Notice_to_Proceed.pdf
PDF 58 KB Posted
- Attached to
- Rob Sullivan Park Maintenance Barn State and local contract opportunity
- Solicitation number
- 05-15
- Issued by
- Volusia County, Florida
About this file
This is a Notice to Proceed form issued by the City of DeBary, Florida, for Bid #05-15 regarding the construction of the Rob Sullivan Park Maintenance Barn. The project involves the delivery and installation of a 25' x 40' x 14' A-frame steel building, with the City of DeBary responsible for obtaining all necessary permits. The Notice to Proceed authorizes the contractor to commence construction, with all work required to reach substantial completion within 15 calendar days from the date the notice is issued. The form provides designated spaces for the owner to enter the agreement date, the specific date of substantial completion, and the final completion date, along with signature blocks for the issuing owner and contractor acceptance.
The document serves as the formal authorization for work to begin under the terms of the executed agreement between the City of DeBary and the selected contractor. No pricing information, set-asides, or funding sources are detailed in this notice form, as it functions solely as the administrative instrument to initiate the construction timeline and establish the completion deadline of 15 calendar days from issuance.
View the file
Other files for this state and local contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Debary – Rob Sullivan Maintenance Barn (Bid # 05-15)
SECTION 00530
NOTICE TO PROCEED FORM
TO: __________________________
DATE:
PROJECT: City Of DeBary- Rob Sullivan Park Maintenance Barn
You are hereby notified to commence WORK in accordance with the Agreement dated_______ . This Notice authorizes the CONTRACTOR to commence construction, and, in accordance with the Agreement, all work shall be substantially complete within 15 calendar days of the date of this Notice to Proceed. Therefore, the date of substantial completion is . The date of Final completion is .
ISSUED BY:
(Name of OWNER)
By (Signature)
(Printed Name and Title)
ACCEPTANCE OF NOTICE
Receipt and acceptance of the above NOTICE TO PROCEED is hereby acknowledged by this day of , .
By
Printed Name and Title
END OF SECTION
File details come from the government source that posted it. Updated .