ROMO 326235 Rehabilitate Kawuneeche Visitor Center
Solicitation number
140P2026R0057
Issued by

About this file

This is Amendment 0005 to a federal solicitation for the rehabilitation of the Kawuneeche Visitor Center at Rocky Mountain National Park (ROMO). The amendment, effective July 30, 2026, adds three updated documents to the bid package: Drawings, Specifications, and a Questions and Answers document. All other terms, conditions, clauses, and provisions remain unchanged. Offerors must acknowledge receipt of this amendment prior to the bid opening hour and date by completing the required form sections and returning them, or by submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.

The primary document included is a comprehensive Questions and Answers record containing 191 industry questions and corresponding government responses addressing the project scope. Key elements covered include: contractor responsibilities for archaeological services and ARPA permitting (with associated timelines included in the performance period); staff relocation and temporary facility management requirements; hazardous materials abatement scope determination based on the hazmat survey and demolition plans; historic preservation and masonry cleaning standards requiring mockup approval; server relocation coordination responsibilities divided between the contractor and NPS/DOI IT; asbestos abatement quantities treated as estimates with additional ACM addressed through differing site conditions procedures; and various technical specifications clarifications for HVAC, plumbing, electrical, fire suppression, structural, and technology systems. The amendment also addresses procurement clarifications, including editable Word document formats for project experience and past performance forms, extension of acceptable project experience timeframe to 10 years, and confirmation that small business prime offerors receive maximum credit for Factor 6 without separate submission requirements.

View the file

Other files

File Type Posted
B09_ROMO_KVC_326235_Final_CD_Specifications_Bid_Revisions_Part3_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Drawing_Set_Bid_Revisions_Part2_0005.pdf PDF
B09_QR_Tracker_ROMO_326235_9_4_26_0005.pdf PDF
Sol_140P2026R0057_Amd_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Specifications_Bid_Revisions_Part2_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Drawing_Set_Bid_Revisions_Part3_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Drawing_Set_Bid_Revisions_Part1_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Specifications_Bid_Revisions_Part1_0005.pdf PDF
B09_ROMO_KVC_326235_Final_CD_Drawing_Set_Bid_Revisions_Part4_0005.pdf PDF
B09_P2026R0057_SF30_QA_and_Clauses_8_26_0004.pdf PDF
Sol_140P2026R0057_Amd_0004.pdf PDF
BaselineScheduleReviewChecklist_Form_10-22-18_v508_0003.docx DOCX document
2nd_Site_Visit_Sign_in_Sheet_0003.pdf PDF
Sol_140P2026R0057_Amd_0003.pdf PDF
B09_P2026R0057_SF30_QA_and_Clauses_8_21_0003.pdf PDF
B09_QR_Tracker_ROMO_326235_0003.pdf PDF
B08_Solit_PSP_Vol_II_Deliverables_LmtOnSubconRpt_REQD_0003.xlsx XLSX spreadsheet
Sol_140P2026R0057_Amd_0002.pdf PDF
B09_P2026R0057_SF30_QA_and_Clauses_8_19_0002.pdf PDF
B09_Attachment_5_Solit_PSP_Vol_I_Exp_REQD_0002.docx DOCX document
Contact_Procedures_Reminder_0002.docx DOCX document
B09_Attachment_6_Solit_PSP_Vol_I_PastPerf_REQD_0002.docx DOCX document
B09_QR_Tracker_ROMO_326235_0002.pdf PDF
B11_PreProposal_Conf_Slides_ROMO_325250_0001.pptx PPTX presentation
B09_Amendment_1_ROMO_KVC_326235_ContractPriceSchedule_Rev_1_8-5-26_0001.xlsx XLSX spreadsheet
B09_P2026R0057_SF30_QA_and_Clauses_8_13_0001.pdf PDF
Sol_140P2026R0057_Amd_0001.pdf PDF
B09_QR_Tracker_ROMO_326235_0001.pdf PDF
ROMO_326235__-_Virtual_PreBid_Conference_Transcription_0001.docx DOCX document
Prebid_sign_in_sheet_0001.pdf PDF
B09_Amendment_1_What_Evaluators_Will_Ask_for_Each_Factor_0001.docx DOCX document
Virtual_sign_in_sheet_0001.pdf PDF
B02_Attatchment_2_26_0330_-_ROMO_KVC_326235_Final_CD_Drawing_Set_Part4.pdf PDF
B02_Attatchment_2_26_0330_-_ROMO_KVC_326235_Final_CD_Drawing_Set_Part1.pdf PDF
B01_Attatchment_1_ROMO_KVC_326235_Final_CD_Specifications_update_Part1.pdf PDF
B08_Attachment_10_ROMO_KVC_326235_CD_ContractPriceSchedule_BLANK.xlsx XLSX spreadsheet
Sol_140P2026R0057.pdf PDF
B08_Attachment_8_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attachment_6_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Attachment_7_Solit_PSP_Vol_II_BidBond.pdf PDF
B02_Attatchment_2_26_0330_-_ROMO_KVC_326235_Final_CD_Drawing_Set_Part2.pdf PDF
B02_Attatchment_2_26_0330_-_ROMO_KVC_326235_Final_CD_Drawing_Set_Part3.pdf PDF
B01_Attatchment_1_ROMO_KVC_326235_Final_CD_Specifications_update_Part2.pdf PDF
B01_Attatchment_1_ROMO_KVC_326235_Final_CD_Specifications_update_Part3.pdf PDF
B08_Attachment_9_Solit_PSP_Vol_II_SubKPlan.pdf PDF
B08_Attachment_5_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attachment_3_Wage_Determination.pdf PDF
B08_Attachment_4_Construction_Contract_Administration.pdf PDF
B08_P2026R0057_SF1442_and_Clauses_7_30_26.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Timothy Burger

See continuation page

NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287

PDS

140P2026R0057

07/30/2026

07/30/2026

1 11

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P2026R0057/0005

Rocky Mountain National Park, Rehabilitate

Kawuneeche Visitor Center, ROMO 326235

1. Add updated Drawings.

2. Add updated Specifications.

3. Add updated Questions and Answers document.

All other Terms and Conditions / Clauses and

Provisions remain unchanged.

