W9128A-19-R-0014_Am-0001_Specifications_-_Package_2.pdf

PDF 897 KB Posted

Attached to
Quad A, Building 131 and Central Utility Plant (CUP), and Buildings 130 and 132, Schofield Barracks, Hawaii
Solicitation number
W9128A-19-R-0014
Issued by

About this file

W9128A-19-R-0014 Am-0001 Specifications - Package 2

View the file

Other files

File Type Posted
W9128A-19-R-0014_-_Section_00_22_16,_Attachment_A.docx DOCX document
W9128A-19-R-0014_Am-0007_Drawings_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0007_Drawings_-_Package_2.pdf PDF
W9128A-19-R-0014_Am-0007_Specifications_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0007.pdf PDF
W9128A-19-R-0014_Am-0006.pdf PDF
W9128A-19-R-0014_Am-0006_Drawings_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0006_Drawings_-_Package_2.pdf PDF
W9128A-19-R-0014_Am-0005.pdf PDF
W9128A-19-R-0014_Am-0004_Specifications_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0004_Drawings_-_Package_2.pdf PDF
W9128A-19-R-0014_Am-0004.pdf PDF
W9128A-19-R-0014_Am-0004_Drawings_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0003.pdf PDF
W9128A-19-R-0014_Am-0002.pdf PDF
W9128A-19-R-0014_Am-0001_Specifications_-_Package_1.pdf PDF
W9128A-19-R-0014_Am-0001_Drawings_-_Package_2_(Part_1_of_2).pdf PDF
W9128A-19-R-0014_Am-0001_Drawings_-_Package_2_(Part_2_of_2).pdf PDF
W9128A-19-R-0014_Am-0001.pdf PDF
W9128A-19-R-0014_Am-0001_Drawings_-_Package_1.pdf PDF
W9128A-19-R-0014_Request_for_Proposal.pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_11_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_6_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_1_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_5_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_13_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_11_of_14).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_1_(Part_3_of_3).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_2_(Part_3_of_3).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_7_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_12_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_9_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_3_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_4_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_10_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_2_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_10_of_11).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_1_(Part_2_of_3).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_2_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_8_of_11).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_2_(Part_2_of_3).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_7_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_14_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_6_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_3_of_11).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_1_(Part_1_of_3).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_9_of_11).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_2_(Part_1_of_14).pdf PDF
W9128A-19-R-0014_Drawings_-_Package_1_(Part_4_of_11).pdf PDF
W9128A-19-R-0014_Specifications_-_Package_2_(Part_1_of_3).pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY18 QUAD A REPAIR BUILDINGS 130 AND 132 QUADA2

PROJECT TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

02 09 20 EXPOSURE ASSESSMENT FOR WORKERS EXPOSED TO

LEAD-CONTAINING PAINT

02 09 30 EXPOSURE ASSESSMENT FOR WORKERS EXPOSED TO RODENT DROPPING

02 41 00 DEMOLITION

02 85 00 MOLD REMEDIATION

DIVISION 03 - CONCRETE

03 01 00 REHABILITATION OF CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 21 16 MINERAL FIBER BLANKET INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 34 73 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL AND DOOR LOUVERS

DIVISION 09 - FINISHES

PROJECT TABLE OF CONTENTS Page 1 j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out

09 22 00 SUPPORTS FOR GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL PROTECTION

10 28 13 TOILET ACCESSORIES

10 51 13 METAL LOCKERS

10 99 00 MISCELLANEOUS SPECIALTIES

DIVISION 11 - EQUIPMENT

11 31 13 ELECTRIC KITCHEN EQUIPMENT

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 48.19 SEISMIC BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

DIVISION 25 - INTEGRATED AUTOMATION

PROJECT TABLE OF CONTENTS Page 2 j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out

25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS

25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED FIRE CONTROL SYSTEMS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

31 31 16.13 CHEMICAL TERMITE CONTROL

31 31 16.19 TERMITE CONTROL BARRIERS

31 32 11 SOIL SURFACE EROSION CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

32 93 00 EXTERIOR PLANTS

32 96 00 TRANSPLANTING EXTERIOR PLANTS

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 61 14 EXTERIOR BURIED PREINSULATED WATER PIPING

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3 j3ecetkn Cross-Out j3ecetkn Cross-Out j3ecetkn Cross-Out

SUBMITTAL REGISTER

Legend: ● - Applies to both BASE BID and OPTION BID B - Applies to BASE BID Only O - Applies to OPTION BID Only

Section No. Section Name Bldg 131 &

CUP (BASE)

Bldg 130 &

132 (OPTION)

