W9123620R2005P0007 - Amendment 7.pdf

PDF 212 KB Posted

Attached to
DLA Aviation Operations Center, Phase II, Defense Supply Center Richmond (DSCR) (Amendments: 1, 2, 3, 5, 6, and 7)
Solicitation number
W91235620R2005
Issued by

About this file

This document summarizes amendments to a solicitation for construction services for the Defense Logistics Agency Aviation Operations Center, Phase II project. The solicitation is being amended to revise attachments including the small business participation plan, CLIN schedule, drawings, and specifications. The opportunity is issued by the Department of the Army Corps of Engineers Norfolk District for construction work at the Defense Supply Center Richmond site. Services required include installation of foundations, piles, pile caps, and construction of the DLA Aviation Operations Center facility. The deadline for responses remains unchanged. Pricing will be on a firm-fixed-price basis by line item number.

View the file

Other files

File Type Posted
DLA Ops Center CLIN Schedule (Rev.2).pdf PDF
Attachment 6 - Small Business Participation Plan (Rev.1).pdf PDF
W91236-20-R-2005 Amendment 5 DLA Ops Center.pdf PDF
DLA Ops Center CLIN Schedule Rev1.pdf PDF
Attachment 138 AMEND4_DLA_OPS_PH II-_A-103.pdf PDF
Attachment 156 Amend4_DLA_OPS_PH II_Spec_32 05 33.pdf PDF
Attachment 148 AMEND4_DLA_OPS_PH II_A-507.pdf PDF
Attachment 153 Amend4_DLA_OPS_PH II_Spec_03 36 00.pdf PDF
Attachment 152 Amend4_DLA_OPS_PH II_Spec_01 50 02-00 50 page6.pdf PDF
Attachment 147 AMEND4_DLA_OPS_PH II_A-506.pdf PDF
Attachment 150 AMEND4_DLA_OPS_PH II_A-514.pdf PDF
Attachment 133 2020-07-17_DLA OPS II_CD101.pdf PDF
Attachment 154 Amend4_DLA_OPS_PH II_Spec_08 41 13 page8.pdf PDF
Attachment 151 AMEND4_DLA_OPS_PH II_A-517.pdf PDF
Attachment 140 AMEND4_DLA_OPS_PH II_A-107.pdf PDF
Attachment 136 2020-07-17_DLA OPS II_CG601.pdf PDF
Attachment 144 AMEND4_DLA_OPS_PH II_A-144.pdf PDF
Attachment 143 AMEND4_DLA_OPS_PH II_A-118.pdf PDF
Attachment 132 2020-07-17_DLA OPS II_C-513.pdf PDF
Attachment 134 2020-07-17_DLA OPS II_CG101-CG106.pdf PDF
Attachment 145 AMEND4_DLA_OPS_PH II_A-416.pdf PDF
Attachment 137 2020-07-17_DLA OPS II_CU102-CU103.pdf PDF
W91236-20-R-0005 0006 DLA Ops Center ProjNet.pdf PDF
Attachment 142 AMEND4_DLA_OPS_PH II_A-114.pdf PDF
Attachment 155 Amend4_DLA_OPS_PH II_Spec_08 44 00 page11.pdf PDF
Attachment 146 AMEND4_DLA_OPS_PH II_A-417.pdf PDF
Attachment 149 AMEND4_DLA_OPS_PH II_A-513.pdf PDF
Attachment 141 AMEND4_DLA_OPS_PH II_A-113.pdf PDF
Attachment 139 AMEND4_DLA_OPS_PH II_A-106.pdf PDF
Attachment 135 2020-07-17_DLA OPS II_CG201.pdf PDF
20-R-2005 Amend 2.pdf PDF
Att 40 - DLA_OPS_PH II_Arch_A-602 - DOOR SCHEDULE.pdf PDF
Att 41 - DLA_OPS_PH II_Arch_A-605 - WINDOW AND CURTAINWALL ELEVATIONS.pdf PDF
Att 38 - DLA_OPS_PH II_Arch_A-527 - MISCELLANEOUS DETAILS.pdf PDF
Att 32 - DLA_OPS_PH II_Arch_A-121 - FIFTH FLOOR PLAN - AREA A5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 29 - DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 25 - DLA_OPS_PH II_Arch_A-112 - FIRST FLOOR PLAN - AREA G1.pdf PDF
Att 27 - DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf PDF
Att 54 - DLA OPS PH-2 SPECIFICATIONS 10 11 00.pdf PDF
A.07.15 Attachment 7 - CLIN Schedule.pdf PDF
Att 55 - DLA OPS PH-2 SPECIFICATIONS 10 14 00-10.pdf PDF
Att 33 - DLA_OPS_PH II_Arch_A-122 - FIFTH FLOOR PLAN - AREA D5.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-601 - DOOR SCHEDULE.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-609 - CURTAIN WALL ELEVATIONS.pdf PDF
Att 26 - DLA_OPS_PH II_Arch_A-113 - SECOND FLOOR PLAN - AREA A2.pdf PDF
Att 20 - DLA_OPS_PH II_Arch_A-107 - FIRST FLOOR PLAN - AREA B1.pdf PDF
Att 53 - DLA OPS PH-2 SPECIFICATIONS 06 20 00.pdf PDF
Amend1_DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf PDF
Att 42 - DLA_OPS_PH II_Arch_A-608 - CURTAIN WALL ELEVA.pdf PDF
Show 40 more

