ORT_Contract_Exhibits_E to M.pdf
PDF 3 MB Posted
- Solicitation number
- RFP 2026-0911
- Issued by
- Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington
About this file
Summary
This document comprises contract exhibits (E through M) for the Washington State Department of Transportation's (WSDOT) Roadway Toll Systems Modernization Programs, specifically related to the Open Road Tolling (ORT) contract solicitation. The exhibits provide detailed technical specifications, operational requirements, and supporting documentation for the design, development, implementation, operation, and maintenance of ORT roadway toll systems throughout Washington State. The exhibits include comprehensive project parameters, system performance standards, equipment specifications, and operational protocols that bidders must address in their proposals. WSDOT intends to award two independent contracts through this single RFP—one for ORT systems and one for Side-Fire systems—with the flexibility to award future facilities to either or both contractors based on project scope and state needs.
The exhibits establish technical benchmarks, operational compliance requirements, and performance metrics that form the foundation for bid evaluation and contract performance standards. These supporting materials define the system architecture, interoperability requirements, and operational frameworks necessary for successful toll system implementation and maintenance. The exhibits serve as binding reference documents that clarify WSDOT's expectations regarding system functionality, security protocols, customer service standards, and long-term operational sustainability, enabling bidders to develop comprehensive and compliant proposals that meet the state's specific technical and operational requirements for modernizing Washington's toll infrastructure.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORT RTS Contract
Exhibit E
Statement of Work No. 05 –
I-405 Bellevue to Lynnwood Roadway Toll System (RTS)
Exhibit E – Statement of Work No. 05
State of Washington Department of Transportation E - 1 Contract No.____
STATEMENT OF WORK NO. 05
for
I-405 Bellevue to Lynnwood Roadway Toll System
Implementation, Operations, and Maintenance
This Statement of Work No. 05 (SOW) for the I-405 Bellevue to Lynnwood (BTL) Roadway Toll
System is made and entered into by and between the Washington State Department of
Transportation, an agency of the State of Washington (WSDOT), and Toll Vendor, licensed to do business in the State of Washington (Vendor).
SECTION 1. RECITALS
WSDOT and Vendor are parties to Contract No.___, dated Month Day, Year, for Roadway Toll
Systems Supply, Installation, and Maintenance (Contract). The Contract was assigned to and assumed by Vendor effective Month Day, Year.
1.1 The Contract allows WSDOT, at its discretion, to issue Statements of Work under which
Vendor shall supply, install and maintain a Roadway Toll System on a specified roadway.
1.2 The I-405 BTL corridor between the junctions of Interstate 5 and state route number 202, has been designated by the Washington State Legislature as a toll facility in RCW 47.56.880.
1.3 Pursuant to the terms of the Contract, WSDOT has elected to have Vendor provide the
Roadway Toll System for I-405 BTL, the terms of which are set forth in this SOW and the other
Contract Documents.
NOW, THEREFORE, Vendor and WSDOT agree to the following SOW for the Roadway Toll
System:
SECTION 2. DEFINITIONS; PURPOSE; TERM AND CONDITIONS
2.1 Definitions
All capitalized terms used herein but not defined herein have the respective meanings set forth in the Contract Documents or, if not defined in the Contract Documents or in this SOW, have their ordinary and usual meaning. All section and exhibit references herein are to the sections and exhibits of the Contract or if so designated, to the Appendices to the RFP, unless otherwise stated.
Department of Transportation E - 2 Contract No.____
2.2 Purpose
The purpose of this SOW No. 05 is to direct Vendor to complete all of the necessary design, supply, installation and maintenance of the I-405 BTL Roadway Toll System (RTS).
2.3 Terms and Conditions
The terms and conditions applicable to the Work performed under this SOW are set forth in the
Contract Documents and this SOW. In the event of a conflict in the provisions of the Contract
Documents and this SOW, the conflict will be resolved in accordance with the Order of
Precedence as set forth in Contract Section 21.13.