01 32 00 PROJECT SCHEDULE ● ●

01 33 00 SUBMITTAL PROCEDURES ● ●

01 33 29 SUSTAINABILITY REPORTING ● ●

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS ● ●

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS ● ●

01 45 00 RMS3 - CONTRACTOR MODE (RMS3/CM) ● ●

01 45 04 CONTRACTOR QUALITY CONTROL ● ●

01 45 35 SPECIAL INSPECTIONS ● ●

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS W/

ATTACHMENT

01 62 35 RECYCLED / RECOVERED MATERIALS ● ●

01 74 19 CONSTRUCTION AND DEMOLITION DEBRIS

RECYCLING

01 78 00 CLOSEOUT SUBMITTALS ● ●

01 78 23 OPERATION AND MAINTENANCE DATA ● ●

01 90 00 MISCELLANEOUS PROVISIONS ● ●

01 91 00.15 TOTAL BUILDING COMMISSIONING ● ●

02 09 20 EXPOSURE ASSESSMENT FOR WORKERS EXPOSED

TO LEAD-CONTAINING PAINT W/ ATTACHMENT ● ●

02 09 30 EXPOSED ASSESSMENT FOR WORKERS EXPOSED

TO RODENT DROPPING

02 41 00 DEMOLITION ● ●

02 85 00 MOLD REMEDIATION W/ ATTACHMENT ● ●

03 01 00 REHABILITATION OF CONCRETE ● ●

03 30 00 CAST-IN-PLACE CONCRETE ● ●

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR

BELOW GRADE CONSTRUCTION ● ●

04 20 00 UNIT MASONRY ● ●

05 12 00 STRUCTURAL STEEL ● ●

Note: All specification sections indicated with "●" in the table below have the same submittals for both BASE BID and OPTION BID. If the OPTION BID is awarded, the contractor may submit and process the submittals as a single transmittal in RMS3/CM. The specification sections indicated with "B" and "O" have submittals and/or other information specific to the BASE BID and OPTION BID, respectively. In the case where the OPTION BID is not awarded, the BASE BID submittals are to be submitted and processed normally in RMS3/CM. The contractor shall be responsible for coordinating and updating the submittal register throughout the project in

RMS3/CM.

DIVISION 03 - CONCRETE

DIVISION 04 - MASONRY

DIVISION 01 - GENERAL REQUIREMENTS

DIVISION 02 - EXISTING CONDITIONS

DIVISION 05 - METALS

Pages 1 of 5 (Am-0001)

Section No. Section Name Bldg 131 &

CUP (BASE)

Bldg 130 &

132 (OPTION)

05 30 00 STEEL DECKS B

05 40 00 COLD-FORMED METAL FRAMING B

05 50 13 MISCELLANEOUS METAL FABRICATIONS ● ●

05 52 00 METAL RAILINGS ● ●

06 10 00 ROUGH CARPENTRY ● ●

06 20 00 FINISH CARPENTRY ● ●

06 61 16 SOLID SURFACING FABRICATIONS ● ●

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM

FOR AIR TIGHTNESS ● ●

07 21 16 MINERAL FIBER BLANKET INSULATION ● ●

07 22 00 ROOF AND DECK INSULATION B

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS ● ●

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM ● ●

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS ● ●

07 60 00 FLASHING AND SHEET METAL ● ●

07 61 14.00 20 STEEL STANDING SEAM ROOFING B

07 84 00 FIRESTOPPING ● ●

07 92 00 JOINT SEALANTS ● ●

08 11 13 STEEL DOORS AND FRAMES ● ●

08 11 16 ALUMINUM DOORS AND FRAMES ● ●

08 14 00 WOOD DOORS ● ●

08 31 00 ACCESS DOORS AND PANELS ● ●

08 33 23 OVERHEAD COILING DOORS B

08 34 59 VAULT DOORS AND DAY GATES B

08 34 73 SOUND CONTROL DOOR ASSEMBLIES ● ●

08 41 13 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 51 13 ALUMINUM WINDOWS ● ●

08 71 00 DOOR HARDWARE W/ ATTACHMENT B

08 71 00 DOOR HARDWARE W/ ATTACHMENT O

08 81 00 GLAZING ● ●

08 91 00 METAL WALL AND DOOR LOUVERS ● ●

09 22 00 SUPPORTS FOR GYPSUM BOARD ● ●

09 29 00 GYPSUM BOARD ● ●

09 30 10 CERAMIC TILING B

09 30 10 CERAMIC TILING O

09 51 00 ACOUSTICAL CEILINGS ● ●

09 62 38 STATIC-CONTROL FLOORING ● ●

09 65 00 RESILIENT FLOORING ● ●

09 68 00 CARPETING O

09 90 00 PAINTS AND COATINGS ● ●

10 11 00 VISUAL DISPLAY UNITS ● ●

10 14 00.10 EXTERIOR SIGNAGE ● ●

10 14 00.20 INTERIOR SIGNAGE ● ●

DIVISION 10 - SPECIALTIES

DIVISION 09 - FINISHES

DIVISION 08 - OPENINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

Pages 2 of 5

Bldg 131 &

CUP (BASE)

Bldg 130 &

132 (OPTION)

10 21 13 TOILET COMPARTMENTS B

10 21 13 TOILET COMPARTMENTS O

10 26 00 WALL PROTECTION ● ●

10 28 13 TOILET ACCESSORIES B

10 28 13 TOILET ACCESSORIES O

10 51 13 METAL LOCKERS ● ●

10 99 00 MISCELLANEOUS SPECIALTIES B

10 99 00 MISCELLANEOUS SPECIALTIES O

11 31 13 ELECTRIC KITCHEN EQUIPMENT ● ●

12 21 00 WINDOW BLINDS ● ●

13 48 00 SEISMIC BRACING FOR MISCELLANEOUS

EQUIPMENT

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE

PROTECTION

22 00 00 PLUMBING, GENERAL PURPOSE B

22 00 00 PLUMBING, GENERAL PURPOSE O

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION,

AND EXHAUST SYSTEMS B

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION,

AND EXHAUST SYSTEMS O

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS ● ●

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC

PIPING AND EQUIPMENT

23 05 48.19 SEISMIC BRACING FOR HVAC ● ●

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC B

24 09 00 INSTRUMENTATION AND CONTROL FOR HVAC O

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR

HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

B

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

O

23 11 25 FACILITY GAS PIPING ● ●

23 21 23 HYDRONIC PUMPS B

23 23 00 REFRIGERANT PIPING B

23 25 00 CHEMICAL TREATMENT OF WATER FOR

MECHANICAL SYSTEMS

B

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS ● ●

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE B

DIVISION 11 - EQUIPMENT

DIVISION 22 - PLUMBING

DIVISON 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

DIVISION 12 - FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

DIVISION 21 - FIRE SUPPRESSION

Pages 3 of 5

Bldg 131 &

CUP (BASE)

Bldg 130 &

132 (OPTION)

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER

WATER PIPING SYSTEMS

B

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER

WATER PIPING SYSTEMS

O

23 65 00 COOLING TOWERS AND REMOTE EVAPORATIVELY-

COOLED CONDENSERS B

25 05 11 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

B

25 05 11 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

O

25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED FIRE

CONTROL SYSTEMS

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION B

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS ● ●

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING ● ●

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS B

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS O

26 13 01 PAD-MOUNTED DEAD-FRONT AIR INSULATED

SWITCHGEAR

B

26 20 00 INTERIOR DISTRIBUTION SYSTEM W/

ATTACHMENT

B

26 20 00 INTERIOR DISTRIBUTION SYSTEM O

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION B

25 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER

600 VOLTS

B

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER

600 VOLTS

O

25 51 00 INTERIOR LIGHTING B

26 51 00 INTERIOR LIGHTING O

25 56 00 EXTERIOR LIGHTING B

26 56 00 EXTERIOR LIGHTING O

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION

SYSTEM

27 10 00 BUILDING TELECOMMUNICATIONS CABLING B

27 10 00 BUILDING TELECOMMUNICATIONS CABLING O

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM,

ADDRESSABLE

B

28 31 76 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM

31 23 00.00 20 EXCAVATION AND FILL ● ●

31 31 16.13 CHEMICAL TERMITE CONTROL ● ●

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

DIVISION 31 - EARTHWORK

DIVISION 25 - INTEGRATED AUTOMATION

DIVISION 26 - ELECTRICAL

DIVISION 27 - COMMUNICATIONS

Pages 4 of 5

Bldg 131 &

CUP (BASE)

Bldg 130 &

132 (OPTION)

31 31 16.19 TERMITE CONTROL BARRIERS ● ●

31 32 11 SOIL SURFACE EROSION CONTROL ● ●

32 05 33 LANDSCAPE ESTABLISHMENT ● ●

32 11 23 AGGREGATE BASE COURSES ● ●

32 12 13 BITUMINOUS TACK AND PRIME COATS ● ●

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS ● ●

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS ● ●

32 17 23 PAVEMENT MARKINGS ● ●

32 31 13 CHAIN LINK FENCES AND GATES B

32 92 19 SEEDING ● ●

32 93 00 EXTERIOR PLANTS ● ●

32 96 00 TRANSPLANTING EXTERIOR PLANTS ● ●

33 11 00 WATER UTILITY DISTRIBUTION PIPING ● ●

33 30 00 SANITARY SEWERAGE W/ ATTACHMENT ● ●

33 61 14 EXTERIOR BURIED PREINSULATED WATER ● ●

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION B

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION O

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP) ● ●

DIVISION 32 - EXTERIOR IMPROVEMENTS

DIVISION 33 - UTILITIES

Pages 5 of 5

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 18 PAGES

FY18 QUAD A REPAIR BUILDINGS 130 AND 132

08 71 00 SD-02 Shop Drawings 1.3Manufacturer's Detail Drawings 1.3Verification of Existing Conditions 1.5Hardware Schedule 2.3.6Keying System

SD-03 Product Data 2.3Hardware Items

SD-08 Manufacturer’s Instructions 3.1Installation

SD-10 Operation and Maintenance Data

1.5Hardware Schedule SD-11 Closeout Submittals

1.6.1Key Bitting 09 30 10 SD-03 Product Data

2.1.1Porcelain Tile 2.2Setting-Bed 2.4Mortar and Grout

SD-04 Samples 2.1Tile 2.1Accessories 2.1Transition Strips 2.5Transition Strips 2.4.2Grout

SD-10 Operation and Maintenance Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 18 PAGES

09 30 10 3.2Installation 09 68 00 SD-02 Shop Drawings

3.4Installation Drawings 2.5Moldings

SD-03 Product Data 2.2Carpet 2.5Moldings

SD-04 Samples 2.2Carpet 2.5Moldings

SD-06 Test Reports 3.2Moisture and Alkalinity Tests

SD-08 Manufacturer’s Instructions 3.1Surface Preparation 3.4Installation

SD-10 Operation and Maintenance Data

2.2Carpet 3.5Cleaning and Protection

SD-11 Closeout Submittals 1.5Warranty

10 21 13 SD-02 Shop Drawings 2.1Fabrication Drawings 3.3Installation Drawings

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 18 PAGES

10 21 13 2.1Cleaning and Maintenance Instructions

2.7Colors And Finishes 2.2.1Anchoring Devices and

Fasteners 2.2.3Hardware and Fittings 2.2.2Brackets 2.2.4Door Hardware 2.3.1Toilet Enclosures 2.3.2Urinal Screens 2.5Pilaster Shoes 2.2.3.2Finishes

SD-04 Samples 2.7Colors and Finishes 2.2.3Hardware and Fittings 2.2.1Anchoring Devices and

Fasteners SD-07 Certificates

1.5Warranty 10 28 13 SD-03 Product Data

2.1.2Finishes 2.2Accessory Items

SD-04 Samples 2.1.2Finishes 2.2Accessory Items

SD-07 Certificates

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 18 PAGES

10 28 13 2.2Accessory Items 10 99 00 SD-01 Preconstruction Submittals

1.2.1Installer Qualifications SD-02 Shop Drawings

1.2.2USPS-Private Commercial Mailboxes

1.2.2Cell Phone Lockers SD-03 Product Data

1.2.2USPS-Private Commercial Mailboxes

1.2.3Cell Phone Locker 2.3Stainless Steel Folding Table 2.4Garment Rack

SD-10 Operation and Maintenance Data

1.2.3Postal Specialties and Finishes 1.2.3Cell Phone Locker

22 00 00 SD-02 Shop Drawings

3.9.1 GPlumbing System

SD-03 Product Data 2.5Fixtures 2.5.2Flush Valve Water Closets 2.5.3Flush Valve Urinals 2.5.5Wall Hung Lavatories 2.5.6Countertop Lavatories 2.5.7Kitchen Sinks

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 18 PAGES

22 00 00 2.5.9Service Sinks

2.5.10 GDrinking-Water Coolers

2.5.13Cast Iron Bathtubs 2.5.11Laundry Trays 2.5.12Washer Box 2.5.14Ice Maker Box

2.9 GWater Heaters

2.11 GPumps

3.9.1.1 GBackflow Prevention Assemblies

2.7.2 GShower Faucets

2.12Domestic Water Service Meter 1.5.1Welding

3.4 GVibration-Absorbing Features

3.9.1Plumbing System

SD-06 Test Reports 3.9Tests, Flushing and Disinfection

3.9.1.1 GTest of Backflow Prevention

Assemblies SD-07 Certificates

1.3Materials and Equipment 2.2.1Bolts

SD-10 Operation and Maintenance Data

3.9.1 GPlumbing System

SD-11 Closeout Submittals

2.1.1 SWater-Efficient Products

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 18 PAGES

22 00 00 2.1.2 SEnergy-Efficient Water Heaters 23 00 00 SD-02 Shop Drawings

1.4.5 GDetail Drawings

SD-03 Product Data

2.10.1.1Metallic Flexible Duct 2.10.1.2Insulated Nonmetallic Flexible

Duct Runouts 2.10.1.2Duct Connectors

2.10.2 GDuct Access Doors

2.10.3Fire Dampers

2.10.4 GManual Balancing Dampers

2.10.7Sound Attenuation Equipment 2.10.8.1Diffusers 2.10.8.2Registers and Grilles 2.10.9Louvers 2.10.10Air Vents, Wall Caps, and

Goosenecks 2.11.1.1In-Line Centrifugal Fans 2.11.1.2Ceiling Exhaust Fans

2.12 GAir Handling Units

2.14.1 GRoom Fan-Coil Units

2.14.2.1 GVariable Volume, Single Duct

Terminal Units

2.15 GEnergy Recovery Devices

2.13 GDedicated Outdoor Air Handling

Units

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 18 PAGES

23 00 00 1.4.6Test Procedures

1.2.1.2 GDiagrams

SD-06 Test Reports

3.13 GPerformance Tests

3.11 GDamper Acceptance Test

SD-07 Certificates 1.4.1Bolts 1.4.7Certification 1.4.3Ozone Depleting Substances

SD-08 Manufacturer’s Instructions 3.3Manufacturer's Installation

Instructions 3.15.2Operation and Maintenance

Training SD-10 Operation and Maintenance Data

3.15.1 GOperation and Maintenance

Manuals

2.10.3 GFire Dampers

2.10.4 GManual Balancing Dampers

2.11.1.1 GIn-Line Centrifugal Fans

2.11.1.2 GCeiling Exhaust Fans

2.12 GAir Handling Units

2.14.1 GRoom Fan-Coil Units

2.14.2.1 GVariable Volume, Single Duct

Terminal Units

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 18 PAGES

23 00 00 2.15 GEnergy Recovery Devices

2.13 GDedicated Outdoor Air Handling

Units SD-11 Closeout Submittals

2.1.1 SEnergy Efficient Equipment

2.1.2 SReduce Volatile Organic

Compounds (VOC)

