012300.pdf
PDF 13 KB Posted
- Attached to
- Illinois National Guard Multiple Award Task Order Contract Federal contract opportunity
- Solicitation number
- W91SMC-09-R-0017
About this file
CP Relocation 012300 Options
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 221119.pdf | ||
| 230700.pdf | ||
| 260526.pdf | ||
| 017700.pdf | ||
| 220553.pdf | ||
| 012900.pdf | ||
| 061000.pdf | ||
| 263213.pdf | ||
| 260529.pdf | ||
| 000115.pdf | ||
| 096513.pdf | ||
| 015000.pdf | ||
| 233113.pdf | ||
| 013200.pdf | ||
| 260500.pdf | ||
| 017329.pdf | ||
| 220500.pdf | ||
| 230500.pdf | ||
| 001000.pdf | ||
| 016000.pdf | ||
| 262416.pdf | ||
| 095113.pdf | ||
| 013300-PFOIL Form 341.pdf | ||
| 010000.pdf | ||
| 262726.pdf | ||
| 123200.pdf | ||
| 260519.pdf | ||
| 220523.pdf | ||
| 014219.pdf | ||
| 024119.pdf | ||
| 262913.pdf | ||
| 017300.pdf | ||
| 262813.pdf | ||
| 099123.pdf | ||
| 260553.pdf | ||
| 017823.pdf | ||
| P101-A101.pdf | ||
| H102-A101.pdf | ||
| A701-A701.pdf | ||
| E-001-Work.pdf | ||
| P102-A101.pdf | ||
| A101-A101.pdf | ||
| V101-A101.pdf | ||
| P601-P601.pdf | ||
| V102-A101.pdf | ||
| FP101-A101.pdf | ||
| V601-A101.pdf | ||
| E-201-Work.pdf | ||
| E-301-Work.pdf | ||
| E-101-Work.pdf |
Show all 50
Illinois National Guard Multiple Award Task Order Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DCFT #082207
Hanson #03S1408GGB
012300-1 012300
OPTIONS
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 012300 - OPTIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for Options.
1.3 DEFINITIONS
A. Option: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the base bid amount if Contracting Officer decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Options described in this Section are part of the Work only if enumerated in the Contract.
2. The cost or credit for each Option is the net addition to or deduction from the Contract
Price to incorporate alternate into the Work. No other adjustments are made to the Contract Price.
1.4 PROCEDURES
A. Coordination: Modify or adjust affected adjacent work as necessary to completely integrate work of the Option into Project.
1. Include as part of each Option, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of Option.
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each Option. Indicate if Options have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to Options.
C. Execute accepted Options under the same conditions as other work of the Contract.
D. Schedule: A schedule of Options is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each Option.
DCFT #082207
Hanson #03S1408GGB
012300-2 012300
OPTIONS
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF OPTIONS
A. Option No.1: Provide Electronic Security System:
1. Base Bid: Not included in base bid.
2. Option: Provide work as shown on drawings, consisting of: a) Security cameras in
Entrapment 103 and in existing corridor outside of Entrapment 103; b) Door position switch, electric strike and related electrical work at Doors 100 and 105, and; c) Vindicator card reader, door position switch and electric strike.
B. Option No.2: Provide Storage Cabinets in Administration/NCOIC area 100 (immediately north of Entrapment 103):
1. Base Bid: Not included in base bid.
2. Option: Provide Storage Cabinets as shown on Sheet A1.1, “Partial First Floor-New
Work”, Sheet A7.1 elevations and details, and specified in Division 12, Section 123200 “Manufactured Wood Casework.”
C. Option No. 3: Provide Base and Wall Cabinets at Kitchenette are in Administration/NCOIC area 100:
1. Base Bid: Not included in base bid.
2. Option: Provide Base and Wall Cabinets as shown on Sheet A1.1, “Partial First Floor-
New Work”, Sheet A7.1 elevations and details, and specified in Division 12, Section 123200 “Manufactured Wood Casework.”
END OF SECTION 012300