This document outlines specifications for an entrance system for the Defense Logistics Agency Aviation Operations Center, Phase II project. The system is to be fabricated from aluminum with hairline joints and welds concealed according to AWS recommendations. Components are to be cleaned and given a medium bronze anodized finish to AA-M10-C22-A32 standards. Fabrication tolerances require rigidly securing units with hairline joints and sealing per manufacturer recommendations. The related federal contract opportunity is solicitation number W91235620R2005 for the DLA Aviation Operations Center, Phase II project to be conducted by the Department of the Army Corps of Engineers Norfolk District. Amendments 1, 2, 3, 5, 6 and 7 have been issued for this solicitation.

View the file

Other files

File Type Posted
DLA Ops Center CLIN Schedule (Rev.2).pdf PDF
W9123620R2005P0007 - Amendment 7.pdf PDF
Attachment 6 - Small Business Participation Plan (Rev.1).pdf PDF
W91236-20-R-2005 Amendment 5 DLA Ops Center.pdf PDF
DLA Ops Center CLIN Schedule Rev1.pdf PDF
Attachment 138 AMEND4_DLA_OPS_PH II-_A-103.pdf PDF
Attachment 156 Amend4_DLA_OPS_PH II_Spec_32 05 33.pdf PDF
Attachment 148 AMEND4_DLA_OPS_PH II_A-507.pdf PDF
Attachment 153 Amend4_DLA_OPS_PH II_Spec_03 36 00.pdf PDF
Attachment 152 Amend4_DLA_OPS_PH II_Spec_01 50 02-00 50 page6.pdf PDF
Attachment 147 AMEND4_DLA_OPS_PH II_A-506.pdf PDF
Attachment 150 AMEND4_DLA_OPS_PH II_A-514.pdf PDF
Attachment 133 2020-07-17_DLA OPS II_CD101.pdf PDF
Attachment 151 AMEND4_DLA_OPS_PH II_A-517.pdf PDF
Attachment 140 AMEND4_DLA_OPS_PH II_A-107.pdf PDF
Attachment 136 2020-07-17_DLA OPS II_CG601.pdf PDF
Attachment 144 AMEND4_DLA_OPS_PH II_A-144.pdf PDF
Attachment 143 AMEND4_DLA_OPS_PH II_A-118.pdf PDF
Attachment 132 2020-07-17_DLA OPS II_C-513.pdf PDF
Attachment 134 2020-07-17_DLA OPS II_CG101-CG106.pdf PDF
Attachment 145 AMEND4_DLA_OPS_PH II_A-416.pdf PDF
Attachment 137 2020-07-17_DLA OPS II_CU102-CU103.pdf PDF
W91236-20-R-0005 0006 DLA Ops Center ProjNet.pdf PDF
Attachment 142 AMEND4_DLA_OPS_PH II_A-114.pdf PDF
Attachment 155 Amend4_DLA_OPS_PH II_Spec_08 44 00 page11.pdf PDF
Attachment 146 AMEND4_DLA_OPS_PH II_A-417.pdf PDF
Attachment 149 AMEND4_DLA_OPS_PH II_A-513.pdf PDF
Attachment 141 AMEND4_DLA_OPS_PH II_A-113.pdf PDF
Attachment 139 AMEND4_DLA_OPS_PH II_A-106.pdf PDF
Attachment 135 2020-07-17_DLA OPS II_CG201.pdf PDF
20-R-2005 Amend 2.pdf PDF
Att 40 - DLA_OPS_PH II_Arch_A-602 - DOOR SCHEDULE.pdf PDF
Att 41 - DLA_OPS_PH II_Arch_A-605 - WINDOW AND CURTAINWALL ELEVATIONS.pdf PDF
Att 38 - DLA_OPS_PH II_Arch_A-527 - MISCELLANEOUS DETAILS.pdf PDF
Att 32 - DLA_OPS_PH II_Arch_A-121 - FIFTH FLOOR PLAN - AREA A5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 29 - DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 25 - DLA_OPS_PH II_Arch_A-112 - FIRST FLOOR PLAN - AREA G1.pdf PDF
Att 27 - DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 54 - DLA OPS PH-2 SPECIFICATIONS 10 11 00.pdf PDF
A.07.15 Attachment 7 - CLIN Schedule.pdf PDF
Att 55 - DLA OPS PH-2 SPECIFICATIONS 10 14 00-10.pdf PDF
Att 33 - DLA_OPS_PH II_Arch_A-122 - FIFTH FLOOR PLAN - AREA D5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-601 - DOOR SCHEDULE.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-609 - CURTAIN WALL ELEVATIONS.pdf PDF
Att 26 - DLA_OPS_PH II_Arch_A-113 - SECOND FLOOR PLAN - AREA A2.pdf PDF
Att 20 - DLA_OPS_PH II_Arch_A-107 - FIRST FLOOR PLAN - AREA B1.pdf PDF
Att 53 - DLA OPS PH-2 SPECIFICATIONS 06 20 00.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 42 - DLA_OPS_PH II_Arch_A-608 - CURTAIN WALL ELEVA.pdf PDF
Show 40 more

Latest 50 of 127 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DLA OPS CENTER PHASE 2 W91236-17-D-002

DEFENSE SUPPLY CENTER RICHMOND (DSCR), RICHMOND, VA

d. Clearly indicate locations of exposed fasteners and joints.

e. Clearly show where and how the manufacturer's system deviates from Contract drawings and these specifications.

2.2.1 Entrance System Fabrication

Provide door corner construction consisting of mechanical clip fastening, SIGMA deep penetration plug welds and 1 1/8 inch long fillet welds inside and outside all four corners. Provide a hook-in type exterior glazing stop with EPDM glazing gaskets reinforced with non-stretchable cord.

Provide an interior glazing stop that is mechanically fastened to the door member and that incorporates a silicone-compatible spacer used with silicone sealant.

Accurately fit and secure joints and corners. Make joints hairline in appearance. Remove burrs and smooth edges. Prepare components with internal reinforcement for door hardware. Arrange fasteners and attachments so that they are concealed from view.

Separate dissimilar metals with protective coating or pre-formed separators to prevent contact and corrosion.

2.2.2 Shop Assembly

Fabricate and assemble units with joints only at the intersection of aluminum members with hairline joints; rigidly secure these units, and seal them in accordance with the manufacturer's recommendations.

2.2.2.1 Welding

Conceal welds on aluminum members in accordance with AWS recommendations or methods recommended by the manufacturer. Members showing welding bloom or discoloration on finish or material distortion will be rejected by the Contacting Officer.

2.2.3 Finish

Before fabrication, clean the units and give them a AA-M-10-C22-A32 medium bronze (color) anodized finish in accordance with the requirements of the

AA DAF45.

c. Color Anodized: Conforming to AA-M12C22A 32 and AAMA 611

Select and edit the following items for appropriate finish; delete types that do not apply.

(1) Architectural Class II

(2) Etched, medium matte

(3) Medium bronze anodic coating, 0.4 mil minimum thickness

2.2.4 Fabrication Tolerance

Fabricate and assemble units with joints only at intersection of aluminum members with hairline joints; rigidly secure these units, and seal them in accordance with the manufacturer's recommendations.

SECTION 08 41 13 Page 8