This Request for Proposal solicits construction and design services for an Operations Support Facility at Fort Bragg, North Carolina. The scope of work includes construction of a 36,000 square foot facility built to sensitive compartmented information standards, including a command section, life support area, private and open office areas, planning and training area, language training area, security office, medical area, operations center, auditorium, break room, latrines with showers and lockers, janitor closets, electrical and mechanical rooms, and communication server rooms. Supporting facilities include utility connections, security lighting, parking, service drives, walks, storm drainage, fiber optic cable service, communications infrastructure relocation, lightning protection, landscaping, signage, and site improvements. Heating and air conditioning will be provided by a self-contained system. Comprehensive interior design services are required. The period of performance is 540 calendar days. The resultant contract will be firm-fixed price.
View the file
Other files for this federal contract opportunity
Show all 50
PN 92594 SOF Operations Support Facility has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. W912PM19R0021
SOF Operations Facility, PN 92594
Fort Bragg, North Carolina
Specifications Vol. 3 of 5
FOUO
February 2020
UNCLASSIFIED//FOR OFFICIAL USE ONLY
UNCLASSIFIED//FOR OFFICIAL USE ONLY
SOF OPERATIONS FACILITY
FORT BRAGG, NC
PN 92594
Solicitation Number W912PM19R0021
PROJECT SPECIFICATIONS - Volume 3 of 4 Divisions 23 thru Division 25
Ready to Advertise (RTA) Submission
Prepared for:
Prepared by:
Project No. 60584960
Date: 24 October 2019
Ft. Bragg - SOF
AECOM
SPECIAL OPERATIONS FACILITY PN 92594
FORT BRAGG, NORTH CAROLINA
Seals Page 1
Architecture and Interior Design Only
Structural Only
Fire Protection Only
Civil Only
Mechanical Only
Plumbing Only
Seals Page 2
Electrical Only
Telecommunication Audio Visual and Security Only
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 37 PROJECT SCHEDULE
01 33 00.00 37 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19.00 37 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00.00 37 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 10 FACILITY DATA REQUIREMENTS
01 91 00.00 37 COMMISSIONING
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
03 45 00 PRECAST ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
PROJECT TABLE OF CONTENTS Page 1
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 13 METAL WALL PANELS
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 34 59 VAULT DOORS AND DAY GATES
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 51 23 STEEL WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 68 00 CARPETING
09 69 13 RIGID GRID ACCESS FLOORING
09 72 00 WALLCOVERINGS
09 84 20 ACOUSTICAL WALL PANELS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 14 53 TRAFFIC SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
10 56 13 STEEL SHELVING
DIVISION 11 - EQUIPMENT
11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT
DIVISION 12 - FURNISHINGS
PROJECT TABLE OF CONTENTS Page 2
12 36 00 COUNTERTOPS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
22 07 19.00 40 PLUMBING PIPING INSULATION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, WATER PIPING SYSTEMS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 CYBER SECURITY FOR FIRE AND LIFE SAFETY SYSTEMS
25 05 11.02 CYBER SECURITY FOR BACNET DIRECT DIGITAL CONTROL SYSTEMS
FOR HVAC
25 05 11.03 CYBER SECURITY FOR POWER SYSTEMS AND METERING
25 05 11.04 CYBER SECURITY FOR LIGHTING SYSTEMS
25 05 11.05 CYBER SECURITY FOR HYDRAULIC PASSENGER ELEVATORS
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END
AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 00 APPARATUS INSPECTION AND TESTING
PROJECT TABLE OF CONTENTS Page 3
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH
AUXILIARIES
26 32 33.00 10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM ABOVE 15 KVA
CAPACITY
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 05 29.00 10 PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR RED
COMMUNICATION SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 41 13 FRONT PROJECTION SCREENS
27 51 19 SOUND MASKING SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION TABLE OF CONTENTS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
SECTION 23 00 00
AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
08/18
PART 1 GENERAL
1.1 REFERENCES
1.2 RELATED SECTIONS
1.3 SYSTEM DESCRIPTION
1.3.1 Mechanical Equipment Identification
1.3.1.1 Charts
1.3.1.2 Diagrams
1.3.2 Service Labeling
1.3.3 Color Coding
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.5.1 Prevention of Corrosion
1.5.2 Asbestos Prohibition
1.5.3 Ozone Depleting Substances Technician Certification
1.5.4 Detail Drawings
1.5.5 Test Procedures
1.6 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
2.2 IDENTIFICATION PLATES