Latest 50 of 127 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to complete the follow ing:

1. Revise the attachment list (indicated in red below ) to include a revisions to Attachment 6 (Attachment 6 - Small Business Participation Plan (Rev.1)) and Attachment 7 (DLA Ops Center CLIN Schedule (Rev.2)), and issue the revisions through this amendment;

2. Provide a summary of the amendments published thus far in beta.sam.gov.

(see the Continuation Page for all details)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123620R2005

X 9B. DATED (SEE ITEM 11)

26-May-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Jul-2020

CODE

USACE, NORFOLK DISTRICT OFFICE

CONTRACTING OFFICE

803 FRONT STREET

NORFOLK VA 23510-1011

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123620R2005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0007

The purpose of this amendment is to complete the following:

1. Revise the attachment list (indicated in red below) to include a revisions to Attachment 6 (Attachment 6 - Small Business Participation Plan (Rev.1) and Attachment 7 (DLA Ops Center CLIN Schedule (Rev.2)), and issue the revisions through this amendment;

2. Provide a summary of the amendments published thus far in beta.sam.gov, as follows:

Amendment 6 (SF30 - 0006) published in beta.sam.gov on July 20, 2020; attachments (dated 20 July) are connected to Amendment 6, although several attachment descriptions contain the language 'Amend 4' within the title;

Amendment 5 (SF30 - 0005) was published in beta.sam.gov on July 21, 2020;

Amendment 4 does not exist;

Amendment 3 (SF30 - 0004) was published in beta.sam.gov on July 10, 2020, and is available at the following link:

https://beta.sam.gov/opp/7249882650224beaacf2f43347aac93d/view?keywords=%22DLA%20 Aviation%20Operations%20Center,%20Phase%20II,%20Defense%20Supply%20Center%20Rich mond%20(DSCR)%20(Amendments:%22&sort=‐relevance&index=&is_active=true&page=1;

Amendment 2 (SF30 – 0002) was published in beta.sam.gov on July 1, 2020;

Amendment 1 (SF30 - 0001) was published in beta.sam.gov on June 29, 2020.

All other terms and conditions remain unchanged.

SECTION 00 10 00 - SOLICITATION

CLIN 0006

The CLIN type priced has been deleted.

The CLIN extended description has changed from:

SPECIAL FOUNDATIONS (PILES AND PILE CAPS) - UNIT COST for installation of new DLA Ops Center special foundations (piles and pile caps), complete as shown on the drawings and specified excluding the work described in CLIN 0001-0005 & 0007-0011 and 0014. Source of funds is MILCON.

To:

SPECIAL FOUNDATIONS (PILES AND PILE CAPS) - Informational Only The pricing detail quantity 5,740.00 has been deleted.

The unit of issue Linear Foot has been deleted.

The FOB Destination has been deleted.

The PSC code Y1AA has been deleted.

The PROG code S10 has been deleted.

The WSC Equipment code 000 has been deleted.

The NAICS code 236220 has been deleted.

The MDAP/MAIS Code 000 has been deleted.

SUBCLIN 0006AA is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006AA 5,740 Linear

Foot

DLA Aviation Ops Center

FFP

SPECIAL FOUNDATIONS (PILES) - Unit Cost for installation of new DLA Ops Center special foundations (piles), complete as shown on the drawings and specified excluding the work described in CLIN 0001-0005 & 0006AB, 0007- 0014. Source of funds is MILCON

FOB: Destination

PSC CD: Y1AA

NET AMT

SUBCLIN 0006AB is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006AB 1 Job DLA Aviation Ops Center

FFP

SPECIAL FOUNDATIONS (PILE CAPS) - Unit Cost for installation of new DLA Ops Center special foundations (pile caps), complete as shown on the drawings and specified excluding the work described in CLIN 0001-0005 & 0006AA, 0007-0014. Source of funds is MILCON.

