This file is a detailed Installation Project Schedule (IMS) showing planned activities for FY25 exercises and communication tower installations across multiple operating positions (OPs). The schedule spans from December 2025 through January 2030, broken down into detailed tasks and subtasks.
The schedule outlines work at multiple sites including OP Mesa, OP Mine, OP Galway, OP Argos, OP Creole, OP America Mine, OP Noble, and OP Boullion. For each site, the work is organized into approximately 16-week phases including NAVSEA initial work, NAVFAC contractor activities, and final NAVSEA installations. Key activities include demolition of existing equipment, foundation preparation, tower construction/repairs, shelter installation, solar panel installation, interior equipment installation, RF cabling, and system testing. The schedule also includes East Microwave updates occurring in multiple phases from December 2025 through May 2026, and several military exercises (IOC, ITX, EWTGPAC, MDMX, MWX) scheduled throughout 2025-2026. Most individual site installations are planned for 96-day durations with specific predecessor relationships defined between tasks.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Mode
WBS Task Name Duration Start Finish Predecessors Resource Names
1 1 FY25 Excercises 255 days Mon 12/1/25Thu 9/24/26
2 1.1 IOC 1‐25 13 days Mon 12/1/25Mon 12/15/2
4 1.3 ITX Event 45 days Thu 1/15/26 Sat 3/7/26
3 1.2 IOC 2‐25 6 days Thu 3/12/26 Wed 3/18/26
5 1.4 EWTGPAC 3‐26 4 days Mon 4/13/26Thu 4/16/26
7 1.6 EWTGPAC 4‐26 4 days Mon 5/18/26Thu 5/21/26
8 1.7 ITX 10 days Wed 6/3/26 Sat 6/13/26
9 1.8 EWTGPAC 5‐26 4 days Mon 6/29/26Thu 7/2/26
10 1.9 ITX 25 days Sun 7/12/26 Sat 8/8/26
11 1.10 MDMX 4 days Tue 8/11/26 Fri 8/14/26
12 1.11 MWX 6 days Mon 8/17/26Sat 8/22/26
13 1.12 ITX 9 days Thu 8/27/26 Sat 9/5/26
14 1.13 IOC 4‐25 5 days Fri 9/11/26 Wed 9/16/26
15 1.14 EWGTPAC 6‐26 4 days Mon 9/21/26Thu 9/24/26
6 1.5 <New Task>
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: P-1241 Installation Sch Date: Mon 12/2/24
WBS Task Name Duration Start Finish Predecessors Resource Names
16 2 East Microwave updates 122 days Thu 12/18/25Sat 5/9/26
17 2.1 NAVSEA Microwave Phase I 21 days Thu 12/18/25Mon 1/12/26
18 2.2 NAVSEA Microwave Phase II 6 days Mon 3/23/26Sat 3/28/26
19 2.3 NAVSEA Microwave Phase III 6 days Mon 4/27/26Sat 5/2/26
20 2.4 NAVSEA Microwave Phase IV 6 days Mon 5/4/26 Sat 5/9/26
21 3 Site Surveys 12 days Mon 4/27/26Sat 5/9/26
22 3.1 NAVFAC KTR Site Survey 6 days Mon 4/27/26Sat 5/2/26
23 3.2 NAVFAC KTR Site Survey 6 days Mon 5/4/26 Sat 5/9/26
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
24 4 OP Mesa 84 days Mon 9/14/26Sat 12/19/26
25 4.1 Week 0 NAVFAC KTR (no site work) 6 days Mon 9/14/26Sat 9/19/26
26 4.1.1 Staging for helo 6 days Mon 9/14/26Sat 9/19/26
27 4.2 Week 1 NAVFAC KTR 6 days Mon 9/21/26Sat 9/26/26
28 4.2.1 Mobilization to hilltop 6 days Mon 9/21/26Sat 9/26/26 26
29 4.3 Week 2 NAVFAC KTR 6 days Mon 9/28/26Sat 10/3/26
30 4.3.1 Foundation preperation 6 days Mon 9/28/26Sat 10/3/26 27
31 4.3.2 Earth moving 6 days Mon 9/28/26Sat 10/3/26 27
32 4.4 Week 3 NAVFAC KTR 6 days Mon 10/5/26Sat 10/10/26
33 4.4.1 Pour foundations 6 days Mon 10/5/26Sat 10/10/26 29
34 4.5 Week 4 NAVFAC KTR/NAVSEA 6 days Mon 10/12/2Sat 10/17/26
35 4.5.1 Shelter foundation cure time to 70%6 days Mon 10/12/2Sat 10/17/26 32
36 4.5.2 NAVFAC KTR work/tower prep 6 days Mon 10/12/2Sat 10/17/26 32
37 4.5.3 NAVSAEA staging for helo lift 6 days Mon 10/12/2Sat 10/17/26 32
38 4.6 Week 5 NAVSEA/NAVFAC KTR 6 days Mon 10/19/2Sat 10/24/26
39 4.6.1 NAVSEA Heavy lift helo 6 days Mon 10/19/2Sat 10/24/26 35
40 4.6.2 NAVSEA place sheters 6 days Mon 10/19/2Sat 10/24/26 35
41 4.6.3 NAVFAC KTR build tower sections 6 days Mon 10/19/2Sat 10/24/26 35
42 4.7 Week 6 NAVFAC KTR 6 days Mon 10/26/2Sat 10/31/26
43 4.7.1 Erect 140' tower on site 6 days Mon 10/26/2Sat 10/31/26 38
44 4.7.2 Tower: FAA lighting/lightning/groun6 days Mon 10/26/2Sat 10/31/26 38
45 4.8 Week 7 NAVFAC KTR 6 days Mon 11/2/26Sat 11/7/26
46 4.8.1 Ice bridge 6 days Mon 11/2/26Sat 11/7/26 42
47 4.8.2 Conduit 6 days Mon 11/2/26Sat 11/7/26 42
48 4.9 Week 8 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26
49 4.9.1 Site grounding 6 days Mon 11/9/26Sat 11/14/26 45
50 4.10 Week 9 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26
51 4.10.1 Demobilization 6 days Mon 11/9/26Sat 11/14/26 45
52 4.10.2 Destaging 6 days Mon 11/9/26Sat 11/14/26 45
53 4.11 Week 10 NAVSEA 6 days Mon 11/16/2Sat 11/21/26
54 4.11.1 Install solar panels 6 days Mon 11/16/2Sat 11/21/26 50
55 4.11.2 Install interior equipment 6 days Mon 11/16/2Sat 11/21/26 50