2.3 EQUIPMENT GUARDS AND ACCESS
2.4 ELECTRICAL WORK
2.5 ANCHOR BOLTS
2.6 SEISMIC ANCHORAGE
2.7 PAINTING
2.8 INDOOR AIR QUALITY
2.9 DUCT SYSTEMS
2.9.1 Metal Ductwork
2.9.1.1 Metallic Flexible Duct
2.9.1.2 Insulated Nonmetallic Flexible Duct Runouts
2.9.1.3 General Service Duct Connectors
2.9.1.4 Aluminum Ducts
2.9.2 Duct Access Doors
2.9.3 Fire Dampers
2.9.4 Manual Balancing Dampers
2.9.5 Air Supply And Exhaust Air Dampers
2.9.6 Air Deflectors (Volume Extractors) and Branch Connections
2.9.7 Plenums and Casings for Field-Fabricated Units
2.9.7.1 Duct Liner
2.9.8 Sound Attenuation Equipment
2.9.8.1 Systems with total pressure above 4 Inches Water Gauge
2.9.8.2 System with total pressure of 4 Inch Water Gauge and Lower
2.9.9 Diffusers, Registers, and Grilles
SECTION 23 00 00 Page 1
2.9.9.1 Diffusers
2.9.9.2 Registers and Grilles
2.9.10 Louvers
2.9.11 Air Vents, Penthouses, and Goosenecks
2.9.12 Bird Screens and Frames
2.10 AIR SYSTEMS EQUIPMENT
2.10.1 Fans
2.10.1.1 Plenum Fans
2.10.1.2 Centrifugal Fans
2.10.1.3 In-Line Centrifugal Fans
2.10.1.4 Centrifugal Type Power Roof Ventilators
2.10.2 Coils
2.10.2.1 Direct-Expansion Coils
2.10.2.2 Water Coils
2.10.3 Air Filters
2.10.3.1 Extended Surface Pleated Panel Filters
2.10.3.2 Cartridge Type Filters
2.10.3.3 Holding Frames
2.10.3.4 Filter Gauges
2.11 AIR HANDLING UNITS
2.11.1 Factory-Fabricated Air Handling Units
2.11.1.1 Casings
2.11.1.2 Heating and Cooling Coils
2.11.1.3 Air Filters
2.11.1.4 Fans
2.11.1.5 Access Sections and Filter/Mixing Boxes
2.11.1.6 Total Energy Recovery Wheel
2.11.1.7 UV Light System
2.12 TERMINAL UNITS
2.12.1 Variable Air Volume (VAV)
2.12.1.1 Constant Volume, Single Duct Terminal Units
2.12.1.2 Variable Volume, Single Duct Terminal Units
2.12.1.3 Reheat Units
2.12.1.3.1 Hot Water Reheat
2.13 FACTORY PAINTING
2.14 SUPPLEMENTAL COMPONENTS/SERVICES
2.14.1 Chilled Water Piping
2.14.2 Refrigerant Piping
2.14.3 Water Heating System Accessories
2.14.4 Condensate Drain Lines
2.14.5 Backflow Preventers
2.14.6 Insulation
2.14.7 Controls
PART 3 EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION
3.2.1 Condensate Drain Lines
3.2.2 Equipment and Installation
3.2.3 Access Panels
3.2.4 Flexible Duct
3.2.5 Metal Ductwork
3.2.6 Dust Control
3.2.7 Insulation
3.2.8 Power Roof Ventilator Mounting
3.2.9 Power Transmission Components Adjustment
3.3 EQUIPMENT PADS
3.4 CUTTING AND PATCHING
SECTION 23 00 00 Page 2
3.5 CLEANING
3.6 PENETRATIONS
3.6.1 Sleeves
3.6.2 Framed Prepared Openings
3.6.3 Insulation
3.6.4 Closure Collars
3.6.5 Firestopping
3.7 FIELD PAINTING OF MECHANICAL EQUIPMENT
3.7.1 Temperatures less than 120 degrees F
3.7.2 Temperatures between 120 and 400 degrees F
3.7.3 Finish Painting
3.8 IDENTIFICATION SYSTEMS
3.9 DUCTWORK LEAK TEST
3.10 DAMPER ACCEPTANCE TEST
3.11 TESTING, ADJUSTING, AND BALANCING
3.12 PERFORMANCE TESTS
3.13 CLEANING AND ADJUSTING
3.14 OPERATION AND MAINTENANCE
3.14.1 Operation and Maintenance Manuals
3.14.2 Operation And Maintenance Training
-- End of Section Table of Contents --
SECTION 23 00 00 Page 3
SECTION 23 00 00
AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
08/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR MOVEMENT AND CONTROL ASSOCIATION INTERNATIONAL (AMCA)
AMCA 201 (2002; R 2011) Fans and Systems
AMCA 210 (2016) Laboratory Methods of Testing Fans for Aerodynamic Performance Rating
AMCA 300 (2014) Reverberant Room Method for Sound Testing of Fans
AMCA 301 (2014) Methods for Calculating Fan Sound Ratings from Laboratory Test Data
AMCA 500-D (2012) Laboratory Methods of Testing Dampers for Rating
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI 410 (2001; Addendum 1 2002; Addendum 2 2005;
Addendum 3 2011) Forced-Circulation Air-Cooling and Air-Heating Coils
AHRI 430 (2009) Central-Station Air-Handling Units
AHRI 880 I-P (2011) Performance Rating of Air Terminals
AHRI 885 (2008; Addendum 2011) Procedure for Estimating Occupied Space Sound Levels in the Application of Air Terminals and Air Outlets
AHRI Guideline D (1996) Application and Installation of Central Station Air-Handling Units
AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)
ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings
ABMA 9 (2015) Load Ratings and Fatigue Life for Ball Bearings
SECTION 23 00 00 Page 4
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 52.2 (2012; Errata 2013; INT 1 2014) Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size
ASHRAE 62.1 (2010) Ventilation for Acceptable Indoor Air Quality
ASHRAE 70 (2006; R 2011) Method of Testing for Rating the Performance of Air Outlets and Inlets
ASHRAE 84 (2013; Addenda A 2013) Method of Testing Air-to-Air Heat Exchangers
ASHRAE 90.1 - IP (2013) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASME INTERNATIONAL (ASME)
ASME A13.1 (2015) Scheme for the Identification of Piping Systems
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A924/A924M (2017a) Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process
