About this file

This file is a detailed Installation Project Schedule (IMS) showing planned activities for FY25 exercises and communication tower installations across multiple operating positions (OPs). The schedule spans from December 2025 through January 2030, broken down into detailed tasks and subtasks.

The schedule outlines work at multiple sites including OP Mesa, OP Mine, OP Galway, OP Argos, OP Creole, OP America Mine, OP Noble, and OP Boullion. For each site, the work is organized into approximately 16-week phases including NAVSEA initial work, NAVFAC contractor activities, and final NAVSEA installations. Key activities include demolition of existing equipment, foundation preparation, tower construction/repairs, shelter installation, solar panel installation, interior equipment installation, RF cabling, and system testing. The schedule also includes East Microwave updates occurring in multiple phases from December 2025 through May 2026, and several military exercises (IOC, ITX, EWTGPAC, MDMX, MWX) scheduled throughout 2025-2026. Most individual site installations are planned for 96-day durations with specific predecessor relationships defined between tasks.

View the file

Other files

File Type Posted
Amendment - 0017 P1241_Request FPRs.pdf PDF
Amendment - 0015 P1241.pdf PDF
Amendment - 0014 P1241_Open Discussions.pdf PDF
Amendment - 0013 P1241.pdf PDF
Amendment - 0012 P1241.pdf PDF
Amendment - 0011 P1241.pdf PDF
Phase 2_ATT 4_Offer Schedule_P1241_REV 1.xlsx XLSX spreadsheet
Amendment - 0010 P1241.pdf PDF
Phase 2_Exhibit F_P1241.docx DOCX document
Phase 2_Exhibit G_P1241.docx DOCX document
Phase 2_ATT 5_RFI Form_P1241.xlsx XLSX spreadsheet
Phase 2_ATT 4_Offer Schedule_P1241.xlsx XLSX spreadsheet
Amendment - 0008 P1241.pdf PDF
Amendment - 0009 P1241.pdf PDF
Phase 2_ATT 3_Site Visit RSVP List_P1241.xlsx XLSX spreadsheet
Phase 2_ATT 6_CA20250026_06-06-2025.pdf PDF
Phase 2_ATT 2_Site Visit Map_P1241.pdf PDF
Phase 2_ATT 1_RFP Part 1_P1241.pdf PDF
PLA Request for Information N6247325R3443.docx DOCX document
RFI Responses - 04-10-2025.xlsx XLSX spreadsheet
Amendment - 0007 P1241.pdf PDF
RFI Responses - 04-04-2025.xlsx XLSX spreadsheet
Amendment0006.pdf PDF
RFI Responses - 03-27-2025.xlsx XLSX spreadsheet
Amendment0005.pdf PDF
Amendment0004.pdf PDF
RFI Responses - 03-24-2025.xlsx XLSX spreadsheet
RR Matrix_Rev1.pdf PDF
Amendment0003.pdf PDF
RFI Responses - 03-14-2025.xlsx XLSX spreadsheet
Amendment-0002 P1241.pdf PDF
CA20250026_02-28-2025.pdf PDF
Amendment0001-P1241.pdf PDF
EXHIBIT E_P1241.pdf PDF
EXHIBIT A_P1241.pdf PDF
EXHIBIT B_P1241.pdf PDF
Surety Form_P1241.pdf PDF
Instructions for Viewing Interested Vendors List.pdf PDF
EXHIBIT C_P1241.pdf PDF
EXHIBIT D_P1241.pdf PDF
EXHIBIT F_P1241.pdf PDF
Financial Questionnaire_P1241.pdf PDF
EXHIBIT G_P1241.pdf PDF
Offerors Team Consent Form_P1241.pdf PDF
P1241 RFP ATT 3_RR Matrix.pdf PDF
P1241 RFP ATT 5_RFI Form.xlsx XLSX spreadsheet
N6247325R3443_P1241 Phase One Solicitation.pdf PDF
P1241 RFP ATT 1_Approval of Proposed Installation Schedule.pdf PDF
P1241 RFP ATT 4_Offer Schedule.xlsx XLSX spreadsheet
P1241 RFP ATT 6_DBA WD CA20250026_2025 02 21.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Mode

WBS Task Name Duration Start Finish Predecessors Resource Names

1 1 FY25 Excercises 255 days Mon 12/1/25Thu 9/24/26

2 1.1 IOC 1‐25 13 days Mon 12/1/25Mon 12/15/2

4 1.3 ITX Event 45 days Thu 1/15/26 Sat 3/7/26

3 1.2 IOC 2‐25 6 days Thu 3/12/26 Wed 3/18/26

5 1.4 EWTGPAC 3‐26 4 days Mon 4/13/26Thu 4/16/26

7 1.6 EWTGPAC 4‐26 4 days Mon 5/18/26Thu 5/21/26

8 1.7 ITX 10 days Wed 6/3/26 Sat 6/13/26

9 1.8 EWTGPAC 5‐26 4 days Mon 6/29/26Thu 7/2/26

10 1.9 ITX 25 days Sun 7/12/26 Sat 8/8/26

11 1.10 MDMX 4 days Tue 8/11/26 Fri 8/14/26

12 1.11 MWX 6 days Mon 8/17/26Sat 8/22/26

13 1.12 ITX 9 days Thu 8/27/26 Sat 9/5/26

14 1.13 IOC 4‐25 5 days Fri 9/11/26 Wed 9/16/26

15 1.14 EWGTPAC 6‐26 4 days Mon 9/21/26Thu 9/24/26

6 1.5 <New Task>

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: P-1241 Installation Sch Date: Mon 12/2/24

