This is a Final Construction Documents specification package for the rehabilitation of Kawuneeche Visitor Center (KVC) at Rocky Mountain National Park in Colorado (PMIS No. 326235). The project involves comprehensive rehabilitation of approximately 5,000 square feet of slab-on-grade wood-framed historic building consisting of three connected nodes: Administrative Wing, Visitor Center with exhibits and auditorium, and Comfort Station. Work includes installation of new electrical, plumbing, telecommunications, ventilation, climate control, fire suppression, and fire alarm systems while maintaining compliance with Secretary of Interior Standards for Historic Preservation. Specific work components include building envelope improvements with new insulation and thermally-broken windows, removal and salvage of historic wood-slat ceilings for system installation, new interior finishes, masonry cleaning and repointing, restoration of historic flat roof with EPDM roofing, site improvements for ADA compliance, parking lot repaving, and exterior component restoration including dark sky-compliant lighting. The contract includes temporary relocation facilities for building occupants, including visitor contact and office trailers with furnishings and utilities, and coordination with a separate exhibit fabrication contract.
The base contract is structured as a single lump-sum prime contract with four line items: (1) Rehab KVC Admin/Auditorium/Comfort Station; (2) Site Work; (3) Temporary Modular Visitor Contact, Office Trailers, and Furniture Move; and (4) Option 1 for Thermally Broken Steel Window Replacement. Contract modifications must follow detailed pricing requirements including itemized labor (by craft with Davis-Bacon compliance), materials with multiple quotes, and equipment rental at lowest documented rates. Home office overhead is capped at 12 percent and profit at 6 percent for contractor self-performed work, with combined markup limit of 25 percent. Extensive environmental and cultural resource protections are mandated including archeological monitoring, bird protection surveys, weed mitigation, equipment cleaning certification, snow management, and coordination with park operations. Contractor must obtain required permits including Colorado Discharge Permit System general permits for stormwater and dewatering, complete pre-construction documentation including quality control and waste management plans, and conduct weekly progress meetings. Final documents include project record drawings, operation and maintenance manuals, photo documentation meeting National Register Historic Places standards, and demonstration and training videos.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROMO 326235 TOC-1
REHABILITATE KAWUNEECHE VISITOR CENTER
ROCKY MOUNTAIN NATIONAL PARK, CO
PMIS NO. 326235
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
FINAL CONSTRUCTION DOCUMENTS
JANUARY 16, 2026
SEPTEMBER 4, 2026
ROMO 326235 TOC-2
TABLE OF CONTENTS
DIVISION 00
SEALS PAGE
DIVISION 01
01 11 00 SUMMARY OF WORK
01 26 01 CONTRACT MODIFICATION PROCEDURES
01 27 00 DEFINITION OF CONTRACT LINE ITEMS
01 31 00 PROJECT MANAGEMENT & COORDINATION
01 32 16 CONSTRUCTION SCHEDULE
01 32 33 PHOTO DOCUMENTATION
01 33 23 SUBMITTAL PROCEDURES
• SUBMITTAL LIST
01 35 13 ARCHEOLOGICAL PROTECTION
01 35 23 SAFETY REQUIREMENTS
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
• DAILY REPORT TEMPLATE
• INSPECTION CHECKLIST
• ACCESSIBILITY INSPECTION REPORT FORM
