Amendment_5_Pkg.pdf

PDF 129 KB Posted

Attached to
South Park Grounds Federal contract opportunity
Solicitation number
P14PS00906
Issued by
Department of the Interior National Park Service National Office

About this file

Amendment No. 5 Package

View the file

Other files for this federal contract opportunity

Other files attached to South Park Grounds, newest first.
File Type Posted
5C2_Sheet_3A.pdf PDF
9C2_Sheet_64A.pdf PDF
7C2_Sheet_56A.pdf PDF
10C2_Sheet_65A.pdf PDF
12Q_and_As _6-30-2014.pdf PDF
Amend__6_Package.pdf PDF
6C2_Sheet_55A.pdf PDF
11C2_Sheet_284.pdf PDF
8C2_Sheet_58A.pdf PDF
1Revised_015000_Temporary_Facilities_and_Controls_-_revised_7-3-14_(3).pdf PDF
JEFF-6-SubContractingPlanForm.1doc.pdf PDF
329300_PLANTINGFINEGRADING_CAR2015_2_BID_revised_2014_06_24.pdf PDF
329200_LAWN_CAR2015_2_BID_revised_2014_06_23.pdf PDF
329119_PLANTING_SOIL_SYSTEM_INSTALLATION_CAR_2015_2_BID_revised_2014_06_23.pdf PDF
RFP_Clauses _Updated.pdf PDF
011100_SECTION__SUMMARY_OF_WORK_-_revised_6-24-14.pdf PDF
Q_and_A's_as_of_06-26-14.pdf PDF
328400_Irrigation_Specs_100__Bid_amended_6-25-14.pdf PDF
321400_SITESTONEWORK_CAR2015_2_BID_revised_2014_06_23.pdf PDF
Site_Visit _Pre-Proposal _Attendance.pdf PDF
Amend__3 _Package.pdf PDF
Amendment_4_pkg.pdf PDF
AirKnife_Exploration.pdf PDF
Engineering_Analysis_of_Modified_DS-50_Barrier.pdf PDF
Utility_Locating_Services.pdf PDF
Subsurface_Exploration_Addendum_2.pdf PDF
Subsurface_Exploration.pdf PDF
2012_1121_JEFF_GeoArcheology_study.pdf PDF
AirKnife_Exploration.pdf PDF
Subsurface_Exploration_Addendum_3.pdf PDF
Subsurface_Exploration.pdf PDF
Subsurface_Exploration_Addendum_2.pdf PDF
2011_0216_CAR_Geotech_Desk_Study_FINAL.pdf PDF
Subsurface_Exploration_Addendum_3.pdf PDF
Supplemental_Utility_Locating_Services.pdf PDF
2011_0211__CAR_Phase_1_ESA_R1.pdf PDF
Subsurface_Exploration_Addendum_1.pdf PDF
Amend_2_Pkg.pdf PDF
Amendment_1_Pkg.pdf PDF
JEFF_CAR2015_Archeological_monitoring_plan_FINAL.pdf PDF
32_91_13__Soil_Blending_Spec.pdf PDF
JEFF_Draw_3_(126-200).pdf PDF
GD__MO140001_05-09-2014__MO1.docx DOCX document
2014.04.17_CAR_TTC_accessible_zones_during_construction_memo.pdf PDF
JEFF_Specification.R1_-revised_5-13-14.pdf PDF
RFP_Clauses.docx DOCX document
JEFF_Draw_2_(76-125).pdf PDF
JEFF_Draw_1_(1-75).pdf PDF
RFP _Proposal_Submission_Pkg.pdf PDF
P14PS00906 _Pre-Sol _Amend__1.docx DOCX document
Show all 50

South Park Grounds has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

P14PS00906

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy DOI, NPS, DSC Contracting Services

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

JEFF-18120206/09/2014000005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/03/2014

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

JEFF-181202 - South Park Grounds, Jefferson National Expansion Memorial, Clayton County, St. Louis, MO