PSC CD: Y1AA

NET AMT

The following Delivery Schedule for CLIN 0006 has been deleted:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

1020 dys. ANP 5,740 PROGRAMS & PROJ MGMT DIV(PPMD)

JONATHAN JONES

US ARMY ENGR DIST NORFOLK ATTN:

CENAO-PM 803

EET

NORFOLK VA 23510-1096

757-201-7254

W91236

The following Delivery Schedule for SUBCLIN 0006AA has been added:

CAGE

1020 dys. ANP 5,740 PROGRAMS & PROJ MGMT DIV(PPMD)

JONATHAN JONES

US ARMY ENGR DIST NORFOLK ATTN:

CENAO-PM 803

EET

NORFOLK VA 23510-1096

757-201-7254

The following Delivery Schedule for SUBCLIN 0006AB has been added:

CAGE

1020 dys. ANP 1 PROGRAMS & PROJ MGMT DIV(PPMD)

JONATHAN JONES

US ARMY ENGR DIST NORFOLK ATTN:

CENAO-PM 803

EET

NORFOLK VA 23510-1096

757-201-7254

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The Acceptance/Inspection Schedule for CLIN 0006 has been changed from:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

To:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A N/A

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AA:

Destination Government Destination Government

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AB:

Destination Government Destination Government

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

ATTACHMENTS

Attachment 1: Proposal Data Sheet.pdf Attachment 2: Project Data Sheet, Relevant Experience.pdf Attachment 3: Past Performance Questionaire.pdf Attachment 4: Telephone Interview Questionaire.pdf Attachment 5: Letter of Commitment Sample.pdf Attachment 6: Small Business Participation Plan.pdf Attachment 6 - Small Business Participation Plan (Rev.1) Attachment 7: CLIN Schedule.pdf Attachment 7: CLIN Schedule.pdf (Rev.1) Attachment 7 (DLA Ops Center CLIN Schedule (Rev.2) Attachment 8: DSCR (Base Map).pdf Attachment 9: DLA OPS PH-2 RTA – FF (&)AND E Package.pdf Attachment 10: DLA OPS PH-2 RTA – SID Package.pdf Attachment 11: DLA OPS PH-2 DESIGN ANALYSIS VOL1.pdf Attachment 12: DLA OPS PH-2 DESIGN ANALYSIS VOL2.pdf Attachment 13: DLA OPS PH-2 DESIGN ANALYSIS VOL3.pdf

Attachment 14: DLA OPS PH-2 SPECIFICATIONS VOL1.pdf Attachment 15: DLA OPS PH-2 SPECIFICATIONS VOL2.pdf Attachment 16: DLA OPS PH-2 DRAWINGS VOL1.pdf Attachment 17: DLA OPS PH-2 DRAWINGS VOL2.pdf Attachment 18: DLA OPS PH-2 DRAWINGS VOL3.pdf

