263213.pdf
PDF 53 KB Posted
- Attached to
- Illinois National Guard Multiple Award Task Order Contract Federal contract opportunity
- Solicitation number
- W91SMC-09-R-0017
About this file
CP Relocation 263213 Engine Generators
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 221119.pdf | ||
| 230700.pdf | ||
| 260526.pdf | ||
| 017700.pdf | ||
| 220553.pdf | ||
| 012900.pdf | ||
| 061000.pdf | ||
| 260529.pdf | ||
| 000115.pdf | ||
| 096513.pdf | ||
| 015000.pdf | ||
| 233113.pdf | ||
| 013200.pdf | ||
| 260500.pdf | ||
| 017329.pdf | ||
| 220500.pdf | ||
| 230500.pdf | ||
| 001000.pdf | ||
| 016000.pdf | ||
| 262416.pdf | ||
| 095113.pdf | ||
| 013300-PFOIL Form 341.pdf | ||
| 010000.pdf | ||
| 262726.pdf | ||
| 123200.pdf | ||
| 260519.pdf | ||
| 220523.pdf | ||
| 014219.pdf | ||
| 024119.pdf | ||
| 262913.pdf | ||
| 017300.pdf | ||
| 262813.pdf | ||
| 099123.pdf | ||
| 260553.pdf | ||
| 017823.pdf | ||
| 072100.pdf | ||
| P101-A101.pdf | ||
| H102-A101.pdf | ||
| A701-A701.pdf | ||
| E-001-Work.pdf | ||
| P102-A101.pdf | ||
| A101-A101.pdf | ||
| V101-A101.pdf | ||
| P601-P601.pdf | ||
| V102-A101.pdf | ||
| FP101-A101.pdf | ||
| V601-A101.pdf | ||
| E-201-Work.pdf | ||
| E-301-Work.pdf | ||
| E-101-Work.pdf |
Show all 50
Illinois National Guard Multiple Award Task Order Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DCFT #082207
Hanson #03S1408GGB
263213-1 263213
ENGINE GENERATORS
DIVISION 26 - ELECTRICAL
SECTION 263213 - ENGINE GENERATORS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes packaged engine-generator sets for standby power supply with the following features:
1. Diesel engine.
2. Unit-mounted cooling system.
3. Unit and remote-mounted control and monitoring.
4. Performance requirements for sensitive loads.
5. Load banks.
6. Outdoor enclosure.
B. Related Sections include the following:
1. Division 26 Section "Transfer Switches" for transfer switches including sensors and relays to initiate automatic-starting and -stopping signals for engine-generator sets.
1.3 SUBMITTALS
A. Product Data: For each type of packaged engine generator indicated. Include rated capacities, operating characteristics, and furnished specialties and accessories. In addition, include the following:
1. Thermal damage curve for generator.
2. Time-current characteristic curves for generator protective device.
B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection:
1. Dimensioned outline plan and elevation drawings of engine-generator set and other components specified.
2. Vibration Isolation Base Details: Signed and sealed by a qualified professional engineer.
Detail fabrication, including anchorages and attachments to structure and to supported equipment. Include base weights.
3. Wiring Diagrams: Power, signal, and control wiring.
263213-2 263213
C. Manufacturer Seismic Qualification Certification: Submit certification that engine-generator set, batteries, battery racks, accessories, and components will withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." Include the following:
1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation:
a. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.
D. Qualification Data: For installer manufacturer and testing agency.
E. Source quality-control test reports:
1. Certified summary of prototype-unit test report.
2. Certified Test Reports: For components and accessories that are equivalent, but not identical, to those tested on prototype unit.
3. Certified Summary of Performance Tests: Certify compliance with specified requirement to meet performance criteria for sensitive loads.
4. Report of factory test on units to be shipped for this Project, showing evidence of compliance with specified requirements.
5. Report of sound generation.
6. Report of exhaust emissions showing compliance with applicable regulations.
7. Certified Torsional Vibration Compatibility: Comply with NFPA 110.
F. Field quality-control test reports.
G. Operation and Maintenance Data: For packaged engine generators to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following:
1. List of tools and replacement items recommended to be stored at Project for ready access.
Include part and drawing numbers, current unit prices, and source of supply.
