SOW Attach S-Engineering Data for Provisioning.pdf

PDF 293 KB Posted

Attached to
B-52 CERP Commercial Engine Replacement Program (CERP) Engine Contract Federal contract opportunity
Solicitation number
FA8107-19-R-0002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

About this file

This document contains a solicitation for the B-52 Commercial Engine Replacement Program engine contract along with an attachment regarding engineering data for provisioning requirements. The solicitation seeks to award an indefinite delivery/indefinite quantity supply contract to provide 608 new commercial engines, additional spare engines, associated support, spares, support equipment and data to re-engine the B-52 bomber fleet. The contract would have a basic period of six years and up to seven one-year option periods, for a potential total performance period of up to 17 years. Proposals are due by July 22, 2020. The estimated contract award date is June 2021. The attachment provides requirements for the contractor to submit engineering data for provisioning, including electronic formats and naming conventions for the data. The Department of the Air Force Materiel Command Lifecycle Management Center at Tinker Air Force Base is the issuing agency.

View the file

Other files for this federal contract opportunity

Other files attached to B-52 CERP Commercial Engine Replacement Program (CERP) Engine Contract, newest first.
File Type Posted
RFP QA 2.pdf PDF
Appendix D-B-52 CERP Pricing Matrix-10June2020-Protected.xlsx XLSX spreadsheet
List of Attachments (Amend1).pdf PDF
RFP QA 1.pdf PDF
FA810719R0002_______0001.pdf PDF
CERP_Schedule_06.04.20.pdf PDF
B-52 CERP JandA Redacted.pdf PDF
CDRLs A046 thru A081 15 May 2020.pdf PDF
CDRLs A001 thru A020 15 May 2020.pdf PDF
SOW Attach L-Safety Report.pdf PDF
SOW Attach K-AMT Engine Report.pdf PDF
CDRLs A108 thru A127 15 May 2020.pdf PDF
SOW Attach Z-Trip Report Template.docx DOCX document
Appendix D-Pricing Matrix-Protected.xlsx XLSX spreadsheet
SOW Attach J-AMT Engine Plan.pdf PDF
Appendix F-Addendum to FAR 52.212-2.pdf PDF
SOW Attach N-Shop Visit Report.pdf PDF
SOW Attach F-IPC-IPB.pdf PDF
Appendix I-Rights In Data.docx DOCX document
Appendix E-Addendum to FAR 52.212-1.pdf PDF
SOW Attach P-LHI Checklist Questionnaire.pdf PDF
CDRLs A083 thru A107 15 May 2020.pdf PDF
Appendix B-CDRL Data Rights List.pdf PDF
Appendix H-Base Index Report.pdf PDF
Appendix A-SOW CERP Engine Contract.pdf PDF
SOW Attach R-Provisioning Technical Documentation.pdf PDF
Limited Distribution Document Request Instructions.docx DOCX document
Appendix C-DD Form 254.pdf PDF
SOW Attach Y-CEMS Requirements.pdf PDF
SOW Attach A-Acronym List.pdf PDF
List of Attachments.pdf PDF
SOW Attach H-DOP ELMP Template.pdf PDF
CDRLs A021 thru A045 15 May 2020.pdf PDF
SOW Attach E-Manual Requirements.pdf PDF
SOW Attach O-FFP Inspection and Repair.pdf PDF
SOW Attach M-Workscope Requirements.pdf PDF
SOW Attach D-NRE Exclusion List.pdf PDF
FA810719R0002.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

March 18, 2020

ATTACHMENT S

ENGINEERING DATA FOR PROVISIONING REQUIREMENTS

A. The Prime Provisioning Activity (PPA) for this effort is AFSC 406 SCMS/GULAB-Tinker.

Physical address is identified in Block 16, E-mail gbmsp.Provisioning@us.af.mil.

B. Developmental costs are not to be charged for EDFP that is equivalent to approved, in-process or incomplete product engineering drawings only costs necessary for reproduction and assemblage.

C. CDRL Block 12. Submission to be concurrent with delivery of Provisioning Technical

Documentation (PTD) to PPA. If complete sets are not provided, identify missing EDFP and provide required sets of this EDFP to the PPA 30 days prior to Spares Provisioning Conference

(SPC) or as required by the PPA. All sets of EDFP are to be delivered in PLISN sequence. A cover sheet with the Name of Equipment/Item Being Provisioned (Acronyms defined), Contract

Number, CAGE Code, PCC, PCCN, SCC, & Contact Information on the first page of each individual drawing is required.

D. EDFP is required for each first appearance, non-stock listed support item. EDFP is required for each first appearance, stock listed (NSN) support item that does not have a full descriptive

Type Item Identification (Type 1, 1A or 1B). Both EDFP requirements listed here are regardless of SMR code (Source, Maintenance, Recoverability) appearing on all types of PTD, unless directed otherwise by the PPA.

E. Regardless of "Limited Rights" claims, the prime contractor and all sub-vendors shall provide required data, translated to the English language, for the express purpose of identifying, government source coding, and cataloging items with a full description. Letters of refusal must clearly state reason(s) for refusal to provide the data requirements levied and recommend alternate methods of furnishing required EDFP to the PPA.

F. CDRL Block 14:

F.1 Electronic EDFP submittals are required. Delivery media shall be: CD +/-R, DVD +/-R or e-mail. Note: CD +/-RW and DVD +/- RW are not acceptable. PPA e-mail address for delivery gbmsp.Provisioning@us.af.mil. DLA-LIS e-mail address for delivery is DLISPSO@dla.mil.

F.1.1 PPL, LLIL, SFPPL, CBIL & RIB: Electronic EDFP submittals are required to be delivered simultaneously with PTD to the PPA (two (2) sets) and DLA-LIS (one (1) set).

F.1.2 DCN: Two (2) sets of EDFP electronic submittals is required to be delivered to the PPA.

F.2 Acceptable electronic EDFP media format are:

F.2.1 .PDF format (preferred) or, F.2.2 .JPG image format (alternative) or, mailto:gbmsp.Provisioning@us.af.mil mailto:DLISPSO@dla.mil

March 18, 2020

F.2.3 .TIF image format (alternative)

F.2.4 Each whole piece of tech data is to be saved in its entirety under one multi-page file.

F.2.5 All tech data files will be named in the following format: PLISN Part Number (e.g. using

A936 as PLISN and 10B520 as Part Number: A936 10B520.PDF). Be sure to have a single space between PLISN and Part Number as this is the established standardized “naming” convention requirement for DLA LIS’ internal server data storage and retrieval system-process.

F.3. Outside labels of all electronic EDFP transmittal documents, including the subject line of emails, are to contain: Name of Provisioning Effort/Contract Number/PCC/PCCN/SCC/Contact

Information.

G. One (1) set of EDFP shall be made available by Prime Contractor for PTD for which a SPC will be held. This set of EDFP will be retained after conference by the Prime Contractor until

PPA advises provisioning is complete.

In the event EDFP submittal deliveries are to be made to a secured program specific electronic site (Contractor or Government), a transmittal notification will be concurrently forwarded to the

PPA via e-mail at gbmsp.Provisioning@us.af.mil.

mailto:gbmsp.Provisioning@us.af.mil.