56 4.11.3 Install antennas and RF cabling 6 days Mon 11/16/2Sat 11/21/26 50
57 4.12 Week 11 NAVSEA 6 days Mon 11/23/2Sat 11/28/26
58 4.12.1 Install solar panels 6 days Mon 11/23/2Sat 11/28/26 53
59 4.12.2 Install interior equipment 6 days Mon 11/23/2Sat 11/28/26 53
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
60 4.12.3 Install antennas and RF cabling 6 days Mon 11/23/2Sat 11/28/26 53
61 4.13 Week 12 NAVSEA 6 days Mon 11/30/2Sat 12/5/26
62 4.13.1 Complete installations 6 days Mon 11/30/2Sat 12/5/26 57
63 4.13.2 LMR 6 days Mon 11/30/2Sat 12/5/26 57
64 4.14 Week 13 NAVSEA 6 days Mon 12/7/26Sat 12/12/26
65 4.14.1 Site tests 3 days Mon 12/7/26Wed 12/9/2661
66 4.14.2 System tests 3 days Thu 12/10/26Sat 12/12/26 65
67 4.15 Week 14 NAVSEA 6 days Mon 12/14/2Sat 12/19/26
68 4.15.1 Demobilization 6 days Mon 12/14/2Sat 12/19/26 64
69 4.15.2 Destaging 6 days Mon 12/14/2Sat 12/19/26 64
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
70 71 OP Mine 96 days Mon 9/14/26Mon 1/4/27
71 71.1 Week 0 NAVSEA (no site work) 6 days Mon 9/14/26Sat 9/19/26
72 71.1.1 Staging for helo 6 days Mon 9/14/26Sat 9/19/26
73 71.2 Week 1 NAVSEA 6 days Mon 9/21/26Sat 9/26/26
74 71.2.1 Demo/remove electronics 6 days Mon 9/21/26Sat 9/26/26 71
75 71.2.2 Demo/remove batteries 6 days Mon 9/21/26Sat 9/26/26 71
76 71.2.3 Demo/remove antennas and cables6 days Mon 9/21/26Sat 9/26/26 71
77 71.3 Week 2 NAVSEA 6 days Mon 9/28/26Sat 10/3/26
78 71.3.1 Demo/remove electronics 6 days Mon 9/28/26Sat 10/3/26 73
79 71.3.2 Demo/remove batteries 6 days Mon 9/28/26Sat 10/3/26 73
80 71.3.3 Demo/remove antennas and cables6 days Mon 9/28/26Sat 10/3/26 73
81 71.3.4 Demo/ready for demobilization LM1 day Mon 9/28/26Mon 9/28/2673
82 71.3.5 NAVFAC KTR Staging for helo 6 days Mon 9/28/26Sat 10/3/26 73
83 71.4 Week 3 NAVFAC KTR 6 days Mon 10/5/26Sat 10/10/26
84 71.4.1 Mobilization to hilltop 6 days Mon 10/5/26Sat 10/10/26 82
85 71.4.2 Demo/Remove two (2) Monopoles 6 days Mon 10/5/26Sat 10/10/26 82
86 71.4.3 Demo/Remove two (2) above groun6 days Mon 10/5/26Sat 10/10/26 82
87 71.4.4 Demo/Remove shelters 6 days Mon 10/5/26Sat 10/10/26 82
88 71.4.5 Demo/Remove solar 6 days Mon 10/5/26Sat 10/10/26 82
89 71.5 Week 4 NAVFAC KTR 6 days Mon 10/12/2Sat 10/17/26
90 71.5.1 Foundation Preperation 6 days Mon 10/12/2Sat 10/17/26 83
91 71.5.2 Earth moving 6 days Mon 10/12/2Sat 10/17/26 83
92 71.6 Week 5 NAVFAC KTR 6 days Mon 10/19/2Sat 10/24/26
93 71.6.1 Pour Foundations 6 days Mon 10/19/2Sat 10/24/26 89
94 71.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/26/2Sat 10/31/26
95 71.7.1 Shelter foundation cure to 70% 6 days Mon 10/26/2Sat 10/31/26 92
96 71.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/26/2Sat 10/31/26 92
97 71.7.3 NAVSAEA staging for helo lift 6 days Mon 10/26/2Sat 10/31/26 92
98 71.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 11/2/26Sat 11/7/26
99 71.8.1 NAVSEA Heavy lift helo 6 days Mon 11/2/26Sat 11/7/26 94
100 71.8.2 NAVSEA place sheters 6 days Mon 11/2/26Sat 11/7/26 94
101 71.8.3 NAVFAC KTR build tower sections 6 days Mon 11/2/26Sat 11/7/26 94
102 71.9 Week 8 NAVFAC KTR 6 days Mon 11/9/26Sat 11/14/26
103 71.9.1 Erect 140' tower on site 6 days Mon 11/9/26Sat 11/14/26 98
104 71.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/9/26Sat 11/14/26 98
105 71.10 Week 9 NAVFAC KTR 6 days Mon 11/16/2Sat 11/21/26
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
106 71.10.1 Ice bridge 6 days Mon 11/16/2Sat 11/21/26 102
107 71.10.2 Conduit 6 days Mon 11/16/2Sat 11/21/26 102
108 71.11 Week 10 NAVFAC KTR 6 days Mon 11/23/2Sat 11/28/26
109 71.11.1 Site grounding 6 days Mon 11/23/2Sat 11/28/26 105
110 71.12 Week 11 NAVFAC KTR 6 days Mon 11/23/2Sat 11/28/26
111 71.12.1 NAVFAC KTR demobilization 6 days Mon 11/23/2Sat 11/28/26 105
112 71.12.2 NAVFAC KTR destaging 6 days Mon 11/23/2Sat 11/28/26 105
113 71.13 Week 12 NAVSEA 6 days Mon 11/30/2Sat 12/5/26
114 71.13.1 Install solar panels 6 days Mon 11/30/2Sat 12/5/26 110
115 71.13.2 Install interior equipment 6 days Mon 11/30/2Sat 12/5/26 110
116 71.13.3 Install antennas and RF cabling 6 days Mon 11/30/2Sat 12/5/26 110
117 71.14 Week 13 NAVSEA 6 days Mon 12/7/26Sat 12/12/26
118 71.14.1 Install solar panels 6 days Mon 12/7/26Sat 12/12/26 113
119 71.14.2 Install interior equipment 6 days Mon 12/7/26Sat 12/12/26 113
120 71.14.3 Install antennas and RF cabling 6 days Mon 12/7/26Sat 12/12/26 113
121 71.15 Week 14 NAVSEA 6 days Mon 12/14/2Sat 12/19/26
122 71.15.1 Complete installations 6 days Mon 12/14/2Sat 12/19/26 117
123 71.15.2 LMR 6 days Mon 12/14/2Sat 12/19/26 117