ASTM B117 (2016) Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM B209 (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
ASTM B280 (2018) Standard Specification for Seamless Copper Tube for Air Conditioning and Refrigeration Field Service
ASTM B766 (1986; R 2015) Standard Specification for Electrodeposited Coatings of Cadmium
ASTM C1071 (2016) Standard Specification for Fibrous
SECTION 23 00 00 Page 5
Glass Duct Lining Insulation (Thermal and Sound Absorbing Material)
ASTM C553 (2013) Standard Specification for Mineral Fiber Blanket Thermal Insulation for Commercial and Industrial Applications
ASTM D1654 (2008; R 2016; E 2017) Standard Test Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments
ASTM D3359 (2017) Standard Test Methods for Rating Adhesion by Tape Test
ASTM D520 (2000; R 2011) Zinc Dust Pigment
ASTM E2016 (2015) Standard Specification for Industrial Woven Wire Cloth
ASTM G21 (2015) Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH SECTION 01350 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA MG 1 (2016; SUPP 2016) Motors and Generators
NEMA MG 10 (2017) Energy Management Guide for Selection and Use of Fixed Frequency Medium AC Squirrel-Cage Polyphase Induction Motors
NEMA MG 11 (1977; R 2012) Energy Management Guide for Selection and Use of Single Phase Motors
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
NFPA 90A (2018) Standard for the Installation of Air Conditioning and Ventilating Systems
NFPA 90B (2018) Standard for the Installation of Warm Air Heating and Air Conditioning Systems
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1819 (2002) Fire, Smoke and Radiation Damper
SECTION 23 00 00 Page 6
Installation Guide for HVAC Systems, 5th Edition
SMACNA 1966 (2005) HVAC Duct Construction Standards Metal and Flexible, 3rd Edition
SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 82 Protection of Stratospheric Ozone
UNDERWRITERS LABORATORIES (UL)
UL 181 (2013; Reprint Apr 2017) UL Standard for Safety Factory-Made Air Ducts and Air Connectors
UL 1995 (2015) UL Standard for Safety Heating and Cooling Equipment
UL 555 (2006; Reprint Aug 2016) UL Standard for Safety Fire Dampers
UL 586 (2009; Reprint Dec 2017) Standard for High-Efficiency Particulate, Air Filter Units
UL 6 (2007; Reprint Nov 2014) Electrical Rigid Metal Conduit-Steel
UL 705 (2017; Reprint Feb 2018) UL Standard for Safety Power Ventilators
UL 900 (2015) Standard for Air Filter Units
UL Bld Mat Dir (updated continuously online) Building Materials Directory
UL Fire Resistance (2014) Fire Resistance Directory
1.2 RELATED SECTIONS
Related work specified elsewhere:
a. Section 01 91 00.00 37 COMMISSIONING.
1.3 SYSTEM DESCRIPTION
Furnish ductwork, piping offsets, fittings, and accessories as required to provide a complete installation. Coordinate the work of the different trades to avoid interference between piping, equipment, structural, and electrical work. Provide complete, in place, all necessary offsets in piping and ductwork, and all fittings, and other components, required to
SECTION 23 00 00 Page 7 install the work as indicated and specified.
1.3.1 Mechanical Equipment Identification
The number of charts and diagrams must be equal to or greater than the number of mechanical equipment rooms. Where more than one chart or diagram per space is required, mount these in edge pivoted, swinging leaf, extruded aluminum frame holders which open to 170 degrees.
1.3.1.1 Charts
Provide chart listing of equipment by designation numbers and capacities such as flow rates, pressure and temperature differences, heating and cooling capacities, horsepower, pipe sizes, and voltage and current characteristics.
1.3.1.2 Diagrams
Submit proposed diagrams, at least 2 weeks prior to start of related testing. provide neat mechanical drawings provided with extruded aluminum frame under 1/8-inch glass or laminated plastic, system diagrams that show the layout of equipment, piping, and ductwork, and typed condensed operation manuals explaining preventative maintenance procedures, methods of checking the system for normal, safe operation, and procedures for safely starting and stopping the system. After approval, post these items where directed.
1.3.2 Service Labeling
Label equipment, including fans, air handlers, terminal units, etc. with labels made of self-sticking, plastic film designed for permanent installation. Provide labels in accordance with the typical examples below:
SERVICE LABEL AND TAG DESIGNATION
Air handling unit Number AHU - _____
Exhaust Fan Number EF - _____
VAV Box Number VAV - TU
Pump Number P - _____
Boiler Number B - _____
Chiller Number C - _____
Identify similar services with different temperatures or pressures. Where pressures could exceed 125 pounds per square inch, gage, include the maximum system pressure in the label. Label and arrow piping in accordance with the following:
a. Each point of entry and exit of pipe passing through walls.
b. Each change in direction, i.e., elbows, tees.
SECTION 23 00 00 Page 8
c. In congested or hidden areas and at all access panels at each point required to clarify service or indicated hazard.
d. In long straight runs, locate labels at distances within eyesight of each other not to exceed 75 feet. All labels must be visible and legible from the primary service and operating area.
For Bare or Insulated Pipes for Outside Diameters of Lettering
1/2 thru 1-3/8 inch 1/2 inch
1-1/2 thru 2-3/8 inch 3/4 inch
2-1/2 inch and larger 1-1/4 inch
1.3.3 Color Coding
Color coding of all piping systems must be in accordance with ASME A13.1 .
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 37 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detail Drawings; G
SD-03 Product Data
Metallic Flexible Duct
Insulated Nonmetallic Flexible Duct Runouts
Duct Connectors
Duct Access Doors; G
Fire Dampers
Manual Balancing Dampers; G
Sound Attenuation Equipment
Diffusers
Registers and Grilles
Louvers
Air Vents, Penthouses, and Goosenecks
SECTION 23 00 00 Page 9
Centrifugal Fans
In-Line Centrifugal Fans
Centrifugal Type Power Roof Ventilators
Air Handling Units; G
Constant Volume, Single Duct Terminal Units; G
Variable Volume, Single Duct Terminal Units; G
Reheat Units; G
Test Procedures
Diagrams; G
Indoor Air Quality for Duct Sealants; S
SD-06 Test Reports
Performance Tests; G
Damper Acceptance Test; G
SD-07 Certificates
Ozone Depleting Substances Technician Certification
SD-08 Manufacturer's Instructions
Manufacturer's Installation Instructions
Operation and Maintenance Training
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G
Fire Dampers; G
Manual Balancing Dampers; G
Centrifugal Fans; G
In-Line Centrifugal Fans; G
Centrifugal Type Power Roof Ventilators; G
Air Handling Units; G
Constant Volume, Single Duct Terminal Units; G
Variable Volume, Single Duct Terminal Units; G
Reheat Units; G
SECTION 23 00 00 Page 10
SD-11 Closeout Submittals
Indoor Air Quality During Construction; S
1.5 QUALITY ASSURANCE
Except as otherwise specified, approval of materials and equipment is based on manufacturer's published data.
a. Where materials and equipment are specified to conform to the standards of the Underwriters Laboratories, the label of or listing with reexamination in UL Bld Mat Dir , and UL 6 is acceptable as sufficient evidence that the items conform to Underwriters Laboratories requirements. In lieu of such label or listing, submit a written certificate from any nationally recognized testing agency, adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the specified requirements. Outline methods of testing used by the specified agencies.
b. Where materials or equipment are specified to be constructed or tested, or both, in accordance with the standards of the ASTM International (ASTM), the ASME International (ASME), or other standards, a manufacturer's certificate of compliance of each item is acceptable as proof of compliance.
c. Conformance to such agency requirements does not relieve the item from compliance with other requirements of these specifications.
1.5.1 Prevention of Corrosion
Protect metallic materials against corrosion. Provide rust-inhibiting treatment and standard finish for the equipment enclosures. Do not use aluminum in contact with earth, and where connected to dissimilar metal.
Protect aluminum by approved fittings, barrier material, or treatment.
Provide hot-dip galvanized ferrous parts such as anchors, bolts, braces, boxes, bodies, clamps, fittings, guards, nuts, pins, rods, shims, thimbles, washers, and miscellaneous parts not of corrosion-resistant steel or nonferrous materials in accordance with ASTM A123/A123M for exterior locations and cadmium-plated in conformance with ASTM B766 for interior locations.
1.5.2 Asbestos Prohibition
Do not use asbestos and asbestos-containing products.
1.5.3 Ozone Depleting Substances Technician Certification
All technicians working on equipment that contain ozone depleting refrigerants must be certified as a Section 608 Technician to meet requirements in 40 CFR 82 , Subpart F. Provide copies of technician certifications to the Contracting Officer at least 14 calendar days prior to work on any equipment containing these refrigerants.
1.5.4 Detail Drawings
Submit detail drawings showing equipment layout, including assembly and installation details and electrical connection diagrams; ductwork layout showing the location of all supports and hangers, typical hanger details, SECTION 23 00 00 Page 11 gauge reinforcement, reinforcement spacing rigidity classification, and static pressure and seal classifications. Include any information required to demonstrate that the system has been coordinated and functions properly as a unit on the drawings and show equipment relationship to other parts of the work, including clearances required for operation and maintenance. Submit drawings showing bolt-setting information, and foundation bolts prior to concrete foundation construction for all equipment indicated or required to have concrete foundations. Submit function designation of the equipment and any other requirements specified throughout this Section with the shop drawings.
1.5.5 Test Procedures
Submit proposed test procedures and test schedules for the ductwork leak test, and performance tests of systems, at least 2 weeks prior to the start of related testing.
1.6 DELIVERY, STORAGE, AND HANDLING
Protect stored equipment at the jobsite from the weather, humidity and temperature variations, dirt and dust, or other contaminants.
Additionally, cap or plug all pipes until installed.
