221119.pdf

PDF 14 KB Posted

Attached to
Illinois National Guard Multiple Award Task Order Contract Federal contract opportunity
Solicitation number
W91SMC-09-R-0017
Issued by
Department of the Army Illinois Army National Guard

About this file

CP Relocation 221119 Domestic Water Piping Specialites

View the file

Other files for this federal contract opportunity

Other files attached to Illinois National Guard Multiple Award Task Order Contract, newest first.
File Type Posted
230700.pdf PDF
260526.pdf PDF
017700.pdf PDF
220553.pdf PDF
012900.pdf PDF
061000.pdf PDF
263213.pdf PDF
260529.pdf PDF
000115.pdf PDF
096513.pdf PDF
015000.pdf PDF
233113.pdf PDF
013200.pdf PDF
260500.pdf PDF
017329.pdf PDF
220500.pdf PDF
230500.pdf PDF
001000.pdf PDF
016000.pdf PDF
262416.pdf PDF
095113.pdf PDF
013300-PFOIL Form 341.pdf PDF
010000.pdf PDF
262726.pdf PDF
123200.pdf PDF
260519.pdf PDF
220523.pdf PDF
014219.pdf PDF
024119.pdf PDF
262913.pdf PDF
017300.pdf PDF
262813.pdf PDF
099123.pdf PDF
260553.pdf PDF
017823.pdf PDF
072100.pdf PDF
P101-A101.pdf PDF
H102-A101.pdf PDF
A701-A701.pdf PDF
E-001-Work.pdf PDF
P102-A101.pdf PDF
A101-A101.pdf PDF
V101-A101.pdf PDF
P601-P601.pdf PDF
V102-A101.pdf PDF
FP101-A101.pdf PDF
V601-A101.pdf PDF
E-201-Work.pdf PDF
E-301-Work.pdf PDF
E-101-Work.pdf PDF
Show all 50

Illinois National Guard Multiple Award Task Order Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCFT #082207

Hanson #03S1408GGB

221119-1 221119

DOMESTIC WATER PIPING SPECIALTIES

DIVISION 22 – PLUMBING

SECTION 221119 – DOMESTIC WATER

PIPING SPECIALTIES

PART 1 - GENERAL

1.1 WORK INCLUDES

A. Base Bid:

1. Plumbing contractor Provide:

a. Water hammer arrestors.

b. Air chambers.

1.2 RELATED WORK

A. Specified Elsewhere:

1. Section 220523 – General Duty Valves for Plumbing Piping.

2. Section 220700 – Plumbing Insulation.

3. Section 221116 – Domestic Water Piping.

4. Section 224000 - Plumbing Fixtures.

1.3 REGULATORY REQUIREMENTS

A. Illinois State Plumbing Code, 1998.

B. Plumbing and Drainage Institute, PDI.

C. Illinois Accessibility Code, April 24, 1997.

D. State of Illinois Department of Public Health Rules and Regulations.

E. National Fire Protection Association (NFPA):

1. NFPA 13 - Installation of Sprinkler Systems.

1.4 SUBMITTALS

A. Submit in accordance with Section 013300.

B. Product Data:

1. Manufacturer's product data and installation instructions.

221119-2 221119

1.5 OPERATION AND MAINTENANCE DATA

A. Submit operation data in accord with Section 017823.

B. Include manufacturer’s descriptive literature, operating instructions, maintenance and repair data, and parts listing.

1.6 DELIVERY, STORAGE AND HANDLING

A. Deliver material to site in factory-fabricated containers with labeling in place. Inspect for damage.

B. Store material in original wrappings and protect from weather and construction traffic.

C. Protect against dirt, water, chemical and mechanical damage.

D. Remove damaged materials from project site. Do not install.

PART 2 - PRODUCTS

2.1 WATER HAMMER ARRESTORS

A. ANSI A112.26.1: sized in accordance with PDI WH-201, precharged suitable for operation in temperature range – 100 to 300°F(-73 to 149°C) and a maximum 250 psig (1,700 Kpa) working pressure:

1. Acceptable Manufacturers:

Josam Mifab Smith Wade Watts Zurn

a. WHA1 75001 WHB-A 5005 W-5 SS-A Z-1700-100

b. WHA2 75002 WHB-B 5010 W-10 SS-B Z-1700-200

c. WHA3 75003 WHB-C 5020 W-20 SS-C Z-1700-300

d. WHA4 75004 WHB-D 5030 W-50 SS-D Z-1700-400

2.2 AIR CHAMBERS

A. Fit water supply to each fixture or group of fixtures with air chambers:

1. Same size as supply line or 3/4 in. (19.1 mm) minimum, and minimum 18 in. (457.2 mm) long; or extend vertically up with capped top as follows:

a. Flush valves, full pipe diameter: 24 in. (609.6 mm) minimum length.

b. Others, full pipe diameter: 8 in. (203.2 mm) minimum length.

c. Mains, full pipe diameter: 24 in. (609.6 mm) minimum length.

221119-3 221119

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install plumbing specialties in accordance with manufacturer’s instructions.

B. Exposed Water Piping in Finished Rooms: Chrome plated.

C. Install approved potable water protection devices on plumbing lines where contamination of domestic water may occur; on boiler feed water lines, janitor rooms, flush valves, interior and exterior hose bibs.

D. Install air chambers on hot and cold water supply piping to each fixture.

END OF SECTION 221119