• STATEMENT OF STRUCTURAL TESTS AND SPECIAL INSPECTIONS
01 42 00 REFERENCE STANDARDS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 19.11 INDOOR AIR QUALITY MANAGEMENT
01 57 19.12 NOISE & ACOUSTICS MANAGEMENT
01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION (SWPP)
01 67 00 PRODUCT REQUIREMENTS
01 73 29 CUTTING AND PATCHING
01 73 40 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
• WASTE MANAGEMENT PLAN WORKSHEET
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
• CLOSEOUT AND OPERATIONS AND MAINTENANCE (O&M)
REQUIREMENTS
01 79 00 DEMONSTRATION & TRAINING
01 81 13 SUSTAINABLE DESIGN REQUIREMENTS FOR NON-LEED PROJECTS
01 91 14 TOTAL BUILDING COMMISSIONING
DIVISION 2
02 41 13 SELECTIVE SITE DEMOLITION
02 41 91 SELECTIVE HISTORIC DEMOLITION
02 50 10 EMPLOYEE OFFICE RELOCATION
02 81 01 OFF-SITE TRANSPORTATION AND DISPOSAL
02 82 13 ASBESTOS ABATEMENT
02 83 33 REMOVAL AND DISPOSAL OF MATERIAL CONTAINING LEAD
02 84 16 HANDLING OF LAMPS CONTAINING MERCURY
ROMO 326235 TOC-3
DIVISION 3
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 4
04 03 10 HISTORIC MASONRY CLEANING
04 03 42 HISTORIC STONE MASONRY REPAIR
DIVISION 5
05 12 00 STRUCTURAL STEEL FRAMING
05 52 13 PIPE AND TUBE RAILINGS
DIVISION 6
06 03 12 HISTORIC WOOD REPAIR
06 10 00 ROUGH CARPENTRY
06 16 00 SHEATHING
06 20 13 EXTERIOR FINISH CARPENTRY
06 40 23 INTERIOR ARCHITECTURAL WOODWORK
06 64 00 PLASTIC PANELING
DIVISION 7
07 21 00 THERMAL INSULATION
07 25 00 WEATHER BARRIERS
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING
07 62 00 SHEET METAL FLASHING AND TRIM
07 92 00 JOINT SEALANTS
DIVISION 8
08 03 14 HISTORIC TREATMENT OF WOOD DOORS
08 11 13 HOLLOW METAL DOORS AND FRAMES
08 14 16 FLUSH WOOD DOORS
08 31 13 ACCESS DOORS AND FRAMES
08 51 13 ALUMINUM WINDOWS
08 51 23.13 HOT ROLLED STEEL WINDOWS
08 71 00 DOOR HARDWARE
08 71 13 POWER DOOR OPERATORS
08 80 00 GLAZING
DIVISION 9
09 03 91 HISTORIC TREATMENT OF PLAIN PAINTING
09 29 00 GYPSUM BOARD
09 30 13 CERAMIC TILING
09 51 23 ACOUSTICAL TILE CEILINGS
09 65 13 RESILIENT BASE AND ACCESSORIES
09 65 43 LINOLEUM FLOORING
09 68 13 TILE CARPETING
09 84 33 SOUND-ABSORBING WALL UNITS
09 91 13 EXTERIOR PAINTING
09 91 24 INTERIOR PAINTING
09 93 01 STAINING AND TRANSPARENT FINISHING
ROMO 326235 TOC-4
DIVISION 10
10 14 23.16 ROOM-IDENTIFICATION PANEL SIGNAGE
10 21 00 HDPE TOILET COMPARTMENTS
10 26 00 WALL AND DOOR PROTECTION
10 28 00 TOILET ACCESSORIES
10 44 13 FIRE PROTECTION CABINETS
10 44 16 FIRE EXTINGUISHERS
10 81 19 RODENT AND BIRD CONTROL
DIVISION 12: FURNISHINGS
12 20 00 WINDOW TREATMENTS
12 32 13 MANUFACTURED WOOD-VENEER-FACED CASEWORK
12 36 61 SIMULATED STONE COUNTERTOPS
12 48 13 ENTRANCE FLOOR MATS AND FRAME
12 93 13 PICNIC TABLES
DIVISION 21: FIRE SUPPRESSION
21 00 00 FIRE SUPPRESSION BASIC REQUIREMENTS
21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION
21 08 00 COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
21 13 00 FIRE SUPPRESSION SPRINKLER SYSTEMS
21 13 19 FIRE SUPPRESSION PREACTION SPRINKLER SYSTEMS
DIVISION 22: PLUMBING
22 05 00 COMMON WORK RESULTS FOR PLUMBING
22 05 17 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
22 05 18 ESCUTCHEONS FOR PLUMBING PIPING
22 05 23.12 BALL VALVES FOR PLUMBING PIPING
22 05 23.14 CHECK VALVES FOR PLUMBING PIPING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 07 19 PLUMBING PIPING INSULATION
22 11 16 DOMESTIC WATER PIPING
22 11 19 DOMESTIC WATER PIPING SPECIALTIES
22 11 23.21 INLINE, DOMESTIC WATER PUMPS
22 13 16 SANITARY WASTE AND VENT PIPING