The purpose of this Amendment #5 is to update several Solicitation/Contract clauses, update the Proposal Submission Package, make changes to the Specifications, and update the

Questions and Answers Log. See following Page(s)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

David E. Thomas

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

a. RFP, Clauses, have several Clause Changes that need to be updated due to changes made to the FAR in the last several weeks and other changes required. Replace the Original Solicitation Package with the attached Revision. The clauses that were affected are listed below:

52.203-5 – Covenant Against Contingent Fees (May 2014) 52.203-7 – Anti-Kickback Procedures (May 2014) 52.203-8 – Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 – Price or Fee Adjustment For Illegal or Improper Activity (May 2014) 52.203-14 – Display of Hotline Poster(s) (Dec 2007) 52.203-17 - Contractor Employee WhistleBlower rights and Requirement To Inform Employees of Whistleblower Rights (April 2014) 52.204-4 – Printed or Copied Double-Sided On Postconsumer Fiber Content Paper (May 2011) 52.219-4 – Notice of Price Evaluation Preference For HubZone Small Business Concerns (Oct 2011) 52.219-8 – Utilization Of Small Business Concerns (May 2014) 52.222-4 – Contract Work Hours And Safety Standards Act – Overtime Compensation (May 2014) 52.222-6 – Construction Wage Rate Requirements (May 2014) 52.222-11 – Subcontracts (Labor Standards) (May 2014) 52.222-12 – Contract Termination – Debarment (May 2014) 52.222-13 – Compliance With Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-15 – Certification Of Eligibility (May 2014) 52.222-3 – Convict Labor (JUN 2003) 52.225-9 – Buy American Requirement – Construction Materials (May 2014) 52.228-12 – Prospective Subcontractor Requests For Bonds (May 2014) 52.232-5 – Payments Under Fixed-Price Construction Contracts (May 2014) 52.232-17 – Interest (May 2014) 52.232-23 – Assignment Of Claims – (May 2014) 52.232-27 – Prompt Payment For Construction Contracts (May 2014) 52.233-1 – Disputes – Alternate 1 (May 2014 – Dec 1991) 52.236-7 – Permits And Responsibilities (Nov 1991)

1452.236.70 – Prohibition Against Use Of Lead-Based Paint – Department Of Interior (Jul 1996) 52.244-6 – Subcontracts For Commercial Items (May 2014) 52.204-8 – Annual Representations And Certifications (May 2014) 52.211-6 – Brand Name Or Equal (Aug 1999) 52.216-1 – Type Of Contract (APR 1984) 52.222-5 – Construction Wage Rate Requirements – Secondary Site Of The Work (May 2014) 52.222-23 – Notice Of Requirement For Affirmative Action To Ensure Equal Employment Opportunity For Construction (FEB 1999) 52.225-10 – Notice Of Buy American Requirement – Construction Materials

b. RFP, Volume 2 of the Proposal Submission Package, Small, HubZone Small, Small Disadvantaged, Women-Owned, Veteran-Owned Small Business Subcontracting Plan form, is replaced with the attached revision. Paragraph 4 of the form is changed as follows:

• FROM:

“4. The bidder (contractor) agrees that the clause entitled Small, HUBZone Small, Small Disadvantaged, Women-Owned Small and Veteran-Owned Small Business Subcontracting Plan (FAR 52.219.9) will be included in all subcontracts which offer further subcontracting opportunities, and all subcontractors except small business concerns who receive subcontracts in excess of $500,000 will be required to adopt and comply with a subcontracting plan similar to this one. …. “

• TO:

“4. The bidder (contractor) agrees that the clause entitled Small, HUBZone Small, Small Disadvantaged, Women-Owned Small and Veteran-Owned Small Business Subcontracting Plan (FAR 52.219.9) will be included in all subcontracts which offer further subcontracting opportunities, and all subcontractors except small business concerns who receive subcontracts in excess of $650,000 will be required to adopt and comply with a subcontracting plan similar to this one. …. “

c. The following Specification Sections have been replaced:

