Notional Work Plan YUM ELC TIM Maint FY26 rev1.xlsx

XLSX spreadsheet 67 KB Posted

Attached to
Yuma, Arizona and El Centro, California Sectors-TI Maintenance Solicitation
Solicitation number
20154783
Issued by

About this file

This document is a Notional Work Plan Excel spreadsheet for Terrain Interdiction (TI) Maintenance in Yuma, Arizona and El Centro, California for Fiscal Year 2026. The work plan details six specific maintenance tasks across border patrol sectors, including vegetation control, road maintenance, gate maintenance, and sand dune clearing. Tasks range from controlling vegetation along 21 miles of enforcement zones to maintaining 4 miles of roads, checking gate hydraulics, and clearing sand dunes to ensure safe border patrol vehicle access.

The associated federal contract opportunity is a solicitation (Number 20154783) issued by the Department of Homeland Security Customs and Border Protection, seeking a contractor to provide technical maintenance services for border infrastructure. The maintenance scope includes roads, bridges, fences, gates, vegetation control, border lighting, electrical systems, drainage systems, and technical infrastructure attributes like cameras and generators. Mandatory site visits for potential contractors are scheduled for January 26-27, 2026, with attendee lists and questions due to the Contracting Officer by January 21, 2026 at 12 pm EST.

View the file

Other files

File Type Posted
Amendment_07_-_ 70B01R26R00000018_-_SF_30 3-2-2026.pdf PDF
QA Phase 2.pdf PDF
Amendment_06_-_ 70B01R26R00000018_-_SF_30.pdf PDF
Amendment_05_-_ 70B01R26R00000018_-_SF_30.pdf PDF
TAB 1.1.3 SOW YUM ELC TI Maint FY26 2-18-26.pdf PDF
Contractor Notional Work Plan YUM ELC TIM Maint FY26 2-18-26.xlsx XLSX spreadsheet
YUM Unit Price Bid Sheet Blank FY26 2-18-26.xlsx XLSX spreadsheet
CUS1449 RFP - UPDATED 70B01C26R00000018 2-18-26.pdf PDF
Scheduled Work Bid Form YUM FY26 2-18-26.xlsx XLSX spreadsheet
Amendment_04_-_ 70B01R26R00000018_-_SF_30.pdf PDF
Scheduled Work Bid Form ELC FY26 2-18-26.xlsx XLSX spreadsheet
ELC Unit Price Bid Sheets Blank FY26 2-18-26.xlsx XLSX spreadsheet
Amendment_03_-_70B01C24Q00000004_-_SF_30.pdf PDF
QA- TI Maintenance Yuma ELC 1-30-26.xlsx XLSX spreadsheet
Corporate Questions YUM ELC TI Maint FY26.docx DOCX document
Contractor Notional Work Plan YUM ELC TIM Maint 1-30-26.xlsx XLSX spreadsheet
Amendment_02_-_70B01C24Q00000004_-_SF_30.pdf PDF
Scheduled Work Bid Form YUM FY26 1-28-26.xlsx XLSX spreadsheet
TAB 1.1.3 SOW YUM ELC TI Maint 1-28-26.pdf PDF
Scheduled Work Bid Form ELC FY26 1-28-26.xlsx XLSX spreadsheet
Amendment_01_-_70B01C24Q00000004_-_SF_30.pdf PDF
Exhibit C TI Design Standards v6 YUM ELC TI Maint FY26.pdf PDF
Yum-ELC Notional Work Plan_01.28.26.xlsx XLSX spreadsheet
CUS1449 RFP - UPDATED 70B01C26R00000018 1-28-26.pdf PDF
SCA WAGES YUMA.pdf PDF
Scheduled Work Bid Form ELC FY26 v3.xlsx XLSX spreadsheet
ELC Unit Price Bid Sheets Blank FY26 v1.xlsx XLSX spreadsheet
DBA WAGES EL CENTROpdf.pdf PDF
SOW YUM ELC TI Maint FY26 1-16-26.pdf PDF
Scheduled Work Bid Form YUM FY26 v3.xlsx XLSX spreadsheet
YUM Unit Price Bid Sheet Blank FY26.xlsx XLSX spreadsheet
SCA WAGES EL CENTRO.pdf PDF
DBA WAGES YUMA.pdf PDF
CUS1449 RFP - Commercial Items (SF1449) 1-16-26.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notional Work Plan