H. Warranty: Special warranty specified in this Section.
1.4 QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for installation of units required for this Project:
1. Maintenance Proximity: Not more than four (4) hours' normal travel time from Installer's place of business to Project site.
263213-3 263213
2. Engineering Responsibility: Preparation of data for vibration isolators and seismic restraints of engine skid mounts, including Shop Drawings, based on testing and engineering analysis of manufacturer's standard units in assemblies similar to those indicated for this Project.
B. Manufacturer Qualifications: A qualified manufacturer with a service center capable of providing training, parts, and emergency maintenance repairs.
C. Testing Agency Qualifications: An independent agency, with the experience and capability to conduct the testing indicated, that is a member company of the InterNational Electrical Testing Association or is a nationally recognized testing laboratory (NRTL), and that is acceptable to authorities having jurisdiction:
1. Testing Agency's Field Supervisor: Person currently certified by the InterNational Electrical Testing Association or the National Institute for Certification in Engineering Technologies to supervise on-site testing specified in Part 3.
D. Source Limitations: Obtain packaged generator sets and auxiliary components through one source from a single manufacturer.
E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
F. Comply with ASME B15.1.
G. Comply with NFPA 37.
H. Comply with NFPA 70.
I. Comply with NFPA 99.
J. Comply with NFPA 110 requirements for Level 1 emergency power supply system.
K. Comply with UL 2200.
L. Engine Exhaust Emissions: Comply with applicable state and local government requirements.
1.5 PROJECT CONDITIONS
A. Interruption of Existing Electrical Service: Do not interrupt electrical service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electrical service according to requirements indicated:
1. Notify Construction Manager no fewer than two days in advance of proposed interruption of electrical service.
B. Environmental Conditions: Engine-generator system shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability:
263213-4 263213
1. Ambient Temperature: 5 to 40°C.
2. Relative Humidity: 0 to 95 percent.
3. Altitude: Sea level to 1,000 ft (300 m).
1.6 COORDINATION
A. Coordinate size and location of concrete bases for package engine generators. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 03.
1.7 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of packaged engine generators and associated auxiliary components that fail in materials or workmanship within specified warranty period:
1. Warranty Period: One (1) year from date of Substantial Completion.
1.8 MAINTENANCE SERVICE
A. Initial Maintenance Service: Beginning at Substantial Completion, provide 12 months' full maintenance by skilled employees of manufacturer's designated service organization. Include quarterly exercising to check for proper starting, load transfer, and running under load. Include routine preventive maintenance as recommended by manufacturer and adjusting as required for proper operation. Provide parts and supplies same as those used in the manufacture and installation of original equipment.
1.9 EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents:
1. Fuses: One (1) for every ten (10) of each type and rating, but no fewer than one (1) of each.
2. Indicator Lamps: Two (2) for every six (6) of each type used, but no fewer than two (2) of each.
3. Filters: One (1) set each of lubricating oil, fuel, and combustion-air filters.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Products: Subject to compliance with requirements, the following are provided as examples of the salient characteristics to be found in the submitted product. Manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
263213-5 263213
1. Caterpillar; Engine Div.
2. Generac Power Systems, Inc.
3. Onan/Cummins Power Generation; Industrial Business Group.
4. Baldor Electric Company.
2.2 ENGINE-GENERATOR SET
A. Factory-assembled and -tested, engine-generator set.
B. Mounting Frame: Maintain alignment of mounted components without depending on concrete foundation; and have lifting attachments:
1. Rigging Diagram: Inscribed on metal plate permanently attached to mounting frame to indicate location and lifting capacity of each lifting attachment and generator-set center of gravity.
C. Capacities and Characteristics:
1. Power Output Ratings: Nominal ratings as indicated.
2. Output Connections: Three-phase, 4-wire.
3. Nameplates: For each major system component to identify manufacturer's name and address, and model and serial number of component.
D. Generator-Set Performance for Sensitive Loads:
1. Generator shall be rated 15kw, 18.8 KVA at 0.8 BF, 208Y/120, 3-Phase, 4-wire, 60Hz.
The generator will be capable of delivering rated output KVA of rated frequency and power factor.
