CP Relocation 096513 Resilient Base and Accessories

View the file

Other files

File Type Posted
262416.pdf PDF
016000.pdf PDF
001000.pdf PDF
095113.pdf PDF
099123.pdf PDF
211313.pdf PDF
230500.pdf PDF
011400.pdf PDF
233713.pdf PDF
262813.pdf PDF
265100.pdf PDF
017823.pdf PDF
260553.pdf PDF
260548.pdf PDF
079200.pdf PDF
260526.pdf PDF
221119.pdf PDF
230700.pdf PDF
220700.pdf PDF
014213.pdf PDF
092900.pdf PDF
012900-form.pdf PDF
072100.pdf PDF
017700.pdf PDF
087100.pdf PDF
263600.pdf PDF
260536.pdf PDF
260533.pdf PDF
233300.pdf PDF
012300.pdf PDF
013113.pdf PDF
220529.pdf PDF
220553.pdf PDF
013300.pdf PDF
014000.pdf PDF
Specs Cover.pdf PDF
078413.pdf PDF
221116.pdf PDF
012900.pdf PDF
263213.pdf PDF
061000.pdf PDF
015000.pdf PDF
000115.pdf PDF
260529.pdf PDF
233113.pdf PDF
013543.pdf PDF
210500.pdf PDF
013200.pdf PDF
101400.pdf PDF
081416.pdf PDF
Show 40 more

Latest 50 of 96 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCFT #082207

Hanson #03S1408GGB

096513-1 096513

RESILIENT BASE AND ACCESSORIES

DIVISION 09 - FINISHES

SECTION 096513 - RESILIENT BASE AND

ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Resilient wall base.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Samples for Initial Selection: For each type of product indicated.

1.4 QUALITY ASSURANCE

A. Fire-Test-Response Characteristics: As determined by testing identical products according to ASTM E 648 or NFPA 253 by a qualified testing agency:

1. Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Store resilient products and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50°F (10°C) or more than 90°F (32°C).

1.6 PROJECT CONDITIONS

A. Maintain ambient temperatures within range recommended by manufacturer, but not less than 70°F (21°C) or more than 95°F (35°C), in spaces to receive resilient products during the following time periods:

1. Forty-eight (48) hours before installation.

2. During installation.

3. Forty-eight (48) hours after installation.

096513-2 096513

B. Install resilient products after other finishing operations, including painting, have been completed.

1.7 EXTRA MATERIALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents:

1. Furnish not less than 10 linear ft (3 linear m) for every or fraction thereof, of each type, color, pattern, and size of resilient product installed.

PART 2 - PRODUCTS

2.1 RESILIENT BASE RB-1

A. Resilient Base:

1. Manufacturers: Subject to compliance with requirements, the following are provided as examples of the salient characteristics to be found in the submitted product.

Manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Armstrong World Industries, Inc.

b. Burke Mercer Flooring Products; Division of Burke Industries, Inc.

c. Flexco, Inc.

d. Johnsonite.

e. Roppe Corporation, USA.

B. Resilient Base Standard: ASTM F 1861:

1. Material Requirement: Type TS (rubber, vulcanized thermoset).

2. Manufacturing Method: Group I (solid, homogeneous).

3. Style: Cove (base with toe).

C. Minimum Thickness: 0.125 in. (3.2 mm).

D. Height: 4 in. (102 mm).

096513-3 096513

E. Lengths: Coils in manufacturer's standard length.

F. Outside Corners: Preformed.

G. Inside Corners: Preformed.

H. Finish: Low luster.

I. Colors and Patterns: MATCH EXISTING.

2.2 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland cement based or blended hydraulic-cement-based formulation provided or approved by manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by manufacturer to suit resilient products and substrate conditions indicated:

1. Use adhesives that comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

a. Cove Base Adhesives: Not more than 50 g/L.

C. Stair-Tread-Nose Filler: Two (2) part epoxy compound recommended by resilient tread manufacturer to fill nosing substrates that do not conform to tread contours.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

B. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of resilient products.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

B. Concrete Substrates for Resilient Stair Treads and Accessories: Prepare according to

ASTM F 710:

096513-4 096513

1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.

2. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using mechanical methods recommended by manufacturer. Do not use solvents.

3. Alkalinity and Adhesion Testing: Perform tests recommended by manufacturer.

C. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and remove bumps and ridges to produce a uniform and smooth substrate.

D. Do not install resilient products until they are same temperature as the space where they are to be installed:

1. Move resilient products and installation materials into spaces where they will be installed at least forty-eight (48) hours in advance of installation.

E. Sweep and vacuum clean substrates to be covered by resilient products immediately before installation.

3.3 RESILIENT BASE INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient base.

B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.

C. Install resilient base in lengths as long as practicable without gaps at seams and with tops of adjacent pieces aligned.

D. Tightly adhere resilient base to substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.

E. Do not stretch resilient base during installation.

F. On masonry surfaces or other similar irregular substrates, fill voids along top edge of resilient base with manufacturer's recommended adhesive filler material.

G. Preformed Corners: Install preformed corners before installing straight pieces.

H. Job-Formed Corners:

1. Outside Corners: Use straight pieces of maximum lengths possible. Form without producing discoloration (whitening) at bends.

2. Inside Corners: Use straight pieces of maximum lengths possible.

3.4 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protection of resilient products.

B. Perform the following operations immediately after completing resilient product installation:

096513-5 096513

1. Remove adhesive and other blemishes from exposed surfaces.

2. Sweep and vacuum surfaces thoroughly.

3. Damp-mop surfaces to remove marks and soil.

C. Protect resilient products from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period.

D. Cover resilient products until Final Inspection/Acceptance.

END OF SECTION 096513