124 71.16 Week 15 NAVSEA 6 days Mon 12/21/2Sat 12/26/26
125 71.16.1 Site tests 3 days Mon 12/21/2Wed 12/23/2121
126 71.16.2 System tests 3 days Thu 12/24/26Sat 12/26/26 125
127 71.17 Week 16 NAVSEA 6 days Mon 12/28/2Mon 1/4/27
128 71.17.1 Demobilization 6 days Mon 12/28/2Mon 1/4/27 124
129 71.17.2 Destaging 6 days Mon 12/28/2Mon 1/4/27 124
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
130 6 OP Galway 96 days Mon 2/15/27Sat 6/5/27
131 6.1 Week 0 NAVSEA (no site work) 6 days Mon 2/15/27Sat 2/20/27
132 6.1.1 Staging for helo 6 days Mon 2/15/27Sat 2/20/27
133 6.2 Week 1 NAVSEA 6 days Mon 2/22/27Sat 2/27/27
134 6.2.1 Demo/remove electronics 6 days Mon 2/22/27Sat 2/27/27 131
135 6.2.2 Demo/remove batteries 6 days Mon 2/22/27Sat 2/27/27 131
136 6.2.3 Demo/remove antennas and cables6 days Mon 2/22/27Sat 2/27/27 131
137 6.3 Week 2 NAVSEA 6 days Mon 3/1/27 Sat 3/6/27
138 6.3.1 Demo/remove electronics 6 days Mon 3/1/27 Sat 3/6/27 133
139 6.3.2 Demo/remove batteries 6 days Mon 3/1/27 Sat 3/6/27 133
140 6.3.3 Demo/remove antennas and cables6 days Mon 3/1/27 Sat 3/6/27 133
141 6.3.4 Demo/ready for demobilization LM1 day Mon 3/1/27 Mon 3/1/27 133
142 6.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/1/27 Sat 3/6/27 133
143 6.4 Week 3 NAVFAC KTR 6 days Mon 3/8/27 Sat 3/13/27
144 6.4.1 Mobilization to hilltop 6 days Mon 3/8/27 Sat 3/13/27 142
145 6.4.2 Demo/Remove two (2) Monopoles 6 days Mon 3/8/27 Sat 3/13/27 142
146 6.4.3 Demo/Remove two (2) above groun6 days Mon 3/8/27 Sat 3/13/27 142
147 6.4.4 Demo/Remove shelters 6 days Mon 3/8/27 Sat 3/13/27 142
148 6.4.5 Demo/Remove solar 6 days Mon 3/8/27 Sat 3/13/27 142
149 6.5 Week 4 NAVFAC KTR 6 days Mon 3/15/27Sat 3/20/27
150 6.5.1 Foundation Preperation 6 days Mon 3/15/27Sat 3/20/27 143
151 6.5.2 Earth moving 6 days Mon 3/15/27Sat 3/20/27 143
152 6.6 Week 5 NAVFAC KTR 6 days Mon 3/22/27Sat 3/27/27
153 6.6.1 Pour Foundations 6 days Mon 3/22/27Sat 3/27/27 149
154 6.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 3/29/27Sat 4/3/27
155 6.7.1 Shelter foundation cure to 70% 6 days Mon 3/29/27Sat 4/3/27 152
156 6.7.2 NAVFAC KTR work/tower prep 6 days Mon 3/29/27Sat 4/3/27 152
157 6.7.3 NAVSAEA staging for helo lift 6 days Mon 3/29/27Sat 4/3/27 152
158 6.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 4/5/27 Sat 4/10/27
159 6.8.1 NAVSEA Heavy lift helo 6 days Mon 4/5/27 Sat 4/10/27 154
160 6.8.2 NAVSEA place sheters 6 days Mon 4/5/27 Sat 4/10/27 154
161 6.8.3 NAVFAC KTR build tower sections 6 days Mon 4/5/27 Sat 4/10/27 154
162 6.9 Week 8 NAVFAC KTR 6 days Mon 4/12/27Sat 4/17/27
163 6.9.1 Erect 140' tower on site 6 days Mon 4/12/27Sat 4/17/27 158
164 6.9.2 Tower: FAA lighting/lightning/groun6 days Mon 4/12/27Sat 4/17/27 158
165 6.10 Week 9 NAVFAC KTR 6 days Mon 4/19/27Sat 4/24/27
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
166 6.10.1 Ice bridge 6 days Mon 4/19/27Sat 4/24/27 162
167 6.10.2 Conduit 6 days Mon 4/19/27Sat 4/24/27 162
168 6.11 Week 10 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27
169 6.11.1 Site grounding 6 days Mon 4/26/27Sat 5/1/27 165
170 6.12 Week 11 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27
171 6.12.1 NAVFAC KTR demobilization 6 days Mon 4/26/27Sat 5/1/27 165
172 6.12.2 NAVFAC KTR destaging 6 days Mon 4/26/27Sat 5/1/27 165
173 6.13 Week 12 NAVSEA 6 days Mon 5/3/27 Sat 5/8/27
174 6.13.1 Install solar panels 6 days Mon 5/3/27 Sat 5/8/27 170
175 6.13.2 Install interior equipment 6 days Mon 5/3/27 Sat 5/8/27 170
176 6.13.3 Install antennas and RF cabling 6 days Mon 5/3/27 Sat 5/8/27 170
177 6.14 Week 13 NAVSEA 6 days Mon 5/10/27Sat 5/15/27
178 6.14.1 Install solar panels 6 days Mon 5/10/27Sat 5/15/27 173
179 6.14.2 Install interior equipment 6 days Mon 5/10/27Sat 5/15/27 173
180 6.14.3 Install antennas and RF cabling 6 days Mon 5/10/27Sat 5/15/27 173
181 6.15 Week 14 NAVSEA 6 days Mon 5/17/27Sat 5/22/27
182 6.15.1 Complete installations 6 days Mon 5/17/27Sat 5/22/27 177
183 6.15.2 LMR 6 days Mon 5/17/27Sat 5/22/27 177
184 6.16 Week 15 NAVSEA 6 days Mon 5/24/27Sat 5/29/27
185 6.16.1 Site tests 3 days Mon 5/24/27Wed 5/26/27181
186 6.16.2 System tests 3 days Thu 5/27/27 Sat 5/29/27 185
187 6.17 Week 16 NAVSEA 6 days Mon 5/31/27Sat 6/5/27
188 6.17.1 Demobilization 6 days Mon 5/31/27Sat 6/5/27 184
189 6.17.2 Destaging 6 days Mon 5/31/27Sat 6/5/27 184
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
190 7 OP Argos 96 days Mon 2/15/27Sat 6/5/27
191 7.1 Week 0 NAVSEA (no site work) 6 days Mon 2/15/27Sat 2/20/27
192 7.1.1 Staging for helo 6 days Mon 2/15/27Sat 2/20/27
193 7.2 Week 1 NAVSEA 6 days Mon 2/22/27Sat 2/27/27
194 7.2.1 Demo/remove electronics 6 days Mon 2/22/27Sat 2/27/27 191
195 7.2.2 Demo/remove batteries 6 days Mon 2/22/27Sat 2/27/27 191
196 7.2.3 Demo/remove antennas and cables6 days Mon 2/22/27Sat 2/27/27 191
197 7.3 Week 2 NAVSEA 6 days Mon 3/1/27 Sat 3/6/27
198 7.3.1 Demo/remove electronics 6 days Mon 3/1/27 Sat 3/6/27 193
199 7.3.2 Demo/remove batteries 6 days Mon 3/1/27 Sat 3/6/27 193
200 7.3.3 Demo/remove antennas and cables6 days Mon 3/1/27 Sat 3/6/27 193
201 7.3.4 Demo/ready for demobilization LM1 day Mon 3/1/27 Mon 3/1/27 193
202 7.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/1/27 Sat 3/6/27 193
203 7.4 Week 3 NAVFAC KTR 6 days Mon 3/8/27 Sat 3/13/27
204 7.4.1 Mobilization to hilltop 6 days Mon 3/8/27 Sat 3/13/27 202
205 7.4.2 Demo/Remove shelters 6 days Mon 3/8/27 Sat 3/13/27 202
206 7.4.3 Demo/Remove solar 6 days Mon 3/8/27 Sat 3/13/27 202
207 7.5 Week 4 NAVFAC KTR 6 days Mon 3/15/27Sat 3/20/27
208 7.5.1 Foundation Preperation 6 days Mon 3/15/27Sat 3/20/27 203
209 7.5.2 Earth moving 6 days Mon 3/15/27Sat 3/20/27 203
210 7.6 Week 5 NAVFAC KTR 6 days Mon 3/22/27Sat 3/27/27
211 7.6.1 Pour Foundations 6 days Mon 3/22/27Sat 3/27/27 207
212 7.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 3/29/27Sat 4/3/27
213 7.7.1 Shelter foundation cure to 70% 6 days Mon 3/29/27Sat 4/3/27 210
214 7.7.2 NAVFAC KTR work/tower prep 6 days Mon 3/29/27Sat 4/3/27 210
215 7.7.3 NAVSAEA staging for helo lift 6 days Mon 3/29/27Sat 4/3/27 210
216 7.8 Week 7 NAVSEA 6 days Mon 4/5/27 Sat 4/10/27
217 7.8.1 NAVSEA Heavy lift helo 6 days Mon 4/5/27 Sat 4/10/27 212
218 7.8.2 NAVSEA place sheters 6 days Mon 4/5/27 Sat 4/10/27 212
219 7.9 Week 8 NAVFAC KTR 6 days Mon 4/12/27Sat 4/17/27
220 7.9.1 Complete tower repairs 6 days Mon 4/12/27Sat 4/17/27 216
221 7.9.2 Tower: FAA lighting/lightning/groun6 days Mon 4/12/27Sat 4/17/27 216
222 7.10 Week 9 NAVFAC KTR 6 days Mon 4/19/27Sat 4/24/27
223 7.10.1 Ice bridge 6 days Mon 4/19/27Sat 4/24/27 219
224 7.10.2 Conduit 6 days Mon 4/19/27Sat 4/24/27 219
225 7.11 Week 10 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
226 7.11.1 Site grounding 6 days Mon 4/26/27Sat 5/1/27 222
227 7.11.2 Site lightning protection 6 days Mon 4/26/27Sat 5/1/27 222
228 7.12 Week 11 NAVFAC KTR 6 days Mon 4/26/27Sat 5/1/27
229 7.12.1 NAVFAC KTR demobilization 6 days Mon 4/26/27Sat 5/1/27 222
230 7.12.2 NAVFAC KTR destaging 6 days Mon 4/26/27Sat 5/1/27 222
231 7.13 Week 12 NAVSEA 6 days Mon 5/3/27 Sat 5/8/27
232 7.13.1 Install solar panels 6 days Mon 5/3/27 Sat 5/8/27 228
233 7.13.2 Install interior equipment 6 days Mon 5/3/27 Sat 5/8/27 228
234 7.13.3 Install antennas and RF cabling 6 days Mon 5/3/27 Sat 5/8/27 228
235 7.14 Week 13 NAVSEA 6 days Mon 5/10/27Sat 5/15/27
236 7.14.1 Install solar panels 6 days Mon 5/10/27Sat 5/15/27 231
237 7.14.2 Install interior equipment 6 days Mon 5/10/27Sat 5/15/27 231
238 7.14.3 Install antennas and RF cabling 6 days Mon 5/10/27Sat 5/15/27 231
239 7.15 Week 14 NAVSEA 6 days Mon 5/17/27Sat 5/22/27
240 7.15.1 Complete installations 6 days Mon 5/17/27Sat 5/22/27 235
241 7.15.2 LMR 6 days Mon 5/17/27Sat 5/22/27 235
242 7.16 Week 15 NAVSEA 6 days Mon 5/24/27Sat 5/29/27
243 7.16.1 Site tests 3 days Mon 5/24/27Wed 5/26/27239
244 7.16.2 System tests 3 days Thu 5/27/27 Sat 5/29/27 243
245 7.17 Week 16 NAVSEA 6 days Mon 5/31/27Sat 6/5/27
246 7.17.1 Demobilization 6 days Mon 5/31/27Sat 6/5/27 242
247 7.17.2 Destaging 6 days Mon 5/31/27Sat 6/5/27 242
248 8 Complete Microwave 6 days Mon 6/7/27 Sat 6/12/27 245
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
249 9 OP Creole 96 days Mon 9/20/27Mon 1/10/28
250 9.1 Week 0 NAVSEA (no site work) 6 days Mon 9/20/27Sat 9/25/27
251 9.1.1 Staging for helo 6 days Mon 9/20/27Sat 9/25/27
252 9.2 Week 1 NAVSEA 6 days Mon 9/27/27Sat 10/2/27
253 9.2.1 Demo/remove electronics 6 days Mon 9/27/27Sat 10/2/27 250
254 9.2.2 Demo/remove batteries 6 days Mon 9/27/27Sat 10/2/27 250
255 9.2.3 Demo/remove antennas and cables6 days Mon 9/27/27Sat 10/2/27 250
256 9.3 Week 2 NAVSEA 6 days Mon 10/4/27Sat 10/9/27
257 9.3.1 Demo/remove electronics 6 days Mon 10/4/27Sat 10/9/27 252
258 9.3.2 Demo/remove batteries 6 days Mon 10/4/27Sat 10/9/27 252
259 9.3.3 Demo/remove antennas and cables6 days Mon 10/4/27Sat 10/9/27 252
260 9.3.4 Demo/ready for demobilization LM1 day Mon 10/4/27Mon 10/4/27252
261 9.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/4/27Sat 10/9/27 252
262 9.4 Week 3 NAVFAC KTR 6 days Mon 10/11/2Sat 10/16/27
263 9.4.1 Mobilization to hilltop 6 days Mon 10/11/2Sat 10/16/27 261
264 9.4.2 Demo/Remove shelters 6 days Mon 10/11/2Sat 10/16/27 261
265 9.4.3 Demo/Remove solar 6 days Mon 10/11/2Sat 10/16/27 261
