Attachment_0014-1_DD_Form_1692_ECP(pg1).pdf

DoD Form PDF 92 KB Posted

Attached to
Expeditionary Shelter Protection System (ESPS)
Solicitation number
W911QY-16-R-0003
Issued by

About this file

Attachment 0014-1_DD Form 1692_ECP(pg1)

View the file

Other versions and copies of DD Form 1692

File Revision Posted Attached to
Section J-13I DD Form 1692 Engineering Change Proposal.pdf Revision not stated Homeland Security Cutter - Light Icebreaker (HSC-L) Solicitation
ATT 0008 DD 1692 EngineeringChangeProposal (ECP).pdf Revision not stated Quick Disconnect Mechanism Assembly LH, RH
Attachment 0005 DD1692 ENGINEERING CHANGE PROPOSAL.docx Revision not stated 60mm (M204, M235, M236); 81mm (M218, M219, M220, M658); and 120mm (M234A1) Propelling Charges
Attachment 0002 DD Form 1692.pdf Revision not stated Type I Family of All Terrain Crane Solicitation Amendment 0009
Attachment 0003 _ DD Form 1692.pdf Revision not stated Type I Family of All Terrain Crane Draft Section C (Scope of Work); Draft Attachments, and Draft Contract Data Requirement Lists (CDRLs)
Attach_0004_-_DD1692_Engineering_Change_Proposal_(ECP).pdf Revision not stated MK3 MOD 0 and MK12 MOD 1 Pallet
Attach_0004_-_DD1692_Engineering_Change_Proposal_(ECP).pdf Revision not stated MK3 MOD 0 & MK12 MOD 1 PALLET
Attachment_0006__DD1692_-_ENGINEERING_CHANGE_PROPOSAL_(ECP).pdf Revision not stated 60mm, 81mm, 120mm Mortar Propelling Charges
dd1692-Instruction.pdf Revision not stated BOMB FUZE PROTECTION ASSEMBLY
dd1692_ECP.pdf Revision not stated BOMB FUZE PROTECTION ASSEMBLY
Attachment_0007_-_DD1692_-_Engineering_Change_Proposal_(ECP).pdf Revision not stated AMMUNITION, OVER 30MM UP TO 75MM
Attachment_0014-3_DD_Form_1692_ECP(pg3).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0014-6_DD_Form_1692_ECP(pg6).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0014-5_DD_Form_1692_ECP(pg5).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0014-7_DD_Form_1692_ECP(pg7).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0014-4_DD_Form_1692_ECP(pg4).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0014-2_DD_Form_1692_ECP(pg2).pdf Revision not stated Expeditionary Shelter Protection System (ESPS)
Attachment_0003_-_DD1692_-_Engineering_Change_Proposal_(ECP).pdf Revision not stated AMMUNITION AND NUCLEAR ORDNANCE BOXES, PACKAGES AND SPECIAL CONTAINERS
Attachment_0017_-_DD1692_-_Engineering_Change_Proposal_(ECP).pdf Revision not stated AMMUNITION, OVER 30MM UP TO 75MM
Show all 19

Who attaches DD Form 1692

Other files

File Type Posted
Attachment_0022_ESPS_Solicitation_Q&A_Revised_05Jan17.pdf PDF
Attachment_0022_ESPS_Solicitation_Q&A_Revised_04Jan17.pdf PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0007.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0007.pdf PDF
Attachment_0022_ESPS_Solicitation_Q&A_Revised_22Dec16.pdf PDF
Attachment_0022_ESPS_Solicitation_Q&A_Revised.pdf PDF
Attachment_0021_Past_Performance_Questionnaire.docx DOCX document
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0006.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0006.pdf PDF
Attachment_0023_5-10-2020_ESPS_REVD_Revised_13Dec16.pdf PDF
Attachment_0024_5-10-2021_SUPPORT_STRUT_ESPS_REVC_Revised_13Dec16.pdf PDF
Attachment_0025_5-10-2022_U-STRUT_HANDLE_ESPS_REVA_Revised_13Dec16.pdf PDF
Attachment_0026_5-10-2023_BLAST_PANEL_ESPS_REVD_Revised_13Dec16.pdf PDF
Attachment_0022_ESPS_Solicitation_Q&A_Revised_13Dec16.pdf PDF
Attachment_0027_5-10-0208_Ground_Anchor_Bracket_REVA_Added_13Dec16.pdf PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0005.pdf PDF
Attachment_0022_ESPS_Solicitation_Q&A_Revised_6Dec16.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0005.pdf PDF
Attachment_0022_ESPS_Solicitation_Q A_Revised_15Nov16.pdf PDF
Attachment_0022_ESPS_Solicitation_Q A_Revised_8Nov16.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0004.pdf PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0004.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0003.pdf PDF
Attachment_0024_5-10-2021_SUPPORT_STRUT_ESPS_Revised_4Nov2016.PDF PDF
Attachment_0025_5-10-2022_U-STRUT_HANDLE_ESPS_Revised_4Nov2016.PDF PDF
Attachment_0023_5-10-2020_ESPS_Revised_4Nov2016.PDF PDF
Attachment_0001_MIL-PRF-32521A_Revised_1Nov2016.pdf PDF
Attachment_0026_5-10-2023_BLAST_PANEL_ESPS_Revised_4Nov2016.PDF PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0003.pdf PDF
Attachment_0022_ESPS_Solicitation_Q A_Revised_4Nov16.pdf PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0002.pdf PDF
Attachment_0022_ESPS_Solicitation_Q A.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0002.pdf PDF
Attachment_0001_MIL-PRF-32521A_18Oct2016.pdf PDF
W911QY-17-R-0003_ESPS_Solicitation_Amendment_0001.pdf PDF
Attachment_0022_ESPS_Solicitation_Q A.pdf PDF
Attachment_0025_5-10-2022_U-STRUT_HANDLE_ESPS.PDF PDF
W911QY-17-R-0003_ESPS_Conformed_Solicitation_Amendment_0001.pdf PDF
Attachment_0023_5-10-2020_ESPS.PDF PDF
Attachment_0026_5-10-2023_BLAST_PANEL_ESPS.PDF PDF
Attachment_0024_5-10-2021_SUPPORT_STRUT_ESPS.PDF PDF
W911QY-17-R-0003_ESPS_Solicitation.pdf PDF
A018_ESPS_PCA_Summary_Report_22_May_2015.pdf PDF
A003_ESPS_MAC_14_May_2015.pdf PDF
Attachment_0007_ESPS_NET_SOW_26_May_2015.pdf PDF
A010_ESPS_NMWR_12_May_2015.pdf PDF
A017_ESPS_FAT_Plan_and_Report_22_May_2015.pdf PDF
Attachment_0010_DI-NDTI-80566A_Test_Plan.pdf PDF
Attachment_0014-3_DD_Form_1692_ECP(pg3).pdf PDF
Attachment_0002_ESPS_Provisioning_SOW_14_May_2015.pdf PDF
Show 40 more

Latest 50 of 100 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

16. DOCUMENTS AFFECTED (Continue on back if necessary)

ENGINEERING CHANGE PROPOSAL

(ECP)

15. ALL LOWER OR HIGHER

ITEMS AFFECTED

f. REVISED

DOCUMENT

ATTACHEDa. CAGE

22. CONTRACT

23. CONTRACTING OFFICER

25. BELOW TO BE COMPLETED BY THE APPROVING ACTIVITY

24. ORIGINATOR

10. NEED FOR CHANGE:

17. BASELINE AFFECTED:

11. MODEL/TYPE DESIGNATION

(e.g., M16) :

5. CLASS OF ECP:

14.a. OTHER EXTERNAL SYSTEM AFFECTED?

3. ECP NUMBER:

1. DATE PREPARED

(DD-MMM-YYYY) OMB No.

0704-0188

4. TITLE OF CHANGE:

c. E-MAIL:b. TELEPHONE:a. NAME:

a. NOMENCLATURE: b. PART NO.: c. NSN:

12. SYSTEM/CONFIGURATION ITEM NOMENCLATURE

(e.g., Rifle):

19. EFFECTIVITY (Lot No., Serial No., Date): 20. EFFECT ON DELIVERY SCHEDULE:

9. DESCRIPTION OF CHANGE:

c. DATE SIGNED (DD-MMM-YYYY): d. SIGNATURE:

2. PROCURING ACTIVITY NO. (PAN):

Functional

Yes No

b. ADDRESS (Street, City, State, Zip Code):

b. DOCUMENT NO.

d.

CURRENT

REVISION

e.

NOR

NO.

b. NAME and TITLE:

a. RECOMMENDATIONS:

The public reporting burden for this collection of information is estimated to average 2 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Executive Services Directorate, Information Management Division, 4800 Mark Center Drive, Alexandria, VA 22350-3100 (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THIS ADDRESS. RETURN COMPLETED FORM TO THE GOVERNMENT ISSUING CONTRACTING OFFICER FOR THE CONTRACT/PROCURING ACTIVITY NUMBER LISTED IN ITEM 2 OF THIS FORM.

Major Minor Administrative

6. PRIORITY:

E - Emergency U - Urgent R - Routine

7. ECP TYPE:

P - Preliminary F - Formal

8. JUSTIFICATION CODE:

O - Operational or Product Improvement P - Production Stoppage

B - Interface C - Compatibility D - Correction of Deficiency L - Logistics Support

R - Cost Reduction S - Safety V - Value Engineering

13. AFFECTED ITEM NOMENCLATURE

(e.g., Bracket):

b. IF BLOCK 14.a. IS YES, LIST OTHER SYSTEMS OR CONFIGURATION ITEMS AFFECTED:

c. NOMENCLATURE

Allocated Product

18. IN PRODUCTION:

Yes No

21.a. RECOMMEND RETROFIT TO EXISTING ASSETS? Yes No

b. IF BLOCK 21.a. IS YES, DESCRIBE RETROFIT

REQUIREMENTS:

a. CONTRACTOR: b. CONTRACT NO./LINE ITEM:

a. NAME (Submitter):

d. E-MAIL:

c. TELEPHONE:

Approval Disapproval Approval with Modification

c. DATE SIGNED (DD-MMM-YYYY): d. SIGNATURE: b. NAME and TITLE:

26.a. DISPOSITION (Configuration Change Authority) Approved Disapproved Approved with Modification

b. DATE NEW REVISION(S) RELEASED: c. SIGNATURE:a. NAME and TITLE:

27. TO BE COMPLETED BY THE ACTIVITY ACCOMPLISHING REVISION UPON NEW REVISION RELEASE

DD FORM 1692, MAR 2013 Adobe Designer 9.0

DISTRIBUTION STATEMENT:

PREVIOUS EDITION IS OBSOLETE.

e. ECP ORIGINATOR

CAGE CODE:

f. SUBMITTING ACTIVITY: h. NAME AND TITLE (Authorizing Official):g. AUTHORIZED SIGNATURE:

Yes Noc. COST IMPACT FROM ECP?

d. IF 21.c. IS YES, DESCRIBE:

DD Form 1692, Engineering Change Proposal Page 1, March 2013

WHS/ESD/IMD

16. DOCUMENTS AFFECTED

(Continue on back if necessary)

ENGINEERING CHANGE PROPOSAL

(ECP)

15. ALL LOWER OR HIGHER

ITEMS AFFECTED

f. REVISED

DOCUMENT

ATTACHED

a. CAGE

22. CONTRACT

23. CONTRACTING OFFICER

25. BELOW TO BE COMPLETED BY THE APPROVING ACTIVITY

24. ORIGINATOR

10. NEED FOR CHANGE:

17. BASELINE AFFECTED:

11. MODEL/TYPE DESIGNATION

(e.g., M16)

5. CLASS OF ECP:

14.a. OTHER EXTERNAL SYSTEM AFFECTED?

3. ECP NUMBER:

1. DATE PREPARED

(DD-MMM-YYYY)

OMB No.

0704-0188

4. TITLE OF CHANGE:

c. E-MAIL:

b. TELEPHONE:

a. NAME

a. NOMENCLATURE:

b. PART NO.:

c. NSN:

12. SYSTEM/CONFIGURATION ITEM NOMENCLATURE

(e.g., Rifle)

19. EFFECTIVITY

(Lot No., Serial No., Date)

20. EFFECT ON DELIVERY SCHEDULE:

9. DESCRIPTION OF CHANGE:

c. DATE SIGNED

(DD-MMM-YYYY)

: d. SIGNATURE:

2. PROCURING ACTIVITY NO. (PAN):

Functional Yes No

b. ADDRESS (Street, City, State, Zip Code)

b. DOCUMENT NO.

d.

CURRENT

REVISION

e.

NOR

NO.

b. NAME and TITLE:

a. RECOMMENDATIONS:

The public reporting burden for this collection of information is estimated to average 2 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Executive Services Directorate, Information Management Division, 4800 Mark Center Drive, Alexandria, VA 22350-3100 (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THIS ADDRESS. RETURN COMPLETED FORM TO THE GOVERNMENT ISSUING CONTRACTING OFFICER FOR THE CONTRACT/PROCURING ACTIVITY NUMBER LISTED IN ITEM 2 OF THIS FORM.

Major Minor Administrative

6. PRIORITY:

E - Emergency U - Urgent R - Routine

7. ECP TYPE:

P - Preliminary F - Formal

8. JUSTIFICATION CODE:

O - Operational or Product Improvement P - Production Stoppage B - Interface C - Compatibility D - Correction of Deficiency L - Logistics Support R - Cost Reduction S - Safety V - Value Engineering

13. AFFECTED ITEM NOMENCLATURE

(e.g., Bracket)

b. IF BLOCK 14.a. IS YES, LIST OTHER SYSTEMS OR CONFIGURATION ITEMS AFFECTED:

c. NOMENCLATURE Allocated Product

18. IN PRODUCTION:

Yes No 21.a. RECOMMEND RETROFIT TO

EXISTING ASSETS?

Yes No

b. IF BLOCK 21.a. IS YES, DESCRIBE RETROFIT

REQUIREMENTS:

a. CONTRACTOR:

b. CONTRACT NO./LINE ITEM:

a. NAME (Submitter)

d. E-MAIL:

c. TELEPHONE:

Approval Disapproval Approval with Modification

c. DATE SIGNED

(DD-MMM-YYYY)

: d. SIGNATURE:

b. NAME and TITLE:

26.a. DISPOSITION (Configuration Change Authority) Approved Disapproved Approved with Modification

b. DATE NEW REVISION(S) RELEASED: c. SIGNATURE:

a. NAME and TITLE:

27. TO BE COMPLETED BY THE ACTIVITY ACCOMPLISHING REVISION UPON NEW REVISION RELEASE

DD FORM 1692, MAR 2013

Adobe Designer 9.0

DISTRIBUTION STATEMENT:

PREVIOUS EDITION IS OBSOLETE.

e. ECP ORIGINATOR

CAGE CODE:

f. SUBMITTING ACTIVITY:

h. NAME AND TITLE (Authorizing Official)

g. AUTHORIZED SIGNATURE:

Yes No

c. COST IMPACT FROM ECP?

d. IF 21.c. IS YES, DESCRIBE:

1. Date prepared (2 digit day-3 letter month-4 digit year).:
2. Procuring Activity Number (PAN).:
3. Engineering Change Proposal (ECP) number.:
4. Title of change.:
26a. Disposition (Configuration change authority). (To be completed by the approving activity). X first box if approved, second if disapproved, third if approved with modification.:
9. Description of change.:
10. Need for change.:
11. Model/type designation (e.g., M-16).:
12. System/configuration item nomenclature (e.g., rifle).:
13. Affected item nomenclature (e.g., bracket).:
b. If yes, list other systems or configuration items affected.:
15. All lower or higher items affected. a. Nomenclature.:
b. Part number.:
c. NSN.:
16. Documents affected. a. CAGE code, line 1.:
b. Document number.:
c. Nomenclature.:
d. Current revision.:
e. Notice of Revision number.:
f. Revised document attached.:
a. CAGE code, line 2.:
b. Document number.:
c. Nomenclature.:
d. Current revision.:
e. Notice of Revision number.:
f. Revised document attached.:
b. Document number.:
a. CAGE code, line 3.:
c. Nomenclature.:
d. Current revision.:
e. Notice of Revision number.:
f. Revised document attached.:
a. CAGE code, line 4.:
b. Document number.:
c. Nomenclature.:
d. Current revision.:
e. Notice of Revision number.:
f. Revised document attached.:
a. CAGE code, line 5.:
b. Document number.:
c. Nomenclature.:
d. Current revision.:
e. Notice of Revision number.:
f. Revised document attached.:
19. Effectivity (lot number, serial number, date).:
20. Effect on delivery schedule.:
b. If yes, describe retrofit requirements.:
d. If yes, describe.:
22. Contract information. a. Contractor.:
b. Contract number and line item.:
23. Contracting officer. a. Name (first, middle initial, last).:
b. Telephone number.:
c. E-mail address.:
24. Originator. a. Name (first, middle initial, last).:
c. Address (include zip code).:
c. Telephone number.:
d. E-mail address.:
e. ECP originator CAGE code.:
f. Submitting activity.:
g. Authorized signature.:
h. Name and title of authorizing official.:
b. Name and title.:
c. Signature.:
d. Date signed (2 digit day-3 letter month-4 digit year).:
b. Name and title.:
c. Signature.:
d. Date signed (2 digit day-3 letter month-4 digit year).:
27. To be completed by the activity accomplishing revision upon new revision release. a. Name and title.:
b. Signature.:
c. Date signed (2 digit day-3 letter month-4 digit year).:
Distribution statement.:

File details come from the government source that posted it. Updated .