Amendment 1

AMENDED DRAWINGS

Attachment 19: DLA_OPS_PH II_Arch_A-106 - FIRST FLOOR PLAN - AREA A1.pdf Attachment 20: DLA_OPS_PH II_Arch_A-107 - FIRST FLOOR PLAN - AREA A1.pdf Attachment 21: DLA_OPS_PH II_Arch_A-108 - FIRST FLOOR PLAN - AREA C1.pdf Attachment 22: DLA_OPS_PH II_Arch_A-109 - FIRST FLOOR PLAN - AREA D1.pdf Attachment 23: DLA_OPS_PH II_Arch_A-110 - FIRST FLOOR PLAN - AREA E1.pdf Attachment 24: DLA_OPS_PH II_Arch_A-111 - FIRST FLOOR PLAN - AREA F1.pdf Attachment 25: DLA_OPS_PH II_Arch_A-112 - FIRST FLOOR PLAN - AREA G1.pdf Attachment 26: DLA_OPS_PH II_Arch_A-113 - SECOND FLOOR PLAN - AREA A2.pdf Attachment 27: DLA_OPS_PH II_Arch_A-114 - SECOND FLOOR PLAN - AREA D2.pdf Attachment 28: DLA_OPS_PH II_Arch_A-116 - SECOND FLOOR PLAN - AREA G2.pdf Attachment 29: DLA_OPS_PH II_Arch_A-117 - THIRD FLOOR PLAN - AREA A3.pdf Attachment 30: DLA_OPS_PH II_Arch_A-118 - THIRD FLOOR PLAN - AREA D3.pdf Attachment 31: DLA_OPS_PH II_Arch_A-120 - FOURTH FLOOR PLAN - AREA D4.pdf Attachment 32: DLA_OPS_PH II_Arch_A-121 - FIFTH FLOOR PLAN - AREA A5.pdf Attachment 33: DLA_OPS_PH II_Arch_A-122 - FIFTH FLOOR PLAN - AREA D5.pdf Attachment 34: DLA_OPS_PH II_Arch_A-416 - ENLARGE TOILET -MOUNTING SCHEDULE.pdf Attachment 35: DLA_OPS_PH II_Arch_A-418 - ENLARGE KIOS SUNDRIES.pdf Attachment 36: DLA_OPS_PH II_Arch_A-422 - EXT SIGNAGE PLAN ELEVATIONS.pdf Attachment 37: DLA_OPS_PH II_Arch_A-423 - DUMPSTER AND ELEVATION.pdf Attachment 38: DLA_OPS_PH II_Arch_A-527 - MISCELLANEOUS DETAILS.pdf Attachment 39: DLA_OPS_PH II_Arch_A-601 - DOOR SCHEDULE.pdf Attachment 40: DLA_OPS_PH II_Arch_A-602 - DOOR SCHEDULE.pdf Attachment 41: DLA_OPS_PH II_Arch_A-605 - WINDOW AND CURTAIN WALL ELEVATIONS.pdf Attachment 42: DLA_OPS_PH II_Arch_A-608 - CURTAIN WALL ELEVATIONS.pdf Attachment 43: DLA_OPS_PH II_Arch_A-609 - CURTAIN WALL ELEVATIONS.pdf Attachment 44: DLA_OPS_PH II_Arch_A-611 - WINDOW DETAILS.pdf Attachment 45: DLA_OPS_PH II_Arch_A-702 - FINISH SCHEDULE.pdf Attachment 46: DLA_OPS_PH II_Civil_C-504.pdf Attachment 47: DLA_OPS_PH II_Civil_CP104.pdf Attachment 48: DLA_OPS_PH II_Civil_CS101.pdf Attachment 49: DLA_OPS_PH II_Civil_CS102.pdf Attachment 50: DLA_OPS_PH II_Arch_A-115 - SECOND FLOOR PLAN - AREA F2.pd

AMENDED SPECIFICATIONS

Attachment 51: Amend1_DLA_OPS_PH II_Spec_31 63 29 - First Page (003).pdf Attachment 52: DLA OPS PH-2 SPECIFICATIONS 01 11 0-00 50.pdf Attachment 53: DLA OPS PH-2 SPECIFICATIONS 06 20 00.pdf Attachment 54: DLA OPS PH-2 SPECIFICATIONS 10 11 00.pdf Attachment 55: DLA OPS PH-2 SPECIFICATIONS 10 14 00-10.pdf Attachment 56: DLA OPS PH-2 SPECIFICATIONS 10 21 13.pdf Attachment 57: DLA_OPS_PH II_Spec_03 36 00.pdf