No. Industry Question Government Response Amendment

1 Will the Exhibits be contracted prior to completion of the project and will coordination be required? The exhibits will be installed after this project is complete. Exhibit team will do a site visit to confirm dimensions and installation during the construction period.

Amendment 0001, Issued

8/12/2026.

2 Has a Hazardous material survey been completed for the buildings? Yes, see appendix to the specifications.

Amendment 0001, Issued

8/12/2026.

3 What is the contractor responsibility for the staff relocation? Please refer to division 1 specifications.

Amendment 0001, Issued

8/12/2026.

4 Is there a Planned suspension of work for winter months? Please refer to division 1 specifications. This project will not have a winter shutdown.

Amendment 0001, Issued

8/12/2026.

5 Is this project subject to the new Revolutionary FAR Overhaul? Yes, this is subject to the new FAR Overhaul.

Amendment 0001, Issued

8/12/2026.

Additionally, given the nature of the rehabilitation work and the importance of understanding the existing conditions, we would like to request the opportunity to conduct an in-person walk-through of the Visitor Center and surrounding project site prior to the proposal due date. If an additional site visit can be accommodated, please let us know if there are any requirements or restrictions for scheduling the visit.

A 2nd site visit will be held on August 20, 2026 at 11am. We will not give the presentation at this meeting.

Amendment 0001, Issued

8/12/2026.

Sheet C0005 Temporary Facilities plan identifies trailers and storage within the construction area. Please confirm if these are for contractor use or NPS Use.

These trailers are for the relocated NPS staff. Contractor and contractor provided construction trailers will need to be accommodated within the limits of construction at the Kawuneeche Visitor Center shown on C004.

Amendment 0001, Issued 8/12/2026.

8 For bidding purposes can information be provided on what furniture and equipment will ned to be relocated for the temporary facilities.

See Appendix D to specifications. Office equipment (provided by NPS) is expected to be limited to typical equipment such as computers, printers, and task lighting. Additionally, please assume 20 furniture pieces (desk, bookshelf, etc.) that certain employees may elect to use during the interim period in the trailers.

Amendment 0001, Issued 8/12/2026.

9 Also Is all of this FF&E currently in the visitor center or is another location housing FF&E?

FFE for temporary visitor center and NPS office trailers will be provided by the contractor, see 01 50 00, 02 50 10 and Appendix D - Temporary Relocation Plan to the specifications.

Amendment 0001, Issued 8/12/2026.

10 Will there be another site visit with full access to the main building including offices for trade partners? A 2nd site visit will be held on August 20, 2026 at 11am. We will not give the presentation at this meeting.

Amendment 0002, Issued

8/19/2026.

11 Is there a specific asbestos abatement scope of work or is the GC to decide what is to be abated based on the demolition plans? Contractor to determine based on Hazardous Material Survey (Appendix B to specifications) and demo plans.

Amendment 0002, Issued

8/19/2026.

Will the Park Service provide the Archeological Monitor during Excavation activities, or will the Contractor be responsible for providing this service to the project?

The contractor shall provide professional archeological services that includes archeological monitoring to observe and document all excavation and ground disturbing activities. See 01 35 13.

Amendment 0002, Issued 8/19/2026.

13 The specification appears to the a performance specification. There are no products or manufactures specifically specified. Can this be confirmed please? We have a combination of specifications (performance, prescriptive, and refence) but mostly performance.

Amendment 0002, Issued

8/19/2026.

Is the contractor going to be responsible for writing and providing the Historic Preservation Treatment Plan or will the Architect of Record be providing that document?

Contractor's Historic Preservation Specialist to write.

Amendment 0002, Issued

8/19/2026.

15 Is the Park Service providing the Construction Permit? Or is the contractor expected to procure the permit from the Local AHJ. Grand County? Contractor to provide, see 01 31 00.

Amendment 0002, Issued

8/19/2026.

Will the Park Service provide the contractor with the environmental training video required for site personnel training or does the contractor have to develop this video themselves?

Contractor to provide.

Amendment 0002, Issued

8/19/2026.

17 Can the Park Service provide additional space for project trailers at the temporary housing location where the Visitor Center Temporary offices ? No.

Amendment 0002, Issued

8/19/2026.

Spec section references a trailer for the Contracting Officers Field Office – will this be required? If so, where will this be located? Is this a single wide or double wide trailer, spec states minimum 300 SF but doesn’t state maximum

Single wide trailer, needs to be located within the limits of construction. Given the paving, we did not locate the trailer as it may need to be moved. We would not require something larger than 300 SF.

Amendment 0002, Issued 8/19/2026.

19 How many offices are needed in the temporary trailers for the staff relocation? Please see Appendix D.

Amendment 0002, Issued

8/19/2026.

20 Is there a quantity of temporary furniture? How many offices/what furniture is needed? Please see Appendix D.

Amendment 0002, Issued

8/19/2026.

Is there a floor plan that can be provided for the temporary trailers? It looks like there is one office in the visitor’s station and the rest is open space please advise.

That is correct.

Amendment 0002, Issued

8/19/2026.

22 Is the contractor responsible for any cleaning or services of the temp trailers once the staff begin using it? See 01 50 00 for weekly cleaning requirements.

Amendment 0002, Issued

8/19/2026.

23 Is there a quantity or idea of what furniture will want to be kept/relocated? Or should we anticipate moving all existing furniture from the building See Appendix D to specifications. Office equipment (provided by NPS) is expected to be limited to typical equipment such as computers, printers, and task lighting. Additionally, please assume 20 furniture pieces (desk, bookshelf, etc.) that certain employees may elect to use during the interim period in the trailers.

