Attch 26 01 14 00 WORK RESTRICTIONS.pdf

PDF 16 KB Posted

Attached to
F-22 Low Observable Component Repair Facility (LOCRF) Federal contract opportunity
Solicitation number
W9123621R2023
Issued by
Department of the Army Corps of Engineers Engineering District Norfolk

About this file

This document provides details for a federal construction contract solicitation to build a Low Observable Component Repair Facility at Langley Air Force Base in Virginia. The solicitation seeks construction of a 6,735 square meter facility with four high-bay spaces, including three low observable critical repair bays and one wash rack bay. The facility will house corrosion control and maintenance operations for additional F-22A aircraft relocated to Langley Air Force Base from Tyndall Air Force Base. Construction must include site work, utilities, foundations, structural steel framework, exterior walls, roofing, air handling systems, fire protection, administrative offices, restrooms, and electrical/mechanical/telecommunications support spaces. The facility design must meet seismic and wind requirements and incorporate sustainable practices. The contract duration is expected to be 730 calendar days. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Norfolk.

View the file

Other files for this federal contract opportunity

Other files attached to F-22 Low Observable Component Repair Facility (LOCRF), newest first.
File Type Posted
Attachment 8 - Revised Bid Schedule.pdf PDF
W9123621R2023 Amendment 13.pdf PDF
Attch 40 06 61 16 AMENDMENT 09 FEB 22.pdf PDF
Attch 38 LOCRF DRAWINGS AMENDMENT 09FEB2022.pdf PDF
Attch 41 Copy of GFE Equipment List_mjm edits 2020.09.24.xlsx XLSX spreadsheet
Attch 38 08 81 00 Glazing.pdf PDF
Attachment 8 - Revised CLIN Schedule.pdf PDF
Attch 35 32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT.pdf PDF
Attch 25 01 11 00 Appendix to 01 11 00 Government Furnished Equipment.pdf PDF
Attch 24 P 601 PLUMBING SCHEDULES.pdf PDF
Attch 23 A 533 ROOF DETAILS.pdf PDF
Attch 22 A 011 EQUIPMENT SCHEDULE METALS TECH and SHOPS.pdf PDF
Attch 36 32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS.pdf PDF
Attch 33 10 56 26.13 MOBILE STORAGE SHELVING UNITS (MECHANICALLY-ASSISTED).pdf PDF
Attch 32 09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES.pdf PDF
Attch 31 09 90 00 PAINTS AND COATINGS.pdf PDF
Attch 30 08 34 16 CORROSION CONTROL HANGAR DOORS.pdf PDF
Attch 27 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.pdf PDF
Attch 37 33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATION.pdf PDF
Attch 34 13 34 19 METAL BUILDING SYSTEMS.pdf PDF
Attch 28 03 45 00 PRECAST ARCHITECTURAL CONCRETE.pdf PDF
W9123621R2023 Amendment 10.pdf PDF
Site Visit 10 January.pdf PDF
W9123621R2023 Amendment 9.pdf PDF
Attachment 19 LOCRF RTA SID PACKAGE.pdf PDF
Attachment 16 LOCRF RTA DWGS PART 2 OF 3.pdf PDF
Attachment 15 LOCRF RTA DWGS PART 1 OF 3.pdf PDF
Attch 13- LOCRF 20Oct21 Blended Drawings Part 3 of 3.pdf PDF
Attch 10- LOCRF 20Oct21 Blended Drawings Part 1 of 3.pdf PDF
W9123621R2023 Amendment 8.pdf PDF
Attch 11- LOCRF 20Oct21 Blended Drawings Part 2 of 3.pdf PDF
W9123621R2023 Amendment 7.pdf PDF
W9123621R2023 Amendment 6.pdf PDF
W9123621R2023 LOCRF Amend 5.pdf PDF
W9123621R2023 Amendment 4.pdf PDF
A.07.24 - Amendment 3.pdf PDF
A.07.24 - Amendment 2.pdf PDF
Attch 12 - LOCRF 100 Specification Part 1 of 1.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Attachment 7 - Small Business Participation Plan.pdf PDF
Attachment 4 - Telephone Interview Questionnaire (For Government Use Only).pdf PDF
Attachment 6 - Small Business Subcontracting Record.pdf PDF
Solicitation W9123621R2023.pdf PDF
Attch 11 - LOCRF 100 Dwgs Part 2 of 2.pdf PDF
Attachment 2 - Company Specialized Experience.pdf PDF
Attachment 8 - CLIN Schedule.pdf PDF
Attch 10 - LOCRF 100 Dwgs Part 1 of 2.pdf PDF
Attachment 1 - Proposal Data Sheet.pdf PDF
Attachment 5 - Letter of Commitment Sample.pdf PDF
Attachment 9 - Langley Environmental Management Special Conditions.pdf PDF
Show all 50

F-22 Low Observable Component Repair Facility (LOCRF) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOW OBSERVABLE COMPOSITE REPAIR FACILITY W91236-21-R-2023

Langley Air Force Base

SECTION 01 14 00

WORK RESTRICTIONS

11/11

AMENDMENT 21 JAN 22

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

"G, AE" code is applied where Architect/Engineer review and approval is required. "G, RO" code is applied where Government Resident Office review and approval is required. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G, RO

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. The Airfield will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

See specification Section 01 35 13 Special Project Procedures for additional information and restrictions.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The

SECTION 01 14 00 Page 1

Contracting Officer will identify designated smoking areas.

1.3.2 Working Hours

Regular working hours may consist of a 10 hour period between 7 a.m. and 5:00 p.m., Monday through Friday, and 7 a.m. to 3:30 p.m. on Saturday, excluding Government holidays.

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 30 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.3.4 Occupied Buildings

The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.

1.3.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

1.4 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

AMENDMENT 21 JAN 22* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

1.4.1 ON-SITE PHOTOGRAPHY

Photos shall be limited to the facility pre-existing conditions, construction and grounds within the limits of disturbance for project related activities only. This includes monthly progress photos and documentation of the site. Photo distribution and access shall be on a need to know basis within the contractor's project team and the Government. Pictures of the airfield and aircraft are expressly prohibited unless otherwise authorized and approved by the COR and shall not be assumed to be authorized for normal construction.

SECTION 01 14 00 Page 2

The Contractor will not be allowed to take photographs at any time on this project site. Photographs may be provided by the Government at the AO's discretion.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * AMENDMENT 21 JAN 22

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 3

RoseborS Line

RoseborS Line

RoseborS Line

01 14 00 - WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
1.3.1.1 Subcontractors and Personnel Contacts
1.3.1.2 No Smoking Policy
1.3.2 Working Hours
1.3.3 Work Outside Regular Hours
1.3.4 Occupied Buildings
1.3.5 Utility Cutovers and Interruptions
1.4 SECURITY REQUIREMENTS
1.4.1 ON-SITE PHOTOGRAPHY
PART 2 PRODUCTS
PART 3 EXECUTION