WBS Task Name Duration Start Finish Predecessors Resource Names

16 2 East Microwave updates 122 days Thu 12/18/25Sat 5/9/26

17 2.1 NAVSEA Microwave Phase I 21 days Thu 12/18/25Mon 1/12/26

18 2.2 NAVSEA Microwave Phase II 6 days Mon 3/23/26Sat 3/28/26

19 2.3 NAVSEA Microwave Phase III 6 days Mon 4/27/26Sat 5/2/26

20 2.4 NAVSEA Microwave Phase IV 6 days Mon 5/4/26 Sat 5/9/26

21 3 Site Surveys 12 days Mon 4/27/26Sat 5/9/26

22 3.1 NAVFAC KTR Site Survey 6 days Mon 4/27/26Sat 5/2/26

23 3.2 NAVFAC KTR Site Survey 6 days Mon 5/4/26 Sat 5/9/26

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

24 4 OP Mesa 84 days Mon 9/14/26Sat 12/19/26

25 4.1 Week 0 NAVFAC KTR (no site work) 6 days Mon 9/14/26Sat 9/19/26

26 4.1.1 Staging for helo 6 days Mon 9/14/26Sat 9/19/26

27 4.2 Week 1 NAVFAC KTR 6 days Mon 9/21/26Sat 9/26/26

28 4.2.1 Mobilization to hilltop 6 days Mon 9/21/26Sat 9/26/26 26

29 4.3 Week 2 NAVFAC KTR 6 days Mon 9/28/26Sat 10/3/26

30 4.3.1 Foundation preperation 6 days Mon 9/28/26Sat 10/3/26 27

31 4.3.2 Earth moving 6 days Mon 9/28/26Sat 10/3/26 27

32 4.4 Week 3 NAVFAC KTR 6 days Mon 10/5/26Sat 10/10/26

33 4.4.1 Pour foundations 6 days Mon 10/5/26Sat 10/10/26 29

34 4.5 Week 4 NAVFAC KTR/NAVSEA 6 days Mon 10/12/2Sat 10/17/26

35 4.5.1 Shelter foundation cure time to 70%6 days Mon 10/12/2Sat 10/17/26 32

36 4.5.2 NAVFAC KTR work/tower prep 6 days Mon 10/12/2Sat 10/17/26 32

37 4.5.3 NAVSAEA staging for helo lift 6 days Mon 10/12/2Sat 10/17/26 32

38 4.6 Week 5 NAVSEA/NAVFAC KTR 6 days Mon 10/19/2Sat 10/24/26

39 4.6.1 NAVSEA Heavy lift helo 6 days Mon 10/19/2Sat 10/24/26 35

40 4.6.2 NAVSEA place sheters 6 days Mon 10/19/2Sat 10/24/26 35

41 4.6.3 NAVFAC KTR build tower sections 6 days Mon 10/19/2Sat 10/24/26 35

42 4.7 Week 6 NAVFAC KTR 6 days Mon 10/26/2Sat 10/31/26

43 4.7.1 Erect 140' tower on site 6 days Mon 10/26/2Sat 10/31/26 38

44 4.7.2 Tower: FAA lighting/lightning/groun6 days Mon 10/26/2Sat 10/31/26 38

45 4.8 Week 7 NAVFAC KTR 6 days Mon 11/2/26Sat 11/7/26

46 4.8.1 Ice bridge 6 days Mon 11/2/26Sat 11/7/26 42

47 4.8.2 Conduit 6 days Mon 11/2/26Sat 11/7/26 42

48 4.9 Week 8 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26

49 4.9.1 Site grounding 6 days Mon 11/9/26Sat 11/14/26 45

50 4.10 Week 9 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26

51 4.10.1 Demobilization 6 days Mon 11/9/26Sat 11/14/26 45

52 4.10.2 Destaging 6 days Mon 11/9/26Sat 11/14/26 45

53 4.11 Week 10 NAVSEA 6 days Mon 11/16/2Sat 11/21/26

54 4.11.1 Install solar panels 6 days Mon 11/16/2Sat 11/21/26 50

55 4.11.2 Install interior equipment 6 days Mon 11/16/2Sat 11/21/26 50

56 4.11.3 Install antennas and RF cabling 6 days Mon 11/16/2Sat 11/21/26 50

57 4.12 Week 11 NAVSEA 6 days Mon 11/23/2Sat 11/28/26

58 4.12.1 Install solar panels 6 days Mon 11/23/2Sat 11/28/26 53

59 4.12.2 Install interior equipment 6 days Mon 11/23/2Sat 11/28/26 53

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

60 4.12.3 Install antennas and RF cabling 6 days Mon 11/23/2Sat 11/28/26 53

61 4.13 Week 12 NAVSEA 6 days Mon 11/30/2Sat 12/5/26

62 4.13.1 Complete installations 6 days Mon 11/30/2Sat 12/5/26 57

63 4.13.2 LMR 6 days Mon 11/30/2Sat 12/5/26 57

64 4.14 Week 13 NAVSEA 6 days Mon 12/7/26Sat 12/12/26

65 4.14.1 Site tests 3 days Mon 12/7/26Wed 12/9/2661

66 4.14.2 System tests 3 days Thu 12/10/26Sat 12/12/26 65

67 4.15 Week 14 NAVSEA 6 days Mon 12/14/2Sat 12/19/26

68 4.15.1 Demobilization 6 days Mon 12/14/2Sat 12/19/26 64

69 4.15.2 Destaging 6 days Mon 12/14/2Sat 12/19/26 64

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

70 71 OP Mine 96 days Mon 9/14/26Mon 1/4/27

71 71.1 Week 0 NAVSEA (no site work) 6 days Mon 9/14/26Sat 9/19/26

72 71.1.1 Staging for helo 6 days Mon 9/14/26Sat 9/19/26

73 71.2 Week 1 NAVSEA 6 days Mon 9/21/26Sat 9/26/26

74 71.2.1 Demo/remove electronics 6 days Mon 9/21/26Sat 9/26/26 71

75 71.2.2 Demo/remove batteries 6 days Mon 9/21/26Sat 9/26/26 71

76 71.2.3 Demo/remove antennas and cables6 days Mon 9/21/26Sat 9/26/26 71

77 71.3 Week 2 NAVSEA 6 days Mon 9/28/26Sat 10/3/26

78 71.3.1 Demo/remove electronics 6 days Mon 9/28/26Sat 10/3/26 73

79 71.3.2 Demo/remove batteries 6 days Mon 9/28/26Sat 10/3/26 73

80 71.3.3 Demo/remove antennas and cables6 days Mon 9/28/26Sat 10/3/26 73

81 71.3.4 Demo/ready for demobilization LM1 day Mon 9/28/26Mon 9/28/2673

82 71.3.5 NAVFAC KTR Staging for helo 6 days Mon 9/28/26Sat 10/3/26 73

83 71.4 Week 3 NAVFAC KTR 6 days Mon 10/5/26Sat 10/10/26

84 71.4.1 Mobilization to hilltop 6 days Mon 10/5/26Sat 10/10/26 82

85 71.4.2 Demo/Remove two (2) Monopoles 6 days Mon 10/5/26Sat 10/10/26 82

86 71.4.3 Demo/Remove two (2) above groun6 days Mon 10/5/26Sat 10/10/26 82

87 71.4.4 Demo/Remove shelters 6 days Mon 10/5/26Sat 10/10/26 82

88 71.4.5 Demo/Remove solar 6 days Mon 10/5/26Sat 10/10/26 82

89 71.5 Week 4 NAVFAC KTR 6 days Mon 10/12/2Sat 10/17/26

90 71.5.1 Foundation Preperation 6 days Mon 10/12/2Sat 10/17/26 83

91 71.5.2 Earth moving 6 days Mon 10/12/2Sat 10/17/26 83

92 71.6 Week 5 NAVFAC KTR 6 days Mon 10/19/2Sat 10/24/26

93 71.6.1 Pour Foundations 6 days Mon 10/19/2Sat 10/24/26 89

94 71.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/26/2Sat 10/31/26

95 71.7.1 Shelter foundation cure to 70% 6 days Mon 10/26/2Sat 10/31/26 92

96 71.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/26/2Sat 10/31/26 92

97 71.7.3 NAVSAEA staging for helo lift 6 days Mon 10/26/2Sat 10/31/26 92

98 71.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 11/2/26Sat 11/7/26

99 71.8.1 NAVSEA Heavy lift helo 6 days Mon 11/2/26Sat 11/7/26 94

100 71.8.2 NAVSEA place sheters 6 days Mon 11/2/26Sat 11/7/26 94

101 71.8.3 NAVFAC KTR build tower sections 6 days Mon 11/2/26Sat 11/7/26 94

102 71.9 Week 8 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26

103 71.9.1 Erect 140' tower on site 6 days Mon 11/9/26Sat 11/14/26 98

104 71.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/9/26Sat 11/14/26 98

105 71.10 Week 9 NAVFAC KTR 6 days Mon 11/16/2Sat 11/21/26

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

106 71.10.1 Ice bridge 6 days Mon 11/16/2Sat 11/21/26 102

107 71.10.2 Conduit 6 days Mon 11/16/2Sat 11/21/26 102

108 71.11 Week 10 NAVFAC KTR 6 days Mon 11/23/2Sat 11/28/26

109 71.11.1 Site grounding 6 days Mon 11/23/2Sat 11/28/26 105

110 71.12 Week 11 NAVFAC KTR 6 days Mon 11/23/2Sat 11/28/26

111 71.12.1 NAVFAC KTR demobilization 6 days Mon 11/23/2Sat 11/28/26 105

112 71.12.2 NAVFAC KTR destaging 6 days Mon 11/23/2Sat 11/28/26 105

113 71.13 Week 12 NAVSEA 6 days Mon 11/30/2Sat 12/5/26

114 71.13.1 Install solar panels 6 days Mon 11/30/2Sat 12/5/26 110

115 71.13.2 Install interior equipment 6 days Mon 11/30/2Sat 12/5/26 110

116 71.13.3 Install antennas and RF cabling 6 days Mon 11/30/2Sat 12/5/26 110

117 71.14 Week 13 NAVSEA 6 days Mon 12/7/26Sat 12/12/26

118 71.14.1 Install solar panels 6 days Mon 12/7/26Sat 12/12/26 113

119 71.14.2 Install interior equipment 6 days Mon 12/7/26Sat 12/12/26 113

120 71.14.3 Install antennas and RF cabling 6 days Mon 12/7/26Sat 12/12/26 113

121 71.15 Week 14 NAVSEA 6 days Mon 12/14/2Sat 12/19/26

122 71.15.1 Complete installations 6 days Mon 12/14/2Sat 12/19/26 117

123 71.15.2 LMR 6 days Mon 12/14/2Sat 12/19/26 117

124 71.16 Week 15 NAVSEA 6 days Mon 12/21/2Sat 12/26/26

125 71.16.1 Site tests 3 days Mon 12/21/2Wed 12/23/2121

126 71.16.2 System tests 3 days Thu 12/24/26Sat 12/26/26 125

127 71.17 Week 16 NAVSEA 6 days Mon 12/28/2Mon 1/4/27

128 71.17.1 Demobilization 6 days Mon 12/28/2Mon 1/4/27 124

129 71.17.2 Destaging 6 days Mon 12/28/2Mon 1/4/27 124

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

130 6 OP Galway 96 days Mon 2/15/27Sat 6/5/27

131 6.1 Week 0 NAVSEA (no site work) 6 days Mon 2/15/27Sat 2/20/27

132 6.1.1 Staging for helo 6 days Mon 2/15/27Sat 2/20/27

133 6.2 Week 1 NAVSEA 6 days Mon 2/22/27Sat 2/27/27

134 6.2.1 Demo/remove electronics 6 days Mon 2/22/27Sat 2/27/27 131

135 6.2.2 Demo/remove batteries 6 days Mon 2/22/27Sat 2/27/27 131

136 6.2.3 Demo/remove antennas and cables6 days Mon 2/22/27Sat 2/27/27 131

137 6.3 Week 2 NAVSEA 6 days Mon 3/1/27 Sat 3/6/27

138 6.3.1 Demo/remove electronics 6 days Mon 3/1/27 Sat 3/6/27 133

139 6.3.2 Demo/remove batteries 6 days Mon 3/1/27 Sat 3/6/27 133

140 6.3.3 Demo/remove antennas and cables6 days Mon 3/1/27 Sat 3/6/27 133

141 6.3.4 Demo/ready for demobilization LM1 day Mon 3/1/27 Mon 3/1/27 133

142 6.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/1/27 Sat 3/6/27 133

143 6.4 Week 3 NAVFAC KTR 6 days Mon 3/8/27 Sat 3/13/27

144 6.4.1 Mobilization to hilltop 6 days Mon 3/8/27 Sat 3/13/27 142

145 6.4.2 Demo/Remove two (2) Monopoles 6 days Mon 3/8/27 Sat 3/13/27 142

146 6.4.3 Demo/Remove two (2) above groun6 days Mon 3/8/27 Sat 3/13/27 142

147 6.4.4 Demo/Remove shelters 6 days Mon 3/8/27 Sat 3/13/27 142

148 6.4.5 Demo/Remove solar 6 days Mon 3/8/27 Sat 3/13/27 142

149 6.5 Week 4 NAVFAC KTR 6 days Mon 3/15/27Sat 3/20/27

150 6.5.1 Foundation Preperation 6 days Mon 3/15/27Sat 3/20/27 143

151 6.5.2 Earth moving 6 days Mon 3/15/27Sat 3/20/27 143

152 6.6 Week 5 NAVFAC KTR 6 days Mon 3/22/27Sat 3/27/27

153 6.6.1 Pour Foundations 6 days Mon 3/22/27Sat 3/27/27 149

154 6.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 3/29/27Sat 4/3/27

155 6.7.1 Shelter foundation cure to 70% 6 days Mon 3/29/27Sat 4/3/27 152

156 6.7.2 NAVFAC KTR work/tower prep 6 days Mon 3/29/27Sat 4/3/27 152

157 6.7.3 NAVSAEA staging for helo lift 6 days Mon 3/29/27Sat 4/3/27 152

158 6.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 4/5/27 Sat 4/10/27

159 6.8.1 NAVSEA Heavy lift helo 6 days Mon 4/5/27 Sat 4/10/27 154

160 6.8.2 NAVSEA place sheters 6 days Mon 4/5/27 Sat 4/10/27 154

161 6.8.3 NAVFAC KTR build tower sections 6 days Mon 4/5/27 Sat 4/10/27 154

162 6.9 Week 8 NAVFAC KTR 6 days Mon 4/12/27Sat 4/17/27

163 6.9.1 Erect 140' tower on site 6 days Mon 4/12/27Sat 4/17/27 158

164 6.9.2 Tower: FAA lighting/lightning/groun6 days Mon 4/12/27Sat 4/17/27 158

165 6.10 Week 9 NAVFAC KTR 6 days Mon 4/19/27Sat 4/24/27

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

166 6.10.1 Ice bridge 6 days Mon 4/19/27Sat 4/24/27 162

167 6.10.2 Conduit 6 days Mon 4/19/27Sat 4/24/27 162

168 6.11 Week 10 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27

169 6.11.1 Site grounding 6 days Mon 4/26/27Sat 5/1/27 165

170 6.12 Week 11 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27

171 6.12.1 NAVFAC KTR demobilization 6 days Mon 4/26/27Sat 5/1/27 165

172 6.12.2 NAVFAC KTR destaging 6 days Mon 4/26/27Sat 5/1/27 165

173 6.13 Week 12 NAVSEA 6 days Mon 5/3/27 Sat 5/8/27

174 6.13.1 Install solar panels 6 days Mon 5/3/27 Sat 5/8/27 170

175 6.13.2 Install interior equipment 6 days Mon 5/3/27 Sat 5/8/27 170

176 6.13.3 Install antennas and RF cabling 6 days Mon 5/3/27 Sat 5/8/27 170

177 6.14 Week 13 NAVSEA 6 days Mon 5/10/27Sat 5/15/27

178 6.14.1 Install solar panels 6 days Mon 5/10/27Sat 5/15/27 173

179 6.14.2 Install interior equipment 6 days Mon 5/10/27Sat 5/15/27 173

180 6.14.3 Install antennas and RF cabling 6 days Mon 5/10/27Sat 5/15/27 173

181 6.15 Week 14 NAVSEA 6 days Mon 5/17/27Sat 5/22/27

182 6.15.1 Complete installations 6 days Mon 5/17/27Sat 5/22/27 177

183 6.15.2 LMR 6 days Mon 5/17/27Sat 5/22/27 177

184 6.16 Week 15 NAVSEA 6 days Mon 5/24/27Sat 5/29/27

185 6.16.1 Site tests 3 days Mon 5/24/27Wed 5/26/27181

186 6.16.2 System tests 3 days Thu 5/27/27 Sat 5/29/27 185

187 6.17 Week 16 NAVSEA 6 days Mon 5/31/27Sat 6/5/27

188 6.17.1 Demobilization 6 days Mon 5/31/27Sat 6/5/27 184

189 6.17.2 Destaging 6 days Mon 5/31/27Sat 6/5/27 184

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

190 7 OP Argos 96 days Mon 2/15/27Sat 6/5/27

191 7.1 Week 0 NAVSEA (no site work) 6 days Mon 2/15/27Sat 2/20/27

192 7.1.1 Staging for helo 6 days Mon 2/15/27Sat 2/20/27

193 7.2 Week 1 NAVSEA 6 days Mon 2/22/27Sat 2/27/27

194 7.2.1 Demo/remove electronics 6 days Mon 2/22/27Sat 2/27/27 191

195 7.2.2 Demo/remove batteries 6 days Mon 2/22/27Sat 2/27/27 191

196 7.2.3 Demo/remove antennas and cables6 days Mon 2/22/27Sat 2/27/27 191

197 7.3 Week 2 NAVSEA 6 days Mon 3/1/27 Sat 3/6/27

198 7.3.1 Demo/remove electronics 6 days Mon 3/1/27 Sat 3/6/27 193

199 7.3.2 Demo/remove batteries 6 days Mon 3/1/27 Sat 3/6/27 193

200 7.3.3 Demo/remove antennas and cables6 days Mon 3/1/27 Sat 3/6/27 193

201 7.3.4 Demo/ready for demobilization LM1 day Mon 3/1/27 Mon 3/1/27 193

202 7.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/1/27 Sat 3/6/27 193

203 7.4 Week 3 NAVFAC KTR 6 days Mon 3/8/27 Sat 3/13/27

204 7.4.1 Mobilization to hilltop 6 days Mon 3/8/27 Sat 3/13/27 202

205 7.4.2 Demo/Remove shelters 6 days Mon 3/8/27 Sat 3/13/27 202

206 7.4.3 Demo/Remove solar 6 days Mon 3/8/27 Sat 3/13/27 202

207 7.5 Week 4 NAVFAC KTR 6 days Mon 3/15/27Sat 3/20/27

208 7.5.1 Foundation Preperation 6 days Mon 3/15/27Sat 3/20/27 203

209 7.5.2 Earth moving 6 days Mon 3/15/27Sat 3/20/27 203

210 7.6 Week 5 NAVFAC KTR 6 days Mon 3/22/27Sat 3/27/27

211 7.6.1 Pour Foundations 6 days Mon 3/22/27Sat 3/27/27 207

212 7.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 3/29/27Sat 4/3/27

213 7.7.1 Shelter foundation cure to 70% 6 days Mon 3/29/27Sat 4/3/27 210

214 7.7.2 NAVFAC KTR work/tower prep 6 days Mon 3/29/27Sat 4/3/27 210

215 7.7.3 NAVSAEA staging for helo lift 6 days Mon 3/29/27Sat 4/3/27 210

216 7.8 Week 7 NAVSEA 6 days Mon 4/5/27 Sat 4/10/27

217 7.8.1 NAVSEA Heavy lift helo 6 days Mon 4/5/27 Sat 4/10/27 212

218 7.8.2 NAVSEA place sheters 6 days Mon 4/5/27 Sat 4/10/27 212

219 7.9 Week 8 NAVFAC KTR 6 days Mon 4/12/27Sat 4/17/27

220 7.9.1 Complete tower repairs 6 days Mon 4/12/27Sat 4/17/27 216

221 7.9.2 Tower: FAA lighting/lightning/groun6 days Mon 4/12/27Sat 4/17/27 216

222 7.10 Week 9 NAVFAC KTR 6 days Mon 4/19/27Sat 4/24/27

223 7.10.1 Ice bridge 6 days Mon 4/19/27Sat 4/24/27 219

224 7.10.2 Conduit 6 days Mon 4/19/27Sat 4/24/27 219

225 7.11 Week 10 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

226 7.11.1 Site grounding 6 days Mon 4/26/27Sat 5/1/27 222

227 7.11.2 Site lightning protection 6 days Mon 4/26/27Sat 5/1/27 222

228 7.12 Week 11 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27

229 7.12.1 NAVFAC KTR demobilization 6 days Mon 4/26/27Sat 5/1/27 222

230 7.12.2 NAVFAC KTR destaging 6 days Mon 4/26/27Sat 5/1/27 222

231 7.13 Week 12 NAVSEA 6 days Mon 5/3/27 Sat 5/8/27

232 7.13.1 Install solar panels 6 days Mon 5/3/27 Sat 5/8/27 228

233 7.13.2 Install interior equipment 6 days Mon 5/3/27 Sat 5/8/27 228

234 7.13.3 Install antennas and RF cabling 6 days Mon 5/3/27 Sat 5/8/27 228

235 7.14 Week 13 NAVSEA 6 days Mon 5/10/27Sat 5/15/27

236 7.14.1 Install solar panels 6 days Mon 5/10/27Sat 5/15/27 231

237 7.14.2 Install interior equipment 6 days Mon 5/10/27Sat 5/15/27 231

238 7.14.3 Install antennas and RF cabling 6 days Mon 5/10/27Sat 5/15/27 231

239 7.15 Week 14 NAVSEA 6 days Mon 5/17/27Sat 5/22/27

240 7.15.1 Complete installations 6 days Mon 5/17/27Sat 5/22/27 235

241 7.15.2 LMR 6 days Mon 5/17/27Sat 5/22/27 235

242 7.16 Week 15 NAVSEA 6 days Mon 5/24/27Sat 5/29/27

243 7.16.1 Site tests 3 days Mon 5/24/27Wed 5/26/27239

244 7.16.2 System tests 3 days Thu 5/27/27 Sat 5/29/27 243

245 7.17 Week 16 NAVSEA 6 days Mon 5/31/27Sat 6/5/27

246 7.17.1 Demobilization 6 days Mon 5/31/27Sat 6/5/27 242

247 7.17.2 Destaging 6 days Mon 5/31/27Sat 6/5/27 242

248 8 Complete Microwave 6 days Mon 6/7/27 Sat 6/12/27 245

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

249 9 OP Creole 96 days Mon 9/20/27Mon 1/10/28

250 9.1 Week 0 NAVSEA (no site work) 6 days Mon 9/20/27Sat 9/25/27

251 9.1.1 Staging for helo 6 days Mon 9/20/27Sat 9/25/27

252 9.2 Week 1 NAVSEA 6 days Mon 9/27/27Sat 10/2/27

253 9.2.1 Demo/remove electronics 6 days Mon 9/27/27Sat 10/2/27 250

254 9.2.2 Demo/remove batteries 6 days Mon 9/27/27Sat 10/2/27 250

255 9.2.3 Demo/remove antennas and cables6 days Mon 9/27/27Sat 10/2/27 250

256 9.3 Week 2 NAVSEA 6 days Mon 10/4/27Sat 10/9/27

257 9.3.1 Demo/remove electronics 6 days Mon 10/4/27Sat 10/9/27 252

258 9.3.2 Demo/remove batteries 6 days Mon 10/4/27Sat 10/9/27 252

259 9.3.3 Demo/remove antennas and cables6 days Mon 10/4/27Sat 10/9/27 252

260 9.3.4 Demo/ready for demobilization LM1 day Mon 10/4/27Mon 10/4/27252

261 9.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/4/27Sat 10/9/27 252

262 9.4 Week 3 NAVFAC KTR 6 days Mon 10/11/2Sat 10/16/27

263 9.4.1 Mobilization to hilltop 6 days Mon 10/11/2Sat 10/16/27 261

264 9.4.2 Demo/Remove shelters 6 days Mon 10/11/2Sat 10/16/27 261

265 9.4.3 Demo/Remove solar 6 days Mon 10/11/2Sat 10/16/27 261

266 9.5 Week 4 NAVFAC KTR 6 days Mon 10/18/2Sat 10/23/27

267 9.5.1 Foundation Preperation 6 days Mon 10/18/2Sat 10/23/27 262

268 9.5.2 Earth moving 6 days Mon 10/18/2Sat 10/23/27 262

269 9.6 Week 5 NAVFAC KTR 6 days Mon 10/25/2Sat 10/30/27

270 9.6.1 Pour Foundations 6 days Mon 10/25/2Sat 10/30/27 266

271 9.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 11/1/27Sat 11/6/27

272 9.7.1 Shelter foundation cure to 70% 6 days Mon 11/1/27Sat 11/6/27 269

273 9.7.2 NAVFAC KTR work/tower prep 6 days Mon 11/1/27Sat 11/6/27 269

274 9.7.3 NAVSAEA staging for helo lift 6 days Mon 11/1/27Sat 11/6/27 269

275 9.8 Week 7 NAVSEA 6 days Mon 11/8/27Sat 11/13/27

276 9.8.1 NAVSEA Heavy lift helo 6 days Mon 11/8/27Sat 11/13/27 271

277 9.8.2 NAVSEA place sheters 6 days Mon 11/8/27Sat 11/13/27 271

278 9.9 Week 8 NAVFAC KTR 6 days Mon 11/15/2Sat 11/20/27

279 9.9.1 Complete tower repairs 6 days Mon 11/15/2Sat 11/20/27 275

280 9.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/15/2Sat 11/20/27 275

281 9.10 Week 9 NAVFAC KTR 6 days Mon 11/22/2Sat 11/27/27

282 9.10.1 Ice bridge 6 days Mon 11/22/2Sat 11/27/27 278

283 9.10.2 Conduit 6 days Mon 11/22/2Sat 11/27/27 278

284 9.11 Week 10 NAVFAC KTR 6 days Mon 11/29/2Sat 12/4/27

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

285 9.11.1 Site grounding 6 days Mon 11/29/2Sat 12/4/27 281

286 9.11.2 Site lightning protection 6 days Mon 11/29/2Sat 12/4/27 281

287 9.12 Week 11 NAVFAC KTR 6 days Mon 11/29/2Sat 12/4/27

288 9.12.1 NAVFAC KTR demobilization 6 days Mon 11/29/2Sat 12/4/27 281

289 9.12.2 NAVFAC KTR destaging 6 days Mon 11/29/2Sat 12/4/27 281

290 9.13 Week 12 NAVSEA 6 days Mon 12/6/27Sat 12/11/27

291 9.13.1 Install solar panels 6 days Mon 12/6/27Sat 12/11/27 287

292 9.13.2 Install interior equipment 6 days Mon 12/6/27Sat 12/11/27 287

293 9.13.3 Install antennas and RF cabling 6 days Mon 12/6/27Sat 12/11/27 287

294 9.14 Week 13 NAVSEA 6 days Mon 12/13/2Sat 12/18/27

295 9.14.1 Install solar panels 6 days Mon 12/13/2Sat 12/18/27 290

296 9.14.2 Install interior equipment 6 days Mon 12/13/2Sat 12/18/27 290

297 9.14.3 Install antennas and RF cabling 6 days Mon 12/13/2Sat 12/18/27 290

298 9.15 Week 14 NAVSEA 6 days Mon 12/20/2Sat 12/25/27

299 9.15.1 Complete installations 6 days Mon 12/20/2Sat 12/25/27 294

300 9.15.2 LMR 6 days Mon 12/20/2Sat 12/25/27 294

301 9.16 Week 15 NAVSEA 6 days Mon 12/27/2Mon 1/3/28

302 9.16.1 Site tests 3 days Mon 12/27/2Wed 12/29/2298

303 9.16.2 System tests 3 days Thu 12/30/27Mon 1/3/28 302

304 9.17 Week 16 NAVSEA 6 days Tue 1/4/28 Mon 1/10/28

305 9.17.1 Demobilization 6 days Tue 1/4/28 Mon 1/10/28301

306 9.17.2 Destaging 6 days Tue 1/4/28 Mon 1/10/28301

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

307 10 OP Crampton 96 days Mon 3/13/28Sat 7/1/28

308 10.1 Week 0 NAVSEA (no site work) 6 days Mon 3/13/28Sat 3/18/28

309 10.1.1 Staging for helo 6 days Mon 3/13/28Sat 3/18/28

310 10.2 Week 1 NAVSEA 6 days Mon 3/20/28Sat 3/25/28

311 10.2.1 Demo/remove electronics 6 days Mon 3/20/28Sat 3/25/28 308

312 10.2.2 Demo/remove batteries 6 days Mon 3/20/28Sat 3/25/28 308

313 10.2.3 Demo/remove antennas and cables6 days Mon 3/20/28Sat 3/25/28 308

314 10.3 Week 2 NAVSEA 6 days Mon 3/27/28Sat 4/1/28

315 10.3.1 Demo/remove electronics 6 days Mon 3/27/28Sat 4/1/28 310

316 10.3.2 Demo/remove batteries 6 days Mon 3/27/28Sat 4/1/28 310

317 10.3.3 Demo/remove antennas and cables6 days Mon 3/27/28Sat 4/1/28 310

318 10.3.4 Demo/ready for demobilization LM1 day Mon 3/27/28Mon 3/27/28310

319 10.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/27/28Sat 4/1/28 310

320 10.4 Week 3 NAVFAC KTR 6 days Mon 4/3/28 Sat 4/8/28

321 10.4.1 Mobilization to hilltop 6 days Mon 4/3/28 Sat 4/8/28 319

322 10.4.2 Demo/Remove shelters 6 days Mon 4/3/28 Sat 4/8/28 319

323 10.4.3 Demo/Remove solar 6 days Mon 4/3/28 Sat 4/8/28 319

324 10.5 Week 4 NAVFAC KTR 6 days Mon 4/10/28Sat 4/15/28

325 10.5.1 Foundation Preperation 6 days Mon 4/10/28Sat 4/15/28 320

326 10.5.2 Earth moving 6 days Mon 4/10/28Sat 4/15/28 320

327 10.6 Week 5 NAVFAC KTR 6 days Mon 4/17/28Sat 4/22/28

328 10.6.1 Pour Foundations 6 days Mon 4/17/28Sat 4/22/28 324

329 10.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 4/24/28Sat 4/29/28

330 10.7.1 Shelter foundation cure to 70% 6 days Mon 4/24/28Sat 4/29/28 327

331 10.7.2 NAVFAC KTR work/tower prep 6 days Mon 4/24/28Sat 4/29/28 327

332 10.7.3 NAVSAEA staging for helo lift 6 days Mon 4/24/28Sat 4/29/28 327

333 10.8 Week 7 NAVSEA 6 days Mon 5/1/28 Sat 5/6/28

334 10.8.1 NAVSEA Heavy lift helo 6 days Mon 5/1/28 Sat 5/6/28 329

335 10.8.2 NAVSEA place sheters 6 days Mon 5/1/28 Sat 5/6/28 329

336 10.9 Week 8 NAVFAC KTR 6 days Mon 5/8/28 Sat 5/13/28

337 10.9.1 Complete tower repairs 6 days Mon 5/8/28 Sat 5/13/28 333

338 10.9.2 Tower: FAA lighting/lightning/groun6 days Mon 5/8/28 Sat 5/13/28 333

339 10.10 Week 9 NAVFAC KTR 6 days Mon 5/15/28Sat 5/20/28

340 10.10.1 Ice bridge 6 days Mon 5/15/28Sat 5/20/28 336

341 10.10.2 Conduit 6 days Mon 5/15/28Sat 5/20/28 336

342 10.11 Week 10 NAVFAC KTR 6 days Mon 5/22/28Sat 5/27/28

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

343 10.11.1 Site grounding 6 days Mon 5/22/28Sat 5/27/28 339

344 10.11.2 Site lightning protection 6 days Mon 5/22/28Sat 5/27/28 339

345 10.12 Week 11 NAVFAC KTR 6 days Mon 5/22/28Sat 5/27/28

346 10.12.1 NAVFAC KTR demobilization 6 days Mon 5/22/28Sat 5/27/28 339

347 10.12.2 NAVFAC KTR destaging 6 days Mon 5/22/28Sat 5/27/28 339

348 10.13 Week 12 NAVSEA 6 days Mon 5/29/28Sat 6/3/28

349 10.13.1 Install solar panels 6 days Mon 5/29/28Sat 6/3/28 345

350 10.13.2 Install interior equipment 6 days Mon 5/29/28Sat 6/3/28 345

351 10.13.3 Install antennas and RF cabling 6 days Mon 5/29/28Sat 6/3/28 345

352 10.14 Week 13 NAVSEA 6 days Mon 6/5/28 Sat 6/10/28

353 10.14.1 Install solar panels 6 days Mon 6/5/28 Sat 6/10/28 348

354 10.14.2 Install interior equipment 6 days Mon 6/5/28 Sat 6/10/28 348

355 10.14.3 Install antennas and RF cabling 6 days Mon 6/5/28 Sat 6/10/28 348

356 10.15 Week 14 NAVSEA 6 days Mon 6/12/28Sat 6/17/28

357 10.15.1 Complete installations 6 days Mon 6/12/28Sat 6/17/28 352

358 10.15.2 LMR 6 days Mon 6/12/28Sat 6/17/28 352

359 10.16 Week 15 NAVSEA 6 days Mon 6/19/28Sat 6/24/28

360 10.16.1 Site tests 3 days Mon 6/19/28Wed 6/21/28356

361 10.16.2 System tests 3 days Thu 6/22/28 Sat 6/24/28 360

362 10.17 Week 16 NAVSEA 6 days Mon 6/26/28Sat 7/1/28

363 10.17.1 Demobilization 6 days Mon 6/26/28Sat 7/1/28 359

364 10.17.2 Destaging 6 days Mon 6/26/28Sat 7/1/28 359

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

365 11 OP America Mine 96 days Mon 9/18/28Mon 1/8/29

366 11.1 Week 0 NAVSEA (no site work) 6 days Mon 9/18/28Sat 9/23/28

367 11.1.1 Staging for helo 6 days Mon 9/18/28Sat 9/23/28

368 11.2 Week 1 NAVSEA 6 days Mon 9/25/28Sat 9/30/28

369 11.2.1 Demo/remove electronics 6 days Mon 9/25/28Sat 9/30/28 366

370 11.2.2 Demo/remove batteries 6 days Mon 9/25/28Sat 9/30/28 366

371 11.2.3 Demo/remove antennas and cables6 days Mon 9/25/28Sat 9/30/28 366

372 11.3 Week 2 NAVSEA 6 days Mon 10/2/28Sat 10/7/28

373 11.3.1 Demo/remove electronics 6 days Mon 10/2/28Sat 10/7/28 368

374 11.3.2 Demo/remove batteries 6 days Mon 10/2/28Sat 10/7/28 368

375 11.3.3 Demo/remove antennas and cables6 days Mon 10/2/28Sat 10/7/28 368

376 11.3.4 Demo/ready for demobilization LM1 day Mon 10/2/28Mon 10/2/28368

377 11.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/2/28Sat 10/7/28 368

378 11.4 Week 3 NAVFAC KTR 6 days Mon 10/9/28Sat 10/14/28

379 11.4.1 Mobilization to hilltop 6 days Mon 10/9/28Sat 10/14/28 377

380 11.4.2 Demo/Remove 40' tower 6 days Mon 10/9/28Sat 10/14/28 377

381 11.4.3 Demo/Remove below ground found6 days Mon 10/9/28Sat 10/14/28 377

382 11.4.4 Demo/Remove shelters 6 days Mon 10/9/28Sat 10/14/28 377

383 11.4.5 Demo/Remove solar 6 days Mon 10/9/28Sat 10/14/28 377

384 11.5 Week 4 NAVFAC KTR 6 days Mon 10/16/2Sat 10/21/28

385 11.5.1 Foundation Preperation 6 days Mon 10/16/2Sat 10/21/28 378

386 11.5.2 Earth moving 6 days Mon 10/16/2Sat 10/21/28 378

387 11.6 Week 5 NAVFAC KTR 6 days Mon 10/23/2Sat 10/28/28

388 11.6.1 Pour Foundations 6 days Mon 10/23/2Sat 10/28/28 384

389 11.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/30/2Sat 11/4/28

390 11.7.1 Shelter foundation cure to 70% 6 days Mon 10/30/2Sat 11/4/28 387

391 11.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/30/2Sat 11/4/28 387

392 11.7.3 NAVSAEA staging for helo lift 6 days Mon 10/30/2Sat 11/4/28 387

393 11.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 11/6/28Sat 11/11/28

394 11.8.1 NAVSEA Heavy lift helo 6 days Mon 11/6/28Sat 11/11/28 389

395 11.8.2 NAVSEA place sheters 6 days Mon 11/6/28Sat 11/11/28 389

396 11.8.3 NAVFAC KTR build tower sections 6 days Mon 11/6/28Sat 11/11/28 389

397 11.9 Week 8 NAVFAC KTR 6 days Mon 11/13/2Sat 11/18/28

398 11.9.1 Erect 140' tower on site 6 days Mon 11/13/2Sat 11/18/28 393

399 11.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/13/2Sat 11/18/28 393

400 11.10 Week 9 NAVFAC KTR 6 days Mon 11/20/2Sat 11/25/28

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

401 11.10.1 Ice bridge 6 days Mon 11/20/2Sat 11/25/28 397

402 11.10.2 Conduit 6 days Mon 11/20/2Sat 11/25/28 397

403 11.11 Week 10 NAVFAC KTR 6 days Mon 11/27/2Sat 12/2/28

404 11.11.1 Site grounding 6 days Mon 11/27/2Sat 12/2/28 400

405 11.12 Week 11 NAVFAC KTR 6 days Mon 11/27/2Sat 12/2/28

406 11.12.1 NAVFAC KTR demobilization 6 days Mon 11/27/2Sat 12/2/28 400

407 11.12.2 NAVFAC KTR destaging 6 days Mon 11/27/2Sat 12/2/28 400

408 11.13 Week 12 NAVSEA 6 days Mon 12/4/28Sat 12/9/28

409 11.13.1 Install solar panels 6 days Mon 12/4/28Sat 12/9/28 405

410 11.13.2 Install interior equipment 6 days Mon 12/4/28Sat 12/9/28 405

411 11.13.3 Install antennas and RF cabling 6 days Mon 12/4/28Sat 12/9/28 405

412 11.14 Week 13 NAVSEA 6 days Mon 12/11/2Sat 12/16/28

413 11.14.1 Install solar panels 6 days Mon 12/11/2Sat 12/16/28 408

414 11.14.2 Install interior equipment 6 days Mon 12/11/2Sat 12/16/28 408

415 11.14.3 Install antennas and RF cabling 6 days Mon 12/11/2Sat 12/16/28 408

416 11.15 Week 14 NAVSEA 6 days Mon 12/18/2Sat 12/23/28

417 11.15.1 Complete installations 6 days Mon 12/18/2Sat 12/23/28 412

418 11.15.2 LMR 6 days Mon 12/18/2Sat 12/23/28 412

419 11.16 Week 15 NAVSEA 6 days Mon 12/25/2Sat 12/30/28

420 11.16.1 Site tests 3 days Mon 12/25/2Wed 12/27/2416

421 11.16.2 System tests 3 days Thu 12/28/28Sat 12/30/28 420

422 11.17 Week 16 NAVSEA 6 days Tue 1/2/29 Mon 1/8/29

423 11.17.1 Demobilization 6 days Tue 1/2/29 Mon 1/8/29 419

424 11.17.2 Destaging 6 days Tue 1/2/29 Mon 1/8/29 419

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

425 12 OP Noble 96 days Mon 3/12/29Sat 6/30/29

426 12.1 Week 0 NAVSEA (no site work) 6 days Mon 3/12/29Sat 3/17/29

427 12.1.1 Staging for helo 6 days Mon 3/12/29Sat 3/17/29

428 12.2 Week 1 NAVSEA 6 days Mon 3/19/29Sat 3/24/29

429 12.2.1 Demo/remove electronics 6 days Mon 3/19/29Sat 3/24/29 426

430 12.2.2 Demo/remove batteries 6 days Mon 3/19/29Sat 3/24/29 426

431 12.2.3 Demo/remove antennas and cables6 days Mon 3/19/29Sat 3/24/29 426

432 12.3 Week 2 NAVSEA 6 days Mon 3/26/29Sat 3/31/29

433 12.3.1 Demo/remove electronics 6 days Mon 3/26/29Sat 3/31/29 428

434 12.3.2 Demo/remove batteries 6 days Mon 3/26/29Sat 3/31/29 428

435 12.3.3 Demo/remove antennas and cables6 days Mon 3/26/29Sat 3/31/29 428

436 12.3.4 Demo/ready for demobilization LM1 day Mon 3/26/29Mon 3/26/29428

437 12.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/26/29Sat 3/31/29 428