3.1 SIndoor Air Quality During

Construction

2.1.3 SOzone Depleting Substances for

Refrigerants 23 09 00 SD-02 Shop Drawings

3.3 GDDC Contractor Design Drawings

3.3 GDraft As-Built Drawings

3.3 GFinal As-Built Drawings

SD-03 Product Data

1.8.4 GCertificate of Networthiness

Documentation

1.8.2 GProgramming Software

1.8.3 GController Application Programs

1.8.1 GConfiguration Software

2.2 GManufacturer's Product Data

SD-05 Design Data 1.9Boiler Or Chiller Plant Gateway

Request SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 18 PAGES

23 09 00 3.1.1Existing Conditions Report

3.5.2 GStart-Up Testing Report

3.6.1 GPVT Procedures

3.6.3 GPVT Report

1.10.1 GPre-Construction Quality Control

(QC) Checklist

1.10.2 GPost-Construction Quality Control

(QC) Checklist SD-10 Operation and Maintenance Data

3.7 GOperation and Maintenance

(O&M) Instructions

3.9.1 GTraining Documentation

SD-11 Closeout Submittals

2.5 GEnclosure Keys

3.2.6.1 GPassword Summary Report

1.10.3 GCloseout Quality Control (QC)

Checklist 23 64 26 SD-03 Product Data

2.3.4 GCalibrated Balancing Valves

2.3.5 GAutomatic Flow Control Valves

2.4.7 GExpansion Joints

SD-06 Test Reports 3.1.1.3Piping Welds NDE Report

3.4.2 GPressure Tests Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 18 PAGES

23 64 26 3.6 GOne-Year Inspection Report For Cooling Water

SD-07 Certificates 3.1.1.1Employer's Record Documents

(For Welding) 3.1.1.2Welding Procedures and

Qualifications SD-08 Manufacturer’s Instructions

3.5 GLesson plan for the Instruction

Course

SD-10 Operation and Maintenance Data

2.3.4 GCalibrated Balancing Valves

2.3.5 GAutomatic Flow Control Valves

2.4.7 GExpansion Joints

25 05 11 SD-01 Preconstruction Submittals

3.1.2.2 GDevice Account Lock Exception

Request

3.9 GMultiple IP Connection Device

Request

1.9.1.4 GContractor Computer

Cybersecurity Compliance Statements

1.9.6 GContractor Temporary Network

Cybersecurity Compliance Statements

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 18 PAGES

25 05 11 SD-02 Shop Drawings

3.1.3.1 GUser Interface Banner Schedule

1.7.1 GNetwork Communication Report

1.7.4 GCybersecurity Riser Diagram

1.7.2 GControl System Inventory Report

SD-03 Product Data

1.7.5 GControl System Cybersecurity

Documentation SD-07 Certificates

1.8 GSoftware Licenses

SD-11 Closeout Submittals

3.5.2.2.4 GPassword Summary Report

1.7.3 GSoftware Recovery And

Reconstitution Images

3.2.2.1 GDevice Audit Record Upload

Software 26 12 19.10 SD-02 Shop Drawings

1.5.1 GPad-mounted Transformer

Drawings

SD-03 Product Data

2.2 GPad-mounted Transformers

SD-06 Test Reports

3.6.1 GAcceptance Checks and Tests

SD-07 Certificates

2.2.2.1 GTransformer Efficiencies

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 18 PAGES

26 12 19.10 SD-09 Manufacturer’s Field Reports

2.8.1Transformer Test Schedule 2.8.2Design Tests 2.8.3Routine and Other Tests

SD-10 Operation and Maintenance Data

1.6.1Transformer(s) 26 20 00 SD-02 Shop Drawings

2.13Panelboards 2.15Transformers 2.4Cable trays 3.1.9.1Marking strips

SD-03 Product Data 2.12Receptacles 2.13.3Circuit breakers 2.11Switches 2.15Transformers 2.14Enclosed circuit breakers 2.17Manual motor starters 2.20.1CATV outlets 2.21.3Grounding Busbar 2.27Surge protective devices

SD-06 Test Reports 3.5.2600-volt wiring test 3.5.5Grounding system test

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 18 PAGES

26 20 00 3.5.3Transformer tests 3.5.4Ground-fault receptacle test

SD-09 Manufacturer’s Field Reports

2.29.1Transformer factory tests SD-10 Operation and Maintenance Data

1.5.1Electrical Systems 26 29 23 SD-02 Shop Drawings

1.5.1 GSchematic Diagrams

1.5.2 GInterconnecting Diagrams

1.5.3 GInstallation Drawings

SD-03 Product Data

2.1 GVariable Frequency Drives

2.3Wires and Cables 1.5.4Equipment Schedule

SD-06 Test Reports 3.2.1VFD Test 3.2.2Performance Verification Tests 3.2.3Endurance Test

SD-08 Manufacturer’s Instructions 1.5.5Installation instructions

SD-09 Manufacturer’s Field Reports

2.5.1 GVFD Factory Test Plan

1.5.6Factory test results

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 18 PAGES

26 29 23 SD-10 Operation and Maintenance Data

2.1Variable Frequency Drives 26 51 00 SD-02 Shop Drawings

1.5.1Luminaire Drawings 1.5.2Occupancy/Vacancy Sensor

Coverage Layout SD-03 Product Data

2.2Luminaires 2.4Light Sources 2.3Drivers 1.6.1LED Luminaire Warranty 1.5.4Luminaire Design Data 2.5.3.2Vacancy Sensors 2.5.2Dimming Controllers (Dimmers) 2.8Power Hook Luminaire Hangers 2.6.1Exit Signs 2.6.2LED Emergency Drivers 2.5.3.1Occupancy Sensors 3.1.8Ambient Light Level Sensor 2.13Emergency Lighting Control Unit 2.14Photocell

SD-06 Test Reports 1.5.5LED Luminaire - IES LM-79 Test

Report

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 18 PAGES

26 51 00 1.5.6LED Light Source - IES LM-80 Test Report

1.5.7LED Light Source - IES TM-21 Test Report

1.5.8Occupancy/Vacancy Sensor Verification Tests

1.5.11.3Energy Efficiency SD-07 Certificates

1.6.1.1Luminaire Useful Life Certificate 1.5.3LED Driver and Dimming Switch

Compatibility Certificate 26 56 00 SD-01 Preconstruction Submittals

1.5.2Photometric Plan 1.6.1LED Luminaire Warranty

SD-02 Shop Drawings 1.5.1.1Luminaire drawings

SD-03 Product Data 2.2.2Luminaire Light Sources 2.2.3Luminaire Power Supply Units

(Drivers) 2.3.2Motion Sensor

SD-04 Samples

2.2 G LEDLED Luminaires

SD-05 Design Data 1.5.3Design Data for luminaires

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 18 PAGES

26 56 00 1.5.4LED Luminaire - IES LM-79 Test Report

1.5.5LED Light Source - IES LM-80 Test Report

3.2Operating test SD-07 Certificates

1.6.1Luminaire Useful Life Certificate SD-10 Operation and Maintenance Data

1.7Operational Service 27 05 14.00 10 SD-02 Shop Drawings

1.2 GCable TV Premises Distribution

System

3.1 GInstallation

SD-03 Product Data

1.7Spare Parts

3.4 GTest Plan

1.4Qualifications

SD-06 Test Reports 3.4Testing

SD-07 Certificates 2.1Materials and Equipment

SD-08 Manufacturer’s Instructions 3.1.2Manufacturer's

Recommendations

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 18 PAGES

27 05 14.00 10 SD-10 Operation and Maintenance Data

3.5Operation and Maintenance Manuals

27 10 00 SD-02 Shop Drawings 1.6.1.1Telecommunications drawings 1.6.1.2Telecommunications Space

Drawings SD-03 Product Data

2.3Telecommunications cabling 2.4.5Patch panels 2.5Telecommunications outlet/connector assemblies 2.4.2Equipment support frame 2.4.3Connector blocks

SD-06 Test Reports

3.5.1 GTelecommunications cabling

testing SD-07 Certificates

1.6.2.1 GTelecommunications Contractor

1.6.2.2 GKey Personnel

1.6.2.3 GManufacturer Qualifications

1.6.3 GTest plan

SD-09 Manufacturer’s Field Reports

2.10.1 GFactory reel tests

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 18 PAGES

27 10 00 SD-10 Operation and Maintenance Data

1.10.1 GTelecommunications cabling and

pathway system

SD-11 Closeout Submittals

1.10.2 GRecord Documentation

33 71 02 SD-03 Product Data 2.5Medium voltage cable 2.7Medium voltage cable joints 2.6Medium voltage cable terminations SD-06 Test Reports