266 9.5 Week 4 NAVFAC KTR 6 days Mon 10/18/2Sat 10/23/27
267 9.5.1 Foundation Preperation 6 days Mon 10/18/2Sat 10/23/27 262
268 9.5.2 Earth moving 6 days Mon 10/18/2Sat 10/23/27 262
269 9.6 Week 5 NAVFAC KTR 6 days Mon 10/25/2Sat 10/30/27
270 9.6.1 Pour Foundations 6 days Mon 10/25/2Sat 10/30/27 266
271 9.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 11/1/27Sat 11/6/27
272 9.7.1 Shelter foundation cure to 70% 6 days Mon 11/1/27Sat 11/6/27 269
273 9.7.2 NAVFAC KTR work/tower prep 6 days Mon 11/1/27Sat 11/6/27 269
274 9.7.3 NAVSAEA staging for helo lift 6 days Mon 11/1/27Sat 11/6/27 269
275 9.8 Week 7 NAVSEA 6 days Mon 11/8/27Sat 11/13/27
276 9.8.1 NAVSEA Heavy lift helo 6 days Mon 11/8/27Sat 11/13/27 271
277 9.8.2 NAVSEA place sheters 6 days Mon 11/8/27Sat 11/13/27 271
278 9.9 Week 8 NAVFAC KTR 6 days Mon 11/15/2Sat 11/20/27
279 9.9.1 Complete tower repairs 6 days Mon 11/15/2Sat 11/20/27 275
280 9.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/15/2Sat 11/20/27 275
281 9.10 Week 9 NAVFAC KTR 6 days Mon 11/22/2Sat 11/27/27
282 9.10.1 Ice bridge 6 days Mon 11/22/2Sat 11/27/27 278
283 9.10.2 Conduit 6 days Mon 11/22/2Sat 11/27/27 278
284 9.11 Week 10 NAVFAC KTR 6 days Mon 11/29/2Sat 12/4/27
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
285 9.11.1 Site grounding 6 days Mon 11/29/2Sat 12/4/27 281
286 9.11.2 Site lightning protection 6 days Mon 11/29/2Sat 12/4/27 281
287 9.12 Week 11 NAVFAC KTR 6 days Mon 11/29/2Sat 12/4/27
288 9.12.1 NAVFAC KTR demobilization 6 days Mon 11/29/2Sat 12/4/27 281
289 9.12.2 NAVFAC KTR destaging 6 days Mon 11/29/2Sat 12/4/27 281
290 9.13 Week 12 NAVSEA 6 days Mon 12/6/27Sat 12/11/27
291 9.13.1 Install solar panels 6 days Mon 12/6/27Sat 12/11/27 287
292 9.13.2 Install interior equipment 6 days Mon 12/6/27Sat 12/11/27 287
293 9.13.3 Install antennas and RF cabling 6 days Mon 12/6/27Sat 12/11/27 287
294 9.14 Week 13 NAVSEA 6 days Mon 12/13/2Sat 12/18/27
295 9.14.1 Install solar panels 6 days Mon 12/13/2Sat 12/18/27 290
296 9.14.2 Install interior equipment 6 days Mon 12/13/2Sat 12/18/27 290
297 9.14.3 Install antennas and RF cabling 6 days Mon 12/13/2Sat 12/18/27 290
298 9.15 Week 14 NAVSEA 6 days Mon 12/20/2Sat 12/25/27
299 9.15.1 Complete installations 6 days Mon 12/20/2Sat 12/25/27 294
300 9.15.2 LMR 6 days Mon 12/20/2Sat 12/25/27 294
301 9.16 Week 15 NAVSEA 6 days Mon 12/27/2Mon 1/3/28
302 9.16.1 Site tests 3 days Mon 12/27/2Wed 12/29/2298
303 9.16.2 System tests 3 days Thu 12/30/27Mon 1/3/28 302
304 9.17 Week 16 NAVSEA 6 days Tue 1/4/28 Mon 1/10/28
305 9.17.1 Demobilization 6 days Tue 1/4/28 Mon 1/10/28301
306 9.17.2 Destaging 6 days Tue 1/4/28 Mon 1/10/28301
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
307 10 OP Crampton 96 days Mon 3/13/28Sat 7/1/28
308 10.1 Week 0 NAVSEA (no site work) 6 days Mon 3/13/28Sat 3/18/28
309 10.1.1 Staging for helo 6 days Mon 3/13/28Sat 3/18/28
310 10.2 Week 1 NAVSEA 6 days Mon 3/20/28Sat 3/25/28
311 10.2.1 Demo/remove electronics 6 days Mon 3/20/28Sat 3/25/28 308
312 10.2.2 Demo/remove batteries 6 days Mon 3/20/28Sat 3/25/28 308
313 10.2.3 Demo/remove antennas and cables6 days Mon 3/20/28Sat 3/25/28 308
314 10.3 Week 2 NAVSEA 6 days Mon 3/27/28Sat 4/1/28
315 10.3.1 Demo/remove electronics 6 days Mon 3/27/28Sat 4/1/28 310
316 10.3.2 Demo/remove batteries 6 days Mon 3/27/28Sat 4/1/28 310
317 10.3.3 Demo/remove antennas and cables6 days Mon 3/27/28Sat 4/1/28 310
318 10.3.4 Demo/ready for demobilization LM1 day Mon 3/27/28Mon 3/27/28310
319 10.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/27/28Sat 4/1/28 310
320 10.4 Week 3 NAVFAC KTR 6 days Mon 4/3/28 Sat 4/8/28
321 10.4.1 Mobilization to hilltop 6 days Mon 4/3/28 Sat 4/8/28 319
322 10.4.2 Demo/Remove shelters 6 days Mon 4/3/28 Sat 4/8/28 319
323 10.4.3 Demo/Remove solar 6 days Mon 4/3/28 Sat 4/8/28 319
324 10.5 Week 4 NAVFAC KTR 6 days Mon 4/10/28Sat 4/15/28
325 10.5.1 Foundation Preperation 6 days Mon 4/10/28Sat 4/15/28 320
326 10.5.2 Earth moving 6 days Mon 4/10/28Sat 4/15/28 320
327 10.6 Week 5 NAVFAC KTR 6 days Mon 4/17/28Sat 4/22/28
328 10.6.1 Pour Foundations 6 days Mon 4/17/28Sat 4/22/28 324
329 10.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 4/24/28Sat 4/29/28
330 10.7.1 Shelter foundation cure to 70% 6 days Mon 4/24/28Sat 4/29/28 327
331 10.7.2 NAVFAC KTR work/tower prep 6 days Mon 4/24/28Sat 4/29/28 327
332 10.7.3 NAVSAEA staging for helo lift 6 days Mon 4/24/28Sat 4/29/28 327
333 10.8 Week 7 NAVSEA 6 days Mon 5/1/28 Sat 5/6/28
334 10.8.1 NAVSEA Heavy lift helo 6 days Mon 5/1/28 Sat 5/6/28 329
335 10.8.2 NAVSEA place sheters 6 days Mon 5/1/28 Sat 5/6/28 329
336 10.9 Week 8 NAVFAC KTR 6 days Mon 5/8/28 Sat 5/13/28
337 10.9.1 Complete tower repairs 6 days Mon 5/8/28 Sat 5/13/28 333
338 10.9.2 Tower: FAA lighting/lightning/groun6 days Mon 5/8/28 Sat 5/13/28 333
339 10.10 Week 9 NAVFAC KTR 6 days Mon 5/15/28Sat 5/20/28
340 10.10.1 Ice bridge 6 days Mon 5/15/28Sat 5/20/28 336
341 10.10.2 Conduit 6 days Mon 5/15/28Sat 5/20/28 336
342 10.11 Week 10 NAVFAC KTR 6 days Mon 5/22/28Sat 5/27/28
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
343 10.11.1 Site grounding 6 days Mon 5/22/28Sat 5/27/28 339
344 10.11.2 Site lightning protection 6 days Mon 5/22/28Sat 5/27/28 339
345 10.12 Week 11 NAVFAC KTR 6 days Mon 5/22/28Sat 5/27/28
346 10.12.1 NAVFAC KTR demobilization 6 days Mon 5/22/28Sat 5/27/28 339
347 10.12.2 NAVFAC KTR destaging 6 days Mon 5/22/28Sat 5/27/28 339
348 10.13 Week 12 NAVSEA 6 days Mon 5/29/28Sat 6/3/28
349 10.13.1 Install solar panels 6 days Mon 5/29/28Sat 6/3/28 345
350 10.13.2 Install interior equipment 6 days Mon 5/29/28Sat 6/3/28 345
351 10.13.3 Install antennas and RF cabling 6 days Mon 5/29/28Sat 6/3/28 345
352 10.14 Week 13 NAVSEA 6 days Mon 6/5/28 Sat 6/10/28
353 10.14.1 Install solar panels 6 days Mon 6/5/28 Sat 6/10/28 348
354 10.14.2 Install interior equipment 6 days Mon 6/5/28 Sat 6/10/28 348
355 10.14.3 Install antennas and RF cabling 6 days Mon 6/5/28 Sat 6/10/28 348
356 10.15 Week 14 NAVSEA 6 days Mon 6/12/28Sat 6/17/28
357 10.15.1 Complete installations 6 days Mon 6/12/28Sat 6/17/28 352
358 10.15.2 LMR 6 days Mon 6/12/28Sat 6/17/28 352
359 10.16 Week 15 NAVSEA 6 days Mon 6/19/28Sat 6/24/28
360 10.16.1 Site tests 3 days Mon 6/19/28Wed 6/21/28356
361 10.16.2 System tests 3 days Thu 6/22/28 Sat 6/24/28 360
362 10.17 Week 16 NAVSEA 6 days Mon 6/26/28Sat 7/1/28
363 10.17.1 Demobilization 6 days Mon 6/26/28Sat 7/1/28 359
364 10.17.2 Destaging 6 days Mon 6/26/28Sat 7/1/28 359
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
365 11 OP America Mine 96 days Mon 9/18/28Mon 1/8/29
366 11.1 Week 0 NAVSEA (no site work) 6 days Mon 9/18/28Sat 9/23/28
367 11.1.1 Staging for helo 6 days Mon 9/18/28Sat 9/23/28
368 11.2 Week 1 NAVSEA 6 days Mon 9/25/28Sat 9/30/28
369 11.2.1 Demo/remove electronics 6 days Mon 9/25/28Sat 9/30/28 366
370 11.2.2 Demo/remove batteries 6 days Mon 9/25/28Sat 9/30/28 366
371 11.2.3 Demo/remove antennas and cables6 days Mon 9/25/28Sat 9/30/28 366
372 11.3 Week 2 NAVSEA 6 days Mon 10/2/28Sat 10/7/28
373 11.3.1 Demo/remove electronics 6 days Mon 10/2/28Sat 10/7/28 368
374 11.3.2 Demo/remove batteries 6 days Mon 10/2/28Sat 10/7/28 368
375 11.3.3 Demo/remove antennas and cables6 days Mon 10/2/28Sat 10/7/28 368
376 11.3.4 Demo/ready for demobilization LM1 day Mon 10/2/28Mon 10/2/28368
377 11.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/2/28Sat 10/7/28 368
378 11.4 Week 3 NAVFAC KTR 6 days Mon 10/9/28Sat 10/14/28
379 11.4.1 Mobilization to hilltop 6 days Mon 10/9/28Sat 10/14/28 377
380 11.4.2 Demo/Remove 40' tower 6 days Mon 10/9/28Sat 10/14/28 377
381 11.4.3 Demo/Remove below ground found6 days Mon 10/9/28Sat 10/14/28 377
382 11.4.4 Demo/Remove shelters 6 days Mon 10/9/28Sat 10/14/28 377
383 11.4.5 Demo/Remove solar 6 days Mon 10/9/28Sat 10/14/28 377
384 11.5 Week 4 NAVFAC KTR 6 days Mon 10/16/2Sat 10/21/28
385 11.5.1 Foundation Preperation 6 days Mon 10/16/2Sat 10/21/28 378
386 11.5.2 Earth moving 6 days Mon 10/16/2Sat 10/21/28 378
387 11.6 Week 5 NAVFAC KTR 6 days Mon 10/23/2Sat 10/28/28
388 11.6.1 Pour Foundations 6 days Mon 10/23/2Sat 10/28/28 384
389 11.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/30/2Sat 11/4/28
390 11.7.1 Shelter foundation cure to 70% 6 days Mon 10/30/2Sat 11/4/28 387
391 11.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/30/2Sat 11/4/28 387
392 11.7.3 NAVSAEA staging for helo lift 6 days Mon 10/30/2Sat 11/4/28 387
393 11.8 Week 7 NAVSEA/NAVFAC KTR 6 days Mon 11/6/28Sat 11/11/28
394 11.8.1 NAVSEA Heavy lift helo 6 days Mon 11/6/28Sat 11/11/28 389
395 11.8.2 NAVSEA place sheters 6 days Mon 11/6/28Sat 11/11/28 389
396 11.8.3 NAVFAC KTR build tower sections 6 days Mon 11/6/28Sat 11/11/28 389
397 11.9 Week 8 NAVFAC KTR 6 days Mon 11/13/2Sat 11/18/28
398 11.9.1 Erect 140' tower on site 6 days Mon 11/13/2Sat 11/18/28 393
399 11.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/13/2Sat 11/18/28 393
400 11.10 Week 9 NAVFAC KTR 6 days Mon 11/20/2Sat 11/25/28
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
401 11.10.1 Ice bridge 6 days Mon 11/20/2Sat 11/25/28 397
402 11.10.2 Conduit 6 days Mon 11/20/2Sat 11/25/28 397
403 11.11 Week 10 NAVFAC KTR 6 days Mon 11/27/2Sat 12/2/28
404 11.11.1 Site grounding 6 days Mon 11/27/2Sat 12/2/28 400
405 11.12 Week 11 NAVFAC KTR 6 days Mon 11/27/2Sat 12/2/28
406 11.12.1 NAVFAC KTR demobilization 6 days Mon 11/27/2Sat 12/2/28 400
407 11.12.2 NAVFAC KTR destaging 6 days Mon 11/27/2Sat 12/2/28 400
408 11.13 Week 12 NAVSEA 6 days Mon 12/4/28Sat 12/9/28
409 11.13.1 Install solar panels 6 days Mon 12/4/28Sat 12/9/28 405
410 11.13.2 Install interior equipment 6 days Mon 12/4/28Sat 12/9/28 405
411 11.13.3 Install antennas and RF cabling 6 days Mon 12/4/28Sat 12/9/28 405
412 11.14 Week 13 NAVSEA 6 days Mon 12/11/2Sat 12/16/28
413 11.14.1 Install solar panels 6 days Mon 12/11/2Sat 12/16/28 408
414 11.14.2 Install interior equipment 6 days Mon 12/11/2Sat 12/16/28 408
415 11.14.3 Install antennas and RF cabling 6 days Mon 12/11/2Sat 12/16/28 408
416 11.15 Week 14 NAVSEA 6 days Mon 12/18/2Sat 12/23/28
417 11.15.1 Complete installations 6 days Mon 12/18/2Sat 12/23/28 412
418 11.15.2 LMR 6 days Mon 12/18/2Sat 12/23/28 412
419 11.16 Week 15 NAVSEA 6 days Mon 12/25/2Sat 12/30/28
420 11.16.1 Site tests 3 days Mon 12/25/2Wed 12/27/2416
421 11.16.2 System tests 3 days Thu 12/28/28Sat 12/30/28 420
422 11.17 Week 16 NAVSEA 6 days Tue 1/2/29 Mon 1/8/29
423 11.17.1 Demobilization 6 days Tue 1/2/29 Mon 1/8/29 419
424 11.17.2 Destaging 6 days Tue 1/2/29 Mon 1/8/29 419
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
425 12 OP Noble 96 days Mon 3/12/29Sat 6/30/29
426 12.1 Week 0 NAVSEA (no site work) 6 days Mon 3/12/29Sat 3/17/29
427 12.1.1 Staging for helo 6 days Mon 3/12/29Sat 3/17/29
428 12.2 Week 1 NAVSEA 6 days Mon 3/19/29Sat 3/24/29
429 12.2.1 Demo/remove electronics 6 days Mon 3/19/29Sat 3/24/29 426
430 12.2.2 Demo/remove batteries 6 days Mon 3/19/29Sat 3/24/29 426
431 12.2.3 Demo/remove antennas and cables6 days Mon 3/19/29Sat 3/24/29 426
432 12.3 Week 2 NAVSEA 6 days Mon 3/26/29Sat 3/31/29
433 12.3.1 Demo/remove electronics 6 days Mon 3/26/29Sat 3/31/29 428
434 12.3.2 Demo/remove batteries 6 days Mon 3/26/29Sat 3/31/29 428
435 12.3.3 Demo/remove antennas and cables6 days Mon 3/26/29Sat 3/31/29 428
436 12.3.4 Demo/ready for demobilization LM1 day Mon 3/26/29Mon 3/26/29428
437 12.3.5 NAVFAC KTR Staging for helo 6 days Mon 3/26/29Sat 3/31/29 428
438 12.4 Week 3 NAVFAC KTR 6 days Mon 4/2/29 Sat 4/7/29
439 12.4.1 Mobilization to hilltop 6 days Mon 4/2/29 Sat 4/7/29 437
440 12.4.2 Demo/Remove shelters 6 days Mon 4/2/29 Sat 4/7/29 437
441 12.4.3 Demo/Remove solar 6 days Mon 4/2/29 Sat 4/7/29 437
442 12.5 Week 4 NAVFAC KTR 6 days Mon 4/9/29 Sat 4/14/29
443 12.5.1 Foundation Preperation 6 days Mon 4/9/29 Sat 4/14/29 438
444 12.5.2 Earth moving 6 days Mon 4/9/29 Sat 4/14/29 438
445 12.6 Week 5 NAVFAC KTR 6 days Mon 4/16/29Sat 4/21/29
446 12.6.1 Pour Foundations 6 days Mon 4/16/29Sat 4/21/29 442
447 12.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 4/23/29Sat 4/28/29
448 12.7.1 Shelter foundation cure to 70% 6 days Mon 4/23/29Sat 4/28/29 445
449 12.7.2 NAVFAC KTR work/tower prep 6 days Mon 4/23/29Sat 4/28/29 445
450 12.7.3 NAVSAEA staging for helo lift 6 days Mon 4/23/29Sat 4/28/29 445
451 12.8 Week 7 NAVSEA 6 days Mon 4/30/29Sat 5/5/29
452 12.8.1 NAVSEA Heavy lift helo 6 days Mon 4/30/29Sat 5/5/29 447
453 12.8.2 NAVSEA place sheters 6 days Mon 4/30/29Sat 5/5/29 447
454 12.9 Week 8 NAVFAC KTR 6 days Mon 5/7/29 Sat 5/12/29
455 12.9.1 Complete tower repairs 6 days Mon 5/7/29 Sat 5/12/29 451
456 12.9.2 Tower: FAA lighting/lightning/groun6 days Mon 5/7/29 Sat 5/12/29 451
457 12.10 Week 9 NAVFAC KTR 6 days Mon 5/14/29Sat 5/19/29
458 12.10.1 Ice bridge 6 days Mon 5/14/29Sat 5/19/29 454
459 12.10.2 Conduit 6 days Mon 5/14/29Sat 5/19/29 454
460 12.11 Week 10 NAVFAC KTR 6 days Mon 5/21/29Sat 5/26/29
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
461 12.11.1 Site grounding 6 days Mon 5/21/29Sat 5/26/29 457
462 12.11.2 Site lightning protection 6 days Mon 5/21/29Sat 5/26/29 457
463 12.12 Week 11 NAVFAC KTR 6 days Mon 5/21/29Sat 5/26/29
464 12.12.1 NAVFAC KTR demobilization 6 days Mon 5/21/29Sat 5/26/29 457
465 12.12.2 NAVFAC KTR destaging 6 days Mon 5/21/29Sat 5/26/29 457
466 12.13 Week 12 NAVSEA 6 days Mon 5/28/29Sat 6/2/29
467 12.13.1 Install solar panels 6 days Mon 5/28/29Sat 6/2/29 463
468 12.13.2 Install interior equipment 6 days Mon 5/28/29Sat 6/2/29 463
469 12.13.3 Install antennas and RF cabling 6 days Mon 5/28/29Sat 6/2/29 463
470 12.14 Week 13 NAVSEA 6 days Mon 6/4/29 Sat 6/9/29
471 12.14.1 Install solar panels 6 days Mon 6/4/29 Sat 6/9/29 466
472 12.14.2 Install interior equipment 6 days Mon 6/4/29 Sat 6/9/29 466
473 12.14.3 Install antennas and RF cabling 6 days Mon 6/4/29 Sat 6/9/29 466
474 12.15 Week 14 NAVSEA 6 days Mon 6/11/29Sat 6/16/29
475 12.15.1 Complete installations 6 days Mon 6/11/29Sat 6/16/29 470
476 12.15.2 LMR 6 days Mon 6/11/29Sat 6/16/29 470
477 12.16 Week 15 NAVSEA 6 days Mon 6/18/29Sat 6/23/29
478 12.16.1 Site tests 3 days Mon 6/18/29Wed 6/20/29474
479 12.16.2 System tests 3 days Thu 6/21/29 Sat 6/23/29 478
480 12.17 Week 16 NAVSEA 6 days Mon 6/25/29Sat 6/30/29
481 12.17.1 Demobilization 6 days Mon 6/25/29Sat 6/30/29 477
482 12.17.2 Destaging 6 days Mon 6/25/29Sat 6/30/29 477
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
483 13 OP Boullion 96 days Mon 9/17/29Mon 1/7/30
484 13.1 Week 0 NAVSEA (no site work) 6 days Mon 9/17/29Sat 9/22/29
485 13.1.1 Staging for helo 6 days Mon 9/17/29Sat 9/22/29
486 13.2 Week 1 NAVSEA 6 days Mon 9/24/29Sat 9/29/29
487 13.2.1 Demo/remove electronics 6 days Mon 9/24/29Sat 9/29/29 484
488 13.2.2 Demo/remove batteries 6 days Mon 9/24/29Sat 9/29/29 484
489 13.2.3 Demo/remove antennas and cables6 days Mon 9/24/29Sat 9/29/29 484
490 13.3 Week 2 NAVSEA 6 days Mon 10/1/29Sat 10/6/29
491 13.3.1 Demo/remove electronics 6 days Mon 10/1/29Sat 10/6/29 486
492 13.3.2 Demo/remove batteries 6 days Mon 10/1/29Sat 10/6/29 486
493 13.3.3 Demo/remove antennas and cables6 days Mon 10/1/29Sat 10/6/29 486
494 13.3.4 Demo/ready for demobilization LM1 day Mon 10/1/29Mon 10/1/29486
495 13.3.5 NAVFAC KTR Staging for helo 6 days Mon 10/1/29Sat 10/6/29 486
496 13.4 Week 3 NAVFAC KTR 6 days Mon 10/8/29Sat 10/13/29
497 13.4.1 Mobilization to hilltop 6 days Mon 10/8/29Sat 10/13/29 495
498 13.4.2 Demo/Remove shelters 6 days Mon 10/8/29Sat 10/13/29 495
499 13.4.3 Demo/Remove solar 6 days Mon 10/8/29Sat 10/13/29 495
500 13.5 Week 4 NAVFAC KTR 6 days Mon 10/15/2Sat 10/20/29
501 13.5.1 Foundation Preperation 6 days Mon 10/15/2Sat 10/20/29 496
502 13.5.2 Earth moving 6 days Mon 10/15/2Sat 10/20/29 496
503 13.6 Week 5 NAVFAC KTR 6 days Mon 10/22/2Sat 10/27/29
504 13.6.1 Pour Foundations 6 days Mon 10/22/2Sat 10/27/29 500
505 13.7 Week 6 NAVFAC KTR/NAVSEA 6 days Mon 10/29/2Sat 11/3/29
506 13.7.1 Shelter foundation cure to 70% 6 days Mon 10/29/2Sat 11/3/29 503
507 13.7.2 NAVFAC KTR work/tower prep 6 days Mon 10/29/2Sat 11/3/29 503
508 13.7.3 NAVSAEA staging for helo lift 6 days Mon 10/29/2Sat 11/3/29 503
509 13.8 Week 7 NAVSEA 6 days Mon 11/5/29Sat 11/10/29
510 13.8.1 NAVSEA Heavy lift helo 6 days Mon 11/5/29Sat 11/10/29 505
511 13.8.2 NAVSEA place sheters 6 days Mon 11/5/29Sat 11/10/29 505
512 13.9 Week 8 NAVFAC KTR 6 days Mon 11/12/2Sat 11/17/29
513 13.9.1 Complete tower repairs 6 days Mon 11/12/2Sat 11/17/29 509
514 13.9.2 Tower: FAA lighting/lightning/groun6 days Mon 11/12/2Sat 11/17/29 509
515 13.10 Week 9 NAVFAC KTR 6 days Mon 11/19/2Sat 11/24/29
516 13.10.1 Ice bridge 6 days Mon 11/19/2Sat 11/24/29 512
517 13.10.2 Conduit 6 days Mon 11/19/2Sat 11/24/29 512
518 13.11 Week 10 NAVFAC KTR 6 days Mon 11/26/2Sat 12/1/29
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
WBS Task Name Duration Start Finish Predecessors Resource Names
519 13.11.1 Site grounding 6 days Mon 11/26/2Sat 12/1/29 515
520 13.11.2 Site lightning protection 6 days Mon 11/26/2Sat 12/1/29 515
521 13.12 Week 11 NAVFAC KTR 6 days Mon 11/26/2Sat 12/1/29
522 13.12.1 NAVFAC KTR demobilization 6 days Mon 11/26/2Sat 12/1/29 515
523 13.12.2 NAVFAC KTR destaging 6 days Mon 11/26/2Sat 12/1/29 515
524 13.13 Week 12 NAVSEA 6 days Mon 12/3/29Sat 12/8/29
525 13.13.1 Install solar panels 6 days Mon 12/3/29Sat 12/8/29 521
526 13.13.2 Install interior equipment 6 days Mon 12/3/29Sat 12/8/29 521
527 13.13.3 Install antennas and RF cabling 6 days Mon 12/3/29Sat 12/8/29 521
528 13.14 Week 13 NAVSEA 6 days Mon 12/10/2Sat 12/15/29
529 13.14.1 Install solar panels 6 days Mon 12/10/2Sat 12/15/29 524
530 13.14.2 Install interior equipment 6 days Mon 12/10/2Sat 12/15/29 524
531 13.14.3 Install antennas and RF cabling 6 days Mon 12/10/2Sat 12/15/29 524
532 13.15 Week 14 NAVSEA 6 days Mon 12/17/2Sat 12/22/29
533 13.15.1 Complete installations 6 days Mon 12/17/2Sat 12/22/29 528
534 13.15.2 LMR 6 days Mon 12/17/2Sat 12/22/29 528
535 13.16 Week 15 NAVSEA 6 days Mon 12/24/2Sat 12/29/29
536 13.16.1 Site tests 3 days Mon 12/24/2Wed 12/26/2532
537 13.16.2 System tests 3 days Thu 12/27/29Sat 12/29/29 536
538 13.17 Week 16 NAVSEA 6 days Mon 12/31/2Mon 1/7/30
539 13.17.1 Demobilization 6 days Mon 12/31/2Mon 1/7/30 535
540 13.17.2 Destaging 6 days Mon 12/31/2Mon 1/7/30 535
J S N J M M J S N J M M J S N J M M J S N J M M J S N J M Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
File details come from the government source that posted it. Updated .