(1) Section 01 11 00 – Summary of Work

(2) Section 32 14 00 – Site Stonework

(3) Section 32 84 00 –Landscape Irrigation

(4) Section 32 91 19 – Planting Soil System – Installation

(5) Section 32 92 00 – Lawn

(6) Section 32 93 00 – Planting and Fine Grading.

d. See Attached Spreadsheet for Questions and Answers as of June 26, 2014.

e. Proposal Submission Date is being changed from July 8th, 2014 to July 11, 2014, 4:00 pm

Mountain Time.

f. All other terms and conditions remain unchanged.

SMALL, HUBZONE SMALL, SMALL DISADVANTAGED, WOMEN-OWNED

VETERAN-OWNED SMALL BUSINESS SUBCONTRACTING PLAN

DATE___________

CONTRACTOR: _________________________________________________________________________________________

ADDRESS: _____________________________________________________________________________________________

SOLICITATION OR CONTRACT NUMBER: ___________________________________________________________________

ITEM/SERVICE: _________________________________________________________________________________________

The following, together with any attachments, is hereby submitted as a Subcontracting Plan to satisfy the applicable requirements of Public Law 95-507 as implemented by OFPP Policy Letter 80-2.

The National Park Service (NPS) subcontracting goals for the participation of small business; small disadvantaged business and small women-owned business at a minimum are as follows: All Small Business Concerns – 40%; Small Disadvantaged Business Concerns –5.0%; Small Women-Owned Business Concerns – 5.0%; Hubzone Small Business Concerns – 3.0%; Veteran-Owned Small Business Concerns – 3.0%; Service-Disabled Veteran Owned Business Concerns – 3.0%.

If your firm indicates in Item No. 1 below a lesser percentage than the subcontracting goals of the NPS, specify in the space provided the reason(s) your firm cannot meet these goals. ________________________________________________________

1. (a) The following percentage goals (expressed in terms of a percentage of total planned subcontracting dollars) are applicable to the contract cited above or to the contract awarded under the solicitation cited.

(i) Small Business Concerns: _____% of total planned subcontracting dollars under this contract will go to subcontractors who are small business concerns.

(ii) HUBZone Small Business Concerns:_____% of total planned subcontracting dollars under this contract will go to subcontractors who are HUBZone small business concerns. This percentage is included in the percentage under 1(a)(i) above, as a subset.

(iii) Small Disadvantaged Business Concerns: _____% of total planned subcontracting dollars under this contract will go to subcontractors who are small business concerns owned and controlled by socially and economically disadvantaged individuals. This percentage is included in the percentage shown under 1.(a)(i), above, as a subset.

(iv) Women-Owned Small Business Concerns: _____% of total planned subcontracting dollars under this contract will go to subcontractors who are women-owned small business concerns. This percentage is included in the percentage shown under 1.(a)(i), above, as a subset.

(v) Veteran-Owned Small Business Concerns: _____% of total planned subcontracting dollars under this contract will go to subcontractors who are veteran-owned small business concerns. This percentage is included in the percentage shown under 1.(a)(i), above, as a subset.

(vi) Service-Disabled Veteran-Owned Small Business Concerns: ____ % of total planned subcontracting dollars under this contract will go to subcontractors who are service-disabled veteran-owned small business concerns. This percentage is included in the percentage shown under 1(a)(i) above, as a subset.

(b) The following dollar values correspond to the percentage goals shown in (a) above.

(i) Total dollars planned to be subcontracted to small business concerns: $____________________.

(ii) Total dollars planned to be subcontracted to HUBZone small business concerns: $________________. This dollar amount is included in the amount shown under 1.(b)(I), above as a subset.

(iii) Total dollars planned to be subcontracted to small disadvantaged business concerns: $____________________.

This dollar amount is included in the amount shown under 1.(b)(i), above, as a subset.