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
Provide components and equipment that are "standard products" of a manufacturer regularly engaged in the manufacturing of products that are of a similar material, design and workmanship. "Standard products" is defined as being in satisfactory commercial or industrial use for 2 years before bid opening, including applications of components and equipment under similar circumstances and of similar size, satisfactorily completed by a product that is sold on the commercial market through advertisements, manufacturers' catalogs, or brochures. Products having less than a 2-year field service record are acceptable if a certified record of satisfactory field operation, for not less than 6000 hours exclusive of the manufacturer's factory tests, can be shown. Provide equipment items that are supported by a service organization.
2.2 IDENTIFICATION PLATES
In addition to standard manufacturer's identification plates, provide engraved laminated phenolic identification plates for each piece of mechanical equipment. Identification plates are to designate the function of the equipment. Submit designation with the shop drawings. Provide identification plates that are layers, black-white-black, engraved to show white letters on black background. Letters must be upper case.
Identification plates that are 1-1/2-inches high and smaller must be 1/16-inch thick, with engraved lettering 1/8-inch high; identification plates larger than 1-1/2-inches high must be 1/8-inch thick, with engraved lettering of suitable height. Identification plates 1-1/2-inches high and larger must have beveled edges. Install identification plates using a compatible adhesive.
2.3 EQUIPMENT GUARDS AND ACCESS
Fully enclose or guard belts, pulleys, chains, gears, couplings, projecting setscrews, keys, and other rotating parts exposed to personnel
SECTION 23 00 00 Page 12 contact according to OSHA requirements. Properly guard or cover with insulation of a type specified, high temperature equipment and piping exposed to contact by personnel or where it creates a potential fire hazard
2.4 ELECTRICAL WORK
a. Provide motors, controllers, integral disconnects, contactors, and controls with their respective pieces of equipment, except controllers indicated as part of motor control centers. Provide electrical equipment, including motors and wiring, as specified in Section 26 20 00INTERIOR DISTRIBUTION SYSTEM. Provide manual or automatic control and protective or signal devices required for the operation specified and control wiring required for controls and devices specified, but not shown. For packaged equipment, include manufacturer provided controllers with the required monitors and timed restart.
b. For single-phase motors, provide high-efficiency type, fractional-horsepower alternating-current motors, including motors that are part of a system, in accordance with NEMA MG 11. Provide premium efficiency type integral size motors in accordance with
NEMA MG 1.
c. For polyphase motors, provide squirrel-cage medium induction motors, including motors that are part of a system , and that meet the efficiency ratings for premium efficiency motors in accordance with NEMA MG 1. Select premium efficiency polyphase motors in accordance with NEMA MG 10.
d. Provide motors in accordance with NEMA MG 1 and of sufficient size to drive the load at the specified capacity without exceeding the nameplate rating of the motor. Provide motors rated for continuous duty with the enclosure specified. Provide motor duty that allows for maximum frequency start-stop operation and minimum encountered interval between start and stop. Provide motor torque capable of accelerating the connected load within 20 seconds with 80 percent of the rated voltage maintained at motor terminals during one starting period. Provide motor starters complete with thermal overload protection and other necessary appurtenances. Fit motor bearings with grease supply fittings and grease relief to outside of the enclosure.
e. Provide variable frequency drives for motors as specified in Section
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS.
2.5 ANCHOR BOLTS
Provide anchor bolts for equipment placed on concrete equipment pads or on concrete slabs. Bolts to be of the size and number recommended by the equipment manufacturer and located by means of suitable templates.
Installation of anchor bolts must not degrade the surrounding concrete.
2.6 SEISMIC ANCHORAGE
Anchor equipment in accordance with applicable seismic criteria for the area and as defined in SMACNA 1981
2.7 PAINTING
Paint equipment units in accordance with approved equipment manufacturer's
SECTION 23 00 00 Page 13 standards unless specified otherwise. Field retouch only if approved.
Otherwise, return equipment to the factory for refinishing.
2.8 INDOOR AIR QUALITY
Provide equipment and components that comply with the requirements of ASHRAE 62.1 unless more stringent requirements are specified herein.
2.9 DUCT SYSTEMS
2.9.1 Metal Ductwork
Provide metal ductwork construction, including all fittings and components, that complies with SMACNA 1966, as supplemented and modified by this specification.
a. Provide double walled internally insulated duct with perforated liner for all exposed exterior rooftop ductwork. Duct liner will be acoustically insulated antimicrobial flexible fiberglass with mylar in compliance with ASTM C1071, Type I; ASTM G21; and NFPA 90A or NFPA 90B as applicable.
a. Provide radius type elbows with a centerline radius of 1.5 times the width or diameter of the duct where space permits. Otherwise, elbows having a minimum radius equal to the width or diameter of the duct or square elbows with factory fabricated turning vanes are allowed.
b. Provide ductwork for all duct systems that meets the requirements of Seal Class A.
c. Provide sealants that conform to fire hazard classification specified in Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS and are suitable for the range of air distribution and ambient temperatures to which it is exposed. Do not use pressure sensitive tape as a sealant. Provide duct sealant products that meet either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 (HVAC duct sealants are classified as "Other" within the SCAQMD Rule 1168 sealants table). Provide validation of indoor air quality for duct sealants.
d. Make spiral lock seam duct, and flat oval with duct sealant and lock with not less than 3 equally spaced drive screws or other approved methods indicated in SMACNA 1966. Apply the sealant to the exposed male part of the fitting collar so that the sealer is on the inside of the joint and fully protected by the metal of the duct fitting. Apply one brush coat of the sealant over the outside of the joint to at least 2 inch band width covering all screw heads and joint gap. Dents in the male portion of the slip fitting collar are not acceptable.