Amendment 0002, Issued 8/19/2026.

How many personnel are required for the prime contractor? A Superintendent, Quality Control Manager, and Site Safety? Can any of these positions act in dual capacity as 1 person?

•Project Manager (can combine with safety or historic preservaƟon) •Superintendent •On-site Quality Control Specialist (can combine with safety or historic preservaƟon) •On-site Safety Specialist (can be combined with other role) •Historic PreservaƟon Treatment Specialist/Firm (see specific requirement in the specificaƟon, this can combine other role)

Amendment 0002, Issued 8/19/2026.

Will the parks service maintain snow removal on trail ridge road for the duration of the project? Is the contractor is only responsible for any snow removal inside the project site? (visitors center parking lot)

See 01 11 00 1.10 H Snow management. Yes, snow removal is responsibility of contractor within limits of construction. The NPS will maintain highway 34.

Please not that the Highway 34 (Trail Ridge Road) from the Colorado River Trailhead over the pass is closed from around October to May. Temporary facilities (both Visitor Contact and NPS Offices) will be maintained by NPS.

Amendment 0002, Issued 8/19/2026.

Section L In Instructions for the Submission of Offers and Other Information, Factor 2 – Key Personnel Experience calls for the following resumes to be submitted: Project Manager, Superintendent, On-Site Quality Control, On-Site Safety Specialist (Can be combined with other role) and Historic Preservation Treatment Specialist. This section also states in the first paragraph “Submit resumes for key personnel as identified in Section H of this solicitation and listed below. All personnel proposed are subject to substitution requirements contained in this solicitation.” Then in Section H under Special Requirement 5: Key Personnel it only lists the following positions: Project Manager, Job Site Superintendent, Job Site Quality Control, Job Site Safety Manager. There is no reference to the Historic Preservation Treatment Specialist in Section H. Can you please confirm if we are to sub a resume for the Historic Preservation Treatment Specialist and indicate if this person needs to be onsite any time work is taking place? Additionally, as is pertains to Key Personnel Experience, there does not appear to be any key requirements, such as education (i.e. Degree in Construction Management, Engineering, etc), time in role (i.e. min 5 years in role), or special certifications (i.e. OSHA 30, First Aid/CPR, USACE QCM Certificate, LEED, etc). Can the NPS please provide these requirements if they exist?

The Historic Preservation Specialist is defined in 01 35 91 as: “An experienced firm with the required certifications and training that can demonstrate through past performance that they are qualified to perform this work.” The specifications do not require an on-site presence and mention 10 years of relevant experience for supervisory roles. This can also be achieved by an individual on the contractors staff with experience. This can be a shared duty, please submit a resume (firm or individual).

For Key Personnel Experience, experience requirements are included in the specifications. You are current that it does not have specific educational, etc.

requirements. •Project Manager (can combine with safety or historic preservaƟon)

•Superintendent •On-site Quality Control Specialist (can combine with safety or historic preservaƟon) •On-site Safety Specialist (can be combined with other role) •Historic PreservaƟon Treatment Specialist/Firm (see specific requirement in the specificaƟon, this can combine other role)

Amendment 0002, Issued 8/19/2026.

Section L In Instructions for the Submission of Offers and Other Information, Factor 3 – Project Experience states “Submit the attached "Project Experience Form” addressing specific experience aspects within the form for up to 4 relevant projects completed in the last 7 years. With this having very stringent requirements for Historic renovation Past Performance and being set-a-side for TSB, would the NPS please consider extending the Project Experience completion in the last 7 years to 10 years?

10 years is acceptable, but more recent will be rated more favorable.

Amendment 0002, Issued

8/19/2026.

RFP 140P2026R0057 - ROMO-326235

Kauwaneeche Visitor Center

In the File labeled B08_P2026R0057_SF1442_and_Clauses_7_30_26, page 62 of the PDF, FAR Clause 52.232-38 Submission of Electronic Funds Transfer Information with Offer (JUL 2023) it states “The offeror shall provide, with its offer, the following information that is required to make payment by electronic funds transfer (EFT) under any contract that results from this solicitation.” Then has 7 individual bullets of information we are to provide with our offer, to include, The name, address, and 9-digit Routing Transit Number of the offeror’s financial agent. & The offeror’s account number and the type of account (checking, savings, or lockbox). This is very unusual for us to provide this information with our offer and we always see it being submitted only after award. We are also concerned about transmitting this information via a non-secured portal or email. Was this FAR clause inserted by mistake and would the DOI/NPS allow for the offerors to omit this information from our proposals and submit only if awarded the contract?

Offerors may include routing information and submission of electronic funds at award.

Amendment 0002, Issued

8/19/2026.

Factor 4 – Past Performance requires offerors to submit the attached Past Performance Questionnaire, B08_Attachment_6_Solit_PSP_Vol_I_PastPerf_REQD.pdf. The rating fields displaying “Choose an item” do not appear to function in the provided PDF.

Please confirm whether evaluators may manually enter the applicable rating in each field.

An editable Word document will be uploaded in Amendment 2 Amendment 0002, Issued

8/19/2026.

Factor 3 – Project Experience requires offerors to submit the attached “Project Experience Form,” B08_Attachment_5_Solit_PSP_Vol_I_Exp_REQD. The provided PDF format offers limited space for complete responses and may create formatting constraints. Please confirm whether the Government can provide the Project Experience Form in an editable Word format to allow offerors to respond to the requested information accurately and completely.

An editable Word document will be uploaded in Amendment 2 Amendment 0002, Issued

8/19/2026.

31 Questions are in regard to the revegetation spec (32 92 00). Will the required seed mix for revegetation be provided? Yes, the seed mix will be provided by the government.