22 13 19 SANITARY WASTE PIPING SPECIALTIES
22 33 00 ELECTRIC, DOMESTIC WATER HEATERS
22 34 00 FUEL-FIRED, DOMESTIC WATER HEATERS
DIVISION 23: HEATING, VENTILATING, AND AIR CONDITIONING
23 01 30.52 EXISTING HVAC AIR DISTRIBUTION SYSTEM CLEANING
23 05 00 COMMON WORK RESULTS FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 DUCT INSULATION
23 07 19 HVAC PIPING INSULATION
23 23 00 REFRIGERANT PIPING
23 31 13 METAL DUCTS
23 33 00 AIR DUCT ACCESSORIES
23 34 16 CENTRIFUGAL HVAC FANS
23 37 13.23 REGISTERS AND GRILLES
23 54 16.13 GAS-FIRED FURNACES
ROMO 326235 TOC-5
23 81 26 SPLIT SYSTEM AIR-CONDITIONERS
23 82 39.19 WALL AND CEILING UNIT HEATERS
DIVISION 26: ELECTRICAL AND LIGHTING
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 05 44 SLEEVES AND SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS
26 09 23 LIGHTING CONTROL DEVICES
26 09 43 NETWORK LIGHTING CONTROLS
26 24 16 PANELBOARDS
26 27 13 ELECTRICITY METERING
26 27 26 WIRING DEVICES
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
26 43 13 TRANSIENT-VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL
POWER CIRCUITS
26 51 00 LIGHTING FIXTURES
DIVISION 27: COMMUNICATIONS
27 00 10 SUPPLEMENTAL REQUIREMENTS FOR COMMUNICATIONS
27 05 26 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
27 05 28 PATHWAYS FOR COMMUNICATIONS SYSTEMS
27 05 36 CABLE TRAY FOR COMMUNICATIONS SYSTEMS
27 05 44 SLEEVES AND SLEEVE SEALS FOR COMMUNICATIONS PATHWAYS AND
CABLING
27 05 53 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS
27 11 16 COMMUNICATIONS RACKS, FRAMES, AND ENCLOSURES
27 13 23 COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING
27 15 13 COMMUNICATIONS COPPER HORIZONTAL CABLING
27 41 00 AUDIO VIDEO SYSTEMS
DIVISION 28: ELECTRONIC SAFETY AND SECURITY
28 00 01 ELECTRONIC SAFETY BASIC REQUIREMENTS
28 00 10 SUPPLEMENTAL REQUIREMENTS FOR ELECTRONIC SAFETY & SECURITY
28 08 00 COMMISSIONING OF FIRE ALARM
28 13 00 ACCESS CONTROL SOFTWARE AND DATABASE MANAGEMENT
28 14 00 ACCESS CONTROL SYSTEM HARDWARE
28 16 00 INTRUSION DETECTION
28 20 00 VIDEO SURVEILLANCE
28 46 00 FIRE DETECTION AND ALARM
DIVISION 31: EARTHWORK
31 10 00 SITE CLEARING
31 20 00 EARTH MOVING
ROMO 326235 TOC-6
31 25 00 EROSION AND SEDIMENT CONTROL
DIVISION 32: EXTERIOR IMPROVEMENTS
32 12 16 ASPHALT PAVING
32 13 20 SITE CONCRETE
32 15 43 PERMEABLE AGGREGATE SURFACING
32 17 00 PAVING SPECIALTIES
32 31 13 GUARDRAIL FENCING
32 31 14 POST AND RAIL FENCE
32 32 00 BOULDER PLACEMENT
32 33 00 SITE FURNISHINGS
32 40 00 TREE AND VEGETATION RETENTION AND PROTECTION
32 92 00 REVEGETATION
DIVISION 33: UTILITIES
33 10 00 WATER UTILITIES
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE
APPENDIX
A - COLORADO CULTURAL RESOURCE SURVEY, ARCHITECTURAL INVENTORY FORM,
DETERMINATION OF ELIGIBILITY
B - HAZARDOUS MATERIALS SURVEY BY LANDMARK ENVIRONMENTAL, OCTOBER 2017
C - INTERPRETIVE DESIGN PACKAGE BY HARPER’S FERRY, SEPTEMBER 2023
D - TEMPORARY RELOCATION PLAN
E - MOCK-UP LIST
F – ORIGINAL AS-CONSTRUCTED DRAWINGS, DATED 1969 PROVIDED BY GOVERNMENT
ROMO 326235 Final Specifications
SEALS PAGE
Civil Engineer
Divisions 31-33
01 57 23
02 41 13
05 52 13
Structural
03 30 00
05 12 00
06 10 00
06 16 00
Architect
Divisions 4, 7-9, 10, 12 (except 10 81 19)
02 41 91
02 50 10
06 03 12
06 20 13
06 40 23
06 64 00
Mechanical and Plumbing Engineer
Divisions 22-23
Fire Protection Engineer
Division 21
Fire Alarm Engineer
28 00 01
28 08 00
28 46 00
1/16/2026
01/16/26
12 93 13 CO
LO
RADO LICENSED
PROFESSIONA L ENGIN
EE
R
KE
V I
N F
RA NC IS DOOLEY JR.