Amendment 3

Attachment 58: DLA OPS_CU101-CU102.pdf Attachment 59: DLA OPS_PH II_C-512.pdf Attachment 60: DLA OPS_PH II_CD101.pdf Attachment 61: DLA OPS_PH II_CS101.pdf Attachment 62: DLA OPS_PH II_V-101.pdf Attachment 63: DLA OPS_PH II_V-102.pdf Attachment 64: DLA OPS_PH II_V-103.pdf Attachment 65: DLA_OPS_PH II_A-103 - OVERALL THIRD FLOOR PLAN.pdf Attachment 66: DLA_OPS_PH II_A-106 - FIRST FLOOR PLAN - AREA A1.pdf Attachment 67: DLA_OPS_PH II_A-111 - FIRST FLOOR PLAN - AREA F1.pdf Attachment 68: DLA_OPS_PH II_A-113 - SECOND FLOOR PLAN - AREA A2.pdf Attachment 69: DLA_OPS_PH II_A-114 - SECOND FLOOR PLAN - AREA D2.pdf Attachment 70: DLA_OPS_PH II_A-115 - SECOND FLOOR PLAN - AREA F2.pdf Attachment 71: DLA_OPS_PH II_A-117 - THIRD FLOOR PLAN - AREA A3.pdf Attachment 72: DLA_OPS_PH II_A-118 - THIRD FLOOR PLAN - AREA D3.pdf Attachment 73: DLA_OPS_PH II_A-119 - FOURTH FLOOR PLAN - AREA A4.pdf Attachment 74: DLA_OPS_PH II_A-120 - FOURTH FLOOR PLAN - AREA D4.pdf Attachment75: DLA_OPS_PH II_A-121 - FIFTH FLOOR PLAN - AREA A5.pdf Attachment76: DLA_OPS_PH II_A-122 - FIFTH FLOOR PLAN - AREA D5.pdf Attachment77: DLA_OPS_PH II_A-145 - PARTIAL LOW LEVEL ROOF PLAN.pdf Attachment78: DLA_OPS_PH II_A-204 - ENLARGED ELEVATIONS.pdf Attachment79: DLA_OPS_PH II_A-205 - ENLARGED ELEVATIONS.pdf Attachment80: DLA_OPS_PH II_A-206 - ENLARGED ELEVATIONS.pdf Attachment81: DLA_OPS_PH II_A-207 - ENLARGED ELEVATIONS.pdf Attachment82: DLA_OPS_PH II_A-208 - ENLARGED ELEVATIONS.pdf Attachment83: DLA_OPS_PH II_A-209 - ENLARGED ELEVATIONS.pdf Attachment84: DLA_OPS_PH II_A-410 - ENLARGED ELEVATOR PLANS, SECTIONS AND DETAILS - AREA D.pdf Attachment85: DLA_OPS_PH II_A-421 - ENLARGED METROLOGY LAB AND MYLAR ROOM PLAN.pdf Attachment86: DLA_OPS_PH II_A-422 - EXTERIOR SIGNAGE PLAN, ELEVATIONS, SECTIONS AND DETAILS.pdf Attachment87: DLA_OPS_PH II_A-512 - COLUMN DETAILS.pdf Attachment88: DLA_OPS_PH II_A-526 - MISCELLANEOUS DETAILS.pdf Attachment89: DLA_OPS_PH II_A-527 - MISCELLANEOUS DETAILS.pdf Attachment90: DLA_OPS_PH II_A-601 - DOOR SCHEDULE.pdf Attachment91: DLA_OPS_PH II_A-602 - DOOR SCHEDULE.pdf Attachment92: DLA_OPS_PH II_A-603 - DOOR SCHEDULE AND DETAILS.pdf Attachment93: DLA_OPS_PH II_A-701 - FINISH SCHEDULE.pdf Attachment94: DLA_OPS_PH II_A-702 - FINISH SCHEDULE.pdf Attachment95: DLA_OPS_PH II_A-703 - FINISH SCHEDULE.pdf Attachment96: DLA_OPS_PH II_A-704 - FINISH SCHEDULE.pdf Attachment97: DLA_OPS_PH II_A-705 - FINISH SCHEDULE.pdf Attachment98: DLA_OPS_PH II_A-801 - INTERIOR SIGNAGE DETAILS.pdf Attachment99: DLA_OPS_PH II_I-106 - FIRST FLOOR FURNITURE PLAN - AREA A1.pdf Attachment100: DLA_OPS_PH II_S-002 - GENERAL NOTES.pdf Attachment101: DLA_OPS_PH II_S-101 - DRILLED PIER AND PIER CAP PLAN - AREA A.pdf Attachment102: DLA_OPS_PH II_S-104 - DRILLED PIER AND PIER CAP PLAN - AREA G.pdf Attachment103: DLA_OPS_PH II_S-110 - FOUNDATION PLAN - AREA F.pdf Attachment104: DLA_OPS_PH II_S-115 - ROOF FRAMING PLAN - AREA C.pdf Attachment105: DLA_OPS_PH II_S-118 - SECOND FLOOR FRAMING PLAN - AREA F.pdf Attachment106: DLA_OPS_PH II_S-130 - STAIRWELL FRAMING PLANS - AREA A.pdf Attachment107: DLA_OPS_PH II_S-131 - STAIRWELL FRAMING PLANS - AREA A AND AREA G.pdf Attachment108: DLA_OPS_PH II_S-132 - STAIRWELL FRAMING PLANS - AREA D.pdf Attachment109: DLA_OPS_PH II_S-133 - STAIRWELL AND ELEVATOR ROOF FRAMING PLANS - AREA D.pdf

