03 30 00.00 10.pdf

PDF 110 KB Posted

Attached to
PN 92594 SOF Operations Support Facility Federal contract opportunity
Solicitation number
W912PM
Issued by
Department of the Army Corps of Engineers Engineering District Wilmington

About this file

This Request for Proposal solicits construction and design services for an Operations Support Facility at Fort Bragg, North Carolina. The scope of work includes construction of an approximately 36,000 square foot facility to sensitive compartmented information standards, including office, training, medical, operations, and support spaces. Comprehensive building and furnishings related interior design services are required. Sustainability, energy enhancement, fire protection, mass notification, cyber security, and intrusion detection systems will be incorporated. The period of performance shall not exceed 540 calendar days. The resultant contract will be firm-fixed price awarded by the Department of the Army Corps of Engineers Engineering District Wilmington.

View the file

Other files for this federal contract opportunity

Other files attached to PN 92594 SOF Operations Support Facility, newest first.
File Type Posted
PN92594_W912PM19R00210005.pdf PDF
FY20PN92594A-602.pdf PDF
FY20PN92594IF601.pdf PDF
FY20PN92594A-102.pdf PDF
FY20PN92594A-412.pdf PDF
FY20PN92594A-601.pdf PDF
PN92594_0003_Technical Summary of Changes.pdf PDF
PN92594_W912PM19R00210003.pdf PDF
FY20PN92594T101.pdf PDF
10 44 16.pdf PDF
FY20PN92594T102.pdf PDF
FY20PN92594M-501.pdf PDF
FY20PN92594M-503.pdf PDF
01 45 35.pdf PDF
PN92594_0002_Technical Summary of Changes.pdf PDF
FY20PN92594M-602.pdf PDF
PN92594_W912PM19R00210002.pdf PDF
FY20PN92594MP102.pdf PDF
08 33 23.pdf PDF
03 45 00.pdf PDF
FY20PN92594IN101.pdf PDF
FY20PN92594TA501.pdf PDF
FY20PN92594IN601.pdf PDF
FY20PN92594A-101.pdf PDF
FY20PN92594A-410.pdf PDF
FY20PN92594T504.pdf PDF
01 33 00.00 37 Submittal Register.pdf PDF
PN 92594_RTA SPECS_VOL 01 (Amend0001).pdf PDF
PN92594_W912PM19R00210001.pdf PDF
PN 92594_RTA SPECS_VOL 05 (Amend0001).pdf PDF
Technical Summary of Changes to W912PM19R0021-0001_pn92594.pdf PDF
Site Visit Sign In Roster 92594 .pdf PDF
J&A W912PM19R0021 (PN92594) Chillers.pdf PDF
PN 92594_RTA SPECS_VOL 03 (1).pdf PDF
PN 92594_RTA SPECS_VOL 05 (1).pdf PDF
PN92594_RTA_PLANS_vol2of2 (1).pdf PDF
NAVFAC_USACE PPQ.pdf PDF
PN 92594_RTA SPECS_VOL 02 (1).pdf PDF
PN 92594_RTA SPECS_VOL 01 (1).pdf PDF
PN 92594_RTA SPECS_VOL 04 (1).pdf PDF
PN92594_RTA_PLANS_vol1of2 (1).pdf PDF
NAVFAC_USACE PPQ.pdf PDF
PN 92594_RTA SPECS_VOL 04 (1).pdf PDF
PN 92594_RTA SPECS_VOL 01 (1).pdf PDF
PN 92594_RTA SPECS_VOL 05 (1).pdf PDF
J&A W912PM19R0021 (PN92594) Chillers.pdf PDF
PN92594_RTA_PLANS_vol2of2 (1).pdf PDF
PN92594_RTA_PLANS_vol1of2 (1).pdf PDF
PN 92594_RTA SPECS_VOL 03 (1).pdf PDF
PN 92594_RTA SPECS_VOL 02 (1).pdf PDF
Show all 50

PN 92594 SOF Operations Support Facility has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL OPERATIONS FACILITY PN 92594