Fabricate outdoor air intake ducts and plenums with watertight soldered or brazed joints and seams.
2.9.1.1 Metallic Flexible Duct
a. Provide duct that conforms to UL 181 and NFPA 90A with factory-applied insulation, vapor barrier, and end connections. Provide duct assembly that does not exceed 25 for flame spread and 50 for smoke developed.
Provide ducts designed for working pressures of 2 inches water gauge positive and 1.5 inches water gauge negative. Provide flexible round
SECTION 23 00 00 Page 14 duct length that does not exceed 5 feet. Secure connections by applying adhesive for 2 inches over rigid duct, apply flexible duct 2 inches over rigid duct, apply metal clamp, and provide minimum of three No. 8 sheet metal screws through clamp and rigid duct.
b. Inner duct core: Provide interlocking spiral or helically corrugated flexible core constructed of zinc-coated steel, aluminum, or stainless steel; or constructed of inner liner of continuous galvanized spring steel wire helix fused to continuous, fire-retardant, flexible vapor barrier film, inner duct core.
c. Insulation: Provide inner duct core that is insulated with mineral fiber blanket type flexible insulation, minimum of 1 inch thick.
Provide insulation covered on exterior with manufacturer's standard fire retardant vapor barrier jacket for flexible round duct.
2.9.1.2 Insulated Nonmetallic Flexible Duct Runouts
Use flexible duct runouts only where indicated. Runout length is indicated on the drawings, and is not to exceed 5 feet. Provide runouts that are preinsulated, factory fabricated, and that comply with NFPA 90A and UL 181 . Provide either field or factory applied vapor barrier.
Provide not less than 20 ounce glass fabric duct connectors coated on both sides with neoprene. Where coil induction or high velocity units are supplied with vertical air inlets, use a streamlined, vaned and mitered elbow transition piece for connection to the flexible duct or hose.
Provide a die-stamped elbow and not a flexible connector as the last elbow to these units other than the vertical air inlet type. Insulated flexible connectors are allowed as runouts. Provide insulated material and vapor barrier that conform to the requirements of Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS. Do not expose the insulation material surface to the air stream.
2.9.1.3 General Service Duct Connectors
Provide a flexible duct connector approximately 6 inches in width where sheet metal connections are made to fans or where ducts of dissimilar metals are connected. For round/oval ducts, secure the flexible material by stainless steel or zinc-coated, iron clinch-type draw bands. For rectangular ducts, install the flexible material locked to metal collars using normal duct construction methods. Provide a composite connector system that complies with NFPA 701 and is classified as "flame-retardent fabrics" in UL Bld Mat Dir .
2.9.1.4 Aluminum Ducts
ASTM B209, alloy 3003-H14 for aluminum sheet and alloy 6061-T6 or equivalent strength for aluminum connectors and bar stock.
2.9.2 Duct Access Doors
Provide hinged access doors conforming to SMACNA 1966 in ductwork and plenums where indicated and at all air flow measuring primaries, automatic dampers, fire dampers, coils, thermostats, and other apparatus requiring service and inspection in the duct system. Provide access doors upstream and downstream of air flow measuring primaries and heating and cooling coils. Provide doors that are a minimum 15 by 18 inches, unless otherwise shown. Where duct size does not accommodate this size door, make the doors as large as practicable. Equip doors 24 by 24 inches or larger with
SECTION 23 00 00 Page 15 fasteners operable from inside and outside the duct. Use insulated type doors in insulated ducts.
2.9.3 Fire Dampers
Use 1.5 hour rated fire dampers unless otherwise indicated. Provide fire dampers that conform to the requirements of NFPA 90A and UL 555 . Perform the fire damper test as outlined in NFPA 90A. Provide a pressure relief door upstream of the fire damper. If the ductwork connected to the fire damper is to be insulated then provide a factory installed pressure relief damper. Provide automatic operating fire dampers with a dynamic rating suitable for the maximum air velocity and pressure differential to which it is subjected. Provide fire dampers approved for the specific application, and install according to their listing. Equip fire dampers with a steel sleeve or adequately sized frame installed in such a manner that disruption of the attached ductwork, if any, does not impair the operation of the damper. Equip sleeves or frames with perimeter mounting angles attached on both sides of the wall or floor opening. Construct ductwork in fire-rated floor-ceiling or roof-ceiling assembly systems with air ducts that pierce the ceiling of the assemblies in conformance with UL Fire Resistance . Provide curtain type with damper blades out of the air stream fire dampers. Install dampers that do not reduce the duct or the air transfer opening cross-sectional area. Install dampers so that the centerline of the damper depth or thickness is located in the centerline of the wall, partition or floor slab depth or thickness.
Unless otherwise indicated, comply with the installation details given in SMACNA 1819 and in manufacturer's instructions for fire dampers. Perform acceptance testing of fire dampers according to paragraph Fire Damper Acceptance Test and NFPA 90A.
2.9.4 Manual Balancing Dampers
Furnish manual balancing dampers with accessible operating mechanisms.
