Amend__6_Package.pdf

PDF 109 KB Posted

Attached to
South Park Grounds Federal contract opportunity
Solicitation number
P14PS00906
Issued by
Department of the Interior National Park Service National Office

About this file

Amendment 6 Package

View the file

Other files for this federal contract opportunity

Other files attached to South Park Grounds, newest first.
File Type Posted
5C2_Sheet_3A.pdf PDF
9C2_Sheet_64A.pdf PDF
7C2_Sheet_56A.pdf PDF
10C2_Sheet_65A.pdf PDF
12Q_and_As _6-30-2014.pdf PDF
8C2_Sheet_58A.pdf PDF
6C2_Sheet_55A.pdf PDF
11C2_Sheet_284.pdf PDF
1Revised_015000_Temporary_Facilities_and_Controls_-_revised_7-3-14_(3).pdf PDF
JEFF-6-SubContractingPlanForm.1doc.pdf PDF
329300_PLANTINGFINEGRADING_CAR2015_2_BID_revised_2014_06_24.pdf PDF
329200_LAWN_CAR2015_2_BID_revised_2014_06_23.pdf PDF
329119_PLANTING_SOIL_SYSTEM_INSTALLATION_CAR_2015_2_BID_revised_2014_06_23.pdf PDF
RFP_Clauses _Updated.pdf PDF
Q_and_A's_as_of_06-26-14.pdf PDF
328400_Irrigation_Specs_100__Bid_amended_6-25-14.pdf PDF
011100_SECTION__SUMMARY_OF_WORK_-_revised_6-24-14.pdf PDF
Amendment_5_Pkg.pdf PDF
321400_SITESTONEWORK_CAR2015_2_BID_revised_2014_06_23.pdf PDF
Site_Visit _Pre-Proposal _Attendance.pdf PDF
Amend__3 _Package.pdf PDF
Amendment_4_pkg.pdf PDF
AirKnife_Exploration.pdf PDF
Engineering_Analysis_of_Modified_DS-50_Barrier.pdf PDF
Utility_Locating_Services.pdf PDF
Subsurface_Exploration_Addendum_2.pdf PDF
Subsurface_Exploration_Addendum_2.pdf PDF
2011_0216_CAR_Geotech_Desk_Study_FINAL.pdf PDF
Subsurface_Exploration_Addendum_3.pdf PDF
Supplemental_Utility_Locating_Services.pdf PDF
2011_0211__CAR_Phase_1_ESA_R1.pdf PDF
Subsurface_Exploration_Addendum_1.pdf PDF
Subsurface_Exploration.pdf PDF
2012_1121_JEFF_GeoArcheology_study.pdf PDF
AirKnife_Exploration.pdf PDF
Subsurface_Exploration_Addendum_3.pdf PDF
Subsurface_Exploration.pdf PDF
Amend_2_Pkg.pdf PDF
Amendment_1_Pkg.pdf PDF
JEFF_CAR2015_Archeological_monitoring_plan_FINAL.pdf PDF
32_91_13__Soil_Blending_Spec.pdf PDF
JEFF_Draw_3_(126-200).pdf PDF
GD__MO140001_05-09-2014__MO1.docx DOCX document
JEFF_Draw_2_(76-125).pdf PDF
2014.04.17_CAR_TTC_accessible_zones_during_construction_memo.pdf PDF
JEFF_Specification.R1_-revised_5-13-14.pdf PDF
RFP_Clauses.docx DOCX document
JEFF_Draw_1_(1-75).pdf PDF
RFP _Proposal_Submission_Pkg.pdf PDF
P14PS00906 _Pre-Sol _Amend__1.docx DOCX document
Show all 50

South Park Grounds has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

P14PS00906

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy DOI, NPS, DSC Contracting Services

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

JEFF-18120206/09/2014000006

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/03/2014

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

JEFF-181202 - South Park Grounds, Jefferson National Expansion Memorial, Clayton County, St. Louis, MO

The purpose of Amendment #6 is to make changes to the Specifications and Drawings, and update the Questions and Answers Log as of June 30, 2014. See the following pages.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

David E. Thomas

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

A. Changes to Specification section 015000, Temporary Facilities and Controls

015000, Temporary Facilities and Controls: entire specification containing Amendment 6 and previous amendment’s with revisions shown issued to replace previous. Only amendment 6 items are noted in the summary below. See amendment 2 for revisions specific to that amendment.