2. Provide a 105°C alternator.
3. Oversizing generator compared with the rated power output of the engine is permissible to meet specified performance:
a. Nameplate Data for Oversized Generator: Show ratings required by the Contract Documents rather than ratings that would normally be applied to generator size installed.
4. Steady-State Voltage Operational Bandwidth: 1 percent of rated output voltage from no load to full load.
5. Transient Voltage Performance: Not more than 10 percent variation for 50 percent step-load increase or decrease. Voltage shall recover and remain within the steady-state operating band within 0.5 second.
6. Steady-State Frequency Operational Bandwidth: Plus or minus 0.25 percent of rated frequency from no load to full load.
7. Steady-State Frequency Stability: When system is operating at any constant load within the rated load, there shall be no random speed variations outside the steady-state operational band and no hunting or surging of speed.
263213-6 263213
8. Transient Frequency Performance: Less than 2-Hz variation for 50 percent step-load increase or decrease. Frequency shall recover and remain within the steady-state operating band within three seconds.
9. Output Waveform: At no load, harmonic content measured line to neutral shall not exceed 2 percent total with no slot ripple. Telephone influence factor, determined according to NEMA MG 1, shall not exceed 50 percent.
10. Sustained Short-Circuit Current: For a 3-phase, bolted short circuit at system output terminals, system shall supply a minimum of 300 percent of rated full-load current for not less than ten (10) seconds and then clear the fault automatically, without damage to winding insulation or other generator system components.
11. Excitation System: Performance shall be unaffected by voltage distortion caused by nonlinear load:
a. Provide permanent magnet excitation for power source to voltage regulator.
12. Start Time: Comply with NFPA 110, Type 10, system requirements.
2.3 ENGINE
A. Fuel: Fuel oil, Grade DF-2.
B. Rated Engine Speed: 1,800 rpm.
C. Maximum Piston Speed for Four-Cycle Engines: 2,250 fpm (11.4 m/s).
D. Lubrication System: The following items are mounted on engine or skid:
1. Filter and Strainer: Rated to remove 90 percent of particles five (5) micrometers and smaller while passing full flow.
2. Thermostatic Control Valve: Control flow in system to maintain optimum oil temperature. Unit shall be capable of full flow and is designed to be fail-safe.
3. Crankcase Drain: Arranged for complete gravity drainage to an easily removable container with no disassembly and without use of pumps, siphons, special tools, or appliances.
E. Engine Fuel System:
1. Main Fuel Pump: Mounted on engine. Pump ensures adequate primary fuel flow under starting and load conditions.
2. Relief-Bypass Valve: Automatically regulates pressure in fuel line and returns excess fuel to source:
a. Carburetor.
b. Fuel-Shutoff Solenoid Valves.
c. Flexible Fuel Connectors.
F. Coolant Jacket Heater: Electric-immersion type, factory installed in coolant jacket system.
Comply with NFPA 110 requirements for Level 1 equipment for heater capacity.
G. Governor: Adjustable isochronous, with speed sensing.
263213-7 263213
H. Cooling System: Closed loop, liquid cooled, with radiator factory mounted on engine-generator-set mounting frame and integral engine-driven coolant pump:
1. Coolant: Solution of 50 percent ethylene-glycol-based antifreeze and 50 percent water, with anticorrosion additives as recommended by engine manufacturer.
2. Size of Radiator: Adequate to contain expansion of total system coolant from cold start to 110 percent load condition.
3. Expansion Tank: Constructed of welded steel plate and rated to withstand maximum closed-loop coolant system pressure for engine used. Equip with gage glass and petcock.
4. Temperature Control: Self-contained, thermostatic-control valve modulates coolant flow automatically to maintain optimum constant coolant temperature as recommended by engine manufacturer.
5. Coolant Hose: Flexible assembly with inside surface of nonporous rubber and outer covering of aging-, ultraviolet-, and abrasion-resistant fabric:
a. Rating: 50-psig (345-kPa) maximum working pressure with coolant at 180°F (82°C), and noncollapsible under vacuum.
b. End Fittings: Flanges or steel pipe nipples with clamps to suit piping and equipment connections.