Use chromium plated operators (with all exposed edges rounded) in finished portions of the building. Provide manual volume control dampers that are operated by locking-type quadrant operators. Install dampers that are 2 gauges heavier than the duct in which installed. Unless otherwise indicated, provide opposed blade type multileaf dampers with maximum blade width of 12 inches. Provide access doors or panels for all concealed damper operators and locking setscrews. Provide stand-off mounting brackets, bases, or adapters not less than the thickness of the insulation when the locking-type quadrant operators for dampers are installed on ducts to be thermally insulated, to provide clearance between the duct surface and the operator. Provide stand-off mounting items that are integral with the operator or standard accessory of the damper manufacturer.
2.9.5 Air Supply And Exhaust Air Dampers
Provide outdoor air supply and exhaust air dampers that have a maximum leakage rate when tested in accordance with AMCA 500-D as required by ASHRAE 90.1 - IP . 2.9.6 Air Deflectors (Volume Extractors) and Branch
Connections
Provide air deflectors (volume extractors) at all duct mounted supply outlets, at takeoff or extension collars to supply outlets, at duct branch takeoff connections, and at 90 degree elbows, as well as at locations as indicated on the drawings or otherwise specified. Conical branch connections or 45 degree entry connections are allowed in lieu of
SECTION 23 00 00 Page 16 deflectors for branch connections. Furnish all air deflectors (volume extractors), except those installed in 90 degree elbows, with an approved means of adjustment. Provide easily accessible means for adjustment inside the duct or from an adjustment with sturdy lock on the face of the duct. When installed on ducts to be thermally insulated, provide external adjustments with stand-off mounting brackets, integral with the adjustment device, to provide clearance between the duct surface and the adjustment device not less than the thickness of the thermal insulation. Provide factory-fabricated air deflectors consisting of curved turning vanes or louver blades designed to provide uniform air distribution and change of direction with minimum turbulence or pressure loss. Provide factory or field assembled air deflectors (volume extractors). Make adjustment from the face of the diffuser or by position adjustment and lock external to the duct. Provide stand-off brackets on insulated ducts as described herein. Provide fixed air deflectors (volume extractors), also called turning vanes, in 90 degree elbows.
2.9.7 Plenums and Casings for Field-Fabricated Units
2.9.7.1 Duct Liner
Unless otherwise specified, duct liner is not permitted.
2.9.8 Sound Attenuation Equipment
2.9.8.1 Systems with total pressure above 4 Inches Water Gauge
Provide sound attenuators on the discharge duct of each fan operating at a total pressure above 4 inch water gauge, and, when indicated, at the intake of each fan system. Provide sound attenuators elsewhere as indicated. Provide factory fabricated sound attenuators, tested by an independent laboratory for sound and performance characteristics. Provide a net sound reduction as indicated. Maximum permissible pressure drop is not to exceed 0.63 inch water gauge. Construct traps to be airtight when operating under an internal static pressure of 10 inch water gauge.
Provide air-side surface capable of withstanding air velocity of 10,000 fpm.
Certify that the equipment can obtain the sound reduction values specified after the equipment is installed in the system and coordinated with the sound information of the system fan to be provided. Provide sound absorbing material conforming to ASTM C1071, Type I or II. Provide sound absorbing material that meets the fire hazard rating requirements for insulation specified in Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS. For connection to ductwork, provide a duct transition section.
Factory fabricated double-walled internally insulated spiral lock seam and round duct and fittings designed for high pressure air system can be provided if complying with requirements specified for factory fabricated sound attenuators, in lieu of factory fabricated sound attenuators.
Construct the double-walled duct and fittings from an outer metal pressure shell of zinc-coated steel sheet, 1 inch thick acoustical blanket insulation, and an internal perforated zinc-coated metal liner. Provide a sufficient length of run to obtain the noise reduction coefficient specified. Certify that the sound reduction value specified can be obtained within the length of duct run provided. Provide welded or spiral lock seams on the outer sheet metal of the double-walled duct to prevent water vapor penetration. Provide duct and fittings with an outer sheet that conforms to the metal thickness of high-pressure spiral and round ducts and fittings shown in SMACNA 1966. Provide acoustical insulation with a thermal conductivity "k" of not more than 0.27 Btu/inch/square foot/hour/degree F at 75 degrees F mean temperature. Provide an internal
SECTION 23 00 00 Page 17 perforated zinc-coated metal liner that is not less than 24 gauge with perforations not larger than 1/4 inch in diameter providing a net open area not less than 10 percent of the surface.
2.9.8.2 System with total pressure of 4 Inch Water Gauge and Lower
Use sound attenuators only where indicated. Provide factory fabricated sound attenuators that are constructed of galvanized steel sheets.
Provide attenuator with outer casing that is not less than 22 gauge.
Provide fibrous glass acoustical fill. Provide net sound reduction indicated. Obtain values on a test unit not less than 24 by 24 inches outside dimensions made by a certified nationally recognized independent acoustical laboratory. Provide air flow capacity as indicated or required. Provide pressure drop through the attenuator that does not exceed the value indicated, or that is not in excess of 15 percent of the total external static pressure of the air handling system, whichever is less. Acoustically test attenuators with metal duct inlet and outlet sections while under the rated air flow conditions. Include with the noise reduction data the effects of flanking paths and vibration transmission. Construct sound attenuators to be airtight when operating at the internal static pressure indicated or specified for the duct system, but in no case less than 2 inch water gauge.