SECTION 3. TERM AND EXTENSIONS
3.1 The term of this SOW shall commence Month Day, Year, and terminate ten (10) years after the date of Substantial Completion is achieved. In addition, this term may be further extended upon the mutual written agreement of the parties as set forth in an Amendment to the
Contract.
3.2 Vendor shall not commence Work on the I-405 BTL Toll System until WSDOT has issued a written Notice to Proceed to Vendor.
3.3 In no event shall the term of this SOW exceed the term of the Contract, or any extensions thereto.
3.4 This SOW may be terminated in accordance with the termination provisions of the
Contract or as mutually agreed in writing between the parties. In any event, this SOW shall terminate concurrent with the termination of the Contract, and termination of the Contract shall automatically terminate this SOW.
SECTION 4. SCOPE OF WORK
4.1 Deliverables
4.1.1 Vendor shall furnish all Products, cables and connections, installation, integration, testing, labor, personnel, transportation, materials, storage, tools, supplies, permits, licenses, equipment, and other Services necessary to supply and install, on a turnkey basis, a fully functional RTS in accordance with the Contract. Vendor shall provide Services and staff, and otherwise do all things necessary for or incidental to the performance of the Work.
4.1.2 The RTS shall identify and classify vehicles traveling through the I-405 BTL Toll System to support revenue collection. The System will include electronic equipment for Transponder
Department of Transportation E - 3 Contract No.____ and Photo Tolling. The RTS will also include Digital Video Audit System (DVAS) to provide camera monitoring of the toll zones.
4.1.3 The specific scope, deliverables and requirements of the Work are set forth in the
Appendices and in the Attachments of this SOW.
4.1.3.1 Vendor shall perform the design, supply, installation, and testing Work for the RTS in accordance with the requirements in the Contract Documents, including but not limited to the
Contract, Appendices, and Attachments of this SOW.
4.1.3.2 Vendor shall deliver the System to meet the performance requirements set forth in
Exhibit J .
4.1.3.3 Vendor shall perform the Operations and Maintenance Work for the RTS in accordance with the requirements in the Contract Documents, including but not limited to the
Contract and Appendices.
4.2 Time Is of the Essence
Time is of the essence for this SOW. Failure to meet the Guaranteed Dates for the Milestones or perform the required operation and maintenance as set forth herein and in the Technical
Appendices may result in the assessment of liquidated damages as set forth in Contract Section
19.9, Section 5 herein, and Exhibit J, at WSDOT’s discretion.
SECTION 5. INCENTIVES AND LIQUIDATED DAMAGES
5.1 Toll Revenue Loss Incentive and Reimbursement
5.1.1 During the period between NTP and Substantial Completion, Vendor shall limit toll revenue losses to not more than $320,000.00 (Toll Revenue Loss Incentive Limit). Vendor will be responsible for any toll revenue loss incurred because of its activities, including any toll revenue loss that incumbent vendor incurs while in degraded mode caused by Vendor’s transition activities. If Vendor achieves Substantial Completion prior to reaching the Toll
Revenue Loss Incentive Limit, WSDOT will pay the Vendor the difference between the Toll
Revenue Loss Incentive Limit and the total toll revenue loss. Toll revenue losses shall be calculated by subtracting the Earned Revenue during the period of the impact from the average
Earned Revenue of the previous comparable four-week period from the same time of day and same day(s) of week.
In the event Vendor exceeds the Toll Revenue Loss Incentive Limit specified above leading up to Substantial Completion, Vendor shall reimburse WSDOT for all lost toll revenue in excess of the Toll Revenue Loss Incentive Limit up to a cap of $1,800,000.00. Lost revenue shall be determined by the methodology described above.
Department of Transportation E - 4 Contract No.____
5.2 Implementation
5.2.1 Pursuant to Contract Section 19.9 and as provided herein, any delay by Vendor in meeting the Guaranteed Date for Installation Readiness and Testing Completion in this SOW will interfere with the proper implementation of the I-405 BTL RTS and will result in losses and damage to WSDOT. As it would be difficult and impracticable to fix the actual damage sustained in the event of any such failure(s) to perform, WSDOT and Vendor agree that in the event of any such failure(s) to perform, that the amounts stated herein are a reasonable approximation of actual damages and Vendor shall pay such amounts as liquidated damages and not as a penalty.
5.2.2 Any delay by Vendor in meeting the Guaranteed Date for Installation Readiness in this
SOW will be assessed on a per day basis and will not be prorated.
5.2.3 Vendor shall pay liquated damages for delay in meeting the Guaranteed Date for
Installation Readiness for the I-405 BTL RTS. The liquidated damages shall be in the amount of
One Thousand, Three Hundred and 00/100 dollars ($1,300.00) for each day of delay and shall not exceed 5% of the Total Price for Implementation as set forth in this SOW.
5.2.4 Any delay by Vendor in meeting the Guaranteed Date for Testing Completion in this
SOW will be assessed on a per day basis and will not be prorated.
5.2.5 Vendor shall pay liquated damages for delay in meeting the Guaranteed Date for Toll
Readiness for the I-405 BTL RTS. The liquidated damages shall be in the amount of Four
Thousand, One Hundred and 00/100 dollars ($4,100.00) for each day of delay and shall not exceed 25% of the Total Price for Implementation as set forth in this SOW.
5.2.6 Cumulative liquidated damages assessed by WSDOT for the combination of Installation
Readiness and Testing Completion for I-405 BTL RTS shall not exceed 25% of the Total
Implementation Price as set forth in this SOW.
5.3 Operations and Maintenance
5.3.1 If the System does not meet the operational and maintenance performance requirements of the Contract, this will interfere with the proper implementation of the I-405 BTL
RTS and will result in losses and damage to WSDOT. As it would be difficult and impracticable to fix the actual damage sustained in the event of any such failure(s) to perform, WSDOT and
Vendor agree that in the event of any such failure(s) to perform, that the amounts stated in
Contract Section 19.9 and Exhibit J are a reasonable approximation of actual damages and
Vendor shall pay such amounts as liquidated damages and not as a penalty.
5.3.2 Total liquidated damages assessed by WSDOT for failure to meet the operational performance requirements of the Contract or compensation for revenue loss in any one year
Department of Transportation E - 5 Contract No.____ shall not exceed the total annual price for Operations and Maintenance of the RTS for that year as set forth in this SOW.
5.3.3 Any other Liquidated Damages assessed will be as stated in Contract Section 19.9 and
Exhibit J.
5.4 Failure to Open Lanes
5.4.1 Vendor agrees to pay WSDOT liquidated damages for failing to open lanes and/or ramps at or before required times as identified in Attachment 1 of this SOW and Appendix 5. In the event traffic control is provided by WSDOT's contractors for Vendor Work and lane and/or ramp closure times are in excess of those as allowed, WSDOT, at its sole discretion, may determine if
Vendor's actions or inactions resulted in failure(s) to perform by WSDOT's contractors. In the event WSDOT determines Vendor's actions or inactions resulted in said failure(s) to perform, Vendor agrees to pay the amount of liquidated damages herein. As it would be difficult and impracticable to fix the actual damage sustained in the event of any such failure(s), WSDOT and Vendor agree that in the event of any such failure(s), that the amounts stated herein are a reasonable approximation of actual damages and Vendor shall pay such amounts as liquidated damages and not as a penalty.
5.4.2 Vendor agrees to pay WSDOT liquidated damages for lane and/or ramp closure times that exceed those under Attachment 1 of this SOW and Appendix 5. For purposes of calculating liquidated damages under this Section 5.4.2, the total time beyond the required opening time will be rounded up to the next five (5) minutes (“Rounded Delay Time”), where 1-5 minutes rounds to 5, 6-10 rounds to 10, and so on. Liquidated Damages will be calculated as the applicable per-15 min rate multiplied by (Rounded Delay Time in minutes ÷ 15), with the resulting amount rounded to the nearest cent.