ROMO 326235 Final Specifications
Electrical Engineer
Division 26-27
28 00 10
28 13 00
28 14 00
28 16 00
28 20 00
Hazardous Materials
02 81 01
02 82 13
02 83 33
02 84 16
10 81 19
Landmark Environmental, Inc 1/8/2026
01/08/2026
ROMO - 326235 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of site.
6. Public use of site.
7. Government’s Occupancy Requirements.
8. Work Restrictions.
9. Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements
10. Special Construction Requirements.
11. Additional Compliance Requirements.
12. References.
13. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Rocky Mountain National Park, Grand Lake, Colorado.
B. The Work consists of the following:
1. Base Contract: The approximately 5,000 SF slab on grade wood-framed historic
Kawuneeche Visitor Center (KVC) shall be rehabilitated with new electrical, plumbing, telecommunications, ventilation and climate control systems, fire suppression, and fire alarm system. This building is eligible for listing on the National Register of Historic
Places as an example of the Mission 66 historic architecture. The Secretary of the Interior
Standards for the Treatment of Historic Properties has been integrated into the design and has been approved through compliance reviews. The building consists of three “nodes”, connected by both internal and external walkways. Node 1 is the Administrative Wing
(Admin. Wing) and houses offices and support spaces for park operations. Connected by an interior walkway is Node 2 - the Visitor Center - where exhibits, merchandising, and an auditorium are located. Node 3 – the Comfort Station - is connected via an exterior walkway and consists of a women’s restroom, men’s restroom, and utility/mechanical space.
Node 1: Building envelope at the Administrative Wing shall be improved with added insulation in the exterior walls and installation of new aluminum thermally-broken double-paned sliding windows to match the profile of the historic steel windows (Refer to Section
01 27 00 – Definition of Contract Line Items for option to replace windows with custom steel in lieu of aluminum). Ceiling finishes shall be removed for running of new systems, ROMO - 326235 01 11 00 - 2 and new ceiling insulation shall be installed to meet code requirements. Office spaces shall be slightly altered with select new walls and doors. Existing staff restrooms shall be reconfigured and updated, and a new kitchenette shall be added in the break room to improve building accessibility. New interior finishes shall be installed throughout. Wood surfaces shall be repainted or refinished, and masonry surfaces cleaned and repointed.
Node 2: The historic, character-defining wood-slat ceiling finish shall be cataloged, removed and salvaged for running of new systems above, and new ceiling insulation shall be installed to meet code requirements. The historic wood ceiling shall be reinstalled and new interior finishes shall be installed throughout. Wood surfaces shall be refinished. UV film product shall be applied to the existing large storefront windows to reduce solar heat gain in the space. An interior partition with glazing, wood framing, and swinging door shall be installed to separate the Exhibit Hall and Wilderness Desk. New conduit is anticipated to run additional utilities across the space below the existing concrete floor.
Custom exhibit installation by others is to be coordinated with this project.
Node 3 – Both restrooms of the Comfort Station will receive new plumbing fixtures and interior finishes and accessories to comply with ABAAS. The existing gable roof shall be removed and the historic flat roof restored with EPDM roofing and tapered insulation.
Exterior improvements include select regrading for ABAAS compliance, parking lot repaving to accommodate utility improvements and parking accommodations, and improvements to site gathering/seating areas/wayfinding. Restoration of exterior components of the building includes paint refinishing and masonry cleaning. Historic pole light fixtures shall be rehabilitated and altered to comply with Dark Sky requirements.
Full antifreeze fire suppression, fire alarm, electrical and data upgrades shall be provided throughout the building. New cooling equipment will be installed for dedicated server room only.