Amendment 0002, Issued

8/19/2026.

Questions are in regard to the revegetation spec (32 92 00). Will the forest litter be provided by NPS? Or can the forest litter be gathered from the surrounding area by the contractor?

Forest litter can be collected by the contractor in the area.

Amendment 0002, Issued

8/19/2026.

The contract documents reference a project DDC system in Section 01 50 00 and a building automation system in Section 01 91 14. However, Division 23 does not include a DDC/BAS specification, and M600/M700 indicate standalone programmable thermostats and Honeywell JADE W7220 economizer/DCV controls. Please confirm whether any HVAC equipment is required to be connected to a central DDC/BAS. If so, please identify whether the BAS is existing or new, the BAS manufacturer/system, required DDC controllers, network architecture, point requirements, and required integration scope.

The design intent was always to provide standalone thermostat controls for the new systems—no central controls system. So, the notes/description of the system controls intent in the mechanical drawings and Div 23 specs is correct.

Amendment 0003, Issued 8/21/2026.

B09_Amendment_1_What_Evaluators_Will_Ask_for_Each_Factor_0001 document – Factor 5 – Schedule bullet 2 states that “Is the schedule in accordance with the Baseline Schedule Review Checklist included in Section J.” However, this document does not appear to be present in Section J of the RFP. Please provide the schedule review checklist Attachment 10.

The Baseline Schedule Review Checklist has been added to Section J as Attachment 11. Offerors shall prepare their proposed baseline schedule in accordance with this checklist.

Amendment 0003, Issued 8/21/2026.

Factor 6 Small Business Participation - Please confirm whether small business Offerors are required to submit anything for Factor 6 – Small Business Participation. If so, please identify the specific information, or confirm if documentation is not required the small business prime offerors receive maximum credit.

Small business prime Offerors will receive the maximum score for Factor 6 and do not need to submit separate Small Business Participation documentation.

Amendment 0003, Issued

8/21/2026.

Business & Price Proposal states: “SUBCONTRACTING PERCENTAGE WORKSHEET: Complete and submit the attached ‘Report on Limitation on Subcontracting’ form. The form itself requests input of amounts paid; however, for solicitation purposes, input projected amounts based on your proposed pricing and that of your anticipated Subcontractors. Refer to Clause” However, the sentence ends at “Refer to Clause” without identifying the applicable clause. In addition, Section J does not identify a “Report on Limitation on Subcontracting” or Subcontracting Percentage Worksheet among the listed attachments. Section J lists Attachments 1 through 10, including the Volume II Subcontracting Plan as Attachment 9, but no Subcontracting Percentage Worksheet. Section M further states: “h. SUBCONTRACTING PERCENTAGE WORKSHEET (SET-ASIDE): This worksheet will be reviewed for completeness and correlation to proposed pricing.” Please confirm whether small business Offerors are required to submit the Subcontracting Percentage Worksheet / “Report on Limitation on Subcontracting” form. If required, please provide the referenced form and identify the applicable clause referenced in Section L.

As this procurement is a Total Small Business Set-Aside, all Offerors are required to submit the “Report on Limitations on Subcontracting” form (Subcontracting Percentage Worksheet) with their Volume II – Business & Price Proposal. The applicable clause is FAR 52.219-14, Limitations on Subcontracting, and the form has now been added to Section J as Attachment 12. Offerors shall input projected amounts based on their proposed pricing and anticipated subcontractors.

Amendment 0003, Issued 8/21/2026.

Requirement 6 lists the KEY Trades as Mason, Mechanical. Electrical and other. Section L Factor 4 and Section M define Key Trade Subcontractors requiring signed LOCs as carpentry, mechanical, plumbing and concrete, no mason. Is a masonry LOC required and what is other?

The Key Trades requiring a Letter of Commitment are Carpentry, Mechanical, Plumbing, and Concrete Amendment 0003, Issued

8/21/2026.

We are asking for a bid date extension. The only site visit that subs attended was held on 8-20-2026 and as you can see from this list not a single subcontractor ask any questions to us as there was not enough time form site visit date until question due date.

The Question Due Date is extended until End of Day on Wednesday, August 26. The proposal Due Date remains August 31.

Amendment 0003, Issued

8/21/2026.

Proposal Submission: Please confirm whether proposals are to be submitted electronically only, or if a hard copy is also required. If both electronic and hard-copy submissions are required, please provide the required format, number of copies, and delivery instructions for the hard-copy submission.

No hard copies - Refer to Section L.

Amendment 0004, Issued

8/26/2026.

40 Note 8.06 on A201 says to block off mechanical vent at interior. Is there scope for the exterior at this location or is it to remain as is?

Exterior vent/louver is to remain. Keynote 08.06 requires the existing mechanical vent opening to be blocked at the interior with new mineral-wool insulation and new GWB finish. No exterior infill or removal is required.

Amendment 0004, Issued 8/26/2026.

41 Will an updated asbestos reinspection and sampling results be issued prior to proposal due date?

Section 02 82 13, Paragraph 1.1.E states that a Colorado Certified Asbestos Building Inspector will conduct a re-inspection and sample as needed because the last inspection occurred in 2017. The intent of this section is for the Contractor to retain the Colorado Certified Asbestos Building Inspector and abate as required.

Amendment 0004, Issued 8/26/2026.

Please identify any mandatory, proprietary or preferred NPS service providers that must be used or coordinated with for fire alarm monitoring, security/access control, fiber-optic service, network systems, server migration or related technology systems, and provide applicable contact information.

The division 27 and 28 scope did not capture any integrator requirements. NPS to confirm if any preferred providers are required. Alarm Specialist for Fire and security, access controls managed in-house by NPS IT, server migration is in-house IT staff, Fiber network is NPS / Internet is NPS

Amendment 0005, Issued 9/4/2026.