(iv) Total dollar planned to be subcontracted to women-owned small business concerns: $_____________________.

This dollar amount is included in the amount shown under 1.(b)(i), above, as a subset.

(v) Total dollar planned to be subcontracted to veteran-owned small business concerns: $_____________________.

This dollar amount is included in the amount shown under 1.(b)(i), above, as a subset.

PARK - PMIS SUBCONTRACTING FORM-1

(vi) Total dollar planned to be subcontracted to service-disabled veteran-owned small business concerns:

$________________. This dollar amount is included in the amount shown under 1(b)(i) above, as a subset.

(vii) Total dollar planned to be subcontracted to 8(a) small business concerns: $________________. This dollar amount is included in the amount shown under 1(b)(i) above, as a subset.

(c) The total estimated dollar value of all planned subcontracting (to all types of business concerns) under this contract is

(d) The following principal products and/or services will be subcontracted under this contract, and the distribution among small business, HUBZone small business, small disadvantaged business concerns, women-owned small business and veteran-owned small business concerns is as follows:

(Products/services planned to be subcontracted to small business concerns are identified by *; to HUBZone small business concerns; by **; to small disadvantaged business concerns by ***; to women-owned small business concerns by **** and to veteran-owned small business concerns *****.)

(e) The following method was used in developing subcontract goals (i.e., statement explaining how the product and service areas to be subcontracted were established, how the areas to be subcontracted to HUBZone small, small disadvantaged, small women-owned business and small veteran-owned business concerns' capabilities were determined, to include identification of source lists utilized in making those determinations).

(f) Indirect and overhead costs (check one below):

[ ] have been [ ] have not been included in the goals specified in 1(a) and 1(b).

(g) If "have been" is checked, explain the method used in determining the proportionate share of indirect and overhead cost to be allocated as subcontracts to small business concerns, HUBZone small business, small disadvantaged business, small women-owned business and veteran-owned business concerns.

2. The following individual will administer the subcontracting program:

Name: _________________________________________________________________________________________________

Address & Telephone: ____________________________________________________________________________________

Titles: _________________________________________________________________________________________________

This individual's specific duties, as they relate to the firm's subcontracting program, are as follows:

General overall responsibility for this company's Small Business Program, the development, preparation, and execution of individual subcontracting plans and for monitoring performance relative to contractual subcontracting requirements contained in this plan, including, but not limited to:

(a) Developing and maintaining bidders lists of small, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business concerns for all possible sources.

(b) Ensuring that procurement packages are structured to permit small, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business concerns to participate to the maximum extent possible.

PARK - PMIS SUBCONTRACTING FORM-2

(c) Assuring inclusion of small, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business concerns in all solicitations for products or services that they are capable of providing.

(d) Reviewing solicitations to remove statements, clauses, etc, which may tend to restrict or prohibit small business, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business participation.

(e) Ensuring periodic rotation of potential subcontractors on bidders' lists.

(f) Ensuring that the bid proposal review board documents its reasons for not selecting low bids submitted by small, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business concerns.

(g) Ensuring the establishment and maintenance of records of solicitations and subcontract award activity.

(h) Attending or arranging for attendance of company counselors at Business Opportunity Workshops, Minority Business Enterprise Seminars, Trade Fairs, etc.

(i) Conducting or arranging for conduct of motivational training for purchasing personnel pursuant to the intent of P.L.

95-507.

(j) Monitoring attainment of proposed goals.

(k) Preparing and submitting periodic subcontracting reports required.

(l) Coordinating contractor's activities during the conduct of compliance reviews by Federal agencies.

(m) Coordinating the conduct of contractor's activities involving its small, HUBZone small, small disadvantaged, women-owned small and veteran-owned small business subcontracting program.