5.4.2.1 Failure to Open Lanes Price table:
Failure to Open Lanes
Closure Type $/15 min
Single Lane $3,000
Two or More Lanes $6,000
5.4.3 In the event Vendor impacts WSDOT provided traffic control, Vendor will pay damages in the amount of the cost incurred by WSDOT or WSDOT's contractor in providing said traffic control for the period of time beyond the scheduled opening time.
5.5 Liquidated Damages for Intelligent Transportation Systems and Signal Disruptions
5.5.1 Planned and unplanned disruptions to the ITS and traffic signals will result in impacts to the traveling public, increased fuel consumption, vehicle operating costs, pollution, and other
Department of Transportation E - 6 Contract No.____ inconveniences and harm. As it would be difficult and impracticable to fix the actual damage sustained in the event of any such disruption(s), WSDOT and Vendor agree that in the event of any such disruption(s), that the amounts stated herein are a reasonable approximation of actual damages and Vendor shall pay such amounts as liquidated damages and not as a penalty.
5.5.2 The Vendor shall pay WSDOT liquidated damages in the following amounts if the Vendor fails to restore the proper operation of a signal or existing ITS element following an unplanned disruption. For purposes of calculating liquidated damages under Section 5.5.2 herein, the total time beyond the allowed time will be rounded up to the next five (5) minutes (“Rounded Delay
Time”), where 1-5 minutes rounds to 5, 6-10 rounds to 10, and so on. Liquidated Damages will be calculated as the applicable per-15 min rate multiplied by (Rounded Delay Time in minutes ÷
15), with the resulting amount rounded to the nearest cent.
5.5.2.1 Intelligent Transportation Systems and Signal Disruptions LD Price table:
System / Element
Trigger Liquidated Damages
Escalation
CCTV not fully operational due to an unplanned disruption or not restored to full operation following a planned disruption at the time specified
$2,000 / 15 min Increases to $8,000 if two or more cameras are affected
VMS not fully operational due to an unplanned disruption or not restored to full operation following a planned disruption at the time specified
$2,000 / 15 min
Increases to $8,000 if two or more VMS are affected
Data Station not fully operational due to an unplanned disruption or not restored to full operation following a planned disruption at the time specified
$2,000 / 15 min
Increases to $8,000 if two or more data stations are affected
SECTION 6. SOFTWARE LICENSE
6.1 The intellectual property provisions set forth in Contract Section 15 apply to this SOW except as expressly modified herein.
SECTION 7. COORDINATION
7.1 Vendor acknowledges that WSDOT has contractors working on I-405 BTL and Vendor agrees to coordinate and cooperate with WSDOT, WSDOT contractors, consultants, and other
Department of Transportation E - 7 Contract No.____ vendors, if any, in performing the Work under this SOW and attempt to see that the Work is properly performed on schedule in accordance with this SOW.
SECTION 8. BONDS
8.1 Vendor shall provide to WSDOT an executed Implementation Bond for Implementation
Work covered by this SOW in accordance with the requirements in Contract Section 8.
8.2 The Implementation Bond for Implementation Work shall be in the amount of eighty percent (80%) of the total Implementation Price, which amount is Written Out Contract Amount dollars and The Amount cents ($). WSDOT to release and return the Contract Bond to Vendor upon System Acceptance.
8.3 Vendor shall provide the Implementation Bond for this SOW to WSDOT prior to the issuance of the Notice to Proceed with this SOW. In no event shall the Notice to Proceed with any of the Work covered by this SOW be issued prior to the receipt of the required Contract
Bond.
8.4 Vendor shall provide to WSDOT an executed Operations and Maintenance Bond for the
Operations and Maintenance Work covered by this SOW in accordance with the requirements in
Contract Section 8.
8.5 The Operations and Maintenance Bond shall be in the amount of one hundred percent
(100%) of the total annual Price for the initial Operations and Maintenance Term, which amount is Written Out Contract Amount dollars and The Amount cents ($).
8.6 Vendor shall provide the Operations and Maintenance Bond as a condition to obtaining
Substantial Completion.
8.7 Vendor shall renew the Operations and Maintenance Bond each year on the anniversary date of the Operations and Maintenance Term commencement in the amount of the upcoming year’s respective total annual Price for Operations and Maintenance.
SECTION 9. INSURANCE
9.1 Vendor shall acquire and maintain in full force and effect the insurance required in
Contract Section 17.2 for the RTS covered by this SOW.
9.2 Vendor shall provide copies of certificates of all insurance required for this SOW to
WSDOT prior to the issuance of this SOW. In no event shall the Notice to Proceed with any of
Department of Transportation E - 8 Contract No.____ the Work covered by this SOW be issued prior to WSDOT’s receipt of the required certificates of insurance.
SECTION 10. PRICE AND PAYMENT TERMS
10.1 Work under this SOW shall not exceed the lump sum Price amount of Written Out
Contract Amount dollars and The Amount cents ($).
10.2 The pricing for the RTS shall be determined in accordance with the Price tables set forth herein.
10.3 WSDOT shall pay Vendor in accordance with the Price tables herein for the Work actually performed by Vendor and for which WSDOT has Approved.
10.4 WSDOT shall retain 5% of the Price for each Milestone for Implementation Work performed under this SOW. Upon System Acceptance, Vendor shall submit a final invoice for the retained amount.
10.5 Prices for Implementation Work
10.5.1 Total Implementation Price table:
Total Price for Implementation
Total Implementation Price: $XX
10.5.2 Payment and Milestone Schedule and Price table for Implementation Work:
Milestone Qualifying Event Guaranteed
Date Payment Amount*
E01. Project
Management – I-
405 BTL System
WSDOT approval of the following:
1.01 Project Management Plan–
Facility Addenda
1.02 Quality Management Plan –
Facility Addenda
1.03 Baseline Project Schedule
Month Day, Year
Within 45 days from NTP
$XX
E02. Preliminary
Toll Infrastructure
Design – I-405 BTL
System
WSDOT approval of the following:
2.01 Preliminary Toll Infrastructure
Design Memo
Within 90 days
$XX
Department of Transportation E - 9 Contract No.____
Milestone Qualifying Event Guaranteed
Date Payment Amount*
E03. Preliminary
Design – I-405 BTL
System
WSDOT approval of the following:
3.01 Preliminary Design
Document– Facility Addenda
3.02 Software Development Plan–
Facility Addenda
3.03 Preliminary Installation
Drawings
3.04 Noise Permit
3.05 Draft Transition Plan
Within 120 days
E04. Final Design –
I-405 BTL System
WSDOT approval of the following:
4.01 System Design Document -
Facility Addendum
4.02 Master Test Plan
4.03 IT Security Plan– Facility
Addenda
4.04 Final Material Test Plan
4.05 Final Transition Plan
Within 180 days
$XX
E05. Factory
Acceptance Test –
I-405 BTL System
WSDOT approval of the following:
5.01 Factory Acceptance Test
Procedures - ETL
5.02 Factory Acceptance Test
Report - ETL
Within 240 days
$XX
E06. Installation
Readiness – I-405
BTL System
WSDOT approval of the following:
6.01 Installation Plan
6.02 Released for Installation
Drawings
6.03 Working Drawings
6.04 Environmental Compliance
Plan - Facility Addenda
6.05 Worker Health and Safety
Plan– Facility Addenda
6.06 Traffic Management Plan
(TMP)
6.07 Traffic Incident Management
Plan (TIMP)
6.08 Maintenance of Traffic
Drawings
At least 210 days before Full
Revenue
Collection
Department of Transportation E - 10 Contract No.____
Milestone Qualifying Event Guaranteed
Date Payment Amount*
E07. Testing
Readiness – I-405
BTL System
WSDOT Approval of the following:
7.01 Site Acceptance Test
Procedures
7.02 Commissioning Test
Procedures
7.03 Operational Test Procedures
At least 180 days
Revenue
Collection
$XX
E08. Operations
Readiness – I-405
BTL System
WSDOT Approval of the following:
8.01 Operational Verification Test
Procedures
8.02 Operations Manual- Facility
Addenda
8.03 Maintenance Plan - Facility
Addenda
8.04 Go-Live Cutover Plan
8.05 Site Acceptance Test
Completion Letter
At least 90 days
Revenue
Collection
$XX
E09. Testing
Completion – I-405
BTL System
WSDOT Approval of the following:
9.01 Commissioning Test
Completion Letter
9.02 Operational Test Completion
Letter
9.03 Operational Verification Test
