This is a Temporary Facilities and Controls specification document for the City of Debary's Rob Sullivan Park Maintenance Barn project (Bid #05-15), a 25' x 40' x 14' A-frame steel building requiring delivery and installation. The specification outlines the contractor's responsibilities for establishing and maintaining temporary construction facilities throughout the project duration. Key requirements include providing temporary electric service with protective enclosures and compliance with NEC and local electrical codes; temporary heating, ventilation, and water systems; potable drinking water dispensers for employees; chemical toilet facilities meeting state and local health regulations; site drainage and pumping to maintain dry conditions; material hoists with skilled operators and safety devices compliant with ANSI standards and OSHA regulations; temporary scaffolding, ladders, and runways meeting federal, state, and municipal standards; and enclosed chutes for material drops. The contractor must also establish temporary roadways and parking areas as needed for material and equipment delivery, provide a field office and storage sheds, and maintain project identification signage. All temporary facilities remain the contractor's property until removal and must be maintained in safe, useful condition throughout construction, with the site properly reconditioned upon completion.
The specification emphasizes contractor responsibility for material protection, security, and site safety from establishment through final project acceptance. The contractor must cover all costs associated with temporary utilities, including temporary electrical service, heating fuel or power, ventilation power, water service fees and usage, and sanitary facility maintenance. Materials must be delivered undamaged in original manufacturer packaging and protected from weather damage and damage from other trades. The contractor bears sole responsibility for structural strength, safety compliance, and daily work area inspection to prevent damage, injury, or loss. Upon project completion or engineer direction, all temporary facilities, roadways, and parking area materials must be removed and legally disposed of, with the site restored to a condition acceptable to the engineer.
View the file
Other files for this state and local contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Debary – Rob Sullivan Park Maintenance Barn (Bid # 05-15) TEMPORARY FACILITIES AND CONTROLS
SECTION 01520
TEMPORARY FACILITIES AND CONTROLS
Note items 2.10 and 2.12 require review.
PART 1 GENERAL
1.01 Section Includes
Construction facilities, controls, temporary utilities, project identification signs, field office and storage sheds, storage of materials and equipment.
1.02 Related Sections
Section 01550 - Maintenance of Traffic
1.03 Submittals
A. Prior to installation of construction facilities and temporary controls, submit the following items for review and approval:
B. Project identification sign - provide proposed text, layout, and sizing of all required signs
1.04 Construction Facilities and Temporary Controls
All construction facilities and temporary controls remain the property of the Contractor establishing them and shall be maintained in a safe and useful condition until removed from the construction site.
1.05 Removal of Temporary Construction
Remove the various temporary facilities, services, and controls and legally dispose of them as soon as the Engineer deems permissible. Portions of the site used for temporary facilities shall be properly reconditioned and restored to a condition acceptable to the Engineer.
1.06 Transportation and Handling
A. Manufactured materials and products shall be delivered to the project site as needed for installation, undamaged, in original packages, containers, or bundles, as packaged by the manufacturer with manufacturer's name, brand, seals, and labels intact.
B. Materials other than those designated within the Specifications or approved by the Engineer shall not be delivered to the project site.
1.07 Storage and Protection
A. The Contractor shall be responsible for protection and preservation of all materials until final acceptance of the Project. Any damage to work prior to acceptance shall be remedied by the Contractor at no additional cost to the Owner.
B. Provide temporary weather-tight enclosures to protect work from damage by the elements, and protect finished surfaces to prevent any damage resulting from the work of any trade.
1.08 Security
A. Contractor shall, at all times, be responsible for the security required in all project areas and shall provide all reasonable protection to prevent damage, injury or loss to employees on the Work and all other persons who may be affected thereby; all the work materials and equipment to be incorporated therein, whether in storage on or off the project site, under the care, custody or control of the Contractor or any subcontractors; and any other property under the care, custody or control of the Contractor or any subcontractors. Contractor shall be responsible for such security and safety until final acceptance of the Work.
B. Full time watchmen will not be specifically required as a part of the Contract, but the Contractor shall provide inspection of work area daily and shall take whatever measures are necessary to protect the safety of the public, workmen, and materials, and provide for the security of the site, both day and night.
PART 2 PRODUCTS
2.01 Temporary Electric Service
A. Furnish and maintain temporary lighting and power required to perform the Work.
Include in the Bid all costs for providing temporary electrical service.
B. Temporary service shall include protective enclosures, branch wiring, outlets, lamps, and grounding as required by NEC and Local Electrical Codes.
2.02 Temporary Heating
The Contractor shall furnish fuel or power and provide and operate all temporary heating units. Heat shall be provided as necessary to perform the Work. Temporary heating units shall be adequately vented and approved devices which will not damage finished areas.
The Contractor shall also furnish all tarpaulins and temporary enclosures necessary to provide this protection.
2.03 Temporary Ventilation
The Contractor shall provide, operate, and furnish power for temporary ventilation required for the proper installation and curing of materials and safety of workmen.
2.04 Temporary Water
A. Provide a temporary water distribution system for all construction purposes and pay for all water used. Obtain temporary meters from the local water utility as required and pay all associated fees.
B. Furnish potable drinking water in suitable dispensers and with cups for use of all employees at the job.
C. Provide all temporary piping, hoses, etc., required to transport water to the point of usage by all trades.
2.05 Temporary Sanitary Facilities
Provide temporary toilet facilities as required. Maintain these during the entire period of construction under this Contract for the use of all construction personnel on the job.
Enough chemical toilets shall be provided to conveniently serve the needs of all personnel. Chemical toilets and their maintenance shall meet the requirements of State and local health regulations and ordinances.
2.06 Temporary Pumping and Site Drainage
Keep the site free from water at all times to permit continuous access and to prevent damage to the work.
2.07 Material Hoists and Cranes
A. Provide material hoists required for normal use by all trades and employ skilled hoist operators. Provide all necessary guards, signals, safety devices, etc., required for safe hoist operation. The construction and operation of material hoists shall be in accordance with the applicable ANSI Standards, the "Manual Code of Accident Prevention in Construction" of the Associated General Contractors of America, OSHA, and of other Federal, State, and municipal codes or ordinances. The Contractor shall prohibit the use of hoists for transporting personnel. Hoists shall be located to avoid risk of damage to completed work.
B. Special rigging and hoisting facilities shall be provided by each trade requiring their use.
2.08 Temporary Runways, Scaffolding, and Ladders
A. Provide temporary ladders, ramps, and runways as required for performance and inspection of the work. The above facilities shall be constructed and maintained in accordance with the applicable Federal, State, and Municipal regulations and codes.
B. Furnish, erect, and maintain all scaffolding required for this work. Scaffolding shall be constructed and maintained in accordance with applicable State and Federal laws and local ordinances. Scaffolding shall be promptly removed after serving its purpose.
C. The structural strength and safety of scaffolding, runways, covers, railings, ladders, stairs, etc., and compliance with law shall be the sole responsibility of the Contractor.
2.09 Temporary Chutes
No materials shall be dropped from structures except through enclosed wooden or metal chutes which shall be provided and maintained as required for the performance of the work by the various trades.
2.10 Project Identification Sign-N/A
2.11 Contractor's Field Office and Storage Sheds
The Contractor shall provide field office and storage sheds that it determines are required for the performance of the Work and protection of materials and equipment.
2.12 Owner / Engineer Field Office –N/A
PART 3 EXECUTION
3.01 Access Roads and Parking Areas
A. Construct temporary roadways and parking areas within the site as required to provide proper access to the site for delivery of material and equipment of all trades. It is up the Contractor to determine whether it needs to construct any temporary roads or parking areas to accommodate its construction (including delivery of materials, equipment, and manpower to the site).
B. At completion of the work or when directed by the Engineer, surfacing and sub-base material used for the temporary road and parking areas shall be removed, unless otherwise approved by the Engineer.
END OF SECTION