About this file

CP Relocation 260536 Cable Trays for Electrical Systems

View the file

Other files for this federal contract opportunity

Other files attached to Illinois National Guard Multiple Award Task Order Contract, newest first.
File Type Posted
013300-PFOIL Form 341.pdf PDF
010000.pdf PDF
262726.pdf PDF
123200.pdf PDF
260519.pdf PDF
220523.pdf PDF
014219.pdf PDF
024119.pdf PDF
262913.pdf PDF
017300.pdf PDF
262813.pdf PDF
099123.pdf PDF
260553.pdf PDF
221119.pdf PDF
230700.pdf PDF
260526.pdf PDF
017700.pdf PDF
220553.pdf PDF
012900.pdf PDF
061000.pdf PDF
263213.pdf PDF
260529.pdf PDF
000115.pdf PDF
096513.pdf PDF
015000.pdf PDF
233113.pdf PDF
013200.pdf PDF
260500.pdf PDF
017329.pdf PDF
220500.pdf PDF
230500.pdf PDF
001000.pdf PDF
016000.pdf PDF
262416.pdf PDF
095113.pdf PDF
017823.pdf PDF
P102-A101.pdf PDF
A101-A101.pdf PDF
V101-A101.pdf PDF
P601-P601.pdf PDF
V102-A101.pdf PDF
FP101-A101.pdf PDF
V601-A101.pdf PDF
E-201-Work.pdf PDF
P101-A101.pdf PDF
H102-A101.pdf PDF
A701-A701.pdf PDF
E-001-Work.pdf PDF
E-301-Work.pdf PDF
E-101-Work.pdf PDF
Show all 50

Illinois National Guard Multiple Award Task Order Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCFT #082207

Hanson #03S1408GGB

260536-1 260536

CABLE TRAYS FOR

ELECTRICAL SYSTEMS

DIVISION 26 - ELECTRICAL

SECTION 260536 - CABLE TRAYS FOR

ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes steel cable trays and accessories.

1.3 SUBMITTALS

A. Product Data: Include data indicating dimensions and finishes for each type of cable tray indicated.

B. Shop Drawings: For each type of cable tray:

1. Show fabrication and installation details of cable tray, including plans, elevations, and sections of components and attachments to other construction elements. Designate components and accessories, including clamps, brackets, hanger rods, splice-plate connectors, expansion-joint assemblies, straight lengths, and fittings.

2. Seismic-Restraint Details: Signed and sealed by a qualified professional engineer, licensed in the state where Project is located, who is responsible for their preparation:

a. Design Calculations: Calculate requirements for selecting seismic restraints.

b. Detail fabrication, including anchorages and attachments to structure and to supported cable trays.

C. Coordination Drawings: Floor plans and sections, drawn to scale. Include scaled cable tray layout and relationships between components and adjacent structural, electrical, and mechanical elements. Show the following:

1. Vertical and horizontal offsets and transitions.

2. Clearances for access above and to side of cable trays.

3. Vertical elevation of cable trays above the floor or bottom of ceiling structure.

D. Field quality-control reports.

E. Operation and Maintenance Data: For cable trays to include in emergency, operation, and maintenance manuals.

260536-2 260536

1.4 QUALITY ASSURANCE

A. Source Limitations: Obtain cable tray components through one source from a single manufacturer.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

C. Comply with NFPA 70.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Steel cable tray, hot dip galvanized after fabrication, may be stored outside without cover, but shall be loosely stacked, elevated off the ground, and ventilated to prevent staining during storage.

B. Store indoors to prevent water or other foreign materials from staining or adhering to cable tray.

Unpack and dry wet materials before storage.

C. Steel, electrogalvanized or factory-primed cable tray shall be stored in a well-ventilated, dry location. Unpack and dry wet materials before storage.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, the following are provided as examples of the salient characteristics to be found in the submitted product. Manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Cooper B-Line, Inc.

2. Cope, T. J., Inc.; a subsidiary of Allied Tube & Conduit.

3. GS Metals Corp.; GLOBETRAY Products.

2.2 MATERIALS AND FINISHES

A. Cable Trays, Fittings, and Accessories: Steel, complying with NEMA VE 1:

1. Factory-standard primer, ready for field painting; with cadmium-plated hardware according to ASTM B 766.

2. Mill galvanized before fabrication, complying with ASTM A 653/A 653M, G90 (Z275) coating; with hardware galvanized according to ASTM B 633.

3. Electrogalvanized before fabrication, complying with ASTM B 633; with hardware galvanized according to ASTM B 633.

260536-3 260536

4. Hot-dip galvanized after fabrication, complying with ASTM A 123/A 123M, Class B2;

with chromium-zinc, ASTM F 1136, hardware.

5. PVC coating applied in a fluidized bed or by electrostatic spray; with chromium-zinc, ASTM F 1136 hardware.

6. Epoxy-resin paint over paint manufacturer's recommended primer and corrosion-inhibiting treatment; with cadmium-plated hardware according to ASTM B 766.

B. Cable Trays, Fittings, and Accessories: Fiberglass, complying with NEMA FG 1 and UL 568.

Splice-plate fasteners, bolts, and screws shall be fiberglass-encapsulated stainless steel. Design fasteners so that no metal is visible when fully assembled and tightened. Fastener encapsulation shall not be damaged when torqued to manufacturer's recommended value.

