Project_Schedule.pdf

PDF 62 KB Posted

Attached to
Rob Sullivan Park Maintenance Barn State and local contract opportunity
Solicitation number
05-15
Issued by
Volusia County, Florida

About this file

This is a Project Completion Schedule document for the City of DeBary, Florida, related to Bid #05-15 for the Rob Sullivan Park Maintenance Barn project. The project involves the delivery and installation of a 25' x 40' x 14' A-frame steel building, with permit responsibilities assigned to the City. The contractor must prepare and submit a detailed project schedule utilizing the Critical Path Method with a precedence diagram prior to the preconstruction conference. The schedule must identify all major activities, material and equipment ordering and delivery timelines, activity start and stop dates, duration, critical path, and float calculations. The schedule must demonstrate a minimum one-day float for every three weeks of construction, with substantial and final completion dates matching or preceding contractual deadlines.

The schedule is subject to monthly updates prior to payment applications, incorporating actual progress data including completed activities, predicted starts and completions, duration changes, sequence modifications, and percent completion percentages. Updates must project the effects of progress for the two subsequent reporting periods. Float shown on the schedule is designated as project float rather than contractor float, establishing that schedule flexibility belongs to the overall project timeline rather than individual contractor activities.

View the file

Other files for this state and local contract opportunity

Other files attached to Rob Sullivan Park Maintenance Barn, newest first.
File Type Posted
00015-List_of_Drawings.pdf PDF
Admin_Requirements.pdf PDF
Agreement_Form.pdf PDF
Certificate_of_Final_Completion.pdf PDF
Consent_of_Surety_to_Final_Payment.pdf PDF
Contract_Closeout.pdf PDF
Contractors_Partial_Release_of_Lien.pdf PDF
Measurement_and_Payment_Lump_Sum.pdf PDF
Notice_to_Proceed.pdf PDF
Pre-Bid_Meeting_-_Sign_In_Sheet_-_Bidders_List.pdf PDF
Product_Selection_and_Substitution.pdf PDF
Temporary_Facilities_and_Controls.pdf PDF
00010-Index.pdf PDF
01110-Summary_of_Work.pdf PDF
Change_Order_Form.pdf PDF
Contractors_Application_for_Payment.pdf PDF
FDOT_Reference.pdf PDF
Insurance_Certification.pdf PDF
Insurance_Requirements.pdf PDF
Map.pdf PDF
Material_and_Workmanship_Bond-Updated_by_CA.pdf PDF
Notice_of_Award.pdf PDF
Partial_Release_of_Lien_Subcontractors_and_Suppliers.pdf PDF
Preconstruction_Video.pdf PDF
Project_Field_Order_Form.pdf PDF
References.pdf PDF
Request_for_Information.pdf PDF
Substantial_Completion.pdf PDF
Work_Directive_Change_Form.pdf PDF
Ad_Bid_05-15_Sullivan_Maintenance_Barn_2.pdf PDF
Bid_Bond_Form.pdf PDF
Final_Release_of_Lien_Subcontractors_and_Suppliers.pdf PDF
Instructions_To_Bidder.pdf PDF
Payment_Bond_City_of_DeBary.pdf PDF
Performance_Bond_City_of_DeBary.pdf PDF
Project_Specifications.pdf PDF
Regulatory_Requirements.pdf PDF
Supplementary_Conditions.pdf PDF
Bid_Form.pdf PDF
Contractors_Final_Release_of_Lien.pdf PDF
Maintenance_of_Traffic.pdf PDF
Project_title_page.pdf PDF
Quality_Control.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Debary – Rob Sullivan Park Maintenance Barn (Bid # 05-15)

SECTION 01320

PROJECT COMPLETION SCHEDULE

PART 1 GENERAL

1.01 Section Includes

Project completion scheduling

1.02 Submittals

A. Prior to construction, prepare a schedule showing all major activities needed to complete project. Include major material and equipment order and delivery times. Submit to Owner no later than the date of the preconstruction conference.

B. Schedule to utilize Critical Path Method formatted by establishing a precedence diagram which is time scaled. Include on schedule activity start dates, stop dates, and duration; critical path; float; delivery schedules. Include submittal dates and durations for components with extended lead times in schedule.

C. Include on the schedule a minimum float of 1 day every 3 weeks during construction.

D. Project substantial and final completion dates shown on schedule shall be same as or earlier than the contractual dates.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.01 Monitoring and Updating of Schedule

A. Float shown on the schedule belongs to the project.

B. Progress data shall be accumulated to update the schedule on a monthly basis, prior to submittal of the application for payment. Progress data shall include:

1. Activities started

2. Activities completed.

3. Predicted activity starts

4. Predicted activity completions

5. Changes in original duration for specific activities

6. Changes in activity sequences

7. Percent complete on activities

C. Update of schedule to include effect of the progress projected for the next two (2) reporting periods.END OF SECTION

File details come from the government source that posted it. Updated .