About this file

This is a Maintenance of Traffic specification section for Bid #05-15 issued by the City of Debary, Florida for the Rob Sullivan Park Maintenance Barn project. The specification outlines comprehensive traffic control and dust management requirements for construction activities. Contractors must submit a detailed traffic control plan that includes proposed signage, markings, barricades, detour routes, and sequencing plans for both vehicular and pedestrian traffic. The specification mandates that at least one field employee (superintendent or foreman) holds International Municipal Signal Association (IMSA) Work Zone Traffic Control Safety Certification and must be present on-site during installation of traffic control measures and all work within traffic zones. All work must comply with Florida Department of Transportation Roadway and Traffic Design Standards and the Manual on Uniform Traffic Control Devices.

Execution requirements include contacting affected property owners to coordinate temporary driveway closures while maintaining access throughout construction, removing existing pavement markings and relocating signs as necessary, and implementing approved lane closures to minimize traffic interruption. Contractors must place excavated materials outside roadway clear zones and away from pedestrian facilities, backfill trenches daily, and install lighted concrete barriers or other traffic control devices where hazards exist. Ongoing maintenance obligations require daily inspection of all traffic control devices to ensure proper placement and function, wet suppression of unstabilized areas to control dust, and adjustment of traffic control devices as needed under emergency conditions.

View the file

Other files for this state and local contract opportunity

Other files attached to Rob Sullivan Park Maintenance Barn, newest first.
File Type Posted
00015-List_of_Drawings.pdf PDF
Admin_Requirements.pdf PDF
Agreement_Form.pdf PDF
Certificate_of_Final_Completion.pdf PDF
Consent_of_Surety_to_Final_Payment.pdf PDF
Contract_Closeout.pdf PDF
Contractors_Partial_Release_of_Lien.pdf PDF
Measurement_and_Payment_Lump_Sum.pdf PDF
Notice_to_Proceed.pdf PDF
Pre-Bid_Meeting_-_Sign_In_Sheet_-_Bidders_List.pdf PDF
Product_Selection_and_Substitution.pdf PDF
Project_Schedule.pdf PDF
Temporary_Facilities_and_Controls.pdf PDF
00010-Index.pdf PDF
01110-Summary_of_Work.pdf PDF
Change_Order_Form.pdf PDF
Contractors_Application_for_Payment.pdf PDF
FDOT_Reference.pdf PDF
Insurance_Certification.pdf PDF
Insurance_Requirements.pdf PDF
Map.pdf PDF
Material_and_Workmanship_Bond-Updated_by_CA.pdf PDF
Notice_of_Award.pdf PDF
Partial_Release_of_Lien_Subcontractors_and_Suppliers.pdf PDF
Preconstruction_Video.pdf PDF
Project_Field_Order_Form.pdf PDF
References.pdf PDF
Request_for_Information.pdf PDF
Substantial_Completion.pdf PDF
Work_Directive_Change_Form.pdf PDF
Ad_Bid_05-15_Sullivan_Maintenance_Barn_2.pdf PDF
Bid_Bond_Form.pdf PDF
Final_Release_of_Lien_Subcontractors_and_Suppliers.pdf PDF
Instructions_To_Bidder.pdf PDF
Payment_Bond_City_of_DeBary.pdf PDF
Performance_Bond_City_of_DeBary.pdf PDF
Project_Specifications.pdf PDF
Regulatory_Requirements.pdf PDF
Supplementary_Conditions.pdf PDF
Bid_Form.pdf PDF
Contractors_Final_Release_of_Lien.pdf PDF
Project_title_page.pdf PDF
Quality_Control.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Debary – Rob Sullivan Park Maintenance Barn (Bid # 05-15)

SECTION 01550

MAINTENANCE OF TRAFFIC

PART 1 GENERAL

1.01 Section Includes

Traffic and dust control

1.02 Related Sections

Section 01520 - Temporary Facilities and Controls

1.03 Definitions

The term "Maintenance of Traffic" as used herein, shall include all facilities, devices, traffic control personnel, and operations as are required for the safety and convenience of the public as well as for minimizing public nuisance.

1.04 References

A. Florida Department of Transportation Roadway and Traffic Design Standards

B. Manual on Uniform Traffic Control Devices

1.05 Submittals

Provide traffic control plan. Include proposed signs, markings, barricades, detour routes, sequencing, and phasing for vehicular and pedestrian traffic routes during construction.

1.06 Qualifications

Provide at least one employee in the field (superintendent or foreman) who holds an IMSA (International Municipal Signal Association) Work Zone Traffic Control Safety Certification. This certified employee shall be on the job site when the traffic control measures are installed and when work is occurring within the zones.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.01 Site Preparation

A. Contact property owners affected by construction. Coordinate temporary driveway closures and sequencing. Maintain access for all property owners during construction.

City of Debary – Rob Sullivan Park Maintenance Barn (Bid # 05-15)

B. Remove existing pavement markings and remove or relocate existing signs as necessary to implement traffic control.

C. Install signs, markings, barricades in accordance with approved traffic control plan.

D. Implement lane closures in accordance with the parameters shown on the drawings and in the approved traffic control plan.

E. Perform work in a manner that will cause minimum interruptions to traffic.

F. Place excavated material outside roadway clear zones, and away from pedestrian facilities.

G. All trenches shall be backfilled each day prior to the completion of construction activities.

H. Where special hazards exist, install traffic control through the use of lighted concrete barriers, barricades, or other such traffic control facilities as needed to ensure public safety.

3.02 Maintenance

A. Inspect traffic control devices on a daily basis to ensure placement of barricades and function of lights is maintained throughout construction.

B. Wet unstabilized areas as necessary to control dust.

C. Adjust traffic control devices as required under emergency conditions.

END OF SECTION