Notional Work Plan
Task #Task DescriptionQuantityAsset ObjectiveWork CategoryLocation CoordinatesLocationSector
Start Coord.Stop Coord.
1ELC IBR V&D - Perform quarterly cycle of vegetation control covering approximately 21 miles. Perform routine vegetation control work on entire enforcement zone to include 5 ft swath on maintenance road. Mow grass 4 inches. Remove and dispose of grass and trimmings off the road. This includes vine removal from the fence and debris/trash collection and removal. Perform inspections to identify repair needs while performing normal vegetation control i.e., a fence breach, loose grounding wires, C-wire, sinkholes, graffiti, etc.21 MilesMaintain clear line of site and accessibility for agents.V&DR32.67785, -115.3130132.65196, -115.67151El Centro, CAELC
2Alamo - Perform vegatation control and mow approximately 12 acres in all areas not to exceed 6 inches and a minimum of 4 inches to include the rivers edge. Assume rough terrain with steep slopes in various areas. No brush or trees to be cut, only cane and grass areas. Assume work is performed outside the Migratory Bird nesting season and that no areas have been restricted.12 AcresMaintain clear line of site and accessibility for agents.V&DR32.67731, -115.3695632.67501, -115.37016El Centro, CAELC
3Blowouts/erosion adding material if required -Contractor is to provide maintenance of TI, FC-3 roads located in El Centro CA to facilitate traffic. Contractor will be required to water, compact and blade native material at a nominal width not to exceed (20 feet). All water must be provided by the Contractor. Blade and shape the existing traveled way, including turnouts, to produce a surface which is uniform, consistent to grade, and crowned or cross-sloped as indicated by the character of the existing surface. All aggregates pulled up while blading must be bladed back into the road. Maintain existing berms to the condition of adjacent segments. Do not create new berms. Immediately following the spreading of the aggregates, it shall be compacted to the full width by rolling with vibratory roller. Rolling shall continue until the road is fully compacted. All drainage points must be cleaned out of any debris and no new drainage is allowed. Do not allow materials resulting from work under this section to remain on or in structures, such as bridges, culverts, fences, or drainage dips. No windrows allowed.2 MilesMaintain safe and reliable roadway for BP operations.R&B32.6958, -115.283232.6797, -115.2895El Centro, CAELC
4Mount Signal TI Roads -Contractor is to provide maintenance of Mount Signal TI Road (Approximately 4 miles), located in El Centro CA to facilitate traffic and provide proper drainage as scheduled by the COR. Contractor will be required to water, compact and blade native material at a nominal width not to exceed (20 feet). Water must be provided by the Contractor. Blade and shape the existing traveled way, including turnouts, to produce a surface which is uniform, consistent to grade, and crowned or cross-sloped as indicated by the character of the existing surface. Maintain existing berms to the condition of adjacent segments. Do not create new berms. Vibratory rolling shall continue until the road is compacted. All drainage points must be cleaned out of any debris and no new drainage is allowed. No windrows allowed.2 MilesMaintain safe and reliable roadway for BP operations.R&B32.6794, -115.691832.6507, -115.6923El Centro, CAELC
5New River Gate Maintenance -Contractor is to provide maintenance of New River gates, located in El Centro CA to facilitate debris removal, proper flow and function as scheduled by the COR. Contractor will be required to check hydraulics, electrical components, mechanical components overall condition of 6 pulley gate panels.6 eaMaintain safe gates for BP operations.F&G32.66558, -115.5018032.66674, -115.50445Calexico, CAELC
6C1 Sand Dunes -Contractor is to provide maintenance of of the border road, located in Buttercup Sand Dunes Yuma, AZ as scheduled by the COR. Contractor will be required to clear sand along the IBR in a 20' swath to allow safe 4x4 vehicle traffic for BP Agents.8.5Maintain safe IBR travel for BP operations.R&B32.71105, -114.8349832.70593, -114.90997Yuma, AZYUM

Task 1

Work Estimate FormTask Order Description: ELC IBR V&D - Perform quarterly cycle of vegetation control covering approximately 21 miles. Perform routine vegetation control work on entire enforcement zone to include 5 ft swath on maintenance road. Mow grass 4 inches. Remove and dispose of grass and trimmings off the road. This includes vine removal from the fence and debris/trash collection and removal. Perform inspections to identify repair needs while performing normal vegetation control i.e., a fence breach, loose grounding wires, C-wire, sinkholes, graffiti, etc.
Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 5 - Vegetation/DebrisSector:ELC
Notional Work Task:ELC IBR V&D
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
32.67785-115.3130132.65196-115.67151
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
Equipment Operator (1)Day15
Laborer CA (3)Day15

Travel

Equipment
Service TruckDay15
Mini Skid Steer w/brush cutter attachmentDay15
6' Deck MowerDay15
Weed Eaters - 8 hr DayDay15
Chainsaw - 8 hr DayDay15
Portable Trailer Mounted Port-A-John MthDay15

Materials

Mobilization/Demobilization

Other

Task 2 Work Estimate Form Task Order Description:

Alamo - Perform vegatation control and mow approximately 12 acres in all areas not to exceed 6 inches and a minimum of 4 inches to include the rivers edge. Assume rough terrain with steep slopes in various areas. No brush or trees to be cut, only cane and grass areas. Assume work is performed outside the Migratory Bird nesting season and that no areas have been restricted.

Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 5-Vegetation/DebrisSector:ELC
Notional Work Task:Alamo
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
32.67731-115.3695632.67501-115.37016
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
(2) Operator CADay10
(2) Laborers CADay10

Travel

Equipment
Service TruckDay10
(2) Skidsteers with 6' Deck MowerDay10
(2) Weed EatersDay10
(1) Excavators with long reach with mulch head/mower attachmentDay10
Masticator attachmentDay10

Materials

Mobilization/Demobilization
Skid SteersEA2
ExcavatorsEA2
Other
Permit Hvy LoadEA2

Task 3

Work Estimate FormTask Order Description: Blowouts/erosion adding material if required -Contractor is to provide maintenance of TI, FC-3 roads located in El Centro CA to facilitate traffic. Contractor will be required to water, compact and blade native material at a nominal width not to exceed (20 feet). All water must be provided by the Contractor. Blade and shape the existing traveled way, including turnouts, to produce a surface which is uniform, consistent to grade, and crowned or cross-sloped as indicated by the character of the existing surface. All aggregates pulled up while blading must be bladed back into the road. Maintain existing berms to the condition of adjacent segments. Do not create new berms. Immediately following the spreading of the aggregates, it shall be compacted to the full width by rolling with vibratory roller. Rolling shall continue until the road is fully compacted. All drainage points must be cleaned out of any debris and no new drainage is allowed. Do not allow materials resulting from work under this section to remain on or in structures, such as bridges, culverts, fences, or drainage dips. No windrows allowed.
Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 2 - Roads and BridgesSector:ELC
Notional Work Task:Blowouts/Erosion
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
(4) OperatorsDay1

Travel

Equipment
Service TruckDay1
GraderDay1
(2) Water Truck 4000 GalDay1
Compactor/RollerDay1
Heavy Haul Transport Truck/Trailer/Operator- 10 HR DayDay1
Materials
WaterGal37,000
(2) Truck loads ABTruck50 tons

Mobilization/Demobilization

Other

Task 4 Work Estimate Form Task Order Description:

Mount Signal TI Roads -Contractor is to provide maintenance of Mount Signal TI Road (Approximately 4 miles), located in El Centro CA to facilitate traffic and provide proper drainage as scheduled by the COR. Contractor will be required to water, compact and blade native material at a nominal width not to exceed (20 feet). Water must be provided by the Contractor. Blade and shape the existing traveled way, including turnouts, to produce a surface which is uniform, consistent to grade, and crowned or cross-sloped as indicated by the character of the existing surface. Maintain existing berms to the condition of adjacent segments. Do not create new berms. Vibratory rolling shall continue until the road is compacted. All drainage points must be cleaned out of any debris and no new drainage is allowed. No windrows allowed.

Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 2-Roads and BridgesSector:ELC
Notional Work Task:Mt Signal TI Road Maintenance
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
32.6794-115.691832.6507-115.6923
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
(4) OperatorsDay2

Travel

Equipment
Service TruckDay2
GraderDay2
(2) Water Truck 4000 GalDay2
Compactor/RollerDay2
Heavy Haul Transport Truck/Trailer/OperatorDay2

Materials

Mobilization/Demobilization
Not Required

Other

Task 5 Work Estimate Form Task Order Description:

New River Gate Maintenance -Contractor is to provide maintenance of New River gates, located in El Centro CA to facilitate debris removal, proper flow and function as scheduled by the COR. Contractor will be required to check hydraulics, electrical components, mechanical components overall condition of 6 pulley gate panels.

Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 1-Fence and GatesSector:ELC
Notional Work Task:New River Gate Maintenance
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
32.66558-115.501832.66674-115.50445
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
(2) OperatorsDay1

Travel

Equipment
Service TruckDay1
Man liftDay1

Materials

Mobilization/Demobilization
Not Required

Other

Task 6 Work Estimate Form Task Order Description:

C1 Sand Dunes -Contractor is to provide maintenance of of the border road, located in Buttercup Sand Dunes Yuma, AZ as scheduled by the COR. Contractor will be required to clear sand North and South of outriggers along the IBR in a 20' swath to allow safe 4x4 vehicle traffic for BP Agents.

Offeror:Date:
WORK DESCRIPTION
Work Category:CLIN 2-Roads and BridgesSector:YUM
Notional Work Task:C1 Dunes TI Road Maintenance
Asset Objective:RoutineWork Duration:
GPS Coordinates:Start Lat.Start Long.Stop Lat.Stop Long.
32.6794-115.691832.6507-115.6923
DETAILED ESTIMATE
ItemUnit of MeasQty
Labor
(4) OperatorsDay20

Travel

Equipment
Service TruckDay20
(2) Excavators with long reachDay20
Dozer (tracks)Day20
Tractor with box scraperDay20
Heavy Haul Transport Truck/Trailer/OperatorDay20

Materials

Mobilization/Demobilization
Not Required

Other