FORT BRAGG, NORTH CAROLINA

SECTION TABLE OF CONTENTS

DIVISION 03 - CONCRETE

SECTION 03 30 00.00 10

CAST-IN-PLACE CONCRETE

05/14

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Cementitious Material

1.2.2 Chemical Admixtures

1.2.3 Complementary Cementing Materials (CCM)

1.2.4 Design Strength (f'c)

1.2.5 Mixture Proportioning

1.2.6 Mixture Proportions

1.2.7 Pozzolan

1.2.8 Workability or Consistency

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Laboratory Accreditation

1.4.1.1 Aggregate Testing and Mix Proportioning

1.4.1.2 Acceptance Testing

1.4.1.3 Contractor Quality Control

1.4.2 Quality Control Plan

1.4.3 Pre-installation Meeting

1.4.4 Special Properties and Products

1.4.5 Government Assurance Inspection and Testing

1.4.5.1 Materials

1.4.5.2 Fresh Concrete

1.4.5.3 Hardened Concrete

1.4.5.4 Inspection

1.5 DELIVERY, STORAGE, AND HANDLING

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

2.1.1 Proportioning Studies-Normal Weight Concrete

2.1.2 Average Compressive Strength

2.1.3 Computations from Test Records

2.1.4 Tolerances

2.1.5 Floor Finish

2.1.6 Strength Requirements

2.1.6.1 Evaluation of Concrete Compressive Strength

2.1.6.2 Investigation of Low-Strength Compressive Test Results

2.1.6.3 Load Tests

2.1.7 Water-Cementitious Material Ratio

2.1.8 Air Entrainment

2.1.9 Slump

2.1.10 Concrete Temperature

2.1.11 Size of Coarse Aggregate

2.2 CEMENTITIOUS MATERIALS

SECTION 03 30 00.00 10 Page 1

2.2.1 Portland Cement

2.2.2 Blended Cements

2.2.3 Fly Ash

2.2.4 Raw or Calcined Natural Pozzolan

2.2.5 Ultra Fine Fly Ash and Ultra Fine Pozzolan

2.2.6 Ground Granulated Blast-Furnace (GGBF) Slag

2.3 AGGREGATES

2.3.1 Fine Aggregate

2.3.2 Coarse Aggregate

2.4 CHEMICAL ADMIXTURES

2.4.1 Air-Entraining Admixture

2.4.2 Accelerating Admixture

2.4.3 Water-Reducing or Retarding Admixture

2.4.4 High-Range Water Reducer

2.4.5 Surface Retarder

2.4.6 Expanding Admixture

2.4.7 Other Chemical Admixtures

2.5 WATER

2.6 NONSHRINK GROUT

2.7 NONSLIP SURFACING MATERIAL

2.8 EMBEDDED ITEMS

2.9 VAPOR RETARDER

2.10 JOINT MATERIALS

2.10.1 Joint Fillers, Sealers, and Waterstops

2.10.2 Contraction Joints in Slabs

PART 3 EXECUTION

3.1 PREPARATION FOR PLACING

3.1.1 Foundations

3.1.1.1 Concrete on Earth Foundations

3.1.1.2 Preparation of Rock

3.1.1.3 Excavated Surfaces in Lieu of Forms

3.1.2 Previously Placed Concrete

3.1.2.1 Air-Water Cutting

3.1.2.2 High-Pressure Water Jet

3.1.2.3 Wet Sandblasting

3.1.2.4 Waste Disposal

3.1.2.5 Preparation of Previously Placed Concrete

3.1.3 Vapor Retarder

3.1.4 Embedded Items

3.2 CONCRETE PRODUCTION

3.2.1 General Requirements

3.2.2 Batching Equipment

3.2.3 Scales

3.2.4 Batching Tolerances

3.2.5 Moisture Control

3.2.6 Concrete Mixers

3.2.7 Stationary Mixers

3.2.8 Truck Mixers

3.3 TRANSPORTING CONCRETE TO PROJECT SITE

3.4 PLACING CONCRETE

3.4.1 Depositing Concrete

3.4.2 Consolidation

3.4.3 Cold Weather Requirements

3.4.4 Hot Weather Requirements

3.4.5 Prevention of Plastic Shrinkage Cracking

3.4.6 Placing Concrete in Congested Areas

3.4.7 Placing Flowable Concrete

SECTION 03 30 00.00 10 Page 2

3.5 JOINTS

3.5.1 Construction Joints

3.5.2 Contraction Joints in Slabs on Grade

3.5.3 Waterstops

3.5.4 Dowels and Tie Bars

3.6 SETTING BASE PLATES AND BEARING PLATES

3.6.1 Damp-Pack Bedding Mortar

3.6.2 Nonshrink Grout

3.6.2.1 Mixing and Placing of Nonshrink Grout

3.6.2.2 Treatment of Exposed Surfaces

3.7 TESTING AND INSPECTION FOR CQC

3.7.1 Grading and Corrective Action

3.7.1.1 Fine Aggregate

3.7.1.2 Coarse Aggregate

3.7.2 Quality of Aggregates

3.7.3 Scales, Batching and Recording

3.7.4 Batch-Plant Control

3.7.5 Concrete Mixture

3.7.5.1 Air Content Testing

3.7.5.2 Air Content Corrective Action

3.7.5.3 Slump Testing

3.7.5.4 Slump Corrective Action

3.7.5.5 Temperature

3.7.5.6 Strength Specimens

3.7.6 Inspection Before Placing

3.7.7 Placing

3.7.8 Cold-Weather Protection

3.7.9 Mixer Uniformity

3.7.9.1 Stationary Mixers

3.7.9.2 Truck Mixers

3.7.9.3 Mixer Uniformity Corrective Action

3.7.10 Reports

3.8 REPAIR, REHABILITATION AND REMOVAL

3.8.1 Repair of Weak Surfaces

3.8.2 Failure of Quality Assurance Test Results

-- End of Section Table of Contents --

SECTION 03 30 00.00 10 Page 3

SECTION 03 30 00.00 10

CAST-IN-PLACE CONCRETE

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary

ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO

ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete

ACI 214R (2011) Evaluation of Strength Test Results of Concrete

ACI 301 (2016) Specifications for Structural Concrete

ACI 304.2R (2017) Guide to Placing Concrete by Pumping Methods

ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete

ACI 305.1 (2014) Specification for Hot Weather Concreting

ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting

ACI 309R (2005) Guide for Consolidation of Concrete

ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;

Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)

ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References

SECTION 03 30 00.00 10 Page 4

ASTM INTERNATIONAL (ASTM)

ASTM C1017/C1017M (2013; E 2015) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete

ASTM C1064/C1064M (2017) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete

ASTM C1077 (2017) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

ASTM C1107/C1107M (2017) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C1157/C1157M (2017) Standard Performance Specification for Hydraulic Cement

ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)

ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete

ASTM C150/C150M (2018) Standard Specification for Portland Cement

ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)

ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete

ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete

ASTM C192/C192M (2016a) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory

ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete

ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing

SECTION 03 30 00.00 10 Page 5

Concrete

ASTM C31/C31M (2018b) Standard Practice for Making and Curing Concrete Test Specimens in the Field

ASTM C311/C311M (2017) Standard Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans for Use in Portland-Cement Concrete

ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates

ASTM C39/C39M (2018) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

ASTM C42/C42M (2018) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete

ASTM C494/C494M (2017) Standard Specification for Chemical Admixtures for Concrete

ASTM C595/C595M (2018) Standard Specification for Blended Hydraulic Cements

ASTM C618 (2017a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete

ASTM C78/C78M (2018) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)

ASTM C937 (2016) Grout Fluidifier for Preplaced-Aggregate Concrete

ASTM C94/C94M (2017a) Standard Specification for Ready-Mixed Concrete

ASTM C989/C989M (2018) Standard Specification for Slag Cement for Use in Concrete and Mortars

ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses

ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates

ASTM E1643 (2018a) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs

ASTM E1745 (2017) Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs

SECTION 03 30 00.00 10 Page 6

ASTM E96/E96M (2016) Standard Test Methods for Water Vapor Transmission of Materials

CONCRETE REINFORCING STEEL INSTITUTE (CRSI)

CRSI 10MSP (2009; 28th Ed; Errata) Manual of Standard Practice

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST HB 44 (2018) Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices

NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)

NRMCA CPMB 100 (2000; R 2006) Concrete Plant Standards

NRMCA QC 3 (2015) Quality Control Manual: Section 3, Plant Certifications Checklist:

Certification of Ready Mixed Concrete Production Facilities

NRMCA TMMB 100 (2001; R 2007) Truck Mixer, Agitator and Front Discharge Concrete Carrier Standards

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 104 (1980) Method of Calculation of the Fineness Modulus of Aggregate

1.2 DEFINITIONS

1.2.1 Cementitious Material

As used herein, includes all portland cement, pozzolan, fly ash, ground granulated blast-furnace slag, and silica fume.

1.2.2 Chemical Admixtures

Materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.

1.2.3 Complementary Cementing Materials (CCM)

Coal fly ash, silica fume, granulated blast-furnace slag, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in considerable improvement to sustainability, durability.

1.2.4 Design Strength (f'c)

The specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.

1.2.5 Mixture Proportioning

The process of designing concrete mixture proportions to enable it to meet

SECTION 03 30 00.00 10 Page 7 the strength, service life and constructability requirements of the project.

1.2.6 Mixture Proportions

The masses or volumes of individual ingredients used to make a unit measure (cubic yard) of concrete.

1.2.7 Pozzolan

Siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.

1.2.8 Workability or Consistency

The ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 37 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Quality Control Plan; G Laboratory Accreditation; G Sampling Plan; G

SD-03 Product Data

Recycled Content Products; S Cementitious Materials Vapor Retarder Floor Finish Chemical Admixtures

SD-04 Samples

Surface Retarder

SD-05 Design Data

Mixture Proportions; G SD-06 Test Reports

Mixture Proportions; G Testing and Inspection for CQC; G Fly Ash

SECTION 03 30 00.00 10 Page 8

Ground Granulated Blast-Furnace (GGBF) Slag Aggregates Air Content Slump Compressive Strength Water

SD-07 Certificates

Contractor Quality Control personnel Ready-Mix Plant

1.4 QUALITY ASSURANCE

Submit qualifications for Contractor Quality Control personnel assigned to concrete construction as American Concrete Institute (ACI) Certified Workmen in one of the following grades or show written evidence of having completed similar qualification programs:

Concrete Field Testing Technician Grade I

Concrete Laboratory Testing Technician Grade I or II

Concrete Construction Inspector Level II

Concrete Transportation Construction Inspector or Reinforced Concrete Special Inspector

Jointly certified by American Concrete Institute (ACI), Building Official and Code Administrators International (BOCA), International Code Council (ICC), and Southern Building Code Congress International (SBCCI)

Foreman or Lead Journeyman of the flatwork finishing crew

Similar qualification for ACI Concrete Flatwork Technician/Finisher or equal, with written documentation

1.4.1 Laboratory Accreditation

Provide laboratory and testing facilities. The laboratories performing the tests must be accredited in accordance with ASTM C1077, including ASTM C78/C78M and ASTM C1260. The accreditation must be current and must include the required test methods, as specified. Furthermore, the testing must comply with the following requirements:

1.4.1.1 Aggregate Testing and Mix Proportioning

Perform aggregate testing and mixture proportioning studies in an accredited laboratory, under the direction of a registered professional engineer in a U.S. state or territory who is competent in concrete materials. This person is required to sign all reports and designs.

1.4.1.2 Acceptance Testing

Furnish all materials, labor, and facilities required for molding, curing, SECTION 03 30 00.00 10 Page 9 testing, and protecting test specimens at the site and in the laboratory.

Furnish and maintain boxes or other facilities suitable for storing and curing the specimens at the site while in the mold within the temperature range stipulated by ASTM C31/C31M.

1.4.1.3 Contractor Quality Control

All sampling and testing must be performed by an approved, onsite, independent, accredited laboratory.

1.4.2 Quality Control Plan

Submit a concrete quality control program in accordance with the guidelines of ACI 121R and as specified herein. Identify the approved laboratories. Provide direct oversight for the concrete qualification program inclusive of associated sampling and testing. Provide all quality control reports to the Quality Manager, Concrete Supplier and the Contracting Officer. Maintain a copy of ACI SP-15 and CRSI 10MSP at the project site.

1.4.3 Pre-installation Meeting

A pre-installation meeting with the Contracting Officer is required at least 10 days prior to start of construction on . Conduct the meeting with the Project Superintendent and active installation personnel present.

1.4.4 Special Properties and Products

Concrete may contain admixtures other than air entraining agents, such as water reducers, superplasticizers, or set retarding agents to provide special properties to the concrete, if specified or approved. Include any of these materials to be used on the project in the mix design studies.

1.4.5 Government Assurance Inspection and Testing

Day-to day inspection and testing is the responsibility of the Contractor Quality Control (CQC) staff. However, representatives of the Contracting Officer can and will inspect construction as considered appropriate and will monitor operations of the CQC staff. Government inspection or testing will not relieve any CQC responsibilities.

1.4.5.1 Materials

The Government will sample and test aggregates, cementitious materials, other materials, and concrete to determine compliance with the specifications as considered appropriate. Provide facilities and labor as may be necessary for procurement of representative test samples. Samples of aggregates will be obtained at the point of batching in accordance with ASTM D75/D75M. Other materials will be sampled from storage at the jobsite or from other locations as considered appropriate. Samples may be placed in storage for later testing when appropriate.

