Scheduled Work Bid Form ELC FY26 v3.xlsx
XLSX spreadsheet 40 KB Posted
- Solicitation number
- 20154783
About this file
The file is a Scheduled Work Bid Form for a U.S. Customs and Border Protection (CBP) technical maintenance solicitation covering the Yuma, Arizona and El Centro, California border sectors. The solicitation requires a contractor to provide comprehensive technical maintenance services including road and bridge maintenance, fence and gate upkeep, vegetation control, border lighting and electrical systems, drainage system repairs, tunnel remediation, and technical infrastructure maintenance involving cameras, shelters, and generators.
Key administrative details include mandatory site visits scheduled for January 26th and 27th, 2026, with attendee lists and solicitation questions due to Contracting Officer Kevin Sarff (Kevin.P.Sarff@cbp.dhs.gov) by January 21, 2026 at 12 pm EST. The solicitation number is 20154783 and is specifically focused on technical infrastructure maintenance for these critical border sectors. The opportunity is directly issued by the Department of Homeland Security's Customs and Border Protection agency.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions ELC
| PMO Scheduled Work Bid Form |
| The Offeror shall complete the sheets for the Base Period, Option Period 1, Option Period 2, and Option Period 3 for ELC by filling the cells highlighted in YELLOW. In addition, the offeror shall propose the co-efficient price by completing Row 11- 17, and propose its coefficient % on the Summary sheet. For the Base, OY1, OY2, & OY3 the Scheduled amounts will transfer automatically to the summary sheet to give the total evaluated price. |
Summary
| El Centro Sector (ELC) | ||||||
| Requirement | Base Period: | |||||
| 04/01/26 - 03/31/27 | Option 1: | |||||
| 04/01/27 - 03/31/28 | Option 2: | |||||
| 04/01/28 - 03/31/2029 | Option 3: | |||||
| 04/01/29 - 03/31/2030 | Total | |||||
| Scheduled Maintenance (ELC)- FFP | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Unscheduled Maintenance (ELC) | $ 4,278,420.03 | $ 4,406,772.63 | $ 4,538,975.81 | $ 4,675,145.08 | $ 17,899,313.54 | |
| Subtotal: | $ 4,278,420.03 | $ 4,406,772.63 | $ 4,538,975.81 | $ 4,675,145.08 | $ 17,899,313.54 | |
| Scheduled Maintenance Co-Efficient ($) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Unscheduled Maintenance Co-Efficient ($) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Program Management Costs - Co-Efficient Subtotal: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Total Estimated Cost: | $ 4,278,420.03 | $ 4,406,772.63 | $ 4,538,975.81 | $ 4,675,145.08 | $ 17,899,313.54 |
| Co-Efficient Factor (ELC) - Percentage % |
| Summary of Co-Efficient Value: |
| Overhead |
| G&A |
| Bond Rate |
| Fee |
| Use Tax |
| Scheduled Maintenance referenced in SOW C.4.1, C.5.1 |
| Coefficient referenced in SOW C.5.4 |
BASE Period (ELC)
| Category | BASE PERIOD: ELC SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration (calendar days) | Total Cost | Cost/Event | Labor ($) | Equipment ($) | Material/ODC ($) |
| F&G | New River Motorized Swing Gates | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 2 ea | 24 | $ - 0 | $ - 0 | ||||
| F&G | Monument Swing gate | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 17 ea | 1 | $ - 0 | $ - 0 | ||||
| R&B | Imperial Sand Dunes Border Road Maintenance | Routine: Blade/ Grade, Clear Sand Drifts in 60 foot path | 200 yrds | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 2) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.51 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 3) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.95 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 1.41 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Schneiders Bridge to IBR) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.14 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (13 Check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6945, -115.28238 Stop: 32.679861, -115.28949 | 1.3 | 6 | $ - 0 | $ - 0 | ||||
| R&B | (Mount Signal) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67941, -115.69195 Stop: 32.64994, -115.69814 | 2.35 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67754, -115.75145 Stop: 32.64755, -115.72879 | 3.18 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 5) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67738, -115.75814 Stop: 32.64490, -115.76449 | 2.68 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 6) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67149, -115.84891 Stop: 32.63948, -115.83904 | 2.48 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 7) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66163, -115.91444 Stop: 32.63416, -115.90860 | 1.97 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Coyote 2) 98 to Exit 7 | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66954, -115.88835 Stop: 32.66166, -115.91448 | 1.64 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Customs and extensions) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66719, -115.87371 Stop: 32.63720, -115.86702 | 2.53 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Old Customs) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66900, -115.88478 Stop: 32.63944, -115.89354 | 2.32 | 4 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag / New Drag) Exit 7 to Old Customs | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.63406, -115.90850 Stop: 32.63930, -115.89336 | 1.04 | 2 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag) Exit 5 east