Attachment110: DLA_OPS_PH II_S-134 - ROOF TOP UNIT SUPPORT FRAMING PLANS AND DETAILS.pdf Attachment111: DLA_OPS_PH II_S-135 - PARTIAL PLANS.pdf Attachment112: DLA_OPS_PH II_S-304 - FOUNDATION SECTIONS.pdf Attachment113: DLA_OPS_PH II_S-312 - FRAMING SECTIONS.pdf Attachment114: DLA_OPS_PH II_S-314 - FRAMING SECTIONS.pdf Attachment115: DLA_OPS_PH II_S-503 - TYPICAL DETAILS.pdf Attachment116: DLA_OPS_PH II_S-603 - COLUMN SCHEDULE.pdf Attachment117: DLA_OPS_PH II_S-604 - COLUMN SCHEDULE.pdf Attachment118: DLA_OPS_PH II_S-606 - COLUMN SCHEDULE.pdf Attachment119: DLA_OPS_PH II_SD109 - STRUCT_DEMO.pdf Attachment120: DLA_OPS_PH II_T-704 - VOICE AND DATA BACKBONE DIAGRAM.pdf Attachment121: DLA OPS PH II - Item W1 Rev.1.pdf

AMENDED SPECIFICATIONS

Attachment122: OpsCtrPhaseII_final_GeotechRpt_Sept2019.pdf Attachment123: DLA_OPS_PH II_084400 SPECIFICATIONS VOL1-Para1.5.6.pdf Attachment124: DLA_OPS_PH II_087100 SPECIFICATIONS VOL1-Door Hardware.pdf Attachment125: DLA_OPS_PH II_089100 SPECIFICATIONS VOL1-OMIT Metal Wall Louvers.pdf Attachment126: DLA_OPS_PH II_092900 SPECIFICATIONS VOL1-Gypsum Board.pdf Attachment 127: DLA_OPS_PH II_316329 SPECIFICATIONS VOL2-Page1.pdf Attachment128: DLA_OPS_PH II_316329 SPECIFICATIONS VOL2-Part 2.3.2.pdf Attachment129: DLA_OPS_PH II_321216 SPECIFICATIONS VOL2-Asphalt.pdf Attachment 130: Spec-Drawing List 07-08-20.pdf

Amendment 4:

Attachment 7: Revised CLIN Schedule Rev1.pdf

Amendment 0006:

Attachment 132: 2020-07-17_DLA OPS II_C-513.pdf Attachment 133: 2020-07-17_DLA OPS II_CD101.pdf Attachment 134: 2020-07-17_DLA OPS II_CG101-CG106.pdf Attachment 135: 2020-07-17_DLA OPS II_CG201.pdf Attachment 136: 2020-07-17_DLA OPS II_CG601.pdf Attachment 137: 2020-07-17_DLA OPS II_CU102-CU103.pdf Attachment 138: AMEND4_DLA_OPS_PH II-_A-103.pdf Attachment 139: AMEND4_DLA_OPS_PH II_A-106.pdf Attachment 140: AMEND4_DLA_OPS_PH II_A-107.pdf Attachment 141: AMEND4_DLA_OPS_PH II_A-113.pdf Attachment 142: AMEND4_DLA_OPS_PH II_A-114.pdf Attachment 143: AMEND4_DLA_OPS_PH II_A-118.pdf Attachment 144: AMEND4_DLA_OPS_PH II_A-144.pdf Attachment 145: AMEND4_DLA_OPS_PH II_A-416.pdf Attachment 146: AMEND4_DLA_OPS_PH II_A-417.pdf Attachment 147: AMEND4_DLA_OPS_PH II_A-506.pdf Attachment 148: AMEND4_DLA_OPS_PH II_A-507.pdf Attachment 149: AMEND4_DLA_OPS_PH II_A-513.pdf Attachment 150: AMEND4_DLA_OPS_PH II_A-514.pdf Attachment 151: AMEND4_DLA_OPS_PH II_A-517.pdf

Attachment 152: Amend4_DLA_OPS_PH II_Spec_01 50 02-00 50 page6.pdf

Attachment 153: Amend4_DLA_OPS_PH II_Spec_03 36 00.pdf Attachment 154: Amend4_DLA_OPS_PH II_Spec_08 41 13 page8.pdf Attachment 155: Amend4_DLA_OPS_PH II_Spec_08 44 00 page11.pdf Attachment 156: Amend4_DLA_OPS_PH II_Spec_32 05 33.pdf

(End of Summary of Changes)