Base bid also includes provisions for the temporary relocation of building occupants, including trailer and furniture rental, two one container rentals, installation of temporary utilities, and the actual packing and moving of furniture out of the building and then back into the building at the close of the project and unpacking. Select office furniture will be utilized in temporary facilities for NPS use during construction.
Temporary facilities shall be provided by the Contractor which include Visitor Contact trailer for merchandising, select exhibits, and reservation desk, and office trailers for NPS staff with restrooms. Visitor Contact trailer will be located in the Harbison Meadows
Picnic Site parking lot where indicated on Drawings and will include one portable toilet and 10 8’x10’ storage shed. Office trailers will be located across Trail Ridge Road to the east where indicated on Drawings. Furnishing of temporary trailers shall be provided by
Contractor as outlined in Section 02 50 10 – Employee Office Relocation.
C. Project shall be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase though sequencing of temporary facilities will be required.
ROMO - 326235 01 11 00 - 3
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations shall be conducted simultaneously with work under this Contract.
1. Interpretive Media Fabrication and Installation: A separate contract will be awarded for fabrication and installation of the exhibit design as detailed in September 2023 design package. Close coordination of power, data, and attachments to historic building material between projects shall be required. Refer to Appendix for exhibit design drawings (not in contract).
1.5 GOVERNMENT-FURNISHED MATERIALS
A. Delivery and Storage
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.
3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.
4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into the
Work.
B. Government-Furnished Products:
1. Server and server racks for installation by Contractor in coordination with Contracting
Officer to ensure no lag time between switching of server locations from temporary to final.
2. Seed for revegetation and regrowth at the construction site as well as Harbison Meadows and temporary staff trailer locations.
3. Plant stock for revegetation and regrowth at the construction site as well as Harbison
Meadows and temporary staff trailer locations.
4. Appliances and FFE to be installed by Government after Substantial Completion.
5. Log benches for installation by Contractor.
ROMO - 326235 01 11 00 - 4
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits of disturbance to be clearly marked visually by the contractor. Markings shall be painted, wooden survey stakes at least 2 ft visible above grade on an interval of 20 feet with stakes at each corner or as needed to clearly delineate the limits. Limit markings to be approved by the Contracting Officer prior to start of work. Requests for approvals by
Contracting Officer is required 7 days prior to work. Contractor to remove stakes at substantial completion.
2. Limit site disturbance, including earthwork and clearing of vegetation, as shown on drawings. Notify Contracting Officer if conflicts or discrepancies exist.
3. To minimize impact to the park’s natural and cultural environment, use lowest impact methodologies for trench excavation.
4. To the extent possible, equipment shall be kept on hardened surfaces.
B. Staging Areas and Storage of Materials:
1. Confine storage of materials to staging area indicated on drawings and approved by
Contracting Officer.
2. Locate staging and stockpiling areas in previously disturbed areas to the extent possible and as approved by Contracting Officer. Return all staging and stockpiling areas to pre-construction conditions following construction.
3. When possible, place soils on asphalt, paved areas, planks or tarps to reduce ground and vegetation disturbance.
C. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Construction Camp: Establishment of a camp within the park will not be permitted.
E. Construction Trailer: Establishment of a construction trailer will be permitted where indicated on drawings. Provide utilities as specified in Division 1 Section “Temporary Facilities and Controls”.
Keep trailer area neat and clean and return site to previous condition at completion of work.
F. Construction Equipment:
1. Construction Equipment shall not be stored along open roadways overnight, without prior approval of the Contracting Officer.
2. Construction equipment shall not be permitted to idle for long periods of time.
G. Hauling Restrictions: Comply with all NPS and DOT load restrictions in the hauling of materials.
Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Chief of Visitor and Resource Protection. Information
ROMO - 326235 01 11 00 - 5
regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.7 PUBLIC USE OF SITE
A. The buildings will be closed to the public during construction.
B. Public access of an existing trail, as indicated on the drawings, shall be maintained throughout construction. When horse traffic is present on the trail, equipment shall be turned off until horses are out of sight.
C. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Road closures will be permitted, when required, upon specific approval of Contracting Officer.
D. Harbison Ditch Riders (ditch maintenance crew): The Harbison Ditch runs through the project area. Contractor will assure that NPS and Harbison Ditch owner/operator has access to the ditch at all times.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 6 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.