2.14.2Medium voltage cable qualification and production tests

3.18.1Field Acceptance Checks and Tests

2.14.1Arc-proofing test 3.3Cable Installation Plan and

Procedure SD-07 Certificates

1.5.1Cable splicer/terminator 1.5.2Cable Installer Qualifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SECTION TABLE OF CONTENTS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

SECTION 23 00 00

AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

08/10

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 Mechanical Equipment Identification

1.2.1.1 Charts

1.2.1.2 Diagrams

1.2.2 Service Labeling

1.2.3 Color Coding

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Prevention of Corrosion

1.4.2 Asbestos Prohibition

1.4.3 Ozone Depleting Substances Used as Refrigerants

1.4.4 Use of Ozone Depleting Substances, Other than Refrigerants

1.4.5 Detail Drawings

1.4.6 Test Procedures

1.4.7 Sustainable Design Certification

1.5 DELIVERY, STORAGE, AND HANDLING

PART 2 PRODUCTS

2.1 PRODUCT SUSTAINABILITY CRITERIA

2.1.1 Energy Efficient Equipment

2.1.2 Reduce Volatile Organic Compounds (VOC) for sealants, coatings or adhesives

2.1.3 Ozone Depleting Substances for Refrigerants

2.2 STANDARD PRODUCTS

2.3 IDENTIFICATION PLATES

2.4 EQUIPMENT GUARDS AND ACCESS

2.5 ELECTRICAL WORK

2.6 ANCHOR BOLTS

2.7 SEISMIC ANCHORAGE

2.8 PAINTING

2.9 INDOOR AIR QUALITY

2.10 DUCT SYSTEMS

2.10.1 Metal Ductwork

2.10.1.1 Metallic Flexible Duct

2.10.1.2 Insulated Nonmetallic Flexible Duct Runouts

2.10.1.3 General Service Duct Connectors

2.10.1.4 High Temperature Service Duct Connections

2.10.1.5 Aluminum Ducts

2.10.1.6 Copper Sheets

2.10.1.7 Corrosion Resisting (Stainless) Steel Sheets

2.10.2 Duct Access Doors

2.10.3 Fire Dampers

SECTION 23 00 00 Page 1

2.10.4 Manual Balancing Dampers

2.10.5 Air Supply And Exhaust Air Dampers

2.10.6 Air Deflectors (Volume Extractors) and Branch Connections

2.10.7 Sound Attenuation Equipment

2.10.7.1 System with total pressure of 4 Inch Water Gauge and Lower

2.10.8 Diffusers, Registers, and Grilles

2.10.8.1 Diffusers

2.10.8.2 Registers and Grilles

2.10.9 Louvers

2.10.10 Air Vents, Wall Caps and Goosenecks

2.10.11 Bird Screens and Frames

2.11 AIR SYSTEMS EQUIPMENT

2.11.1 Fans

2.11.1.1 In-Line Centrifugal Fans

2.11.1.2 Ceiling Exhaust Fans

2.11.2 Coils

2.11.2.1 Water Coils

2.11.3 Air Filters

2.11.3.1 Extended Surface Pleated Panel Filters

2.11.3.2 Holding Frames

2.11.3.3 Filter Gauges

2.12 AIR HANDLING UNITS

2.12.1 Factory-Fabricated Air Handling Units

2.12.1.1 Casings

2.12.1.2 Heating and Cooling Coils

2.12.1.3 Air Filters

2.12.1.4 Fans

2.13 DEDICATED OUTDOOR AIR HANDLING UNITS

2.14 TERMINAL UNITS

2.14.1 Room Fan-Coil Units

2.14.1.1 Enclosures

2.14.1.2 Fans

2.14.1.3 Coils

2.14.1.4 Drain Pans

2.14.1.5 Filters

2.14.1.6 Motors

2.14.2 Variable Air Volume (VAV) and Terminal Units

2.14.2.1 Variable Volume, Single Duct Terminal Units

2.15 ENERGY RECOVERY DEVICES

2.15.1 Energy Recovery Ventilator

2.16 FACTORY PAINTING

2.17 SUPPLEMENTAL COMPONENTS/SERVICES

2.17.1 Chilled, Condenser Water Piping

2.17.2 Condensate Drain Lines

2.17.3 Backflow Preventers

2.17.4 Insulation

2.17.5 Controls

PART 3 EXECUTION

3.1 CONSTRUCTION-RELATED SUSTAINABILITY CRITERIA

3.2 EXAMINATION

3.3 INSTALLATION

3.3.1 Condensate Drain Lines

3.3.2 Equipment and Installation

3.3.3 Access Panels

3.3.4 Flexible Duct

3.3.5 Dust Control

3.3.6 Insulation

SECTION 23 00 00 Page 2

3.3.7 Duct Test Holes

3.3.8 Power Transmission Components Adjustment

3.4 EQUIPMENT PADS

3.5 CUTTING AND PATCHING

3.6 CLEANING

3.7 PENETRATIONS

3.7.1 Sleeves

3.7.2 Framed Prepared Openings

3.7.3 Insulation

3.7.4 Closure Collars

3.7.5 Firestopping

3.8 FIELD PAINTING OF MECHANICAL EQUIPMENT

3.8.1 Temperatures less than 120 degrees F

3.8.2 Temperatures between 120 and 400 degrees F

3.8.3 Finish Painting

3.8.4 Color Coding Scheme for Locating Hidden Utility Components

3.9 IDENTIFICATION SYSTEMS

3.10 DUCTWORK LEAK TEST

3.11 DAMPER ACCEPTANCE TEST

3.12 TESTING, ADJUSTING, AND BALANCING

3.13 PERFORMANCE TESTS

3.14 CLEANING AND ADJUSTING

3.15 OPERATION AND MAINTENANCE

3.15.1 Operation and Maintenance Manuals

3.15.2 Operation And Maintenance Training

-- End of Section Table of Contents --

SECTION 23 00 00 Page 3

SECTION 23 00 00

AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

08/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR MOVEMENT AND CONTROL ASSOCIATION INTERNATIONAL, INC. (AMCA)

