About this file

This document is a Marine Corps memorandum approving the proposed installation schedule for Military Construction project P1241 Communication Towers at Marine Corps Air Ground Combat Center, Twentynine Palms. The project involves constructing 4 new communication towers and repairing 6 existing towers to improve range control safety and communication infrastructure for training exercises, including installation of communication equipment, equipment shelters, and photovoltaic systems with battery storage.

The schedule details specific timing requirements including: Microwave Re-alignment Phases 1-4 having no conflict with range training; Site work #1/Phase V must complete by January 11, 2027; Site work #2/Phase IV starts February 1, 2027; Crampton, Creole, and Bullion Towers must be completed sequentially with Bullion being last; contractors will have up to three 3-day interruptions during each Site Work Phase; contractors get a 16-week working window within the full availability period; and must participate in daily aviation planning board meetings. The document includes a detailed map showing tower locations and a Gantt chart timeline for the construction phases. Five checkpoint locations (69, 13, 51, 78, and RTAMS LZ) will serve as project staging areas during construction.

View the file

Other files

File Type Posted
Amendment - 0017 P1241_Request FPRs.pdf PDF
Amendment - 0016 P1241_Close Discussions.pdf PDF
Amendment - 0015 P1241.pdf PDF
Amendment - 0014 P1241_Open Discussions.pdf PDF
Amendment - 0013 P1241.pdf PDF
Amendment - 0012 P1241.pdf PDF
Amendment - 0011 P1241.pdf PDF
Phase 2_ATT 4_Offer Schedule_P1241_REV 1.xlsx XLSX spreadsheet
Amendment - 0010 P1241.pdf PDF
Phase 2_ATT 4_Offer Schedule_P1241.xlsx XLSX spreadsheet
Phase 2_Exhibit G_P1241.docx DOCX document
Phase 2_ATT 1_RFP Part 1_P1241.pdf PDF
Phase 2_ATT 5_RFI Form_P1241.xlsx XLSX spreadsheet
Amendment - 0008 P1241.pdf PDF
Phase 2_Exhibit F_P1241.docx DOCX document
Phase 2_ATT 2_Site Visit Map_P1241.pdf PDF
Phase 2_ATT 6_CA20250026_06-06-2025.pdf PDF
Amendment - 0009 P1241.pdf PDF
Phase 2_ATT 3_Site Visit RSVP List_P1241.xlsx XLSX spreadsheet
PLA Request for Information N6247325R3443.docx DOCX document
RFI Responses - 04-10-2025.xlsx XLSX spreadsheet
Amendment - 0007 P1241.pdf PDF
Amendment0006.pdf PDF
RFI Responses - 04-04-2025.xlsx XLSX spreadsheet
Amendment0005.pdf PDF
RFI Responses - 03-27-2025.xlsx XLSX spreadsheet
Amendment0004.pdf PDF
RFI Responses - 03-24-2025.xlsx XLSX spreadsheet
RR Matrix_Rev1.pdf PDF
Amendment0003.pdf PDF
Amendment-0002 P1241.pdf PDF
RFI Responses - 03-14-2025.xlsx XLSX spreadsheet
CA20250026_02-28-2025.pdf PDF
Financial Questionnaire_P1241.pdf PDF
EXHIBIT F_P1241.pdf PDF
EXHIBIT C_P1241.pdf PDF
EXHIBIT G_P1241.pdf PDF
EXHIBIT E_P1241.pdf PDF
Amendment0001-P1241.pdf PDF
Offerors Team Consent Form_P1241.pdf PDF
EXHIBIT D_P1241.pdf PDF
Instructions for Viewing Interested Vendors List.pdf PDF
EXHIBIT A_P1241.pdf PDF
Surety Form_P1241.pdf PDF
EXHIBIT B_P1241.pdf PDF
P1241 RFP ATT 3_RR Matrix.pdf PDF
P1241 RFP ATT 6_DBA WD CA20250026_2025 02 21.pdf PDF
P1241 RFP ATT 4_Offer Schedule.xlsx XLSX spreadsheet
N6247325R3443_P1241 Phase One Solicitation.pdf PDF
P1241 RFP ATT 2_Installation IMS Expanded.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES MARINE CORPS

