Multi-wire branch circuits shall not be provided for new circuits."

AD4.3 E201 / E202 CHANGE General Sheet Note A to read:

A. Where light fixtures and control switches are replaced on a 1-to-1 basis, the existing branch circuiting may be reused. If existing multi-wire circuits are encountered, the contractor shall ensure NEC compliance by provision of an approved handle tie to operate adjacent circuit breakers simultaneously, including any rearrangement of circuit breakers to ensure adjacency. For other lighting fixtures and switches that are not replaced on a 1-to-1 basis, remove and replace branch circuiting to accommodate new light fixtures and/or switch locations.

AD4.4

DENA 332037

Eielson Visitor Center Rehabilitation Denali National Park, Alaska Addendum #2

Design Alaska, Inc. Page 2 of 2

DRAWINGS

AD4.5

END OF ADDENDUM #2

File details come from the government source that posted it. Updated .