Completion Letter
Within 45 days after Full
Revenue
Collection
$XX
E10. Full Revenue
Collection – I-405
BTL System
Full Revenue Collection
Summer 2030
N/A
E11. Substantial
Completion – I-405
BTL System
WSDOT Approval of the following:
11.01 Site Acceptance Test Report
11.02 Commissioning Test Report
11.03 Operational Test Report
11.04 Operational Verification Test
Report
11.05 Performance Audit
Procedures
11.06 Transition Closeout Letter
Within two months after Full
N/A
Department of Transportation E - 11 Contract No.____
Milestone Qualifying Event Guaranteed
Date Payment Amount*
E12. System
Acceptance – I-405
BTL System
WSDOT Approval of the following:
12.01 As-Built Installation Drawings
12.02 As-Built SDD
12.03 Final Records
Within three months after Full
*Implementation Milestone amounts shall be subject to the following requirements relative to the total Implementation Price: each Milestone payment must be at least five percent. Milestone E01 shall be capped at 10 percent. Milestones E01 through E05 collectively shall not exceed 40 percent. Milestones E06 through E09 collectively shall not exceed 40 percent. Milestone E12 shall be fixed at 20 percent.
These parameters apply to all Milestones up to and including System Acceptance.
10.6 Prices for Operations and Maintenance Work
10.6.1 Operations and Maintenance Price table:
Monthly Pricing by Year for Operations and Maintenance
Monthly Price Months Annual Price
Year 1: $XX 12 $XX
Year 2: $XX 12 $XX
Year 3: $XX 12 $XX
Year 4: $XX 12 $XX
Year 5: $XX 12 $XX
Year 6: $XX 12 $XX
Year 7: $XX 12 $XX
Year 8: $XX 12 $XX
Year 9: $XX 12 $XX
Year 10: $XX 12 $XX
Total Price for 10 years of O&M $XX
10.6.2 Performance Audit Price table:
Annual Pricing for Performance Audit Annual Price
End of Year 1: $XX
End of Year 2: $XX
End of Year 3: $XX
End of Year 4: $XX
End of Year 5: $XX
End of Year 6: $XX
Department of Transportation E - 12 Contract No.____
Annual Pricing for Performance Audit Annual Price
End of Year 7: $XX
End of Year 8: $XX
End of Year 9: $XX
Total Price for 9 years of annual Performance Audit
10.7 Modification to Price tables and to Payment and Milestone Schedule.
Any modification to the Price tables and Payment and Milestone Schedule shall be done by written amendment executed by WSDOT and Vendor.
SECTION 11. STAFFING
11.1 Vendor Personnel
11.1.1 WSDOT hereby approves the individuals listed in Section 11.1.2 herein to fulfill the Key
Personnel Roles for the RTS covered by this SOW. This approval is given on the express
Vendor commitment that said individuals currently report directly to the person filling the respective Key Personnel Role and will continue to do so for the duration of this SOW.
11.1.2 The contact information for the Vendor Key Personnel for this SOW are:
Key Project Role Contact Information
Project Manager First Last
Systems Engineer First Last
Network Design and Integration Manager First Last
System Test Manager First Last
Operations & Maintenance Manager First Last
Project Quality Manager First Last
Installation Manager First Last
Coordination Manager First Last
Technical Delivery/Software Design Manager First Last
Operations Liaison First Last
Safety Manager First Last
Traffic Management Supervisor First Last
11.1.3 Vendor may replace the individuals designated as the Key Personnel Roles for this
SOW upon prior written approval of the WSDOT Contract Manager as detailed in this Section
11. At least thirty (30) Calendar Days in advance of a proposed replacement, Vendor shall
Department of Transportation E - 13 Contract No.____ provide to WSDOT written notification of its proposed replacement, including the name and qualifications of the proposed replacement. All proposed replacements must have equal or better qualifications than the personnel being replaced. WSDOT shall be allowed to interview replacements, if WSDOT so desires. WSDOT may, in its sole discretion, accept or reject any proposed replacement. Upon WSDOT’s approval of a Key Personnel Roles replacement for this
SOW, the change in the contact information and the effective date of such personnel replacement shall be memorialized by written amendment to this SOW.