1. No work shall be performed beyond normal working hours, on weekends or federal holidays without prior approval of the Contracting Officer minimum 48 hours in advance.
B. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
1. The utilities shown in the drawings are indicated in accordance with available records. All utilities may not be shown and those which are shown may not be shown accurately. The contractor shall be responsible for field locating all utilities including public utilities and
NPS owned utilities to determine exact locations, elevations, and sizes. Contractor shall be responsible for locating and preventing damage to known or marked utilities.
2. Contractor shall be responsible for calling the Colorado 811, (800) 922-1987 a minimum three working days in advance of digging. Contractor may be required to use additional methods for utility locations, such as electromagnetic utility locating, acoustic pipe locating, ground penetrating radar or potholing.
a. Public Utilities include:
1) Primary Power – Mountain Park Electric
2) Gas Lines – Xcel Energy
3) Telephone – Comcast and Vonage
4) Cable/Internet – Comcast, Century Link, Exede, Direct TV, HughesNet.
5) Sewer outside the Park – Three Lakes Water and Sanitation District
b. NPS Utilities include:
ROMO - 326235 01 11 00 - 6
1) Water within park boundary
2) Sewer within park boundary
3) Telephone within park boundary
4) Cable within park boundary
5) Fiber Optics within park boundary
3. Damage to Fiber Utilities:
a. If damage occurs, notify utility owner and repair or coordinate repairs to utility at no additional expense to the Government.
b. Any severing or damage of the fiber optics cabling shall be repaired by a reputable fiber optics company using the fusion splicing method at the expense of the
Contractor. Line test results shall be provided for all damaged fibers once splicing is completed with each fiber having no loss greater than 0.1 Db
4. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
a. Notify Contracting Officer not less than three days in advance of proposed utility interruptions.
b. Do not proceed with utility interruptions without Contracting Officer’s written permission.
c. Hours for Utility Shutdowns: 8 hours maximum shutdown.
d. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the government
C. Nonsmoking Building: Smoking is not permitted within buildings or within 20 feet of entrances, operable windows, or outdoor air intakes. Designated paved areas to be proposed by contractor for CO approval.
D. Fire Restrictions: The contractor shall be responsible for keeping informed and informing all on-site staff regarding current fire restrictions at the park. This may include an outdoor smoking prohibition if fire conditions warrant.
E. Hot Work Permits: Hot work permits are required for any equipment or work that is capable of producing a spark.
1. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of the National Park Service Authority
Having Jurisdiction.
2. Hot work permits, approved through the Contracting Officer by the park’s structural fire coordinator, are required for any hot work. Submittal of permit request is required no less than one week in advance of the work. Do not proceed until notified by the Contracting
Officer that the permit has been approved.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES
AND IMPROVEMENTS
A. As required by FAR Clause 52.236-9:
ROMO - 326235 01 11 00 - 7
1. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The
Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, the Contracting Officer will provide guidance for repair or restoration.
2. The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site, and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
B. Provide temporary barriers to protect existing trees and plants and root zones.
C. Do not drive under tree crowns or on tree roots.
D. Provide temporary barriers to protect existing cultural features, as identified by the Contracting
Officer or their representative. This includes the Harbison Ditch, which will still need to be accessed by the ditch rider.
E. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
F. Do not fasten ropes, cables, or guy wires to existing trees.
G. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
H. No storage, parking, or excavation shall be allowed within the drip line of protected trees without approval from the Contracting Officer.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. Weed Mitigation
1. All borrow, road base, aggregate, crusher fines, bedding, topsoil, hay bales and other fill materials brought into Rocky Mountain National Park and used in this project shall be certified weed free. Without certification, materials will come from commercial sources that have been approved by the Contracting Officer, prior to materials entering the Park.
2. Equipment Cleaning:
a. Clean vehicles and construction equipment prior to entry into the Park to minimize the potential for introduction and/or proliferation of invasive non-native weeds through project actions. The contractor is required to wash equipment, with
ROMO - 326235 01 11 00 - 8
emphasis on undercarriages, with a high-pressure spray prior to transporting such equipment to Rocky Mountain National Park.
b. All vehicles and construction equipment entering Rocky Mountain National Park shall be inspected and approved by the Contracting Officer prior to entering the park.
c. Equipment not deemed clean by the Contracting Officer will not be allowed to enter the park. The contractor remains liable for additional transportation fees incurred when equipment fails inspection.