1.4.5.2 Fresh Concrete

Fresh concrete will be sampled as delivered in accordance with ASTM C172/C172M and tested in accordance with these specifications, as considered necessary.

SECTION 03 30 00.00 10 Page 10

1.4.5.3 Hardened Concrete

Tests on hardened concrete will be performed by the Government when such tests are considered necessary.

1.4.5.4 Inspection

Concrete operations may be tested and inspected by the Government as the project progresses. Failure to detect defective work or material will not prevent rejection later when a defect is discovered nor will it obligate the Government for final acceptance.

1.5 DELIVERY, STORAGE, AND HANDLING

Follow ACI 301 and ACI 304R requirements and recommendations. Store cement and other cementitious materials in weathertight buildings, bins, or silos that exclude moisture and contaminants and keep each material completely separated. Arrange and use aggregate stockpiles in a manner to avoid excessive segregation and to prevent contamination with other materials or with other sizes of aggregates. Do not store aggregate directly on ground unless a sacrificial layer is left undisturbed. Store reinforcing bars and accessories above the ground on platforms, skids or other supports. Store other materials in a manner to avoid contamination and deterioration. Admixtures which have been in storage at the project site for longer than 6 months or which have been subjected to freezing cannot be used unless retested and proven to meet the specified requirements. Materials must be capable of being accurately identified after bundles or containers are opened.

PART 2 PRODUCTS

In accordance with Section 01 33 29 SUSTAINABILITY REPORTING submit documentation indicating: distance between manufacturing facility and the project site, distance of raw material origin from the project site, percentage of post-industrial and post-consumer recycled content per unit of product and relative dollar value of recycled content products to total dollar value of products included in project. Provide Submittals as specified in the subject Section.

2.1 SYSTEM DESCRIPTION

Provide concrete composed of portland cement, other cementitious and pozzolanic materials as specified, aggregates, water and admixtures as specified.

2.1.1 Proportioning Studies-Normal Weight Concrete

Trial design batches, mixture proportions studies, and testing requirements for various types of concrete specified are the responsibility of the Contractor. Base mixture proportions on compressive strength as determined by test specimens fabricated in accordance with ASTM C192/C192M and tested in accordance with ASTM C39/C39M. Obtain mix design approval from the Contracting Officer prior to concrete placement.

a. Samples of all materials used in mixture proportioning studies must be representative of those proposed for use in the project and be accompanied by the manufacturer's or producer's test reports indicating compliance with these specifications.

SECTION 03 30 00.00 10 Page 11

b. Make trial mixtures having proportions, consistencies, and air content suitable for the work based on methodology described in ACI 211.1 , using at least three different water-cementitious material ratios for each type of mixture, which produce a range of strength encompassing those required for each type of concrete required on the project.

c. The maximum water-cementitious material ratios allowed in subparagraph WATER-CEMENTITIOUS MATERIAL RATIO below will be the equivalent water-cementitious material ratio as determined by conversion from the weight ratio of water to cement plus pozzolan by the weight equivalency method as described in ACI 211.1 . In the case where silica fume or GGBF slag is used, include the weight of the silica fume and GGBF slag in the equations in ACI 211.1 for the term P, which is used to denote the weight of pozzolan. If pozzolan is used in the concrete mixture, the minimum pozzolan content is 15 percent by weight of the total cementitious material, and the maximum is 35 percent.

d. Design laboratory trial mixtures for maximum permitted slump and air content. Make separate sets of trial mixture studies for each combination of cementitious materials and each combination of admixtures proposed for use. No combination of either may be used until proven by such studies, except that, if approved in writing and otherwise permitted by these specifications, an accelerator or a retarder may be used without separate trial mixture study. Separate trial mixture studies must also be made for concrete for any conveying or placing method proposed which requires special properties and for concrete to be placed in unusually difficult placing locations. For previously approved concrete mix designs used within the past twelve months, the previous mix design may be re-submitted without further trial batch testing if accompanied by material test data conducted within the last six months.

e. Report the temperature of concrete in each trial batch. For each water-cementitious material ratio, make at least three test cylinders for each test age, cure in accordance with ASTM C192/C192M and test at 7 and 28 days in accordance with ASTM C39/C39M. From these test results, plot a curve showing the relationship between water-cementitious material ratio and strength for each set of trial mix studies. In addition, plot a curve showing the relationship between 7 day and 28 day strengths. Design each mixture to promote easy and suitable concrete placement, consolidation and finishing, and to prevent segregation and excessive bleeding.

f. Submit the results of trial mixture design studies along with a statement giving the maximum nominal coarse aggregate size and the proportions of ingredients that will be used in the manufacture of each strength of concrete, at least 60 days prior to commencing concrete placing operations. Base aggregate weights on the saturated surface dry condition. Accompany the statement with test results from an approved independent commercial testing laboratory, showing that mixture design studies have been made with materials proposed for the project and that the proportions selected will produce concrete of the qualities indicated. No substitutions may be made in the materials used in the mixture design studies without additional tests to show that the quality of the concrete is satisfactory.

2.1.2 Average Compressive Strength

The mixture proportions selected during mixture design studies must

SECTION 03 30 00.00 10 Page 12 produce a required average compressive strength (f'cr) exceeding the specified compressive strength (f'c) by the amount indicated below, but may not exceed the specified strength at the same age by more than 20 percent. This required average compressive strength, f'cr, will not be a required acceptance criteria during concrete production. However, whenever the daily average compressive strength at 28 days drops below f'cr during concrete production, or daily average 7-day strength drops below a strength correlated with the 28-day f'cr, adjust the mixture, as approved, to bring the daily average back up to f'cr. During production, the required f'cr must be adjusted, as appropriate, based on the standard deviation being attained on the job.

2.1.3 Computations from Test Records

Where a concrete production facility has test records, establish a standard deviation in accordance with the applicable provisions of ACI 214R .