to Border | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.64605, -115.76452 Stop: 32.64550, -115.75732 | 0.44 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Dump Road | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66397, -115.68093 Stop: 32.65118, -115.68312 | 0.97 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Mon 229 to Check 20) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6319, -115.9325 Stop: 32.6527, -115.6625 | 15 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Check 20 to 13 check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6527, -115.6625 Stop: 32.68052, -115.28296 | 21.86 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (13 check to drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68052, -115.28296 Stop: 32.68485, -115.2191 | 4.3 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (drop 4 to mon 210) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68485, -115.2191 Stop: 32.70607, -114.90998 | 18.09 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Davies) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: 32.7001, -116.0049, 32.6281, -115.9901 | 8.5 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Access Rd (Skull) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6480860,-115.9538 Stop: 32.6320, -115.9546 | 4.3 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Rd (Skull to Davies Mon 230) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6303, -115.9538 Stop: 32.6282, -115.9819 | 3.24 | 2 | $ - 0 | $ - 0 | ||||
| R&B | El Centro Sector All Access and Border Road Maintenance (Road Subtotal) | Blade, Grade, Water, Compact, soil tac as directed within the duration period | 98.19 | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| L&E | Maintenace Water Wells | Routine: Excercise, Clean and Inspect. Include Gallons Per Minute (GPM) report. | 5 ea | 4 | $ - 0 | $ - 0 | ||||
| V&D | El Centro Vegetation and Debris Control | Routine: (1) Mech cut, (2) Herbicide application/Cut and dispose of vegetation and debris in Alamo outside of nesting season | 12 acres | 1 | $ - 0 | $ - 0 | ||||
| Scheduled Subtotal | $ - 0 |
OPT 1 Period (ELC)
| Category | Opt PERIOD 1: ELC SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration (days) | Total Cost* | Cost/Event* | Labor ($) | Equipment ($) | Material/ODC ($) | ODC ($) |
| F&G | New River Motorized Swing Gates | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 2 ea | 24 | $ - 0 | $ - 0 | |||||
| F&G | Monument Swing gate | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 17 ea | 1 | $ - 0 | $ - 0 | |||||
| R&B | Imperial Sand Dunes Border Road Maintenance | Routine: Blade/ Grade, Clear Sand Drifts in 60 foot path | 200 yrds | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Drop 2) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.51 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Drop 3) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.95 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 1.41 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Schneiders Bridge to IBR) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.14 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (13 Check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6945, -115.28238 Stop: 32.679861, -115.28949 | 1.3 | 6 | $ - 0 | $ - 0 | |||||
| R&B | (Mount Signal) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67941, -115.69195 Stop: 32.64994, -115.69814 | 2.35 | 6 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Exit 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67754, -115.75145 Stop: 32.64755, -115.72879 | 3.18 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Exit 5) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67738, -115.75814 Stop: 32.64490, -115.76449 | 2.68 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Exit 6) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67149, -115.84891 Stop: 32.63948, -115.83904 | 2.48 | 6 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Exit 7) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66163, -115.91444 Stop: 32.63416, -115.90860 | 1.97 | 6 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Coyote 2) 98 to Exit 7 | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66954, -115.88835 Stop: 32.66166, -115.91448 | 1.64 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Customs and extensions) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66719, -115.87371 Stop: 32.63720, -115.86702 | 2.53 | 4 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Old Customs) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66900, -115.88478 Stop: 32.63944, -115.89354 | 2.32 | 4 | $ - 0 | $ - 0 | |||||
| R&B | (Pinto Wash Drag / New Drag) Exit 7 to Old Customs | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.63406, -115.90850 Stop: 32.63930, -115.89336 | 1.04 | 2 | $ - 0 | $ - 0 | |||||
| R&B | (Pinto Wash Drag) Exit 5 east to Border | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.64605, -115.76452 Stop: 32.64550, -115.75732 | 0.44 | 2 | $ - 0 | $ - 0 | |||||
| R&B | Dump Road | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66397, -115.68093 Stop: 32.65118, -115.68312 | 0.97 | 2 | $ - 0 | $ - 0 | |||||
| R&B | Border Road (Mon 229 to Check 20) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6319, -115.9325 Stop: 32.6527, -115.6625 | 15 | 1 | $ - 0 | $ - 0 | |||||
| R&B | Border Road (Check 20 to 13 check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6527, -115.6625 Stop: 32.68052, -115.28296 | 21.86 | 1 | $ - 0 | $ - 0 | |||||