Please clarify the required manufacturer/product for the architectural wood casework. The specifications identify material, construction, veneer, and finish requirements but do not identify a manufacturer or approved manufacturer list

No proprietary manufacturer is required. Provide manufactured wood-veneer-faced casework complying with Section 12 32 13, the indicated configuration on A102/A610, AWI requirements, and the specified materials/finish. Product data, shop drawings, and samples are required for review.

Amendment 0004, Issued 8/26/2026.

44 Please clarify the required reference for matching the cabinet / casework stain to adjacent wood trim.

Casework stain is to custom-match the adjacent existing wood trim in the Break Room/Admin Wing. Section 12 32 13 specifies White Maple veneer with stain to match adjacent wood trim; Section 09 93 01 requires custom stain matching, samples, and mockups, with final approval by the Contracting Officer.

Amendment 0004, Issued 8/26/2026.

45 Please confirm if there are any additional insurance requirements outside of general liability.

The solicitation requires liability insurance in accordance with 1452.228-70. Minimum required limits are: $100,000 each person, $500,000 each occurrence, $1,000,000 property damage. These are the only insurance limits specified in the solicitation. Additional insurance types (auto liability, workers’ compensation, employer’s liability) are not separately listed in the solicitation and are therefore governed by state law and standard industry practice, but must be sufficient for safe performance of the work.

Amendment 0004, Issued 8/26/2026.

46 Is the projector a true 4K resolution or emulated 4K. There is a cost difference between the two True 4k Amendment 0004, Issued

8/26/2026.

47 Is there an equipment list for AV scope Div 27 41? This would help for an apples-to-apples comparison when looking at other bids. There is an extensive equipment list/schedule in the AV specification 274100 depicting the basis of design equipment.

Amendment 0004, Issued

8/26/2026.

Spec 096543: The resilient flooring called out is calling for sheet flooring but the material spec'd call out only comes in tiles and does not get heat welded like in the specs. Please clarify the style and color of LVT required for the job.

Provide LCT-1 as SHEET linoleum flooring, Basis of Design: Forbo Marmoleum Sheet, color T3717 Moon Rock, with heat-welded seams. The 50 cm x 50 cm size stated in Section 09 65 43 is not applicable and should be deleted.

Amendment 0004, Issued 8/26/2026.

49 Can you confirm that ALL floor substrate beneath existing flow finishes is concrete per Note 8 on A520?

For bidding, the Contract Documents include removal of all existing floor finishes to the concrete slab-on-grade and preparation for the new finish.

Contractor remains responsible for field verification of existing conditions. This intent was guided by NPS-provided as-builts of the building from 1960s and subsequent additions.

Amendment 0004, Issued 8/26/2026.

The asbestos portion of the specification refers to sections of the building by era of construction. Is there a map of the construction years for the buildings that can be used to line up the areas?

Use the construction chronology shown on G002: original KVC construction 1968-1969, Auditorium addition 1989, and Comfort Station addition 1999. The asbestos specification's references to the '1963 construction era' do not match the architectural record and should be corrected. The 2005 office-bathroom renovation referenced in the hazardous-material documents is a later interior renovation, not one of the principal building

Amendment 0004, Issued 8/26/2026.

Is there a comprehensive pre-demolition asbestos inspection report for the project? The information provide with the construction documents appears to be insufficient. The Colorado Department of Public Health & Environment (CDPHE) requires a comprehensive pre-demolition asbestos inspection report before any demolition activities.

The bid documents include the 2017 hazardous-material survey in Appendix B and Section 02 82 13 establishes known and presumed ACM. They do not include the updated comprehensive pre-demolition re-inspection identified in §1.1.E. The intent of is for the Contractor to retain the Colorado Certified Asbestos Building Inspector and abate as required.

Amendment 0004, Issued 8/26/2026.

The table for Egress Component Widths Per IBC 1005.3.2 on G003 Code Analysis indicates a reduced egress capacity factor of 0.15 inches per occupant. Can this be revised to the standard factor of 0.20 inches per occupant? Based on the occupant load and egress capacity provided, it does not appear that the additional capacity from using the reduced factor is needed. Leaving the 0.15 factor on the drawings may cause the AHJ to require a voice evacuation system. Please confirm if the drawings can be revised to use the standard 0.20 factor. If the 0.15 factor must remain, please confirm wheter a voice evacuation system will be required.

Revise the egress-width factor on G003 from 0.15 inch/occupant to 0.20 inch/occupant for doors/corridors. The project does not need the reduced factor for capacity. The revised factor does not change the adequacy of the indicated egress widths. No voice-evacuation system is intended solely as a consequence of egress-width sizing.

Amendment 0004, Issued 8/26/2026.

Demolition - No floor demo is noted in the demo drawings. What are the existing flooring types throughout the buildings that are to be demoed?

All existing floor finishes are to be removed to the concrete slab-on-grade per A520 General Note 8. Existing finishes vary and include flooring identified by the hazardous-material survey, including 9x9 resilient floor tile/mastic in portions of the building. Contractor shall coordinate demolition with Appendix B, Section 02 82 13, and pre-bid walkthrough observations.

Amendment 0004, Issued 8/26/2026.

54 Demolition - what is the construction of the existing demising wall in the Comfort Station that is to be demoed?

The concealed existing wall construction is not positively documented by this design team. As-built information provided by NPS indicates a 2x8 wall at 16 O.C. Contractor is to field verify existing construction.

Amendment 0004, Issued 8/26/2026.

55 Demolition - what is the construction of the existing sink walls in the Confort Station that are to be demoed?

The existing sink wall construction is not positively documented by this design team. As-built information provided by NPS does not clearly indicate this wall construction beyond the ceramic tile and cementious backer board. A 1x8 wall "cap" is identified. Contractor is to field verify

Amendment 0004, Issued 8/26/2026.