(n) To help new suppliers the following duties are added (or deleted) to those specified above:

3. The following efforts will be taken to assure that small, HUBZone small, small disadvantaged business concerns, women-owned small business concerns and veteran-owned small business concerns will have an equitable opportunity to compete for subcontracts:

(a) Outreach efforts will be made as follows:

(i) contacts with minority, women-owned and small business trade associations,

(ii) contacts with business development organizations;

(iii) attendance at small, women-owned small business and minority business procurement conferences and trade fairs;

(iv) sources will be requested from SBA's PRO-Net system.

(b) The following internal efforts will be made to guide and encourage buyers:

(i) workshops, seminars, and training programs will be conducted;

(ii) activities will be monitored to evaluate compliance with this subcontracting plan.

(c) Small, HUBZone small, small disadvantaged, women-owned and veteran-owned small business concern source lists, guides, and other data identifying small and small disadvantaged, women-owned and veteran-owned small business concerns will be maintained and utilized by buyers in soliciting subcontracts.

(d) Additions to (or deletions from) the above listed efforts are as follows:

PARK - PMIS SUBCONTRACTING FORM-3

4. The bidder (contractor) agrees that the clause entitled Small, HUBZone Small, Small Disadvantaged, Women-Owned Small and Veteran-Owned Small Business Subcontracting Plan (FAR 52.219.9) will be included in all subcontracts which offer further subcontracting opportunities, and all subcontractors except small business concerns who receive subcontracts in excess of $650,000 will be required to adopt and comply with a subcontracting plan similar to this one. Such plans will be reviewed by comparing them with the provisions of Public Law 95-507, and assuring that all minimum requirements of an acceptable subcontracting plan have been satisfied. The acceptability of percentage goals shall be determined on a case-by-case basis depending on the supplies/services involved, the availability of potential small, HUBZone small, women-owned small business, small disadvantaged, and veteran-owned small business subcontractors and prior experience. Once approved and implemented, plans will be monitored through the submission of periodic reports, and/or, as time and availability of funds permit, periodic visits to subcontractors' facilities to review applicable records and subcontracting program progress.

5. The bidder (contractor) agrees to submit such periodic reports and cooperate in any studies or surveys as may be required by the contracting agency or the SBA in order to determine the extent of compliance by the bidder with the subcontracting plan and with the clause entitled Small Business Subcontracting Plan (FAR 52.219.9) contained in the contract.

6. The bidder (contractor) agrees that he will maintain at least the following types of records to document compliance with this subcontracting plan:

(a) Small, HUBZone small, small disadvantaged, women-owned, veteran-owned small business concern source lists, guides, and other data identifying SB/SDBA vendors.

(b) Organizations contacted for small, HUBZone small, small disadvantaged, women-owned and veteran-owned small business sources.

(c) On a contract-by-contract basis, records on all subcontract solicitations over $100,000, indicating on each solicitation (1) whether small business concerns were solicited, and if not, why not; (2) whether HUBZone small, small disadvantaged, women-owned and veteran-owned small business concerns were solicited, and if not, why not; and (3) reasons for the failure of solicited small, HUBZone small, small disadvantaged, women-owned or veteran-owned small business concerns to receive the subcontract award.

(d) Records to support other outreach efforts: Contacts with Minority and Small Business Trade Associations, etc. Attendance at small, women-owned small business and minority business procurement conferences and trade fairs.

(e) Records to support internal activities to guide and encourage buyers; workshops, seminars, training programs, etc;

monitoring activities to evaluate compliance.

(f) On a contract-by-contract basis, records to support subcontract award data to include name and address of subcontractor.

(g) Records to be maintained in addition to the above are as follows:

Signed:_______________________________________________________________

Typed name:__________________________________________________________

Title:_________________________________________________________________

Date:_________________________________________________________________

Plan accepted by: ______________________________________________________ Contracting Officer

Date:_________________________________________________________________

PARK - PMIS SUBCONTRACTING FORM-4

SF30
amendment 5 narrative
JEFF-6-SubContractingPlanForm.1doc

File details come from the government source that posted it. Updated .