| R&B | Border Road (13 check to drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68052, -115.28296 Stop: 32.68485, -115.2191 | 4.3 | 1 | $ - 0 | $ - 0 | |||||
| R&B | Border Road (drop 4 to mon 210) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68485, -115.2191 Stop: 32.70607, -114.90998 | 18.09 | 1 | $ - 0 | $ - 0 | |||||
| R&B | Access Road (Davies) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: 32.7001, -116.0049, 32.6281, -115.9901 | 8.5 | 2 | $ - 0 | $ - 0 | |||||
| R&B | Access Rd (Skull) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6480860,-115.9538 Stop: 32.6320, -115.9546 | 4.3 | 2 | $ - 0 | $ - 0 | |||||
| R&B | Border Rd (Skull to Davies Mon 230) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6303, -115.9538 Stop: 32.6282, -115.9819 | 3.24 | 2 | $ - 0 | $ - 0 | |||||
| R&B | El Centro Sector All Access and Border Road Maintenance (Road Subtotal) | Blade, Grade, Water, Compact, soil tac as directed within the duration period | 98.19 | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| L&E | Maintenace Water Wells | Routine: Excercise, Clean and Inspect. Include Gallons Per Minute (GPM) report. | 5 ea | 4 | $ - 0 | $ - 0 | |||||
| V&D | El Centro Vegetation and Debris Control | Routine: (1) Mech cut, (2) Herbicide application/Cut and dispose of vegetation and debris in Alamo outside of nesting season | 12 acres | 1 | $ - 0 | $ - 0 | |||||
| Scheduled Subtotal | $ - 0 |
OPT 2 Period (ELC)
| Category | Opt PERIOD 2: ELC SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration (days) | Total Cost* | Cost/Event* | Labor ($) | Equipment ($) | Material/ODC ($) |
| F&G | New River Motorized Swing Gates | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 2 ea | 24 | $ - 0 | $ - 0 | ||||
| F&G | Monument Swing gate | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 17 ea | 1 | $ - 0 | $ - 0 | ||||
| R&B | Imperial Sand Dunes Border Road Maintenance | Routine: Blade/ Grade, Clear Sand Drifts in 60 foot path | 200 yrds | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 2) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.51 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 3) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.95 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 1.41 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Schneiders Bridge to IBR) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.14 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (13 Check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6945, -115.28238 Stop: 32.679861, -115.28949 | 1.3 | 6 | $ - 0 | $ - 0 | ||||
| R&B | (Mount Signal) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67941, -115.69195 Stop: 32.64994, -115.69814 | 2.35 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67754, -115.75145 Stop: 32.64755, -115.72879 | 3.18 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 5) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67738, -115.75814 Stop: 32.64490, -115.76449 | 2.68 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 6) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67149, -115.84891 Stop: 32.63948, -115.83904 | 2.48 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 7) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66163, -115.91444 Stop: 32.63416, -115.90860 | 1.97 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Coyote 2) 98 to Exit 7 | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66954, -115.88835 Stop: 32.66166, -115.91448 | 1.64 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Customs and extensions) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66719, -115.87371 Stop: 32.63720, -115.86702 | 2.53 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Old Customs) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66900, -115.88478 Stop: 32.63944, -115.89354 | 2.32 | 4 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag / New Drag) Exit 7 to Old Customs | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.63406, -115.90850 Stop: 32.63930, -115.89336 | 1.04 | 2 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag) Exit 5 east to Border | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.64605, -115.76452 Stop: 32.64550, -115.75732 | 0.44 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Dump Road | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66397, -115.68093 Stop: 32.65118, -115.68312 | 0.97 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Mon 229 to Check 20) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6319, -115.9325 Stop: 32.6527, -115.6625 | 15 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Check 20 to 13 check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6527, -115.6625 Stop: 32.68052, -115.28296 | 21.86 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (13 check to drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68052, -115.28296 Stop: 32.68485, -115.2191 | 4.3 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (drop 4 to mon 210) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68485, -115.2191 Stop: 32.70607, -114.90998 | 18.09 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Davies) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: 32.7001, -116.0049, 32.6281, -115.9901 | 8.5 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Access Rd (Skull) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6480860,-115.9538 Stop: 32.6320, -115.9546 | 4.3 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Rd (Skull to Davies Mon 230) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6303, -115.9538 Stop: 32.6282, -115.9819 | 3.24 | 2 | $ - 0 | $ - 0 | ||||
| R&B | El Centro Sector All Access and Border Road Maintenance (Road Subtotal) | Blade, Grade, Water, Compact, soil tac as directed within the duration period | 98.19 | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| L&E | Maintenace Water Wells | Routine: Excercise, Clean and Inspect. Include Gallons Per Minute (GPM) report. | 5 ea | 4 | $ - 0 | $ - 0 | ||||
| V&D | El Centro Vegetation and Debris Control | Routine: (1) Mech cut, (2) Herbicide application/Cut and dispose of vegetation and debris in Alamo outside of nesting season | 12 acres | 1 | $ - 0 | $ - 0 | ||||
| Scheduled Subtotal | $ - 0 |
OPT 3 Period (ELC)
| Category | Opt PERIOD 3: ELC SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration (days) | Total Cost* | Cost/Event* | Labor ($) | Equipment ($) | Material/ODC ($) |
| F&G | New River Motorized Swing Gates | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 2 ea | 24 | $ - 0 | $ - 0 | ||||
| F&G | Monument Swing gate | Routine: Exercise , Clean (pests and debris), Lubricate and Inspect | 17 ea | 1 | $ - 0 | $ - 0 | ||||
| R&B | Imperial Sand Dunes Border Road Maintenance | Routine: Blade/ Grade, Clear Sand Drifts in 60 foot path | 200 yrds | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 2) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.51 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 3) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.95 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 1.41 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Schneiders Bridge to IBR) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: | 0.14 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (13 Check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6945, -115.28238 Stop: 32.679861, -115.28949 | 1.3 | 6 | $ - 0 | $ - 0 | ||||
| R&B | (Mount Signal) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67941, -115.69195 Stop: 32.64994, -115.69814 | 2.35 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67754, -115.75145 Stop: 32.64755, -115.72879 | 3.18 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 5) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67738, -115.75814 Stop: 32.64490, -115.76449 | 2.68 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 6) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.67149, -115.84891 Stop: 32.63948, -115.83904 | 2.48 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Exit 7) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66163, -115.91444 Stop: 32.63416, -115.90860 | 1.97 | 6 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Coyote 2) 98 to Exit 7 | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66954, -115.88835 Stop: 32.66166, -115.91448 | 1.64 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Customs and extensions) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66719, -115.87371 Stop: 32.63720, -115.86702 | 2.53 | 4 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Old Customs) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66900, -115.88478 Stop: 32.63944, -115.89354 | 2.32 | 4 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag / New Drag) Exit 7 to Old Customs | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.63406, -115.90850 Stop: 32.63930, -115.89336 | 1.04 | 2 | $ - 0 | $ - 0 | ||||
| R&B | (Pinto Wash Drag) Exit 5 east to Border | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.64605, -115.76452 Stop: 32.64550, -115.75732 | 0.44 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Dump Road | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.66397, -115.68093 Stop: 32.65118, -115.68312 | 0.97 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Mon 229 to Check 20) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6319, -115.9325 Stop: 32.6527, -115.6625 | 15 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (Check 20 to 13 check) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6527, -115.6625 Stop: 32.68052, -115.28296 | 21.86 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (13 check to drop 4) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68052, -115.28296 Stop: 32.68485, -115.2191 | 4.3 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Border Road (drop 4 to mon 210) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.68485, -115.2191 Stop: 32.70607, -114.90998 | 18.09 | 1 | $ - 0 | $ - 0 | ||||
| R&B | Access Road (Davies) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: Stop: 32.7001, -116.0049, 32.6281, -115.9901 | 8.5 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Access Rd (Skull) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6480860,-115.9538 Stop: 32.6320, -115.9546 | 4.3 | 2 | $ - 0 | $ - 0 | ||||
| R&B | Border Rd (Skull to Davies Mon 230) | Blade, Grade, Water, Compact and add soil tac to FC-3 as directed within the duration period Start: 32.6303, -115.9538 Stop: 32.6282, -115.9819 | 3.24 | 2 | $ - 0 | $ - 0 | ||||
| R&B | El Centro Sector All Access and Border Road Maintenance (Road Subtotal) | Blade, Grade, Water, Compact, soil tac as directed within the duration period | 98.19 | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| L&E | Maintenace Water Wells | Routine: Excercise, Clean and Inspect. Include Gallons Per Minute (GPM) report. | 5 ea | 4 | $ - 0 | $ - 0 | ||||
| V&D | El Centro Vegetation and Debris Control | Routine: (1) Mech cut, (2) Herbicide application/Cut and dispose of vegetation and debris in Alamo outside of nesting season | 12 acres | 1 | $ - 0 | $ - 0 | ||||
| Scheduled Subtotal | $ - 0 |