About this file
This is a Project Completion Schedule document for the City of DeBary, Florida, related to Bid #05-15 for the Rob Sullivan Park Maintenance Barn project. The project involves the delivery and installation of a 25' x 40' x 14' A-frame steel building, with permit responsibilities assigned to the City. The contractor must prepare and submit a detailed project schedule utilizing the Critical Path Method with a precedence diagram prior to the preconstruction conference. The schedule must identify all major activities, material and equipment ordering and delivery timelines, activity start and stop dates, duration, critical path, and float calculations. The schedule must demonstrate a minimum one-day float for every three weeks of construction, with substantial and final completion dates matching or preceding contractual deadlines.
The schedule is subject to monthly updates prior to payment applications, incorporating actual progress data including completed activities, predicted starts and completions, duration changes, sequence modifications, and percent completion percentages. Updates must project the effects of progress for the two subsequent reporting periods. Float shown on the schedule is designated as project float rather than contractor float, establishing that schedule flexibility belongs to the overall project timeline rather than individual contractor activities.
View the file
Other files for this state and local contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Debary – Rob Sullivan Park Maintenance Barn (Bid # 05-15)
SECTION 01320
PROJECT COMPLETION SCHEDULE
PART 1 GENERAL
1.01 Section Includes
Project completion scheduling
1.02 Submittals
A. Prior to construction, prepare a schedule showing all major activities needed to complete project. Include major material and equipment order and delivery times. Submit to Owner no later than the date of the preconstruction conference.
B. Schedule to utilize Critical Path Method formatted by establishing a precedence diagram which is time scaled. Include on schedule activity start dates, stop dates, and duration; critical path; float; delivery schedules. Include submittal dates and durations for components with extended lead times in schedule.
C. Include on the schedule a minimum float of 1 day every 3 weeks during construction.
D. Project substantial and final completion dates shown on schedule shall be same as or earlier than the contractual dates.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION
3.01 Monitoring and Updating of Schedule
A. Float shown on the schedule belongs to the project.
B. Progress data shall be accumulated to update the schedule on a monthly basis, prior to submittal of the application for payment. Progress data shall include:
1. Activities started
2. Activities completed.
3. Predicted activity starts
4. Predicted activity completions
5. Changes in original duration for specific activities
6. Changes in activity sequences
7. Percent complete on activities
C. Update of schedule to include effect of the progress projected for the next two (2) reporting periods.END OF SECTION