2.9.9 Diffusers, Registers, and Grilles
Provide factory-fabricated units of steel or aluminum that distribute the specified quantity of air evenly over space intended without causing noticeable drafts, air movement faster than 50 fpm in occupied zone, or dead spots anywhere in the conditioned area. Provide outlets for diffusion, spread, throw, and noise level as required for specified performance. Certify performance according to ASHRAE 70. Provide sound rated and certified inlets and outlets according to ASHRAE 70. Provide sound power level as indicated. Provide opposed blade type volume dampers for all diffusers and registers, except linear slot diffusers. Provide linear slot diffusers with round or elliptical balancing dampers. Where the inlet and outlet openings are located less than 7 feet above the floor, protect them by a grille or screen according to NFPA 90A.
2.9.9.1 Diffusers
Provide diffuser types indicated. Furnish ceiling mounted units with anti-smudge devices, unless the diffuser unit minimizes ceiling smudging through design features. Provide diffusers with air deflectors of the type indicated. Install ceiling mounted units with rims tight against ceiling. Provide sponge rubber gaskets between ceiling and surface mounted diffusers for air leakage control. Provide suitable trim for flush mounted diffusers. For connecting the duct to diffuser, provide duct collar that is airtight and does not interfere with volume controller. Provide return or exhaust units that are similar to supply diffusers.
2.9.9.2 Registers and Grilles
Provide units that are four-way directional-control type, except provide return and exhaust registers that are fixed horizontal or vertical louver type similar in appearance to the supply register face. Furnish registers with sponge-rubber gasket between flanges and wall or ceiling. Install wall supply registers at least 6 inches below the ceiling unless otherwise indicated. Locate return and exhaust registers 6 inches above the floor
SECTION 23 00 00 Page 18 unless otherwise indicated. Achieve four-way directional control by a grille face which can be rotated in 4 positions or by adjustment of horizontal and vertical vanes. Provide grilles as specified for registers, without volume control damper.
2.9.10 Louvers
Provide louvers for installation in exterior walls that are associated with the air supply and distribution system as specified in Section
08 91 00 METAL WALL AND DOOR LOUVERS.
2.9.11 Air Vents, Penthouses, and Goosenecks
Fabricate air vents, penthouses, and goosenecks from galvanized steel or aluminum sheets with galvanized or aluminum structural shapes. Provide sheet metal thickness, reinforcement, and fabrication that conform to SMACNA 1966. Accurately fit and secure louver blades to frames. Fold or bead edges of louver blades for rigidity and baffle these edges to exclude driving rain. Provide air vents, penthouses, and goosenecks with bird screen.
2.9.12 Bird Screens and Frames
Provide bird screens that conform to ASTM E2016, No. 2 mesh, aluminum or stainless steel. Provide "medium-light" rated aluminum screens. Provide "light" rated stainless steel screens. Provide removable type frames fabricated from either stainless steel or extruded aluminum.
2.10 AIR SYSTEMS EQUIPMENT
2.10.1 Fans
Test and rate fans according to AMCA 210. Calculate system effect on air moving devices in accordance with AMCA 201 where installed ductwork differs from that indicated on drawings. Install air moving devices to minimize fan system effect. Where system effect is unavoidable, determine the most effective way to accommodate the inefficiencies caused by system effect on the installed air moving device. The sound power level of the fans must not exceed 85 dBA when tested according to AMCA 300 and rated in accordance with AMCA 301. Provide all fans with an AMCA seal. Connect fans to the motors either directly or indirectly with V-belt drive. Use V-belt drives designed for not less than 150 percent of the connected driving capacity. Provide variable pitch motor sheaves for 15 hp and below, and fixed pitch as defined by AHRI Guideline D (A fixed-pitch sheave is provided on both the fan shaft and the motor shaft. This is a non-adjustable speed drive.). Select variable pitch sheaves to drive the fan at a speed which can produce the specified capacity when set at the approximate midpoint of the sheave adjustment. When fixed pitch sheaves are furnished, provide a replaceable sheave when needed to achieve system air balance. Provide motors for V-belt drives with adjustable rails or bases. Provide removable metal guards for all exposed V-belt drives, and provide speed-test openings at the center of all rotating shafts. Provide fans with personnel screens or guards on both suction and supply ends, except that the screens need not be provided, unless otherwise indicated, where ducts are connected to the fan. Provide fan and motor assemblies with vibration-isolation supports or mountings as indicated. Use vibration-isolation units that are standard products with published loading ratings. Select each fan to produce the capacity required at the fan static pressure indicated. Provide sound power level as indicated.
SECTION 23 00 00 Page 19
Obtain the sound power level values according to AMCA 300. Provide standard AMCA arrangement, rotation, and discharge as indicated. Provide power ventilators that conform to UL 705 and have a UL label.
2.10.1.1 Plenum Fans
Provide single width, single inlet plenum fans. Provide aluminum, backward inclined fan blades. Provide direct drive motors with open drip proof enclosures. Provide variable frequency drive as specified in Section 26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS. Where multiple fans are required to meet the scheduled capacity, all fans shall accept a common control signal to modulate fan speed. Provide integral low loss backdraft damper.