Demolition - Keynote 02.57 on A202, Visitor Center North Building Elevation, what is the extent of paint removal requried from the building foundation?

Keynote 02.57 applies to ALL exposed concrete foundation shown at the Visitor Center north elevation. Remove paint from the full exposed face of the concrete foundation in that elevation/work area; do not remove material below grade.

Amendment 0004, Issued 8/26/2026.

Lightning Protection System - Detail 1/A602 shows new LPS downleads running through the new furring walls and out through the existing building foundations?

Yes; where shown as concealed, route the new downlead within the new furring wall and out through the existing foundation, coordinated with Structural and Electrical. Existing foundation is to remain except for the required penetration.

Amendment 0004, Issued 8/26/2026.

58 Electrical - Drawing E203 shows a Keynote 1 and Keynote 2 on the plan , though no Keynote Legend?

Please see below for the missing keynotes. These will be added to the drawings in a future issuance.

1) CONTRACTOR SHALL LOCATE REMOTE TEST SWITCH IN ACCESSIBLE LOCATION NEAR INVERTER.

2) EC SHALL LOCATE REMOTE LIGHTING CONTROLLER FOR EXTERIOR LIGHTING POLES UPSTREAM OF THE CIRCUIT, IN THIS ROOM NEAR THE PANEL. EXISTING WIRING SHALL BE REUSED, AND SPLICES MADE AS NECESSARY TO INTEGRATE THE LIGHTING CONTROLLER.

Amendment 0004, Issued 8/26/2026.

59 Is there a specified BAS manufacturer? The intent is to provide standalone thermostat controls for the new systems—no central controls system/BAS.

Amendment 0004, Issued

8/26/2026.

The interior finishes plan on A520 does not list a wall base for Rm 115 Mech/ Elec. Does this room have existing wall base that is to remain? If not, should wall base be added in this location? And if so, please specify the type.

No wall base is required in Room 115 Mechanical/Electrical.

Amendment 0004, Issued

8/26/2026.

61 Please confirm locations where wood trim is to be removed and reinstalled. Drawings are not clear.

Wood trim removal/reinstallation is limited to locations specifically tagged on the demolition/new-work drawings. Keynote 02.32 on AD02 identifies historic wood trim to be carefully removed and salvaged; A102 Keynotes 09.06 and 09.07 identify salvaged wall-base trim and salvaged door trim to be installed at new locations. Other existing trim is to remain/protect unless specifically noted or required to be removed to facilitate the new work.

Amendment 0004, Issued 8/26/2026.

Confirm that a Commercial General Liability policy with $1,000,000 Each Occurrence / $2,000,000 Aggregate (with a Per-Project Aggregate endorsement) satisfies the split limits listed in the clause.

A Commercial General Liability policy providing $1,000,000 per occurrence and $2,000,000 aggregate , including a per-project aggregate endorsement , satisfies and exceeds the minimum insurance requirements listed in 1452.228-70. These levels are acceptable to the Government.

Amendment 0004, Issued 8/26/2026.

Confirm if standard limits of $1,000,000 Combined Single Limit for Commercial Auto and Statutory Workers' Compensation / $1,000,000 Employer's Liability are required for this solicitation.

The solicitation does not specify limits for Commercial Auto, Workers’ Compensation, or Employer’s Liability. Contractors shall comply with Colorado statutory requirements for workers’ compensation and must carry Commercial Auto and Employer’s Liability insurance limits adequate for safe performance of the work. Standard federal construction contract limits, such as $1,000,000 Combined Single Limit Auto Liability , statutory Workers’ Compensation, and $1,000,000 Employer’s Liability, are acceptable to the Government.

Amendment 0004, Issued 8/26/2026.

64 Please confirm the doorway of Office 112 is the only location where salvaged wood frame is to be reinstalled. (09.07 - A102) That is the design intent.

Amendment 0004, Issued

8/26/2026.

65 Please confirm where wood trim (09.07 - A102) is to be relocated from. Is this just both sides of the single wall between office 122 and 123?

Salvaged wood trim is to come from the locations tagged 02.32 on AD02 and be reinstalled at locations tagged 09.06/09.07 on A102. The intent is not limited solely to both sides of the wall between Offices 122 and 123; follow all keyed locations.

Amendment 0004, Issued 8/26/2026.

66 Please confirm if historic wood trim to be removed and relocated from detail 02.32 on AD02 is in reference to the door frames.

Keynote 02.32 refers to historic wood trim at the keyed locations, including door trim where the keynote is placed at door openings. Salvaged door trim is reinstalled where A102 is tagged 09.07; salvaged wall-base trim is reinstalled where tagged 09.06.

Amendment 0004, Issued 8/26/2026.

Please clarify wall assembly types to be installed for all four restrooms. Documents clarify removal of finishes down to framing, but do not clarify a) any wall types in RR 112 and 113 and b) 2 of 4 walls in both RRs at comfort station..

Where existing restroom framing remains, a new full wall assembly is not required: remove existing finishes to framing, then provide new CTBB behind ceramic wall tile per A520/G005. New partitions are to use the wall types specifically tagged on A102/A104 and detailed on G005. Existing framing is to remain unless demolition drawings indicate removal.

Amendment 0004, Issued 8/26/2026.

68 Please confirm material specs for existing wood trim. 06.21 on A102 calls for patch to match existing. Specs are not clear.

Patch material is to match the existing adjacent wood trim in species, grade, graining, texture, profile, and finish. Where exterior trim is affected by downspout removal under Keynote 06.21, provide repair/replacement in kind and finish to match adjacent. Contractor is responsible for verifying existing material to

Amendment 0004, Issued 8/26/2026.

69 Please confirm specs for existing wd wall base trim per 09.11 A102; 09.11 on A103 New wood wall base under Keynote 09.11 shall comply with Section 06 40 23: Premium-grade standing/running trim; match adjacent existing trim in species, grade, graining, texture, and profile; transparent finish to match adjacent unless the drawings indicate opaque finish.

Amendment 0004, Issued 8/26/2026.

Please confirm location and specs for 12.05 on A102. Note calls out A610 but it's unclear what is being referenced. Is the note applicable to the project?

Keynote 12.05 is not applicable; keynotes 06.12, 06.23, 06.24 replaced 12.05.

Amendment 0004, Issued

8/26/2026.

71 Please confirm specs of wd material exterior of building so it can be patched per 06.19 on A202 Patch the same material as the receiving exterior wood element. A520 identifies T1-11 plywood siding at exterior walls/upper fascia and Douglas Fir at lower fascia, soffits, beams, mullions, and columns. Match existing material, profile, texture, and finish in kind at each Keynote 06.19 location.

Amendment 0004, Issued 8/26/2026.

Site Lighting Wiring: Please confirm whether the existing site lighting raceways and wiring are to be reused. If only the wiring is to be reused, please clarify the requirements for the existing raceways.

Site lighting wiring and conduit shall be reused. Only the lamps of the historic site lights are to be replaced.

Amendment 0004, Issued

8/26/2026.

Lightning Protection: Please confirm whether the lightning protection system is required to be certified upon completion. If so, please provide the applicable certification/testing requirements.

The lightning protection system note on the cover sheet E000 and the Division 264113 specifications call for an Underwriter's Laboratories listed Master C Label for the system, requiring the installed system to be inspected and certified.

Amendment 0004, Issued 8/26/2026.

EV Charger Breaker: Please confirm the electrical requirements for the selected EV charger. Based on the current equipment selection, a minimum 50A, 2-pole breaker will be required. Please confirm this is acceptable.

Basis of design in the drawings is a Blink IQ 200 series or approved equal. The connection shall be 40A/2P breaker with 2#6, 1#8G, in 1-1/4" conduit with an extra (1) 1-1/4" conduit for future connection as described in keynote #2 on sheet E002.

Amendment 0004, Issued 8/26/2026.

Main Disconnect: Please confirm the location of the building main disconnect. Is the main disconnect located on the exterior of the building upstream of the service taps?

The existing building main disconnect is shown on sheet E002 next to the utility transformer, upstream of the existing bussed gutter on the exterior of the building.

Amendment 0004, Issued 8/26/2026.

Temporary Metering: Please confirm whether 30-day temporary metering is required for the project. If so, please provide the applicable metering requirements.

30-day metering is not required for this project.

Amendment 0004, Issued

8/26/2026.

77 Plumbing Fixtures: Please confirm whether plumbing fixtures are required to be touchless/automatic.

The water closet and urinal flush valves are intended to be sensor type automatic (battery powered) flush valves. Lavatory faucet is intended to be metering type, not sensor/automatic. Other fixtures are intended to be manually operated.

Amendment 0004, Issued 8/26/2026.

Server Room Condensate: The split-system HVAC unit serving the server room does not appear to indicate a condensate drain/piping connection. Please confirm the required method for condensate disposal.

Refer to enlarged view plan 1/M-401, condensate drainage from AC-1 shown to route around mechanical/electrical room 115 (to avoid conflict with electrical/communications equipment) and drain into floor drain within Mech/Elec 115.

Amendment 0004, Issued 8/26/2026.

Nesting: Please confirm whether there are any existing or anticipated bird nesting restrictions or other nesting-related requirements that need to be considered during construction.

See 01 11 00 1.10 C. The concern would be for Bald or Golden Eagle nests in the area, which are uncommon in this busier area.

Amendment 0005, Issued

9/4/2026.

The existing gas vault located on the south side of the Admin Building appears to be abandoned. Please clarify whether the project requires any work, modifications, or other scope associated with this vault.

The existing vault shall remain in place. No work, modifications, removal, or other project scope associated with the existing gas vault is required.

Amendment 0004, Issued

8/26/2026.

Section L, Factor 5 requires the proposed construction schedule to comply with the Baseline Schedule Review Checklist included in Section J.

The checklist does not appear to be identified in the Section J attachment list. Please provide the applicable Baseline Schedule Review Checklist and confirm whether it is required to be submitted with the proposal.

Can be found here: https://www.nps.gov/dscw/precon_act114.htm Amendment 0005, Issued

9/4/2026.

SF 1442, Block 11 requires the Contractor to begin performance within 10 calendar days after receipt of Notice to Proceed and complete within 548 calendar days. Section H, Special Requirement 1 states that the Contractor shall commence work within 548 calendar days and complete within 548 calendar days. Please confirm that the required commencement period is 10 calendar days after NTP and that the total contract duration is 548 calendar days.

The required commencement period is 10 calendar days after the Contractor receives the Notice to Proceed, as stated in SF 1442, Block 11. The total contract duration is 548 calendar days. The reference in Section H indicating the Contractor shall “commence work within 548 calendar days” is a clerical error; the correct commencement requirement remains 10 days after NTP and the required completion period remains 548 calendar days.

Amendment 0004, Issued 8/26/2026.

Archaeological Services / ARPA Permit Responsibility and Timing Amendment 0002, Government Response No. 12, confirms that the Contractor shall provide professional archaeological services, including archaeological monitoring of excavation and ground-disturbing activities in accordance with Section 01 35 13.

Section 01 35 13 also identifies permitting requirements associated with archaeological activities.

Please confirm:

1. Whether the Contractor is responsible for obtaining the required ARPA permit associated with the Contractor-provided archaeological monitoring services;

2. Whether the anticipated permitting duration is included within the Contract performance period; and

3. Whether mobilization and non-ground-disturbing construction activities may proceed following Notice to Proceed while the ARPA permit is being processed, provided no excavation or other ground-disturbing activities requiring archaeological monitoring are performed.

1. Yes, the contractor is responsible for getting the APRA permit

2. Yes, it is included in the Period of Performance. The NPS may be able to provide monitoring services for the two temporary trailers at the housing area is this work happens before the ARPA permit is in place. The permitting should be started as soon as possible after award and is not tied to the period of performance.

3. The ARPA permit would only impact ground disturbing activities.

Amendment 0005, Issued 9/4/2026.

Server Relocation / NPS-DOI IT Responsibility Factor 1 requires the Contractor to describe a server-relocation strategy while maintaining Park operations and network connectivity. The Contract Documents identify Contractor-installed telecommunications infrastructure associated with Server Room 116 and identify certain active components as Owner equipment.

To establish the appropriate relocation, temporary-service and cutover approach, please clarify the division of responsibility between the Contractor and NPS/DOI IT personnel for the following activities:

1. Shutdown and startup of active NPS server/network equipment;

2. Physical relocation of active Owner equipment;

3. Disconnect and reconnection of Owner switches, UPS and other active/headend equipment;

4. Fiber and data disconnect, cutover and reconnection;

5. Network configuration, programming and IP addressing;

6. Testing and commissioning of the completed network;

7. Authorization to return the systems to service; and

8. Provision and configuration of temporary connectivity necessary to maintain Park operations during relocation.

Please also identify any maximum allowable outage duration and required advance notification period associated with planned network/server outages

1. NPS Responsibility

2. NPS Responsibility

3. NPS Responsibility

4. Contractor Responsibility

5. NPS Responsibility

6. NPS Responsibility

7. NPS Responsibility

8. NPS Responsibility

Coordinate with Contracting Officer for outage maximums.

A telecom transition document was provided on 11.25.2025 to NPS. This document should be included with bid documents.

Amendment 0004, Issued 8/26/2026.

Historic Wood-Slat Ceiling / Existing Material Unsuitable for Reinstallation The Contract Documents require the historic wood-slat ceiling to be documented/cataloged, carefully removed, protected, stored and reinstalled. Amendment 0002, Government Responses Nos. 14 and 26, further confirm that the Contractor's Historic Preservation Treatment Specialist/Firm is responsible for preparation of the Historic Preservation Treatment Plan.

During removal, individual historic ceiling components may be discovered to be deteriorated, damaged or otherwise unsuitable for reinstallation.

Please clarify:

1. Who has final authority to determine whether an existing historic ceiling component is suitable for reuse, repairable, or requires replacement;

2. Whether the Contractor's Historic Preservation Treatment Specialist is to document the condition and submit a recommended disposition to NPS for review/approval;

3. The required replacement standard where NPS determines that an original component cannot be reused, including required matching of species, dimensions/profile, texture, finish and/or other historic characteristics; and

4. Whether replacement material requires NPS review/approval of samples or mockups prior to procurement and installation.

1. The Contracting Officer has final approval of reuse, repair, or replacement.

2. The Contractor's Historic Preservation Treatment Specialist shall document the condition of salvaged ceiling components and submit a recommended disposition to the Contracting Officer.

3. A105 directs the Contractor to assume 5% replacement boards and requires replacements to match existing in species, grade, size, and finish.

4. Replacement material/finish is subject to the required samples/mockups and CO approval.

Amendment 0004, Issued 8/26/2026.

Historic Ceiling / Concealed Conditions and Design Responsibility The Contract Documents require removal, cataloging, protection and reinstallation of historic ceiling materials while coordinating new mechanical, electrical, fire-protection, fire-alarm and technology systems within and above the affected historic areas. The demolition documents also require field verification of concealed existing conditions.

Amendment 0002, Government Response No. 13, confirms that the Contract Documents include a combination of performance, prescriptive and reference specifications, with the majority being performance specifications.

Where previously concealed existing framing, historic construction or structural conditions conflict with the indicated new work and cannot be resolved through normal trade coordination without modifying an existing historic or structural assembly, please confirm that:

1. The Contractor shall document the concealed condition and notify the Contracting Officer prior to modifying the affected historic or structural assembly;

2. NPS review/approval is required before altering historic fabric beyond the work specifically indicated in the Contract Documents; and

3. Engineering or redesign of existing historic or structural assemblies necessitated by previously concealed conditions will be provided by the Government's design team unless such delegated-design responsibility is expressly assigned to the Contractor elsewhere in the Contract Documents.

1. Confirmed. Contractor shall document concealed conditions and notify the Contracting Officer before modifying historic fabric or structural assemblies beyond the indicated Work.

2. NPS approval is required before such alteration.

3. Engineering/redesign caused by previously concealed conditions remains with the Government design team unless the Contract Documents expressly assign a delegated-design requirement to the Contractor.

Amendment 0004, Issued 8/26/2026.

Hazardous Materials / Unsampled Existing Materials Within Demolition Scope Amendment 0002, Government Response No. 11, states that the Contractor is to determine the asbestos-abatement scope based upon the Hazardous Material Survey contained in Appendix B and the demolition plans.

For proposal and pricing purposes, please confirm that:

1. The Contractor's base proposal abatement scope is to be established from regulated hazardous materials identified in Appendix B within areas indicated for disturbance or demolition in the Contract Documents; and

2. Existing materials encountered within the required demolition limits that were not sampled or characterized in Appendix B and are subsequently determined during construction to contain regulated hazardous materials will be addressed in accordance with the applicable Contract provisions governing unforeseen/differing site conditions and changes.

Please refer to previous abatement question responses Amendment 0004, Issued

8/26/2026.

Historic Masonry Cleaning / Mockup and Acceptance Criteria I would add this one back into the final package.

The Contract Documents require cleaning of existing historic masonry as part of the preservation work.

To establish the required means, methods and acceptance standard, please confirm whether a cleaning mockup/test area is required prior to proceeding with production cleaning.

If required, please identify or confirm:

1. Required…