I. Muffler/Silencer: Critical type, sized as recommended by engine manufacturer and selected with exhaust piping system to not exceed engine manufacturer's engine backpressure requirements:
1. Minimum sound attenuation of 25 dB at 500 Hz. Provide a Level 2 sound attenuated enclosure.
2. Sound level measured at a distance of 23 ft (7 m) from exhaust discharge after installation is complete shall be 66 dBA or less.
J. Air-Intake Filter: Heavy-duty, engine-mounted air cleaner with replaceable dry-filter element and "blocked filter" indicator.
K. Starting System: 12-Volt electric, with negative ground:
1. Components: Sized so they will not be damaged during a full engine-cranking cycle with ambient temperature at maximum specified in Part 1 "Project Conditions" Article.
2. Cranking Motor: Heavy-duty unit that automatically engages and releases from engine flywheel without binding.
3. Cranking Cycle: As required by NFPA 110 for system level specified.
4. Battery: Adequate capacity within ambient temperature range specified in Part 1 "Project
Conditions" Article to provide specified cranking cycle at least three times without recharging.
5. Battery Cable: Size as recommended by engine manufacturer for cable length indicated.
Include required interconnecting conductors and connection accessories.
6. Battery Compartment: Factory fabricated of metal with acid-resistant finish and thermal insulation. Thermostatically controlled heater shall be arranged to maintain battery above 10°C regardless of external ambient temperature within range specified in Part 1 "Project Conditions" Article. Include accessories required to support and fasten batteries in place.
7. Battery-Charging Alternator: Factory mounted on engine with solid-state voltage regulation and 35-A minimum continuous rating.
263213-8 263213
8. Battery Charger: Current-limiting, automatic-equalizing and float-charging type. Unit shall comply with UL 1236 and include the following features:
a. Operation: Equalizing-charging rate of 10 A shall be initiated automatically after battery has lost charge until an adjustable equalizing voltage is achieved at battery terminals. Unit shall then be automatically switched to a lower float-charging mode and shall continue to operate in that mode until battery is discharged again.
b. Automatic Temperature Compensation: Adjust float and equalize voltages for variations in ambient temperature from minus 40°C to plus 60°C to prevent overcharging at high temperatures and undercharging at low temperatures.
c. Automatic Voltage Regulation: Maintain constant output voltage regardless of input voltage variations up to plus or minus 10 percent.
d. Ammeter and Voltmeter: Flush mounted in door. Meters shall indicate charging rates.
e. Safety Functions: Sense abnormally low battery voltage and close contacts providing low battery voltage indication on control and monitoring panel. Sense high battery voltage and loss of ac input or dc output of battery charger. Either condition shall close contacts that provide a battery-charger malfunction indication at system control and monitoring panel.
f. Mounted inside the ATS.
2.4 FUEL OIL STORAGE
A. Comply with NFPA 30.
B. Base-Mounted Fuel Oil Tank: Factory installed and piped, complying with UL 142 fuel oil tank. Features include the following:
1. Tank level indicator.
2. Capacity: Provide a minimum capacity of 126 gallons.
3. Vandal-resistant fill cap.
4. Containment Provisions: Comply with requirements of authorities having jurisdiction.
2.5 CONTROL AND MONITORING
A. Automatic Starting System Sequence of Operation: When mode-selector switch on the control and monitoring panel is in the automatic position, remote-control contacts in one or more separate automatic transfer switches initiate starting and stopping of generator set. When mode-selector switch is switched to the on position, generator set starts. The off position of same switch initiates generator-set shutdown. When generator set is running, specified system or equipment failures or derangements automatically shut down generator set and initiate alarms.
Operation of a remote emergency-stop switch also shuts down generator set.
B. Manual Starting System Sequence of Operation: Switching on-off switch on the generator control panel to the on position starts generator set. The off position of same switch initiates generator-set shutdown. When generator set is running, specified system or equipment failures or derangements automatically shut down generator set and initiate alarms. Operation of a remote emergency-stop switch also shuts down generator set.
263213-9 263213
C. Configuration: Operating and safety indications, protective devices, basic system controls, and engine gages shall be grouped in a common control and monitoring panel mounted on the generator set. Mounting method shall isolate the control panel from generator-set vibration.