Test records from which a standard deviation is calculated must represent materials, quality control procedures, and conditions similar to those expected; must represent concrete produced to meet a specified strength or strengths (f'c) within 1000 psi of that specified for proposed work; and must consist of at least 30 consecutive tests. A strength test must be the average of the strengths of two cylinders made from the same sample of concrete and tested at 28 days. Required average compressive strength f'cr used as the basis for selection of concrete proportions must be in accordance with ACI 318 Chapter 5.

2.1.4 Tolerances

Except as otherwise specified herein, tolerances for concrete batching, mixture properties, and construction as well as definition of terms and application practices must be in accordance with ACI 117 . Take level and grade tolerance measurements of slabs as soon as possible after finishing;

when forms or shoring are used, the measurements must be made prior to removal.

2.1.5 Floor Finish

For floor finishes, see Section 03 35 00.00 10 CONCRETE FINISHING.

2.1.6 Strength Requirements

Specified compressive strength (f'c) must be as follows:

COMPRESSIVE STRENGTH STRUCTURE OR PORTION OF STRUCTURE

4000 psi at 28 days All concrete not otherwise specified

3000 psi at 28 days Foundations

Concrete made with high-early strength cement must have a 7-day strength equal to the specified 28-day strength for concrete made with Type I or II portland cement. Compressive strength must be determined in accordance

SECTION 03 30 00.00 10 Page 13 with ASTM C39/C39M.

2.1.6.1 Evaluation of Concrete Compressive Strength

Fabricate six compressive strength specimens, 6 inch by 12 inch cylinders, laboratory cure them in accordance with ASTM C31/C31M and test them in accordance with ASTM C39/C39M. Test two cylinders at 7 days, two cylinders at 28 days, and hold two cylinder in reserve. The strength of the concrete is considered satisfactory so long as the average of all sets of three consecutive test results do not exceed the specified compressive strength f'c by 20 percent and no individual test result falls below the specified strength f'c by more than 500 psi), unless approved by the Contracting Officer. A "test" is defined as the average of two companion cylinders, or if only one cylinder is tested, the results of the single cylinder test. Additional analysis or testing, including taking cores and/or load tests may be required when the strength of the concrete in the structure is considered potentially deficient.

2.1.6.2 Investigation of Low-Strength Compressive Test Results

When any strength test of standard-cured test cylinders falls below the specified strength requirement by more than 500 psi or if tests of field-cured cylinders indicate deficiencies in protection and curing, take steps to assure that the load-carrying capacity of the structure is not jeopardized. When the strength of concrete in place is considered potentially deficient, obtain cores and test in accordance with ASTM C42/C42M. Take at least three representative cores from each member or area of concrete in place that is considered potentially deficient.

The location of cores will be determined by the Contracting Officer to least impair the strength of the structure. Concrete in the area represented by the core testing will be considered adequate if the average strength of the cores is equal to at least 85 percent of the specified strength requirement and if no single core is less than 75 percent of the specified strength requirement. Non-destructive tests (tests other than test cylinders or cores) may not be used as a basis for acceptance or rejection. Perform the coring and repair the holes; cores will be tested by the Government.

2.1.6.3 Load Tests

If the core tests are inconclusive or impractical to obtain or if structural analysis does not confirm the safety of the structure, load tests may be directed by the Contracting Officer in accordance with the requirements of ACI 318 . Correct concrete work evaluated by structural analysis or by results of a load test as being understrength in a manner satisfactory to the Contracting Officer. Perform all investigations, testing, load tests, and correction of deficiencies approved by the Contracting Officer, except that if all concrete is found to be in compliance with the drawings and specifications, the cost of investigations, testing, and load tests will be at the expense of the Government.

2.1.7 Water-Cementitious Material Ratio

Maximum water-cementitious material ratio (w/c) for normal weight concrete is as follows:

SECTION 03 30 00.00 10 Page 14

WATER-CEMENTITIOUS MATERIAL RATIO, BY

WEIGHT

STRUCTURE OR PORTION OF STRUCTURE

0.45 Foundation Walls and Exterior

Slabs-on-Grade

0.50 Suspended Slabs

0.55 Slab-on-Grade

0.65 Footings

2.1.8 Air Entrainment

Air entrain normal weight concrete based on the following table.

MINIMUM AIR CONTENT Percent STRUCTURE OR PORTION OF STRUCTURE

6.0 Foundation Walls, Exterior Slab-on-Grade and Suspended

Slabs

Attain specified air content at point of placement into the forms within plus or minus 1.5 percent. Determine air content for normal weight concrete in accordance with ASTM C231/C231M.

2.1.9 Slump

Slump of the concrete, as delivered to the point of placement into the forms, must be within the following limits. Determine slump in accordance with ASTM C143/C143M.

Structural Element Slump inches

Minimum Maximum

Walls, columns and beams 2 4

Foundation walls, substructure walls, footings, slabs

1 3

Any structural concrete approved for placement by pumping:

At pump 2 8

SECTION 03 30 00.00 10 Page 15

At discharge of line 1 4

When use of a plasticizing admixture conforming to ASTM C1017/C1017M or when a Type F or G high range water reducing admixture conforming to ASTM C494/C494M is permitted to increase the slump of concrete, concrete must have a slump of 2 to 4 inches before the admixture is added and a maximum slump of 8 inches at the point of delivery after the admixture is added.

2.1.10 Concrete Temperature

The temperature of the concrete as delivered must not exceed 90 degrees F.

When the ambient temperature during placing is 40 degrees F or less, or is expected to be at any time within 6 hours after placing, the temperature of the concrete as delivered must be between 55 and 75 degrees F.