MARINE AIR GROUND TASK FORCE TRAINING COMMAND

MARINE CORPS AIR GROUND COMBAT CENTER

BOX 788104

TWENTYNINE PALMS, CALIFORNIA 92278-8104

11000

CG

Subj: APPROVAL OF PROPOSED INSTALLATION SCHEDULE OF P1241 COMMUNICATION TOWER PROJECT

Encl: (1) NAVSEA P1241 Construction Schedule

(2) MCAGCC Range Map

1. Purpose: This memorandum is made to document an agreed construction schedule for Military Construction project P1241 COMMUNICATION TOWERS by key stakeholders in the MAGTFTC training mission. This schedule has the smallest possible impact to the Installation’s training mission and will be utilized as a guide in the request for proposal (RFP) when the contract goes out to bid.

2. Background: P1241 COMMUNICATION TOWERS is a planned Military Construction (MILCON) project which aims to construct 4 new and repair 6 existing communication towers to improve range control safety and communication infrastructure to support full-scale training exercises within Marine Corps Base Twentynine Palms for improved combat readiness. Collateral equipment at the towers will include communication equipment, equipment shelters with supporting services, and photovoltaic systems with battery storage.

3. Discussion:

a. The proposed NAVSEA schedule for Microwave Re-alignment Phases 1-4 will have no conflict with range training per G-3 and TTECG.

b. Site work #1/Microwave Re-alignment Phase V work must be completed no later than January 11th, 2027, to support training efforts occurring in mid-January. Site work #2/Microwave Phase IV can start February 1st, 2027.

c. Crampton, Creole, and Bullion Towers will be completed one at a time, as requested by TTECG, G6, and G3. Bullion Tower shall be the last tower site in the full construction schedule.

d. Per TTECG’s guidelines, the contractor needs to account for the following:

(1) During each Site Work Phase there will be up to three (3) interruptions for up to three (3) days maximum, which will be classified as “non-workdays”. This is not a demobilization; this is strictly no-human access to the site location for the specified time.

e. Regarding each site work phase, contractors will be given the entire window block listed on enclosure (1) for the contractors to best select a 16-week consecutive working window within the full availability window provided by the Installation.

f. Per Installation request, the contractor shall participate in the daily aviation planning board meeting. The FEAD Construction Manager shall validate daily activities with range scheduling. Coordination of construction schedule input into RFMSS shall be completed by Asset Management Branch within PWD, Requirements Section.

AMB will provide the point of contact for this matter to the contractor.

4. Decision Points:

a. Among stakeholders, the order of tasks was agreed upon with the following stipulations:

(1) The Argos and Mine Towers were switched to have Mine and Mesa Towers be the first paired site work locations.

(2) Creole, Crampton, and Bullion Towers need to be completed individually.

Subj: APPROVAL OF PROPOSED INSTALLATION SCHEDULE OF P1241 COMMUNICATION TOWER PROJECT

(3) Bullion Tower shall be the last tower worked on.

b. As noted in Encl. (2), checkpoint numbers 69, 13, 51, 78, and RTAMS LZ will be used as project staging areas during construction.

5. Recommendation: Approval of the proposed project schedule to be delivered to NAVSEA for RFP input.

Prepared By: Elizabeth Bevan, Civil Engineer, Public Works Division, Installation Support Directorate (ISD), (760) 830-7027.

Approved By: Lieutenant Commander David M. Dreyer, Public Works Officer, Public Works Division, ISD, (760) 830-7690.

DECISION GRID

AC/S, G-4 Recommendation: Approval: ________________________________

Disapproval: ________________________________

AC/S, G-3 Recommendation: Approval: ________________________________

AC/S, G-6 Recommendation: Approval: ________________________________

CO, TTECG Recommendation: Approval: ________________________________

Chief of Staff Recommendation: Approval: ________________________________

Commanding General Recommendation: Approval: ________________________________

P1241 Decision Memorandum 20241125
2024.12.05_Tower Map