AMCA 201 (2002; R 2011) Fans and Systems

AMCA 210 (2016) Laboratory Methods of Testing Fans for Aerodynamic Performance Rating

AMCA 300 (2014) Reverberant Room Method for Sound Testing of Fans

AMCA 301 (2014) Methods for Calculating Fan Sound Ratings from Laboratory Test Data

AMCA 500-D (2018) Laboratory Methods of Testing Dampers for Rating

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

AHRI 260 I-P (2012) Sound Rating of Ducted Air Moving and Conditioning Equipment

AHRI 350 (2015) Sound Rating of Non-Ducted Indoor Air-Conditioning Equipment

AHRI 410 (2001; Addendum 1 2002; Addendum 2 2005;

Addendum 3 2011) Forced-Circulation Air-Cooling and Air-Heating Coils

AHRI 430 (2009) Central-Station Air-Handling Units

AHRI 440 (2008) Performance Rating of Room Fan-Coils

AHRI 880 I-P (2011) Performance Rating of Air Terminals

AHRI 885 (2008; Addendum 2011) Procedure for Estimating Occupied Space Sound Levels in the Application of Air Terminals and Air Outlets

AHRI Guideline D (1996) Application and Installation of Central Station Air-Handling Units

SECTION 23 00 00 Page 4

AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)

ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings

ABMA 9 (2015) Load Ratings and Fatigue Life for Ball Bearings

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 52.2 (2012) Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size

ASHRAE 62.1 (2010) Ventilation for Acceptable Indoor Air Quality

ASHRAE 68 (1997) Laboratory Method of Testing to Determine the Sound Power In a Duct

ASHRAE 70 (2006; R 2011) Method of Testing for Rating the Performance of Air Outlets and Inlets

ASHRAE 90.1 - IP (2016; ERTA 1-8 2017; INT 1-5 2017) Energy Standard for Buildings Except Low-Rise Residential Buildings

ASME INTERNATIONAL (ASME)

ASME A13.1 (2015) Scheme for the Identification of Piping Systems

ASTM INTERNATIONAL (ASTM)

ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A924/A924M (2017a) Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process

ASTM B117 (2016) Standard Practice for Operating Salt Spray (Fog) Apparatus

ASTM B152/B152M (2013) Standard Specification for Copper Sheet, Strip, Plate, and Rolled Bar

SECTION 23 00 00 Page 5

ASTM B209 (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

ASTM B766 (1986; R 2015) Standard Specification for Electrodeposited Coatings of Cadmium

ASTM C1071 (2016) Standard Specification for Fibrous Glass Duct Lining Insulation (Thermal and Sound Absorbing Material)

ASTM C553 (2013) Standard Specification for Mineral Fiber Blanket Thermal Insulation for Commercial and Industrial Applications

ASTM D1654 (2008; R 2016; E 2017) Standard Test Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments

ASTM D3359 (2017) Standard Test Methods for Rating Adhesion by Tape Test

ASTM D520 (2000; R 2011) Zinc Dust Pigment

ASTM E2016 (2015) Standard Specification for Industrial Woven Wire Cloth

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2016; SUPP 2016) Motors and Generators

NEMA MG 10 (2017) Energy Management Guide for Selection and Use of Fixed Frequency Medium AC Squirrel-Cage Polyphase Induction Motors

NEMA MG 11 (1977; R 2012) Energy Management Guide for Selection and Use of Single Phase Motors

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 701 (2015) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films

NFPA 90A (2018) Standard for the Installation of Air Conditioning and Ventilating Systems

SCIENTIFIC CERTIFICATION SYSTEMS (SCS)

SCS SCS Global Services (SCS) Indoor Advantage

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1819 (2002) Fire, Smoke and Radiation Damper Installation Guide for HVAC Systems, 5th Edition

SMACNA 1966 (2005) HVAC Duct Construction Standards

SECTION 23 00 00 Page 6

Metal and Flexible, 3rd Edition

SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition

U.S. DEPARTMENT OF ENERGY (DOE)

Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 82 Protection of Stratospheric Ozone

PL 109-58 Energy Policy Act of 2005 (EPAct05)

UL ENVIRONMENT (ULE)

ULE Greenguard UL Greenguard Certification Program

UNDERWRITERS LABORATORIES (UL)

UL 181 (2013; Reprint Apr 2017) UL Standard for Safety Factory-Made Air Ducts and Air Connectors

UL 1995 (2015) Heating and Cooling Equipment

UL 555 (2006; Reprint Aug 2016) UL Standard for Safety Fire Dampers

UL 586 (2009; Reprint Dec 2017) UL Standard for Safety High-Efficiency Particulate, Air Filter Units

UL 6 (2007; Reprint Nov 2014) Electrical Rigid Metal Conduit-Steel

UL 705 (2017) UL Standard for Safety Power Ventilators

UL 900 (2015) Standard for Air Filter Units

UL 94 (2013; Reprint Sep 2017) UL Standard for Safety Tests for Flammability of Plastic Materials for Parts in Devices and Appliances

UL Bld Mat Dir (updated continuously online) Building Materials Directory

UL Electrical Constructn (2012) Electrical Construction Equipment Directory

UL Fire Resistance (2014) Fire Resistance Directory

1.2 SYSTEM DESCRIPTION

Furnish ductwork, piping offsets, fittings, and accessories as required to

SECTION 23 00 00 Page 7 provide a complete installation. Coordinate the work of the different trades to avoid interference between piping, equipment, structural, and electrical work. Provide complete, in place, all necessary offsets in piping and ductwork, and all fittings, and other components, required to install the work as indicated and specified.