D. Configuration: Operating and safety indications, protective devices, basic system controls, and engine gages shall be located inside the generator enclosure.
E. Indicating and Protective Devices and Controls: As required by NFPA 110 including the following:
1. AC voltmeter.
2. AC ammeter.
3. AC frequency meter.
4. DC voltmeter (alternator battery charging).
5. Engine-coolant temperature gage.
6. Engine lubricating-oil pressure gage.
7. Running-time meter.
8. Ammeter-voltmeter, phase-selector switch(es).
9. Generator-voltage adjusting rheostat.
10. Start-stop switch.
11. Overspeed shutdown device.
12. Coolant high-temperature shutdown device.
13. Coolant low-level shutdown device.
14. Oil low-pressure shutdown device.
15. Fuel tank derangement alarm.
16. Fuel tank high-level shutdown of fuel supply alarm.
17. Generator overload.
F. Supporting Items: Include sensors, transducers, terminals, relays, and other devices and include wiring required to support specified items. Locate sensors and other supporting items on engine or generator, unless otherwise indicated.
G. Connection to Data Link: A separate terminal block, factory wired to Form C dry contacts, for each alarm and status indication is reserved for connections for data-link transmission of indications to remote data terminals.
H. Common Remote Audible Alarm: Comply with NFPA 110 requirements for Level 1 systems.
Include necessary contacts and terminals in control and monitoring panel.
1. Overcrank shutdown.
2. Coolant low-temperature alarm.
3. Control switch not in auto position.
4. Battery-charger malfunction alarm.
5. Battery low-voltage alarm.
I. Common Remote Audible Alarm: Signal the occurrence of any events listed below without differentiating between event types. Connect so that after an alarm is silenced, clearing of initiating condition will reactivate alarm until silencing switch is reset.
1. Engine high-temperature shutdown.
2. Lube-oil, low-pressure shutdown.
263213-10 263213
3. Overspeed shutdown.
4. Remote emergency-stop shutdown.
5. Engine high-temperature prealarm.
6. Lube-oil, low-pressure prealarm.
7. Fuel tank, low-fuel level.
8. Low coolant level.
J. Remote Alarm Annunciator: Comply with NFPA 99. An LED labeled with proper alarm conditions shall identify each alarm event and a common audible signal shall sound for each alarm condition. Silencing switch in face of panel shall silence signal without altering visual indication. Connect so that after an alarm is silenced, clearing of initiating condition will reactivate alarm until silencing switch is reset. Cabinet and faceplate are surface or flush-mounting type to suit mounting conditions indicated.
2.6 GENERATOR OVERCURRENT AND FAULT PROTECTION
A. Generator Circuit Breaker: Molded-case, electronic-trip type; 100 percent rated; complying with UL 489:
1. Tripping Characteristics: Adjustable long-time and short-time delay and instantaneous.
2. Trip Settings: Selected to coordinate with generator thermal damage curve.
3. Shunt Trip: Connected to trip breaker when generator set is shut down by other protective devices.
4. Mounting: Adjacent to or integrated with control and monitoring panel.
B. Ground-Fault Indication: Comply with NFPA 70, "Emergency System" signals for ground-fault. Integrate ground-fault alarm indication with other generator-set alarm indications.
2.7 GENERATOR, EXCITER, AND VOLTAGE REGULATOR
A. Comply with NEMA MG 1.
B. Drive: Generator shaft shall be directly connected to engine shaft. Exciter shall be rotated integrally with generator rotor.
C. Electrical Insulation: Class H or Class F.
D. Stator-Winding Leads: Brought out to terminal box to permit future reconnection for other voltages if required.
E. Construction shall prevent mechanical, electrical, and thermal damage due to vibration, overspeed up to 125 percent of rating, and heat during operation at 110 percent of rated capacity.
F. Enclosure: Dripproof.
G. Instrument Transformers: Mounted within generator enclosure.
H. Voltage Regulator: Solid-state type, separate from exciter, providing performance as specified:
263213-11 263213
1. Adjusting rheostat on control and monitoring panel shall provide plus or minus 5 percent adjustment of output-voltage operating band.
I. Strip Heater: Thermostatically controlled unit arranged to maintain stator windings above dew point.
J. Windings: Two-thirds pitch stator winding and fully linked amortisseur winding.
K. Subtransient Reactance: 12 percent, maximum.
2.8 OUTDOOR GENERATOR-SET ENCLOSURE
A. Description: Vandal-resistant, weatherproof steel housing, wind resistant up to 100 mph (160 km/h). Multiple panels shall be lockable and provide adequate access to components requiring maintenance. Panels shall be removable by one person without tools. Instruments and control shall be mounted within enclosure.
B. Description: Prefabricated or preengineered walk-in enclosure with the following features:
1. Construction: Galvanized-steel, metal-clad, integral structural-steel-framed building erected on concrete foundation.
2. Structural Design and Anchorage: Comply with ASCE 7 for wind loads.
3. Space Heater: Thermostatically controlled and sized to prevent condensation.
4. Louvers: Equipped with bird screen and filter arranged to permit air circulation when engine is not running while excluding exterior dust, birds, and rodents.
5. Hinged Doors: With padlocking provisions.
6. Ventilation: Louvers equipped with bird screen and filter arranged to permit air circulation while excluding exterior dust, birds, and rodents.
7. Thermal Insulation: Manufacturer's standard materials and thickness selected in coordination with space heater to maintain winter interior temperature within operating limits required by engine-generator-set components.
8. Muffler Location: Within enclosure.
C. Engine Cooling Airflow through Enclosure: Maintain temperature rise of system components within required limits when unit operates at 110 percent of rated load for two (2) hours with ambient temperature at top of range specified in system service conditions:
1. Louvers: Fixed-engine, cooling-air inlet and discharge. Storm-proof and drainable louvers prevent entry of rain and snow.
2. Automatic Dampers: At engine cooling-air inlet and discharge. Dampers shall be closed to reduce enclosure heat loss in cold weather when unit is not operating.
2.9 VIBRATION ISOLATION DEVICES
A. Restrained Spring Isolators: Freestanding, steel, open-spring isolators with seismic restraint.
1. Housing: Steel with resilient vertical-limit stops to prevent spring extension due to wind loads or if weight is removed; factory-drilled baseplate bonded to 1/4 in. (6 mm) thick, 263213-12 263213 elastomeric isolator pad attached to baseplate underside; and adjustable equipment mounting and leveling bolt that acts as blocking during installation.
2. Outside Spring Diameter: Not less than 80 percent of compressed height of the spring at rated load.
3. Minimum Additional Travel: 50 percent of required deflection at rated load.
4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.
5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure.
2.10 FINISHES
A. Indoor and Outdoor Enclosures and Components: Manufacturer's standard finish over corrosion-resistant pretreatment and compatible primer.
2.11 SOURCE QUALITY CONTROL
A. Prototype Testing: Factory test engine-generator set using same engine model, constructed of identical or equivalent components and equipped with identical or equivalent accessories:
1. Tests: Comply with NFPA 110, Level 1 Energy Converters and with IEEE 115.
B. Project-Specific Equipment Tests: Before shipment, factory test engine-generator set and other system components and accessories manufactured specifically for this Project. Perform tests at rated load and power factor. Include the following tests:
1. Test components and accessories furnished with installed unit that are not identical to those on tested prototype to demonstrate compatibility and reliability.
2. Full load run.
3. Maximum power.
4. Voltage regulation.
5. Transient and steady-state governing.
6. Single-step load pickup.
7. Safety shutdown.
8. Provide fourteen (14) days' advance notice of tests and opportunity for observation of tests by Owner's representative.
9. Report factory test results within ten (10) days of completion of test.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, equipment bases, and conditions, with Installer present, for compliance with requirements for installation and other conditions affecting packaged engine-generator performance.
B. Examine roughing-in of piping systems and electrical connections. Verify actual locations of connections before packaged engine-generator installation.
263213-13 263213
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Comply with packaged engine-generator manufacturers' written installation and alignment instructions and with NFPA 110.
B. Install packaged engine generator to provide access, without removing connections or accessories, for periodic maintenance.
C. Install packaged engine generator with restrained spring isolators having a minimum deflection of 1 in. (25 mm) on 4 in. (100 mm) high concrete base. Secure sets to anchor bolts installed in concrete bases. Concrete base construction is specified in Division 26 Section "Vibration and Seismic Controls for Electrical Systems."
3.3 CONNECTIONS
A. Piping installation requirements are specified in Division 23 Sections. Drawings indicate general arrangement of piping and specialties.
B. Connect fuel, cooling-system, and exhaust-system piping adjacent to packaged engine generator to allow service and maintenance.
C. Ground equipment according to Division 26 Section "Grounding and Bonding for Electrical Systems."
D. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables."
3.4 FIELD QUALITY CONTROL
A. Testing Agency: Engage a qualified testing agency to perform tests and inspections and prepare test reports.
B. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections.
Report results in writing.
C. Perform tests and inspections and prepare test reports:
1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing.
D. Tests and Inspections:
1. Perform tests recommended by manufacturer and each electrical test and visual and mechanical inspection for "AC Generators and for Emergency Systems" specified in NETA Acceptance Testing Specification. Certify compliance with test parameters.
263213-14 263213
2. NFPA 110 Acceptance Tests: Perform tests required by NFPA 110 that are additional to those specified here including, but not limited to, single-step full-load pickup test.
3. Battery Tests: Equalize charging of battery cells according to manufacturer's written instructions. Record individual cell voltages:
a. Measure charging voltage and voltages between available battery terminals for full-charging and float-charging conditions. Check electrolyte level and specific gravity under both conditions.
b. Test for contact integrity of all connectors. Perform an integrity load test and a capacity load test for the battery.
c. Verify acceptance of charge for each element of the battery after discharge.
d. Verify that measurements are within manufacturer's specifications.
4. Battery-Charger Tests: Verify specified rates of charge for both equalizing and float-charging conditions.
5. System Integrity Tests: Methodically verify proper installation, connection, and integrity of each element of engine-generator system before and during system operation. Check for air, exhaust, and fluid leaks.
6. Exhaust-System Back-Pressure Test: Use a manometer with a scale exceeding 40 in. wg (120 kPa). Connect to exhaust line close to engine exhaust manifold. Verify that back pressure at full-rated load is within manufacturer's written allowable limits for the engine.
7. Exhaust Emissions Test: Comply with applicable government test criteria.
8. Voltage and Frequency Transient Stability Tests: Use recording oscilloscope to measure voltage and frequency transients for 50 and 100 percent step-load increases and decreases, and verify that performance is as specified.
9. Harmonic-Content Tests: Measure harmonic content of output voltage under 25 percent and at 100 percent of rated linear load. Verify that harmonic content is within specified limits.
10. Noise Level Tests: Measure A-weighted level of noise emanating from generator-set installation, including engine exhaust and cooling-air intake and discharge, at four locations 5 ft, 10 ft, 15 ft, and 20 ft from the genset.
E. Coordinate tests with tests for transfer switches and run them concurrently.
F. Test instruments shall have been calibrated within the last twelve (12) months, traceable to standards of NIST, and adequate for making positive observation of test results. Make calibration records available for examination on request.
G. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until no leaks exist.
H. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation.
I. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.
J. Remove and replace malfunctioning units and retest as specified above.
K. Retest: Correct deficiencies identified by tests and observations and retest until specified requirements are met.
263213-15 263213
L. Report results of tests and inspections in writing. Record adjustable relay settings and measured insulation resistances, time delays, and other values and observations. Attach a label or tag to each tested component indicating satisfactory completion of tests.
M. Infrared Scanning: After Substantial Completion, but not more than 60 days after Final Acceptance, perform an infrared scan of each power wiring termination and each bus connection. Remove all access panels so terminations and connections are accessible to portable scanner:
1. Follow-up Infrared Scanning: Perform an additional follow-up infrared scan eleven (11) months after date of Substantial Completion.
2. Instrument: Use an infrared scanning device designed to measure temperature or to detect significant deviations from normal values. Provide calibration record for device.
3. Record of Infrared Scanning: Prepare a certified report that identifies terminations and connections checked and that describes scanning results. Include notation of deficiencies detected, remedial action taken, and observations after remedial action.
3.5 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain packaged engine generators.
END OF SECTION 263213