B. Avoid Soil Compaction
1. Avoid compaction from heavy equipment to surrounding area by keeping equipment inside the limits of disturbance.
2. Compacted soils must be ripped or decompacted post construction to enable vegetation.
3. All disturbances must be returned to grade and any tracks from equipment must be raked out.
C. Bird Protection Acts
1. In order to protect birds under the Migratory Bird Treaty Act (MBTA, 16 U.S.C. 703–
712), all construction work performed between February 1 and August 31 requires a site survey, to be performed by a trained park employee. The survey must be completed within two weeks prior to the start of construction. Additional surveys will be required when all activities are not completed within the two-week timeframe from the date of the survey.
The Contractor will be required to avoid cutting down trees with active nests, however, other work would be permitted to continue. Some species may also require a buffer around active nests where work cannot occur. Request site survey a minimum of one month prior to work.
2. In order to protect eagles under the Bald and Golden Eagle Protection Act (BGEPA, 16
U.S.C. 668-668c), all construction work requires a site survey, to be performed by a trained park employee. The survey must be completed within two weeks prior to the start of construction. If an active bald eagle or golden eagle nest is found, the Contractor may have to work in areas that are 100 meters or more away from the active nest. If avoiding work in the 100-meter area around the active nest is not possible, the Contractor may be required to postpone work in the area until a repeat survey indicates no impact to nesting eagles. If an active or inactive nest is found, the Contractor will be required to avoid cutting down trees with nests. Request site survey a minimum of one month prior to work.
D. Wildlife
1. Do not feed or disturb wildlife within the Park boundaries. Do not approach or remain within 25 yards of any wildlife.
2. All construction personnel working in the field must follow park food storage regulations, 36 CFR 2.10. All food, garbage, toiletry, or other bear attractants must not be left unattended for any length of time.
a. These items shall be stored inside vehicle trunks.
b. In vehicles with no trunk, place these items as low in the vehicle compartment as possible and covered from sight, with all windows and doors closed and locked.
3. On-site construction personnel are required to report all bear and moose sightings in the work area to the CO.
ROMO - 326235 01 11 00 - 9
E. Archeological Monitoring
1. The Contractor is required to provide archeological monitoring for all excavation activities, as specified in Section 01 35 13 “Archeological Protection.”
F. Work Within Rocky Mountain National Park and Coordination with Park Employees
1. Contractors will coordinate with park staff to reduce disruption to normal park activities.
2. Construction workers and job superintendent will be required to attend park resource orientation session lasting no more than two hours to learn about the special sensitivity of park values, regulations, and appropriate litter and trash control measures. The Contracting
Officer or a representative will coordinate orientation session with the NPS Cultural
Resource Specialist and NPS Natural Resource Specialist to develop resource awareness.
Work schedule, equipment to be used on project and resource protection plan will be discussed. This training session shall occur prior to the start of work and will be repeated for changes of key personnel.
3. The National Park Service will ensure that all contractors and subcontractors are informed of the penalties for illegally collecting artifacts or intentionally damaging archeological and/or natural sites and/or historic properties. Contractors and subcontractors will also be instructed on procedures to follow, in case previously unknown archeological and/or natural resources are uncovered during construction.
4. Trail Ridge Road (US 34) is closed to through travel during the winter. Locations of closures will vary based on weather and road conditions. It is generally closed at the first significant snowfall (usually mid to late October) and reopened through plowing by late
May. Check https://www.nps.gov/romo for up to date information.
5. If construction vehicles will be traveling to the project from the east side of the park via
Trail Ridge Road, pilot cars are required for tractor trailers from the switchbacks of Trail
Ridge Road on the west side to Hidden Valley on the east side. This must be planned in advance with the CO.
G. Blasting is not permitted in this project.
H. Snow management will be required in this project. Contractor shall assume responsibility for snow management within the limits of disturbance unless otherwise agreed upon by the
Contracting Officer. Temporary facilities (both Visitor Contact and NPS Offices) will be maintained by NPS, except for clearing of snow from temporary structure roofs. Contractor responsible for roof snow removal.
I. Harbison Ditch Riders
1. Harbison Ditch runs through the project area. Contractor will assure NPS and Harbison
Ditch owner/operator has access to the ditch at all times. The ditch routinely overtops in the project area at the grate near the comfort station.
J. Existing FFE
1. Packing, moving, and storage of existing FFE within the building shall be completed by
Contractor prior to start of work. Contractor shall coordinate with Contracting Officer regarding furniture to be removed and stored versus removed and disposed of.
K. Server
1. The existing server in Room 110 will remain during construction. Protection of server including dedicated ventilation and dust mitigation are required. Coordination with CO of https://www.nps.gov/romo
ROMO - 326235 01 11 00 - 10
installation of new server racks is to be conducted so as to limit downtime when moving existing server to new location.
L. Weather Station
1. The existing weather station is to be connected to the Visitor Center through new conduit provided by the Contractor. Contractor shall coordinate this work closely with CO and
NOAA so as to limit downtime.
M. Exhibit Installation
1. A separate contract will be awarded for fabrication and installation of the exhibit design as detailed in September 2023 design package. Close coordination of power, data, and attachments to historic building material between projects shall be required. Refer to
Appendix for exhibit design drawings (not in contract).
1.11 ADDITIONAL COMPLIANCE REQUIREMENTS
A. The work of this project has been reviewed and approved by the State Historic Preservation Office for compliance with the requirements of Section 106 of the National Historic Preservation Act.
To minimize impact to the cultural resources, work shall be performed as specified in Section 01
35 13 “Archeological Protection.”, Section 01 35 91 “Historic Preservation Treatment Plan”, and applicable specifications within Divisions 2-33.
1.12 REFERENCES
A. Industry Standards.
1. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.
2. Publication Dates: Comply with standards in effect as of the date of the Contract
Documents unless otherwise indicated.
1.13 ADDITIONAL REPORTS
A. Colorado Cultural Resource Survey, Architectural Inventory Form, Determination of Eligibility
(See Appendix A)
B. Hazardous Material Survey Report, 2017 has been prepared by Landmark Environmental, Inc.
(See Appendix B)
C. Original building as-constructed drawings, dated 1969 provided by the Government (See
Appendix D) has been included for reference and contextual understanding only.
1. The accuracy, completeness, or current applicability of these drawings has not been validated. Conditions depicted may be incomplete, outdated, or inconsistent with existing conditions due to undocumented alterations, deterioration, code-driven modifications, or changes over time.
ROMO - 326235 01 11 00 - 11
2. Inclusion of these drawings in the Contract Documents does not constitute a representation or warranty, express or implied, of their accuracy or suitability for construction, pricing, coordination, or code compliance. The Contractor shall not rely exclusively on these drawings and shall verify all existing conditions through field investigation, measurements, and coordination with other Contract Documents prior to construction.
3. Any discrepancies between the historic as-constructed drawings and observed field conditions shall be promptly reported to the CO.
D. A copy of the reports is available to all plan holders within this package.
E. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
ROMO 326235 01 26 01 - 1
091025 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating
General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
ROMO 326235 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General
Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week, and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens include insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
ROMO 326235 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General
Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Consent of Surety:
1. When any contract is modified, the Contractor shall provide the consent of surety if-
a. An additional bond is obtained from other than the original surety;
b. No additional bond is required and
1) The modification is for new work beyond the scope of the original contract;
or
2) The modification does not change the contract scope but changes the contract price (upward or downward) by more than 25 percent or $50,000;
or
c. Consent of surety is required for a novation agreement.
2. When a contract for which performance or payment is secured by any of the types of security listed in FAR 28.204 is modified as described in paragraph (a) of this subsection, no consent of surety is required.
3. Agencies shall use Standard Form 1414, Consent of Surety, for all types of contracts.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
http://en.wikipedia.org/wiki/Employee
ROMO 326235 01 26 01 - 4
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or the contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the
Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a
Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurance, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
ROMO 326235 01 26 01 - 5
1. The equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense
Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army
Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on the job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………12%
Profit……………… 6%
ROMO 326235 01 26 01 - 6
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 26 01
ROMO - 326235 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 1, Rehab KVC Admin/Auditorium/Comfort Station
1. This item consists of all work associated with rehabilitation of the Admin/Auditorium/Comfort Station:
a. Restoration of exterior components of the building includes paint refinishing and masonry cleaning. Existing gable roof at Comfort Station to be removed and replaced with a flat roof.