1.2.1 Mechanical Equipment Identification

The number of charts and diagrams shall be equal to or greater than the number of mechanical equipment rooms. Where more than one chart or diagram per space is required, mount these in edge pivoted, swinging leaf, extruded aluminum frame holders which open to 170 degrees.

1.2.1.1 Charts

Provide chart listing of equipment by designation numbers and capacities such as flow rates, pressure and temperature differences, heating and cooling capacities, horsepower, pipe sizes, and voltage and current characteristics.

1.2.1.2 Diagrams

Submit proposed diagrams, at least 2 weeks prior to start of related testing. provide neat mechanical drawings provided with extruded aluminum frame under 1/8-inch glass or laminated plastic, system diagrams that show the layout of equipment, piping, and ductwork, and typed condensed operation manuals explaining preventative maintenance procedures, methods of checking the system for normal, safe operation, and procedures for safely starting and stopping the system. After approval, post these items where directed.

1.2.2 Service Labeling

Label equipment, including fans, air handlers, terminal units, etc. with labels made of self-sticking, plastic film designed for permanent installation. Labels shall be in accordance with the typical examples below:

SERVICE LABEL AND TAG DESIGNATION

Air handling unit Number AHU - 1

Control and instrument air CONTROL AND INSTR.

Exhaust Fan Number EF - 1

VAV Box Number VAV - 1

Fan Coil Unit Number FC - 1

Energy Recovery Ventilator Number ERV - 1

Identify similar services with different temperatures or pressures. Where pressures could exceed 125 pounds per square inch, gage, include the maximum system pressure in the label. Label and arrow piping in accordance with the following:

SECTION 23 00 00 Page 8

a. Each point of entry and exit of pipe passing through walls.

b. Each change in direction, i.e., elbows, tees.

c. In congested or hidden areas and at all access panels at each point required to clarify service or indicated hazard.

d. In long straight runs, locate labels at distances within eyesight of each other not to exceed 75 feet. All labels shall be visible and legible from the primary service and operating area.

For Bare or Insulated Pipes for Outside Diameters of Lettering

1/2 thru 1-3/8 inch 1/2 inch

1-1/2 thru 2-3/8 inch 3/4 inch

2-1/2 inch and larger 1-1/4 inch

1.2.3 Color Coding

Color coding of all piping systems shall be in accordance with ASME A13.1

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Detail Drawings; G

SD-03 Product Data

Metallic Flexible Duct Insulated Nonmetallic Flexible Duct Runouts Duct Connectors Duct Access Doors; G Fire Dampers Manual Balancing Dampers; G Sound Attenuation Equipment Diffusers Registers and Grilles Louvers Air Vents, Wall Caps, and Goosenecks In-Line Centrifugal Fans Ceiling Exhaust Fans Air Handling Units; G Room Fan-Coil Units; G Variable Volume, Single Duct Terminal Units; G Energy Recovery Devices; G Dedicated Outdoor Air Handling Units; G

SECTION 23 00 00 Page 9

Test Procedures Diagrams; G

SD-06 Test Reports

Performance Tests; G Damper Acceptance Test; G

SD-07 Certificates

Bolts Certification Ozone Depleting Substances

SD-08 Manufacturer's Instructions

Manufacturer's Installation Instructions Operation and Maintenance Training

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals; G

Fire Dampers; G Manual Balancing Dampers; G In-Line Centrifugal Fans; G Ceiling Exhaust Fans; G Air Handling Units; G Room Fan-Coil Units; G Variable Volume, Single Duct Terminal Units; G Energy Recovery Devices; G Dedicated Outdoor Air Handling Units; G

SD-11 Closeout Submittals

Energy Efficient Equipment; S Reduce Volatile Organic Compounds (VOC); S Indoor Air Quality During Construction; S Ozone Depleting Substances for Refrigerants; S

1.4 QUALITY ASSURANCE

Except as otherwise specified, approval of materials and equipment is based on manufacturer's published data.

a. Where materials and equipment are specified to conform to the standards of the Underwriters Laboratories, the label of or listing with reexamination in UL Bld Mat Dir, and UL 6 is acceptable as sufficient evidence that the items conform to Underwriters Laboratories requirements. In lieu of such label or listing, submit a written certificate from any nationally recognized testing agency, adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the specified requirements. Outline methods of testing used by the specified agencies.

b. Where materials or equipment are specified to be constructed or tested, or both, in accordance with the standards of the ASTM International (ASTM), the ASME International (ASME), or other standards, a

SECTION 23 00 00 Page 10 manufacturer's certificate of compliance of each item is acceptable as proof of compliance.

c. Conformance to such agency requirements does not relieve the item from compliance with other requirements of these specifications.

d. Where products are specified to meet or exceed the specified energy efficiency requirement of FEMP-designated or Energy Star certified product categories, equipment selected shall have as a minimum the efficiency rating identified under "Energy-Efficient Products" at http://www1.eere.energy.gov/femp/procurement.

These specifications conform to the efficiency requirements as defined in Public Law PL 109-58, "Energy Policy Act of 2005" for federal procurement of energy-efficient products. Equipment having a lower efficiency than Energy Star or FEMP requirements may be specified if the designer determines the equipment to be more life-cycle cost effective using the life-cycle cost analysis methodology and procedure in 10 CFR 436.

1.4.1 Prevention of Corrosion

Protect metallic materials against corrosion. Manufacturer shall provide rust-inhibiting treatment and standard finish for the equipment enclosures. Do not use aluminum in contact with earth, and where connected to dissimilar metal.