C. Sizes and Configurations: Refer to the Cable Tray Schedule on Drawings for specific requirements for types, materials, sizes, and configurations:

1. Center-hanger supports may be used only when specifically indicated.

2.3 CABLE TRAY ACCESSORIES

A. Fittings: Tees, crosses, risers, elbows, and other fittings as indicated, of same materials and finishes as cable tray.

B. Barrier Strips: Same materials and finishes as cable tray.

C. Cable tray supports and connectors, including bonding jumpers, as recommended by cable tray manufacturer.

2.4 WARNING SIGNS

A. Lettering: 1-1/2 in. (40 mm) high, black letters on yellow background with legend

"WARNING! NOT TO BE USED AS WALKWAY, LADDER, OR SUPPORT FOR

LADDERS OR PERSONNEL."

B. Materials and fastening are specified in Division 26 Section 260553 "Identification for Electrical Systems."

2.5 SOURCE QUALITY CONTROL

A. Perform design and production tests according to NEMA VE 1.

260536-4 260536

PART 3 - EXECUTION

3.1 CABLE TRAY INSTALLATION

A. Comply with recommendations in NEMA VE 2. Install as a complete system, including all necessary fasteners, hold-down clips, splice-plate support systems, barrier strips, hinged horizontal and vertical splice plates, elbows, reducers, tees, and crosses.

B. Remove burrs and sharp edges from cable trays.

C. Fasten cable tray supports to building structure:

1. Design each fastener and support to carry load indicated by seismic requirements

2. Place supports so that spans do not exceed maximum spans on schedules.

3. Construct supports from channel members, threaded rods, and other appurtenances furnished by cable tray manufacturer. Arrange supports in trapeze or wall-bracket form as required by application.

4. Support bus assembly to prevent twisting from eccentric loading.

5. Manufacture center-hung support, designed for 60 percent versus 40 percent eccentric loading condition, with a safety factor of 3.

6. Locate and install supports according to NEMA VE 1.

D. Make connections to equipment with flanged fittings fastened to cable tray and to equipment.

Support cable tray independent of fittings. Do not carry weight of cable tray on equipment enclosure.

E. Install expansion connectors where cable tray crosses building expansion joint and in cable tray runs that exceed dimensions recommended in NEMA VE 1. Space connectors and set gaps according to applicable standard.

F. Make changes in direction and elevation using standard fittings.

G. Make cable tray connections using standard fittings.

H. Seal penetrations through fire and smoke barriers according to Division 07 Section 078413 "Penetration Firestopping."

I. Sleeves for Future Cables: Install capped sleeves for future cables through firestop-sealed cable tray penetrations of fire and smoke barriers.

J. Workspace: Install cable trays with enough space to permit access for installing cables.

K. Install barriers to separate cables of different systems, such as power, communications, and data processing; or of different insulation levels, such as 600, 5000, and 15 000-Volt.

L. After installation of cable trays is completed, install warning signs in visible locations on or near cable trays.

260536-5 260536

3.2 CABLE INSTALLATION

A. Install cables only when cable tray installation has been completed and inspected.

B. Fasten cables on horizontal runs with cable clamps or cable ties as recommended by NEMA VE 2. Tighten clamps only enough to secure the cable, without indenting the cable jacket. Install cable ties with a tool that includes an automatic pressure-limiting device.

C. On vertical runs, fasten cables to tray every 18 in. (457 mm). Install intermediate supports when cable weight exceeds the load-carrying capacity of the tray rungs.

D. In existing construction, remove inactive or dead cables from cable tray.

E. Install covers after installation of cable is completed.

3.3 CONNECTIONS

A. Ground cable trays according to manufacturer's written instructions.

B. Install an insulated equipment grounding conductor with cable tray, in addition to those required by NFPA 70.

3.4 FIELD QUALITY CONTROL

A. After installing cable trays and after electrical circuitry has been energized, survey for compliance with requirements. Perform the following field quality-control survey:

1. Visually inspect cable insulation for damage. Correct sharp corners, protuberances in cable tray, vibration, and thermal expansion and contraction conditions, which may cause or have caused damage.

2. Verify that the number, size, and voltage of cables in cable tray do not exceed that permitted by NFPA 70. Verify that communication or data-processing circuits are separated from power circuits by barriers.

3. Verify that there is no intrusion of such items as pipe, hangers, or other equipment that could damage cables.

4. Remove deposits of dust, industrial process materials, trash of any description, and any blockage of tray ventilation.

5. Visually inspect each cable tray joint and each ground connection for mechanical continuity. Check bolted connections between sections for corrosion. Clean and retorque in suspect areas.

6. Check for missing or damaged bolts, bolt heads, or nuts. When found, replace with specified hardware.

7. Perform visual and mechanical checks for adequacy of cable tray grounding; verify that all takeoff raceways are bonded to cable tray.

B. Report results in writing.

260536-6 260536

3.5 PROTECTION

A. Protect installed cable trays:

1. Repair damage to galvanized finishes with zinc-rich paint recommended by cable tray manufacturer.

2. Repair damage to PVC or paint finishes with matching touchup coating recommended by cable tray manufacturer.

3. Install temporary protection for cables in open trays to protect exposed cables from falling objects or debris during construction. Temporary protection for cables and cable tray can be constructed of wood or metal materials until the risk of damage is over.

END OF SECTION 260536