438 12.4 Week 3 NAVFAC KTR 6 days Mon 4/2/29 Sat 4/7/29

439 12.4.1 Mobilization to hilltop 6 days Mon 4/2/29 Sat 4/7/29 437

440 12.4.2 Demo/Remove shelters 6 days Mon 4/2/29 Sat 4/7/29 437

441 12.4.3 Demo/Remove solar 6 days Mon 4/2/29 Sat 4/7/29 437

442 12.5 Week 4 NAVFAC KTR 6 days Mon 4/9/29 Sat 4/14/29

443 12.5.1 Foundation Preperation 6 days Mon 4/9/29 Sat 4/14/29 438

444 12.5.2 Earth moving 6 days Mon 4/9/29 Sat 4/14/29 438

445 12.6 Week 5 NAVFAC KTR 6 days Mon 4/16/29Sat 4/21/29

446 12.6.1 Pour Foundations 6 days Mon 4/16/29Sat 4/21/29 442

447 12.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 4/23/29Sat 4/28/29

448 12.7.1 Shelter foundation cure to 70% 6 days Mon 4/23/29Sat 4/28/29 445

449 12.7.2 NAVFAC KTR work/tower prep 6 days Mon 4/23/29Sat 4/28/29 445

450 12.7.3 NAVSAEA staging for helo lift 6 days Mon 4/23/29Sat 4/28/29 445

451 12.8 Week 7 NAVSEA 6 days Mon 4/30/29Sat 5/5/29

452 12.8.1 NAVSEA Heavy lift helo 6 days Mon 4/30/29Sat 5/5/29 447

453 12.8.2 NAVSEA place sheters 6 days Mon 4/30/29Sat 5/5/29 447

454 12.9 Week 8 NAVFAC KTR 6 days Mon 5/7/29 Sat 5/12/29

455 12.9.1 Complete tower repairs 6 days Mon 5/7/29 Sat 5/12/29 451

456 12.9.2 Tower: FAA lighting/lightning/groun6 days Mon 5/7/29 Sat 5/12/29 451

457 12.10 Week 9 NAVFAC KTR 6 days Mon 5/14/29Sat 5/19/29

458 12.10.1 Ice bridge 6 days Mon 5/14/29Sat 5/19/29 454

459 12.10.2 Conduit 6 days Mon 5/14/29Sat 5/19/29 454

460 12.11 Week 10 NAVFAC KTR 6 days Mon 5/21/29Sat 5/26/29

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

461 12.11.1 Site grounding 6 days Mon 5/21/29Sat 5/26/29 457

462 12.11.2 Site lightning protection 6 days Mon 5/21/29Sat 5/26/29 457

463 12.12 Week 11 NAVFAC KTR 6 days Mon 5/21/29Sat 5/26/29

464 12.12.1 NAVFAC KTR demobilization 6 days Mon 5/21/29Sat 5/26/29 457

465 12.12.2 NAVFAC KTR destaging 6 days Mon 5/21/29Sat 5/26/29 457

466 12.13 Week 12 NAVSEA 6 days Mon 5/28/29Sat 6/2/29

467 12.13.1 Install solar panels 6 days Mon 5/28/29Sat 6/2/29 463

468 12.13.2 Install interior equipment 6 days Mon 5/28/29Sat 6/2/29 463

469 12.13.3 Install antennas and RF cabling 6 days Mon 5/28/29Sat 6/2/29 463

470 12.14 Week 13 NAVSEA 6 days Mon 6/4/29 Sat 6/9/29

471 12.14.1 Install solar panels 6 days Mon 6/4/29 Sat 6/9/29 466

472 12.14.2 Install interior equipment 6 days Mon 6/4/29 Sat 6/9/29 466

473 12.14.3 Install antennas and RF cabling 6 days Mon 6/4/29 Sat 6/9/29 466

474 12.15 Week 14 NAVSEA 6 days Mon 6/11/29Sat 6/16/29

475 12.15.1 Complete installations 6 days Mon 6/11/29Sat 6/16/29 470

476 12.15.2 LMR 6 days Mon 6/11/29Sat 6/16/29 470

477 12.16 Week 15 NAVSEA 6 days Mon 6/18/29Sat 6/23/29

478 12.16.1 Site tests 3 days Mon 6/18/29Wed 6/20/29474

479 12.16.2 System tests 3 days Thu 6/21/29 Sat 6/23/29 478

480 12.17 Week 16 NAVSEA 6 days Mon 6/25/29Sat 6/30/29

481 12.17.1 Demobilization 6 days Mon 6/25/29Sat 6/30/29 477

482 12.17.2 Destaging 6 days Mon 6/25/29Sat 6/30/29 477

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

483 13 OP Boullion 96 days Mon 9/17/29Mon 1/7/30

484 13.1 Week 0 NAVSEA (no site work) 6 days Mon 9/17/29Sat 9/22/29

485 13.1.1 Staging for helo 6 days Mon 9/17/29Sat 9/22/29

486 13.2 Week 1 NAVSEA 6 days Mon 9/24/29Sat 9/29/29

487 13.2.1 Demo/remove electronics 6 days Mon 9/24/29Sat 9/29/29 484

488 13.2.2 Demo/remove batteries 6 days Mon 9/24/29Sat 9/29/29 484

489 13.2.3 Demo/remove antennas and cables6 days Mon 9/24/29Sat 9/29/29 484

490 13.3 Week 2 NAVSEA 6 days Mon 10/1/29Sat 10/6/29

491 13.3.1 Demo/remove electronics 6 days Mon 10/1/29Sat 10/6/29 486

492 13.3.2 Demo/remove batteries 6 days Mon 10/1/29Sat 10/6/29 486

493 13.3.3 Demo/remove antennas and cables6 days Mon 10/1/29Sat 10/6/29 486

494 13.3.4 Demo/ready for demobilization LM1 day Mon 10/1/29Mon 10/1/29486

495 13.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/1/29Sat 10/6/29 486

496 13.4 Week 3 NAVFAC KTR 6 days Mon 10/8/29Sat 10/13/29

497 13.4.1 Mobilization to hilltop 6 days Mon 10/8/29Sat 10/13/29 495

498 13.4.2 Demo/Remove shelters 6 days Mon 10/8/29Sat 10/13/29 495

499 13.4.3 Demo/Remove solar 6 days Mon 10/8/29Sat 10/13/29 495

500 13.5 Week 4 NAVFAC KTR 6 days Mon 10/15/2Sat 10/20/29

501 13.5.1 Foundation Preperation 6 days Mon 10/15/2Sat 10/20/29 496

502 13.5.2 Earth moving 6 days Mon 10/15/2Sat 10/20/29 496

503 13.6 Week 5 NAVFAC KTR 6 days Mon 10/22/2Sat 10/27/29

504 13.6.1 Pour Foundations 6 days Mon 10/22/2Sat 10/27/29 500

505 13.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/29/2Sat 11/3/29

506 13.7.1 Shelter foundation cure to 70% 6 days Mon 10/29/2Sat 11/3/29 503

507 13.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/29/2Sat 11/3/29 503

508 13.7.3 NAVSAEA staging for helo lift 6 days Mon 10/29/2Sat 11/3/29 503

509 13.8 Week 7 NAVSEA 6 days Mon 11/5/29Sat 11/10/29

510 13.8.1 NAVSEA Heavy lift helo 6 days Mon 11/5/29Sat 11/10/29 505

511 13.8.2 NAVSEA place sheters 6 days Mon 11/5/29Sat 11/10/29 505

512 13.9 Week 8 NAVFAC KTR 6 days Mon 11/12/2Sat 11/17/29

513 13.9.1 Complete tower repairs 6 days Mon 11/12/2Sat 11/17/29 509

514 13.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/12/2Sat 11/17/29 509

515 13.10 Week 9 NAVFAC KTR 6 days Mon 11/19/2Sat 11/24/29

516 13.10.1 Ice bridge 6 days Mon 11/19/2Sat 11/24/29 512

517 13.10.2 Conduit 6 days Mon 11/19/2Sat 11/24/29 512

518 13.11 Week 10 NAVFAC KTR 6 days Mon 11/26/2Sat 12/1/29

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

WBS Task Name Duration Start Finish Predecessors Resource Names

519 13.11.1 Site grounding 6 days Mon 11/26/2Sat 12/1/29 515

520 13.11.2 Site lightning protection 6 days Mon 11/26/2Sat 12/1/29 515

521 13.12 Week 11 NAVFAC KTR 6 days Mon 11/26/2Sat 12/1/29

522 13.12.1 NAVFAC KTR demobilization 6 days Mon 11/26/2Sat 12/1/29 515

523 13.12.2 NAVFAC KTR destaging 6 days Mon 11/26/2Sat 12/1/29 515

524 13.13 Week 12 NAVSEA 6 days Mon 12/3/29Sat 12/8/29

525 13.13.1 Install solar panels 6 days Mon 12/3/29Sat 12/8/29 521

526 13.13.2 Install interior equipment 6 days Mon 12/3/29Sat 12/8/29 521

527 13.13.3 Install antennas and RF cabling 6 days Mon 12/3/29Sat 12/8/29 521

528 13.14 Week 13 NAVSEA 6 days Mon 12/10/2Sat 12/15/29

529 13.14.1 Install solar panels 6 days Mon 12/10/2Sat 12/15/29 524

530 13.14.2 Install interior equipment 6 days Mon 12/10/2Sat 12/15/29 524

531 13.14.3 Install antennas and RF cabling 6 days Mon 12/10/2Sat 12/15/29 524

532 13.15 Week 14 NAVSEA 6 days Mon 12/17/2Sat 12/22/29

533 13.15.1 Complete installations 6 days Mon 12/17/2Sat 12/22/29 528

534 13.15.2 LMR 6 days Mon 12/17/2Sat 12/22/29 528

535 13.16 Week 15 NAVSEA 6 days Mon 12/24/2Sat 12/29/29

536 13.16.1 Site tests 3 days Mon 12/24/2Wed 12/26/2532

537 13.16.2 System tests 3 days Thu 12/27/29Sat 12/29/29 536

538 13.17 Week 16 NAVSEA 6 days Mon 12/31/2Mon 1/7/30

539 13.17.1 Demobilization 6 days Mon 12/31/2Mon 1/7/30 535

540 13.17.2 Destaging 6 days Mon 12/31/2Mon 1/7/30 535

J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress