This is a Contract Modification Procedures section from the National Park Service for the Rehabilitation of the Eielson Visitor Center at Denali National Park and Preserve, Alaska, revised under Amendment 0003 dated September 11, 2026.

The document establishes procedures for estimating and pricing equipment costs and overhead and profit percentages for contract modifications. Equipment rate estimates must include all operating costs such as fuel, oil, lubrication, supplies, small tools, attachments, ground engaging components, tires, tracks, routine repairs and maintenance, depreciation, storage, insurance, and incidentals, with mobilization costs listed separately when applicable. Equipment rates should be estimated only for the duration the equipment will be utilized, and standby rates apply when equipment is not in use but maintained on site due to documented NPS delays or for up to five consecutive days if the equipment has been or will be used for modification work; after five days of non-use, equipment will not be compensable. All standby time requests must be justified, documented, and itemized separately, with timeframes estimated to reflect the lowest cost to the Government. Home Office Overhead and Profit (OH&P) shall be applied only to direct costs, with profit not applied to overhead and overhead not applied to profit. The total aggregate markup limit for Contractor and Subcontractors on modification work shall not exceed 25%, with the NPS bearing no responsibility for allocation of percentages between contractor and subcontractors at any tier.

View the file

Other files for this federal contract opportunity

Other files attached to DENA 332037 Eielson Roof Replacement, newest first.
File Type Posted
32_Finalized_Q_and_A_amendment_011_responses_0011.pdf PDF
Sol_140P2026R0087_Amd_0011.pdf PDF
Sol_140P2026R0087_Amd_0010.pdf PDF
Sol_140P2026R0087_Amd_0009.pdf PDF
31_Finalized_Q___A_for_DENA_Amendment_0009_0009.pdf PDF
30_01_50_00_Temporary_Facilities_and_Controls_0008_0008.pdf PDF
Sol_140P2026R0087_Amd_0008.pdf PDF
29_Amendment_Summary_0008_0008.pdf PDF
Sol_140P2026R0087_Amd_0007.pdf PDF
25_DENA_332037_-_Pictures_0007.pdf PDF
26_DENA_332037_Submittal_List_2026-07-20_R1_0007.pdf PDF
28_DENA_332037_EVC_Rehabilitation_Addendum_2R1_0007.pdf PDF
27_Finalized_Q___A_for_DENA_Amendment_0005_0007.pdf PDF
Sol_140P2026R0087_Amd_0006.pdf PDF
D01_Amendment_0006_DENA_Roof_and_Interior_Repair_0006.pdf PDF
Sol_140P2026R0087_Amd_0005.pdf PDF
21_DENA_332037_-_EVC_Rehabilitation_Amendment_0004_0004.pdf PDF
22_DENA_332037_Q_A_9_18_26_Amend_0004_0004.xlsx XLSX spreadsheet
Sol_140P2026R0087_Amd_0004.pdf PDF
23_Q_A_6_Submittal_List_2026-07-20_Amendment_0004_0004.xlsx XLSX spreadsheet
Sol_140P2026R0087_Amd_0003.pdf PDF
12_07_52_16_SBS_Modified_Bituminous_Membrane_Roofing_-_Amendment_0003_0003.pdf PDF
10_02_85_00_Microbial_Remediation_-_Amendment_0003_0003.pdf PDF
14_21_13_00_Fire_Suppression_Sprinkler_System_-_Amendment_0003_0003.pdf PDF
15_26_30_00_Facility_Electrical_Power_Generating__-_Amendment_0003_0003.pdf PDF
17_32_96_13_Groundwater_Transplanting_-_Amendment_0003_0003.pdf PDF
18_Contract_Price_Schedule_(Fields_Blank)_Amendment_0003_0003.xlsx XLSX spreadsheet
06_Specification_Index_-_Amendment_0003_0003.pdf PDF
13_12_36_00_Countertops_-_Amendment_0003_0003.pdf PDF
08_01_27_00_Definition_of_Contract_Line_Items_Amendment_0003_0003.pdf PDF
09_02_41_19_Selective_Demolition_Pg_1-3_Amednment_0003_0003.pdf PDF
11_05_50_00_Metal_Fabrications_-_Amendment_0003_0003.pdf PDF
16_31_20_00_Earth_Moving_-_Amendment_0003_0003.pdf PDF
19_DENA_332037_-_EVC_Rehabilitation_Addendum_01_-_Amendment_0003_0003.pdf PDF
20_Eielson_Visitor_Center_-_Fire_Sprinkler_As-Builts_-_Amendment_0003_0003.pdf PDF
Sol_140P2026R0087_Amd_0002.pdf PDF
Amendment_0002_0002.pdf PDF
Sol_140P2026R0087_Amd_0001.pdf PDF
DENA_332037_Final_Construction_Documents_Amendment_1_0001.pdf PDF
Amendment_1_DENA_332037_0001.pdf PDF
DENA_332037_As_Built_Drawings_0001.pdf PDF
Drawings_56-99.pdf PDF
1-55.pdf PDF
04_WD_AK20260001_May_17_2026.pdf PDF
05__Subcontracting_Percentage_Worksheet.pdf PDF
Sol_140P2026R0087.pdf PDF
B08_FINAL_Solicitation_updated_7_31_26.pdf PDF
03__Final__Submittal_List_2026-06-12.xlsx XLSX spreadsheet
01_DENA_332037_Final_Construction_Documents_07-20-2026.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL PARK SERVICE

REHABILITATION OF THE EIELSON VISITOR CENTER

DENALI NATIONAL PARK AND PRESERVE, ALASKA

SECTION 01 26 01

CONTRACT MODIFICATION PROCEDURES

Revised: Amendment 0003 – 9/11/2026

Design Alaska, Inc. 01 26 01- 7

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S.

Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only.

Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 15.

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.