2.1.11 Size of Coarse Aggregate

Use the largest feasible nominal maximum size aggregate (NMSA), specified in PART 2 paragraph AGGREGATES, in each placement. However, do not exceed nominal maximum size of aggregate for any of the following: three-fourths of the minimum cover for reinforcing bars, three-fourths of the minimum clear spacing between reinforcing bars, one-fifth of the narrowest dimension between sides of forms, or one-third of the thickness of slabs or toppings.

2.2 CEMENTITIOUS MATERIALS

Cementitious Materials must be portland cement or portland cement in combination with pozzolan or ground granulated blast furnace slag or silica fume conforming to appropriate specifications listed below.

Restrict usage of cementitious materials in concrete that will have surfaces exposed in the completed structure so there is no change in color, source, or type of cementitious material.

2.2.1 Portland Cement

ASTM C150/C150M, Type I II with a maximum 10 percent amount of tricalcium aluminate, and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent. White portland cement must meet the above requirements except that it may be Type I, Type II

2.2.2 Blended Cements

Conform blended cement to ASTM C595/C595M and ASTM C1157/C1157M , Type IP or IS, including the optional requirement for mortar expansion and sulfate soundness and consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a complementary cementing material. The slag added to the Type IS blend must be ASTM C989/C989M ground granulated blast-furnace slag.

The pozzolan added to the Type IP blend must be ASTM C618 Class F and must be interground with the cement clinker. Provide a manufacturer's statement that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot-to-lot or within a lot. Do not change the percentage and type of mineral admixture used in the blend from that submitted for the aggregate evaluation and mixture proportioning.

SECTION 03 30 00.00 10 Page 16

2.2.3 Fly Ash

Conform fly ash to ASTM C618, Class F,except that the maximum allowable loss on ignition cannot exceed 3 percent. If pozzolan is used, it must never be less than 40 percent by weight of the total cementitious material. Report the chemical analysis of the fly ash in accordance with ASTM C311/C311M. Evaluate and classify fly ash in accordance with ASTM D5759. Comply with EPA requirements in accordance with Section

01 33 29 SUSTAINABILITY REPORTING.

2.2.4 Raw or Calcined Natural Pozzolan

Natural pozzolan must be raw or calcined and conform to ASTM C618, Class N, including the optional requirements for uniformity and effectiveness in controlling Alkali-Silica reaction and must have an on ignition loss not exceeding 3 percent. Class N pozzolan for use in mitigating Alkali-Silica Reactivity must have a Calcium Oxide (CaO) content of less than 13 percent and total equivalent alkali content less than 3 percent.

2.2.5 Ultra Fine Fly Ash and Ultra Fine Pozzolan

Conform Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) ASTM C618, Class F or N, and the following additional requirements:

a. The strength activity index at 28 days of age is at least 95 percent of the control specimens.

b. The average particle size does not exceed 6 microns.

c. The sum of SiO2 + Al2O3 + Fe2O3 is greater than 77 percent.

2.2.6 Ground Granulated Blast-Furnace (GGBF) Slag

ASTM C989/C989M, Grade 100. Slag content must be a minimum of 25 percent by weight of cementitious material. Submit test results in accordance with ASTM C989/C989M for GGBF slag. Submit test results performed within 6 months of submittal date..

2.3 AGGREGATES

Test and evaluate fine and coarse aggregates for alkali-aggregate reactivity in accordance with ASTM C1260. Evaluate the fine and coarse aggregates separately and in combination, which matches the proposed mix design proportioning. All results of the separate and combination testing must have a measured expansion less than 0.10 (0.08) percent at 16 days after casting. Should the test data indicate an expansion of 0.10 (0.08) percent or greater, reject the aggregate(s) or perform additional testing using ASTM C1260 and ASTM C1567. Perform the additional testing using ASTM C1260 and ASTM C1567 using the low alkali portland cement in combination with ground granulated blast furnace (GGBF) slag, or Class F fly ash. Use GGBF slag in the range of 40 to 50 percent of the total cementitious material by mass. Use Class F fly ash in the range of 25 to 40 percent of the total cementitious material by mass. Provide fine and coarse aggregates conforming to the following.

2.3.1 Fine Aggregate

Conform to the quality and gradation requirements of ASTM C33/C33M.

SECTION 03 30 00.00 10 Page 17

2.3.2 Coarse Aggregate

Conform to ASTM C33/C33M, Class 5S, size designation M.

2.4 CHEMICAL ADMIXTURES

When required or permitted, conform to the appropriate specification listed. Furnish admixtures in liquid form and of suitable concentration for easy, accurate control of dispensing.

2.4.1 Air-Entraining Admixture

ASTM C260/C260M and must consistently entrain the air content in the specified ranges under field conditions.

2.4.2 Accelerating Admixture

ASTM C494/C494M, Type C or E, except that calcium chloride or admixtures containing calcium chloride cannot be used.

2.4.3 Water-Reducing or Retarding Admixture

ASTM C494/C494M, Type A, B, or D, except that the 6-month and 1-year compressive strength tests are waived.

2.4.4 High-Range Water Reducer

ASTM C494/C494M, Type F or G, except that the 6-month and 1-year strength requirements are waived. Use the admixture only when approved in writing, such approval being contingent upon particular mixture control as described in the Contractor's Quality Control Plan and upon performance of separate mixture design studies.

2.4.5 Surface Retarder

ASTM C309. Submit sample of surface retarder material with manufacturer's instructions for application in conjunction with air-water cutting.

2.4.6 Expanding Admixture

Aluminum powder type expanding admixture conforming to ASTM C937.

2.4.7 Other Chemical Admixtures

Provide chemical admixtures for use in producing flowing concrete in compliance with ASTM C1017/C1017M , Type I or II. Use these admixtures only when approved in writing, such approval being contingent upon particular mixture control as described in the Contractor's Quality Control Plan and upon performance of separate mixture design studies.

2.5 WATER

Provide water complying with the requirements of ASTM C1602/C1602M .

Provide potable water for mixing, free of injurious amounts of oil, acid, salt, or alkali. Submit test report showing water complies with

ASTM C1602/C1602M .

