DLA Aviation Operations Center, Phase II, Defense Supply Center Richmond (DSCR) (Amendments: 1, 2, 3, 5, 6, and 7)
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W91235620R2005
- Agency
-
ENDIST Norfolk
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Y1AA Construction Of Office Buildings
- Place of performance
- Richmond Va Usa
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks design-build construction services for Phase II of the Defense Logistics Agency Aviation Operations Center located at the Defense Supply Center Richmond site in Virginia. The Department of the Army Corps of Engineers Norfolk District is procuring these services. Key requirements include demolishing an existing warehouse and constructing a new 281,075 square foot office building to accommodate 1,622 employees. Proposals will be evaluated using best value tradeoff criteria including past performance, technical approach, small business participation plan, and price. Proposals are due no later than July 10, 2020 through the DoD SAFE system.
There is no set-aside designated. The main NAICS code is 236220 with a PSC code of V499. The incumbent is the Department of the Army Corps of Engineers Engineering District Norfolk. The estimated value is $89 million and the period of performance is 1,020 calendar days from notice to proceed. The place of performance will be at the Defense Supply Center Richmond facility in Virginia.
Notice text
9 versions
Update #9 · Latest ·
Please read the following carefully before proceeding:
Amendment 7 (SF30 - 0007) is now available
Amendment 6 (SF30 - 0006) is available; please note that the attachments (dated 20 July) are for Amendment 6, although several attachment decscriptions contain language 'Amend 4' within the title.
Amendment 5 (SF30 - 0005) was not previously posted, but is now available. see attachments
Amendment 4 does not exist.
Amendment 3 (SF30 - 0004) is available at the following link: https://beta.sam.gov/opp/7249882650224beaacf2f43347aac93d/view?keywords=%22DLA%20Aviation%20Operations%20Center,%20Phase%20II,%20Defense%20Supply%20Center%20Richmond%20(DSCR)%20(Amendments:%22&sort=-relevance&index=&is_active=true&page=1
Amendment 2 (SF30 - 0002) is available. see attachments
Amendment 1 (SF30 - 0001) is available. see attachments
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #8 ·
Please read the following carefully before proceeding:
Amendment 6 (SF30 - 0006) is available; please note that the attachments (dated 20 July) are for Amendment 6, although the several attachment decscriptions contain language 'Amend 4' within the title.
Amendment 5 (SF30 - 0005) was not previously posted, but is now available. see attachments
Amendment 4 does not exist.
Amendment 3 (SF30 - 0004) is available at the following link: https://beta.sam.gov/opp/7249882650224beaacf2f43347aac93d/view?keywords=%22DLA%20Aviation%20Operations%20Center,%20Phase%20II,%20Defense%20Supply%20Center%20Richmond%20(DSCR)%20(Amendments:%22&sort=-relevance&index=&is_active=true&page=1.
Amendment 2 (SF30 - 0002)is available. see attachments
Amendment 1 (SF30 - 0001) is available. see attachments
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #7 ·
Please read the following carefully before proceeding:
Amendment 6 (SF30 - 0006) is available; please note that the attachments (dated 20 July) are for Attachment 6, although the several attachment decscriptions contain language 'Amend 4' within the title.
Amendment 5 (SF30 - 0005) was not previously posted, but is now available. see attachments
Amendment 4 does not exist.
Amendment 3 (SF30 - 0004) is available at the following link: https://beta.sam.gov/opp/7249882650224beaacf2f43347aac93d/view?keywords=%22DLA%20Aviation%20Operations%20Center,%20Phase%20II,%20Defense%20Supply%20Center%20Richmond%20(DSCR)%20(Amendments:%22&sort=-relevance&index=&is_active=true&page=1.
Amendment 2 (SF30 - 0002)is available. see attachments
Amendment 1 (SF30 - 0001) is available. see attachments
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #6 ·
Amendment 0006 is issued to provide the following:
1. To provide ProjNet Inquiries.
2. To provide additional attachments.
All other terms and conditions remain unchanged.
(Amendment 5 available)
(Amendment 4 available)
(Amendment 2 available)
(Amendment 1 available)
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #5 ·
(Amendment 2 available)
(Amendment 1 available)
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #4 ·
(Amendment 1 available)
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #3 ·
(Site Visit Attendance List Available)
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #2 ·
The DLA Aviation Operations Center Phase II project requirements will construct a multi-story office building of 281,075 SF to accommodate 1,622 employees in an administrative operations center. The Operations Center includes: open and individual administrative office and support areas (mail distribution, packing, shipping, reception space, reproduction area, unclassified conference and Video Tele-Conference (VTC) space, law library, kitchenette/break, restrooms, storage, equipment and supply rooms, passenger and service elevators, lightning protection, fire suppression, fire alarm, mass notification systems, Intrusion Detection System (IDS) and energy management control system (EMCS), and building information systems.
The project will utilize conventional design and construction methods to accommodate the mission of the facility. The facility will be compatible with the Department of Defense (DoD), DLA, and Defense Supply Center, Richmond design standards. Local material and construction techniques will be used where cost effective. The facility will be designed as a permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. The project will comply with DoD minimum Antiterrorism Standards for buildings per UFC 4-010-01. The project also includes emergency generators, site improvements, special foundations, parking and all necessary supporting facilities.
Update #1 ·
Upload of solicitation for DLA Aviation OPs Center, Phase II
Files
Show 40 more
50 files listed here. See the rest on GovTribe.
Notice history
| Notice | Type | Posted |
|---|---|---|
| DLA Aviation Operations Center, Phase II, Defense Supply Center Richmond (DSCR) (Amendments: 1, 2, 3, 5, 6, and 7) | Award Notice | |
| This notice | Solicitation | |
| DLA Aviation Operations Center, Phase II, Defense Supply Center Richmond (DSCR) (Amendment 3 & 5) SEE RELATED NOTICE ID: W91235620R2005 FOR THE ORIGINAL SOLICITATION & OTHER SUBSEQUENT AMENDMENTS | Pre-Solicitation | |
| DLA Aviation, Ops Center, Phase 2. | Special Notice |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| INDUSTRY DAY - Richmond Army Reserve Center - MILCON | ENDIST Louisville | No set-aside | |
| ICD-705 Controlled Spaces Modernization and Sustainment Program - (Progressive Design-build (PDB) Other Transaction Agreement (OTA) | ENDIST Far East | No set-aside |