DLA Ops Center CLIN Schedule Rev1.pdf

PDF 556 KB Posted

Attached to
DLA Aviation Operations Center, Phase II, Defense Supply Center Richmond (DSCR) (Amendments: 1, 2, 3, 5, 6, and 7)
Solicitation number
W91235620R2005
Issued by

About this file

This document is a price schedule attachment for a solicitation seeking construction services for the Defense Logistics Agency Aviation Operations Center, Phase II project at Defense Supply Center Richmond. The solicitation requests pricing for demolition of an existing warehouse, construction of a new operations center building and site work, installation of geothermal wells through soil and rock, pile foundations, and optional bid items for asphalt paving, a building canopy, generator relocation, furniture and equipment, a new generator, and audiovisual equipment. Pricing is to be provided using unit costs and lump sums for the various contract line item numbers as detailed. The statutory cost limitation for the project is $89,013,000 and the contract completion date is 1,020 days after notice to proceed. The soliciting agency is the Department of the Army Corps of Engineers Norfolk District.

View the file

Other files

File Type Posted
DLA Ops Center CLIN Schedule (Rev.2).pdf PDF
W9123620R2005P0007 - Amendment 7.pdf PDF
Attachment 6 - Small Business Participation Plan (Rev.1).pdf PDF
W91236-20-R-2005 Amendment 5 DLA Ops Center.pdf PDF
Attachment 138 AMEND4_DLA_OPS_PH II-_A-103.pdf PDF
Attachment 156 Amend4_DLA_OPS_PH II_Spec_32 05 33.pdf PDF
Attachment 148 AMEND4_DLA_OPS_PH II_A-507.pdf PDF
Attachment 153 Amend4_DLA_OPS_PH II_Spec_03 36 00.pdf PDF
Attachment 152 Amend4_DLA_OPS_PH II_Spec_01 50 02-00 50 page6.pdf PDF
Attachment 147 AMEND4_DLA_OPS_PH II_A-506.pdf PDF
Attachment 150 AMEND4_DLA_OPS_PH II_A-514.pdf PDF
Attachment 133 2020-07-17_DLA OPS II_CD101.pdf PDF
Attachment 154 Amend4_DLA_OPS_PH II_Spec_08 41 13 page8.pdf PDF
Attachment 151 AMEND4_DLA_OPS_PH II_A-517.pdf PDF
Attachment 140 AMEND4_DLA_OPS_PH II_A-107.pdf PDF
Attachment 136 2020-07-17_DLA OPS II_CG601.pdf PDF
Attachment 144 AMEND4_DLA_OPS_PH II_A-144.pdf PDF
Attachment 143 AMEND4_DLA_OPS_PH II_A-118.pdf PDF
Attachment 132 2020-07-17_DLA OPS II_C-513.pdf PDF
Attachment 134 2020-07-17_DLA OPS II_CG101-CG106.pdf PDF
Attachment 145 AMEND4_DLA_OPS_PH II_A-416.pdf PDF
Attachment 137 2020-07-17_DLA OPS II_CU102-CU103.pdf PDF
W91236-20-R-0005 0006 DLA Ops Center ProjNet.pdf PDF
Attachment 142 AMEND4_DLA_OPS_PH II_A-114.pdf PDF
Attachment 155 Amend4_DLA_OPS_PH II_Spec_08 44 00 page11.pdf PDF
Attachment 146 AMEND4_DLA_OPS_PH II_A-417.pdf PDF
Attachment 149 AMEND4_DLA_OPS_PH II_A-513.pdf PDF
Attachment 141 AMEND4_DLA_OPS_PH II_A-113.pdf PDF
Attachment 139 AMEND4_DLA_OPS_PH II_A-106.pdf PDF
Attachment 135 2020-07-17_DLA OPS II_CG201.pdf PDF
20-R-2005 Amend 2.pdf PDF
Att 40 - DLA_OPS_PH II_Arch_A-602 - DOOR SCHEDULE.pdf PDF
Att 41 - DLA_OPS_PH II_Arch_A-605 - WINDOW AND CURTAINWALL ELEVATIONS.pdf PDF
Att 38 - DLA_OPS_PH II_Arch_A-527 - MISCELLANEOUS DETAILS.pdf PDF
Att 32 - DLA_OPS_PH II_Arch_A-121 - FIFTH FLOOR PLAN - AREA A5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 29 - DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 25 - DLA_OPS_PH II_Arch_A-112 - FIRST FLOOR PLAN - AREA G1.pdf PDF
Att 27 - DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 54 - DLA OPS PH-2 SPECIFICATIONS 10 11 00.pdf PDF
A.07.15 Attachment 7 - CLIN Schedule.pdf PDF
Att 55 - DLA OPS PH-2 SPECIFICATIONS 10 14 00-10.pdf PDF
Att 33 - DLA_OPS_PH II_Arch_A-122 - FIFTH FLOOR PLAN - AREA D5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-601 - DOOR SCHEDULE.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-609 - CURTAIN WALL ELEVATIONS.pdf PDF
Att 26 - DLA_OPS_PH II_Arch_A-113 - SECOND FLOOR PLAN - AREA A2.pdf PDF
Att 20 - DLA_OPS_PH II_Arch_A-107 - FIRST FLOOR PLAN - AREA B1.pdf PDF
Att 53 - DLA OPS PH-2 SPECIFICATIONS 06 20 00.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 42 - DLA_OPS_PH II_Arch_A-608 - CURTAIN WALL ELEVA.pdf PDF
Show 40 more