SECTION 03 30 00.00 10 Page 18

2.6 NONSHRINK GROUT

Provide nonshrink grout conforming to ASTM C1107/C1107M , and a commercial formulation suitable for the proposed application.

2.7 NONSLIP SURFACING MATERIAL

Provide nonslip surfacing material consisting of 55 percent, minimum, aluminum oxide or silicon-dioxide abrasive ceramically bonded together to form a homogeneous material sufficiently porous to provide a good bond with portland cement paste; or factory-graded emery aggregate consisting of not less than 45 percent aluminum oxide and 25 percent ferric oxide.

Use well graded aggregate from particles retained on the No. 30 sieve to particles passing the No. 8 sieve.

2.8 EMBEDDED ITEMS

Provide the size and type indicated or as needed for the application.

Dovetail slots must be galvanized steel. Provide hangers for suspended ceilings as specified in Section 09 51 00 ACOUSTICAL CEILINGS. Provide inserts for shelf angles and bolt hangers of malleable iron or cast or wrought steel.

****Amendment0002****

2.9 PERIMETER INSULATION

Polystyrene conforming to ASTM C578, Type II; polyurethane conforming to ASTM C591, Type II; or cellular glass conforming to ASTM C552, Type I or IV. Comply with EPA requirements in accordance with Section 01 33 29

SUSTAINABILITY REPORTING.

2.9 VAPOR RETARDER

Polyethylene sheeting, ASTM E1745 Class A, with a minimum thickness of 15 mils or other equivalent material having a vapor permeance rating not exceeding 0.04 perms as determined in accordance with ASTM E96/E96M.

****Amendment0002****

2.10 JOINT MATERIALS

2.10.1 Joint Fillers, Sealers, and Waterstops

Provide materials for expansion joint fillers and waterstops in accordance with Section 03 15 00.00 10 CONCRETE ACCESSORIES. Provide materials for and sealing of joints conforming to the requirements of Section 07 92 00

JOINT SEALANTS.

2.10.2 Contraction Joints in Slabs

Provide materials for contraction joint inserts in accordance with Section

03 15 00.00 10 CONCRETE ACCESSORIES.

PART 3 EXECUTION

3.1 PREPARATION FOR PLACING

Before commencing concrete placement, perform the following: Clean

SECTION 03 30 00.00 10 Page 19 surfaces to receive concrete, free from frost, ice, mud, and water.

Place, clean, coat, and support forms in accordance with Section 03 11 13.00 10 STRUCTURAL CONCRETE FORMWORK. Place, clean, tie, and support reinforcing steel in accordance with Section 03 20 00.00 10 CONCRETE REINFORCEMENT. Transporting and conveying equipment is in-place, ready for use, clean, and free of hardened concrete and foreign material.

Equipment for consolidating concrete is at the placing site and in proper working order. Equipment and material for curing and for protecting concrete from weather or mechanical damage is at the placing site, in proper working condition and in sufficient amount for the entire placement. When hot, windy conditions during concreting appear probable, equipment and material is at the placing site to provide windbreaks, shading, fogging, or other action to prevent plastic shrinkage cracking or other damaging drying of the concrete as required in Section 03 39 00.00 10

CONCRETE CURING.

3.1.1 Foundations

3.1.1.1 Concrete on Earth Foundations

Earth (subgrade, base, or subbase courses) surfaces upon which concrete is to be placed is clean, damp, and free from debris, frost, ice, and standing or running water. Prior to placement of concrete, the foundation must be well drained, satisfactorily graded and uniformly compacted.

3.1.1.2 Preparation of Rock

Rock surfaces upon which concrete is to be placed is free from oil, standing or running water, ice, mud, drummy rock, coating, debris, and loose, semidetached or unsound fragments. Clean joints in rock to a satisfactory depth, as determined by the Contracting Officer, and to firm rock on the sides. Immediately before the concrete is placed, thoroughly clean rock surfaces by the use of air-water jets or sandblasting as specified below for Previously Placed Concrete. Keep rock surfaces continuously moist for at least 24 hours immediately prior to placing concrete thereon. Cover all horizontal and approximately horizontal surfaces, immediately before the concrete is placed, with a layer of mortar proportioned similar to that in the concrete mixture. Place concrete before the mortar stiffens.

3.1.1.3 Excavated Surfaces in Lieu of Forms

Concrete for footings may be placed directly against the soil provided the earth or rock has been carefully trimmed, is uniform and stable, and meets the compaction requirements of Section 31 00 00 EARTHWORK. Place the concrete without becoming contaminated by loose material, and outlined within the specified tolerances.

3.1.2 Previously Placed Concrete

Prepare concrete surfaces to which additional concrete is to be bonded for receiving the next horizontal lift by cleaning the construction joint surface with either air-water cutting, sandblasting, high-pressure water jet, or other approved method. Prepare concrete at the side of vertical construction joints as approved by the Contracting Officer. Do not use air-water cutting on formed surfaces or surfaces congested with reinforcing steel. Regardless of the method used, the resulting surfaces must be free from all laitance and inferior concrete so that clean surfaces of well bonded coarse aggregate are exposed and make up at least

SECTION 03 30 00.00 10 Page 20

10-percent of the surface area, distributed uniformly throughout the surface. Do not undercut the edges of the coarse aggregate. Keep the surface of horizontal construction joints continuously wet for the first 12 hours during the 24-hour period prior to placing fresh concrete. Wash the surface completely clean as the last operation prior to placing the next lift. For heavy duty floors and two-course floors, thoroughly scrub a thin coat of neat cement grout of about the consistency of thick cream into the existing surface immediately ahead of the topping placing. The grout must be a 1:1 mixture of portland cement and sand passing the No. 8 sieve. Deposit the topping concrete before the grout coat has had time to stiffen.

3.1.2.1 Air-Water Cutting

Perform air-water cutting of a fresh concrete surface at the proper time and only on horizontal construction joints. The air pressure used in the jet mustl be 100 psi, plus or minus 10 psi, and the water pressure must be just sufficient to bring the water into effective influence of the air pressure. When approved by the Contracting Officer, a surface retarder complying with the requirements of ASTM C309 may be applied to the surface of the lift in order to prolong the period of time during which air-water cutting is effective. After cutting, wash and rinse the surface as long as there is any trace of cloudiness of the wash water. Where necessary to remove accumulated laitance, coatings, stains, debris, and other foreign material, use high-pressure waterjet or sandblasting as the last operation before placing the next lift.

3.1.2.2 High-Pressure Water Jet

Use a stream of water under a pressure of not less than 3,000 psi for cutting and cleaning. Delay its use until the concrete is sufficiently hard so that only the surface skin or mortar is removed and there is no undercutting of coarse-aggregate particles. If the waterjet is incapable of a satisfactory cleaning, clean the surface by sandblasting.

3.1.2.3 Wet Sandblasting

Use wet sandblasting after the concrete has reached sufficient strength to prevent undercutting of the coarse aggregate particles. After wet sandblasting, thoroughly wash the surface of the concrete to remove all loose materials.

3.1.2.4 Waste Disposal

Dispose of waste water employed in cutting, washing, and rinsing of concrete surfaces in a manner that the waste water does not stain, discolor, or affect exposed surfaces of the structures, or damage the environment of the project area. The method of disposal is subject to approval.

3.1.2.5 Preparation of Previously Placed Concrete

Abrade concrete surfaces to which other concrete is to be bonded in an approved manner that exposes sound aggregate uniformly without damaging the concrete. Remove laitance and loose particles. Thoroughly wash surfaces, leaving them moist but without free water when concrete is placed.

SECTION 03 30 00.00 10 Page 21

3.1.3 Vapor Retarder

Provide vapor retarder beneath the interior on-grade concrete floor slabs installed in accordance with ASTM E1643. Use the greatest widths and lengths practicable to eliminate joints wherever possible. Lap joints a minimum of 12 inches. Remove torn, punctured, or damaged vapor retarder material and provide new vapor retarder prior to placing concrete. For minor repairs, patches may be made using laps of at least 12 inches. Seal lapped joints and patch edges with pressure-sensitive adhesive or tape not less than 2 inches wide and compatible with the membrane. Place vapor retarder directly on underlying subgrade, base course, or capillary water retarder, unless it consists of crushed material or large granular material which could puncture the vapor retarder. In this case, a thin layer of approximately 1/2 inch of fine graded material should be rolled or compacted over the fill before installation of the vapor retarder to reduce the possibility of puncture. Control concrete placement so as to prevent damage to the vapor retarder.

****Amendment0002****

3.1.4 Perimeter Insulation

Install perimeter insulation at locations indicated. Use adhesive where insulation is applied to the interior surface of foundation walls and may be used for exterior application.

3.1.4 Embedded Items

Before placement of concrete, determine that all embedded items are firmly and securely fastened in place as indicated on the drawings, or required.

Conduit and other embedded items must be clean and free of oil and other foreign matter such as loose coatings or rust, paint, and scale. The embedding of wood in concrete is permitted only when specifically authorized or directed. Temporarily fill voids in sleeves, inserts, and anchor slots with readily removable materials to prevent the entry of concrete into voids. Do not Weld on embedded metals within 12 inches of the surface of the concrete. Do not tack weld on or to embedded items.

****Amendment0002****

3.2 CONCRETE PRODUCTION

3.2.1 General Requirements

Batch and mix concrete onsite or furnish from a ready-mixed concrete plant. Batch, mix, and transport ready-mixed concrete in accordance with ASTM C94/C94M, except as otherwise specified. Truck mixers, agitators, and nonagitating transporting units must comply with NRMCA TMMB 100.

Ready-mix plant equipment and facilities must be certified in accordance with NRMCA QC 3. Furnish approved batch tickets for each load of ready-mixed concrete. Conform site-mixed concrete to the following subparagraphs.

3.2.2 Batching Equipment

Use semiautomatic or automatic batching controls as defined in NRMCA CPMB 100. Provide a semiautomatic batching system with interlocks such that the discharge device cannot be actuated until the indicated material is within the applicable tolerance. Equip the batching system with accurate recorder or recorders that meet the requirements of

SECTION 03 30 00.00 10 Page 22

NRMCA CPMB 100. Record the weight of water and admixtures if batched by weight. Provide separate bins or compartments for each size group of aggregate and type of cementitious material, to prevent intermingling at any time. Weigh aggregates either in separate weigh batchers with individual scales or, provided the smallest size is batched first, cumulatively in one weigh batcher on one scale. Do not weigh aggregate in the same batcher with cementitious material. If both portland cement and other cementitious material are used, they may be batched cumulatively, provided that the portland cement is batched first, except always batch silica fume separately. Water may be measured by weight or volume. Do not weigh or measure water cumulatively with another ingredient.

Interlock filling and discharging valves for the water metering or batching system so that the discharge valve cannot be opened before the filling valve is fully closed. Piping for water and for admixtures must be free from leaks and valved to prevent backflow or siphoning. Furnish admixtures as a liquid of suitable concentration for easy control of dispensing. Provide an adjustable, accurate, mechanical device for measuring and dispensing each admixture. Interlock each admixture dispenser with the batching and discharging operation of the water so that each admixture is separately batched and individually discharged automatically in a manner to obtain uniform distribution throughout the water as it is added to the batch in the specified mixing period. When use of truck mixers makes this requirement impractical, interlock the admixture dispensers with the sand batchers. Different admixtures cannot be combined prior to introduction in water and are not allowed to intermingle until in contact with the cement. Provide admixture dispensers with devices to detect and indicate flow during dispensing or have a means for visual observation. Arrange the plant so as to facilitate the inspection of all operations at all times.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .