This is a Summary of Work document for the City of Debary, Florida, related to Bid #05-15 for the Rob Sullivan Park Maintenance Barn project. The project scope involves the installation of a 25' x 40' x 14' A-frame steel building at Rob Sullivan Park, with the contractor responsible for furnishing all materials, equipment, tools, and labor necessary for proper completion. The contractor must secure and pay for temporary construction permits and licenses, while the City of Debary will procure all fees and permits for permanent construction required by controlling agencies. The project will be executed under a single lump sum contract, with the contractor having flexibility in sequencing work to accommodate the existing park operations, which must continue 24 hours per day, 7 days per week. The contractor assumes full responsibility for coordination with all utilities regarding locates, testing, or relocations, and must protect and safeguard all products stored on-site.
The contractor is required to repair, replace, or settle with the Owner for any damage to property, existing facilities, pavements, utilities, lawns, or structures that occurs during construction. All operations must be confined to areas permitted by applicable laws, ordinances, and permits, with the contractor assuming responsibility for ensuring compliance with schedules and coordinating the work of employees, subcontractors, and suppliers. The document does not specify pricing terms, set-asides, award dates, contract term, or renewal options, as this is a summary of work section outlining general execution requirements rather than a complete bidding document.
View the file
Other files for this state and local contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Debary – Rob Sullivan Park Maintenance Barn ( Bid # 05-15)
SECTION 01110
SUMMARY OF WORK
PART 1 GENERAL
1.01 Section Includes
Summary of work, other contracts, work sequence, operation of existing facilities, use of premises, Owner furnished products, coordination, cutting and patching
1.02 Summary of Work
A. The project consists of the installation of a 25’ x 40’ maintenance barn at Rob Sullivan Park.
B. Furnish all materials, equipment, tools, and labor which is reasonably and properly inferable and necessary for the proper completion of the Work, whether specifically indicated in the Contract Documents or not.
C. All fees and permits for the permanent construction that are required by controlling agencies or authorities, including fees for the review of Contract Documents prior to construction, will be procured by the Owner. Other licenses or permits for construction facilities of a temporary nature that are necessary for the prosecution of the work shall be secured and paid for by the Contractor.
D. Repair, replace, or otherwise settle with the Owner, if damage to property or existing facilities occurs, including damage to pavements, utilities, lawns, structures, etc.
E. Construct the Project under a single lump sum contract.
1.03 Work Under Other Contracts - N/A
1.04 Work Sequence
The Contractor’s sequence of work may be of his choosing in order to complete the work in the allowed time frame while accommodating other contractors on site.
1.05 Operation of Existing Facilities
The Owner shall be able to operate existing facilities 24 hours per day, 7 days per week.
1.06 Contractor Use of Premises
Confine operations at the site to areas permitted by applicable laws, ordinances, permits, and by the Contract Documents. Do not unreasonably encumber the site with materials or equipment. Do not load structures with weight that will endanger the
City of Debary – Rob Sullivan Park Maintenance Barn ( Bid # 05-15) structure. The Contractor shall assume full responsibility for protection and safekeeping of products stored on the job site.
1.07 Owner Furnished Products - N/A
1.08 Coordination
A. The Contractor shall be fully responsible for the coordination of his work and the work of his employees, subcontractors, and suppliers and to assure compliance with schedules.
B. The coordination requirements of this Section are in addition to the requirements of Section 00700, General Conditions, and 00800, Supplementary Conditions.
C. It is the Contractor’s responsibility to coordinate with all the utilities regarding locates, testing, or relocations.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
END OF SECTION