1. Section 1.4 Add item D:

ADD:

1.4 USE CHARGES

D. Contractor shall obtain electrical power service for all contract use, including Contracting Officers field office, from local utility company at contractor’s expense.

2. Section 1.5 Add item B:

1.5 ACTION SUBMITTALS

B. Overlook Structure Calculations and Drawings for Temporary Construction Trailer Loading:

1. Should the Contractor propose to place temporary construction trailers on the North and

South Overlook structures, the Contractor shall first submit dimensioned plans showing the number and location of all proposed construction trailers, dimensioned cut sheets showing the trailer sizes, trailer axle weights and spacing, and the loading pattern of the trailers once they are parked and on temporary supports.

2. The Contractor shall submit signed and sealed calculations prepared by a Missouri P.E. to show that the construction trailer placement will not overstress or damage the existing overlook structural slabs. The submitted calculations shall reference the IBC 2009 and ACI 318-08 building code requirements for structural concrete and reinforcing steel.

3. Construction trailers will not be permitted to be placed on the north and south overlook structures until the Contractor has submitted the drawings and calculations described above, and the Contracting Officer has reviewed and approved the submittal.

4. Prepare a Protection and Maintenance Plan for the protection and upkeep of the Overlook structures. Protection and Maintenance requirements shall be as per NPS and the Contracting Officer and shall be reviewed and accepted prior to the placement of any trailers.

3. Section 2.2 Add item A.1:

2.2 TEMPORARY FACILITIES

A. .

1. Field Office Location: Contractor may site field offices at a location within the construction limits. Alternatively, upon submittal by contractor and approval by Contracting Officer, contractor may place field offices on the South Overlook as identified on Sheet G004 of the contract drawings. Siting field offices on the South Overlook shall require contractor protection of and repair of damage to existing pavement and features of the South Overlook.

4. Section 3.2.H Change:

FROM:

H. Security Cameras: Contractor shall temporarily re-locate removed site surveillance cameras to maintain surveillance during construction. No more than the total number of cameras removed shall be installed in a temporary manner. Contractor shall furnish temporary poles, power, transmission medium and required splicing and termination of medium. Medium may be existing fiber pulled back and re-terminated, temporary above grade fiber in conduit, or any other solution as defined and furnished by the Contractor such as wireless integrated. Temporary cameras shall be monitored and recorded on the existing video surveillance system. Contractor shall coordinate with Contracting Officer to determine the temporary locations.

TO:

H. Security Cameras: Contractor shall coordinate with Contractor 1 and Contractor 1 shall temporarily re-locate removed site surveillance cameras to maintain surveillance during construction. No more than the total number of cameras removed shall be installed in a temporary manner. Contractor 1 shall furnish temporary poles, power, transmission medium and required splicing and termination of medium. Medium may be existing fiber pulled back and re-terminated, temporary above grade fiber in conduit, or any other solution as defined and furnished by the Contractor such as wireless integrated. Temporary cameras shall be monitored and recorded on the existing video surveillance system. Contractor shall coordinate with Contracting Officer to determine the temporary locations.