Latest 50 of 127 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 7

PART I - THE PRICE SCHEDULE - DLA OPS CENTER (PH-2)

REVISION 1 Dated 15 July 2020

SECTION 00010 - SUPPLIES OR SERVICES AND PRICES

SCHEDULE I - BASE BID

CLIN # DESCRIPTION QUANTITY

UNIT

MEASURE

UNIT

PRICE AMOUNT

BASE

BID

CLIN DEMO BLDG 33 - All costs in connection with 1 JOB $0 0001 demolition of warehouse Building 33, including removal and disposal of Hazardous Materials, all related site demolition, site improvements and site utilities complete as shown on the drawings and specified excluding the work described in CLIN 0002- 0014. Source of funds is MILCON.

CLIN CONSTRUCT OPS CTR PH2 - All costs in 1 JOB $0 0002 connection with construction of new DLA Ops Center, building construction only, excluding all "special costs" as identified in CLIN 0006, complete as shown on the drawings and specified excluding the work described in CLIN 0001 & 0003-0014. Source of funds is MILCON.

CLIN SITE WORK - All costs in connection with 1 JOB $0 0003 construction of new DLA Ops Center Site Work, including all related site preparation, site improvements and site utilities complete as shown on the drawings and specified excluding the work described in CLIN 0001-0002 & 0004-0014. Source of funds is MILCON.

WELLS IN SOIL - UNIT COST for installation of

16,280

LF

$/LF

$0

CLIN

geothermal wells through SOIL (installation is as described in SPEC SECTION 23 81 47); include drilling, steel encasement, grouting and associated vertical piping. The cost of the rest of the items in SPEC SECTION 23 21 47 (including permits, heat pumps, system equipment, piping pumps, electrical equipment, controls, ground heat exchanger) shall be included in CLIN 0003. Assume total bid quantity for well installation through SOIL is 16,280 LF; in accordance with FAR 52.211-18, the UNIT PRICE in this CLIN 0004 is intended to provide for field adjustment in the case where the actual field amount drilled through SOIL varies. Complete work as shown on the drawings and specified excluding the work described in CLIN 001-0003 & 0005-0014. Source of funds is MILCON.

UNIT UNIT

CLIN # DESCRIPTION QUANTITY MEASURE PRICE AMOUNT

WELLS IN ROCK - UNIT COST for installation of geothermal wells through ROCK (installation is as described in SPEC SECTION 23 81 47); include drilling, grouting and associated vertical piping. The cost of the rest of the items in SPEC SECTION 23 81 47 (including permits, heat pumps, system equipment, piping pumps, electrical equipment, controls, ground heat exchanger) shall be included in CLIN 0003. Assume total bid quantity for well installation through ROCK is 93,720 LF; in accordance with FAR 52.211-18, the UNIT PRICE in this CLIN 0005 is intended to provide for field adjustment in the case where the actual field amount drilled through ROCK varies. Complete work as shown on the drawings and specified excluding the work described in CLIN 0001-0004 & 0006-0014.

Source of funds is MILCON.

SPECIAL FOUNDATIONS (PILES AND PILE CAPS) -

Unit Cost for installation of new DLA Ops Center special foundations (piles and pile caps), complete as shown on the drawings and specified excluding the work described in CLIN 0001-0005 & 0007-0014.

Source of funds is MILCON.

93,720 LF $/LF $0

5,740 LF $/LF $0

TOTAL BASE BID $0

SCHEDULE II - OPTIONAL BID ITEMS MILCON FUNDED COSTS

PARKING LOT PAVEMENT - All costs in connection with provision of asphalt to final grade in lieu of gravel

1 JOB $0

OPTION in employee parking lot (COST DIFFERENCE - Cost to provide gravel parking should remain in CLIN 0003 Site Work), as indicated on CP103 and CP104 and specified excluding the work described in CLIN 0001- 0006 & 0008 -0014. Source of funds is MILCON.

Option to be exercise within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

CLIN ADDITIONAL CANOPY - All costs in connection with 1 JOB $0

OPTION

construction of a canopy that stretches from the entrance vestibule of the two-story portion of the building to the east and west, stopping at the five-story portion and at the finished face of Building 32 complete as shown on drawings and specified excluding the work described in CLIN 0001-0007 & 0009-0014. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.

UNIT UNIT

CLIN # DESCRIPTION QUANTITY MEASURE PRICE AMOUNT

OPTION

GENERATOR RELOCATION - All costs in connection with relocation of existing emergency generators, site demolition, site repair, and site preparation complete as shown on drawings and specified excluding the work described in CLIN 0001-0008 & 0010-0014. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52. 217-7.

1 JOB $0

TOTAL SCHEDULE II - OPTIONAL BID ITEMS MILCON FUNDED COSTS $0

Sum of Statutory Lines $0

SCHEDULE III - OPTIONAL BID ITEMS NON-MILCON FUNDED COSTS

OPTION

FF&E - All costs in connection with providing Furniture, Fixtures & Equipment (FF&E) complete as shown on the drawings and specified excluding the work described in CLIN 0001-0009 & 0011-0014.

Sources of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To

OPTION

NEW GENERATOR - All costs to procure and install all 150 KW Standby Diesel Generator per specifications SECTION 26 32 15.00 10 for the DLA Operations Center – PH-2, complete, including all work incidental therto as shown on the drawings and as specified exclusive of CLIN 0001-0010 & 0012- 0014. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To

OPTION

PROCURE & INSTALL TVs - All costs to Procure and install all Audio-Visual Equipment (Televisions) for the DLA Operations Center – PH-2, complete, including all work incidental thereto as shown on the drawings and specified exclusive of CLIN 0001-0011. Sources of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217.7.

TOTAL SCHEDULE III - OPTIONAL BID ITEMS NON-MILCON FUNDED COSTS $0

TOTAL SCHEDULE I, II, & III- BASE BID, OPTIONAL NON-MILCON AND OPTIONAL ITEMS $0

STATUTORY COST LIMITATION IN THIS SOLICITATION:

Per FAR 36.205 CLINS 0001 ‐ 0009 are subject to STATUTORY COST LIMITATION OF $89,013,000.

1 JOB $0

JOB

1 JOB

1. For purposes of source selection as referenced in Section 00 22 16 of the Solicitation, and in particular Subsection 6.1, "Price" shall mean the Total Evaluated Price which will be the sum of the pricing submitted for CLINs 0001 through 0014, inclusive. Failure to provide a price for each CLIN may be deemed a deficiency because it may prevent the Government from conducting a meaningful evaluation of price, which could result in the proposal being ineligible for award.

2. Contract Completion Date: Unless indicated otherwise, the completion date for the scope of the

CLIN is 1,020 days after notice to proceed.

Draft CLIN Revision 07162020 ko changes