B. Changes to Specification Section 26 56 00 Exterior Lighting

1. Section 2.5.A.9 Change:

9. Product:

a. DAC D8012-LED8-277-MG-WET

b. Hubbell Lighting VNGL-1

c. Or approved equal by Lithonia Lighting, Cooper Lighting

9. Product:

a. Lithonia Lighting OLVTCM-4000K-MVOLT-Grey

b. Hubbell Lighting VNGL-1

c. DAC D8012-LED8-277-MG-WET

2. Sections 2.5.C.9. Change:

REMOVE:

2.5.C.9.B and 2.5.C.9.C

3. Sections 2.5.D.9. Change:

REMOVE:

2.5.C.9.B and 2.5.C.9.C

4. Section 2.5.E.9.A Change:

9. Dimensions (Pole):

a. H: 108.0”

9. Dimensions (Pole):

a. H: 144.0”

C. Specification section 321313 Concrete Pavements

1. Section 1.4.B.2.a Change:

b. Light Concrete

1) Light Mix 1: 100% LaGrange Aggregate,3 lbs/CY colorant

2) Light Mix 2: 100% LaGrange Aggregate, 4 lbs/CY colorant

3) Light Mix 3: 85% LaGrange Aggregate, 15% Meramec C Aggregate, 3 lbs/CY colorant

4) Light Mix #3 shall be used as the base bid.

5) Light Mix 4: 70% LaGrange Aggregate, 30% Meramec C Aggregate, 3 lbs/CY colorant

a. Light Concrete

1) Light Mix 1: 100% LaGrange Aggregate,4 lbs/CY colorant

2) Light Mix 2: 100% LaGrange Aggregate, 5 lbs/CY colorant

3) Light Mix 3: 85% LaGrange Aggregate, 15% Meramec C Aggregate, 5 lbs/CY colorant

4) Light Mix #3 shall be used as the base bid.

5) Light Mix 4: 70% LaGrange Aggregate, 30% Meramec C Aggregate, 3 lbs/CY colorant

2. Sections 2.3.G.2. Change:

2. Color:

a. For Light pavement: Davis Colors “Sandstone”. Ratio shall be one of the following, as determined in the sample panel:

1) 3.0 pounds per cubic yard

2) 4.0 pounds per cubic yard

TO:

2. Color:

a. For Light pavement: Davis Colors “Sandstone”. Ratio shall be one of the following, as determined in the sample panel:

1) 3.0 pounds per cubic yard

2) 4.0 pounds per cubic yard

3. Replacement pages for the above Specification changes are attached.

4. Drawings, sheets #1, 3, 55, 56, 58, 64, and 65, are changed. Replacement sheets are attached.

5. Drawings, sheet #284, is added. Sheet #284 is attached.

6. Attached is the updated Questions and Answers Log as of June 30, 2014.

7. All other terms and conditions remain unchanged.

SF 30
Amend 6 Narrative
1.4 USE CHARGES
D. Contractor shall obtain electrical power service for all contract use, including Contracting Officers field office, from local utility company at contractor’s expense.
1.5 ACTION SUBMITTALS
B. Overlook Structure Calculations and Drawings for Temporary Construction Trailer Loading:
1. Should the Contractor propose to place temporary construction trailers on the North and South Overlook structures, the Contractor shall first submit dimensioned plans showing the number and location of all proposed construction trailers, dimension...
2. The Contractor shall submit signed and sealed calculations prepared by a Missouri P.E. to show that the construction trailer placement will not overstress or damage the existing overlook structural slabs. The submitted calculations shall reference...
3. Construction trailers will not be permitted to be placed on the north and south overlook structures until the Contractor has submitted the drawings and calculations described above, and the Contracting Officer has reviewed and approved the submittal.
4. Prepare a Protection and Maintenance Plan for the protection and upkeep of the Overlook structures. Protection and Maintenance requirements shall be as per NPS and the Contracting Officer and shall be reviewed and accepted prior to the placement o...
2.2 TEMPORARY FACILITIES
A. .
1. Field Office Location: Contractor may site field offices at a location within the construction limits. Alternatively, upon submittal by contractor and approval by Contracting Officer, contractor may place field offices on the South Overlook as iden...
H. Security Cameras: Contractor shall temporarily re-locate removed site surveillance cameras to maintain surveillance during construction. No more than the total number of cameras removed shall be installed in a temporary manner. Contractor shall fu...
H. Security Cameras: Contractor shall coordinate with Contractor 1 and Contractor 1 shall temporarily re-locate removed site surveillance cameras to maintain surveillance during construction. No more than the total number of cameras removed shall be i...