11.1.4 It is expressly understood and agreed that nothing herein does or is intended to relieve the persons filling the Key Personnel Roles listed herein from direct responsibility for the fulfillment of the terms and conditions of this SOW and the other Contract Documents.
11.2 WSDOT Personnel
The contact information for WSDOT Key Personnel for this SOW are:
Key Personnel Role Contact Information
Implementation Project Manager Melissa Garr
Operations & Maintenance Project Manager Michael Severance
Contracts Manager Rick Naten
Department of Transportation E - 14 Contract No.____
In Witness Whereof, the parties hereto, having read this Contract in its entirety, including all attachments, do agree in each and every particular and have thus set their hands hereunto.
Department of Transportation
Signature
Print or Type Name Date
Title
Toll Vendor
ATTACHMENTS
Attachment 1 – I-405 BTL Project Specific Elements
Attachment 2 – I-405 BTL Infrastructure Background
Attachment 3 – I-405 BTL Toll Infrastructure Demarcation
Exhibit E – SOW 5 – Attachment 1
Department of Transportation E1 - 1 Contract No.____
ORT RTS Exhibit E, Attachment 1
I-405 BTL RTS PROJECT SPECIFIC ELEMENTS
SECTION 1. PROJECT BACKGROUND
The I-405 BTL RTS Project comprises the design, installation, integration, testing, transition, operation, and maintenance of an open, multi-point, dynamically priced Express Toll Lane
System spanning from Bellevue to Lynnwood.
The Vendor shall provide Toll Equipment and multi-point Trip assembly in two directions for a maximum of 32 Toll Points. The pricing approach for the I-405 BTL System calls for three toll fare-zones in each direction. Customers using the I-405 BTL System will be detected at one or more Toll Points and, depending on the length of their Trip, be charged a toll rate displayed in advance of entering the I-405 BTL RTS.
This system will replace the legacy I-405 BTL RTS, which has been in operation since 2015.
Continuous operation is desired during the transition from the legacy RTS to the new RTS.
Figure 1 below illustrates the limits of the I-405 BTL RTS Project corridor.
Department of Transportation E1 - 2 Contract No.____
Figure 1. I-405 BTL RTS Map
Figure 2 below illustrates the I-405 Toll Zones.
Department of Transportation E1 - 3 Contract No.____
Figure 2. I-405 Toll and Fare Zones
Figure 3 illustrates an example of how the access to the Express Toll Lanes could be laid out. There may or may not be a buffer between the Express Toll Lanes and adjacent general purpose lanes. There will not be any fixed barriers (such as guardrails or concrete barriers) between the Express Toll Lanes and general purpose lanes.
Department of Transportation E1 - 4 Contract No.____
Figure 3. Express Toll Lanes Access Types
The I-405 corridor is an important regional facility which carries high volumes of commuter and general purpose traffic. The System shall accommodate the traffic volumes traveling in the I-405
Express Toll Lanes. WSDOT logs of recently collected volumes are available online in the NW
Region Annual Ramp and Roadway Report:
http://www.wsdot.wa.gov/Northwest/TrafficVolume/
As of 2025, there were 9.8 million toll trips annually on the Bellevue to Lynnwood ETL.
1.1 Projects in the Vicinity
It is anticipated that different local and regional agency projects could occur within the immediate vicinity of, or at the same time, as the Roadway Toll System project implementation.
http://www.wsdot.wa.gov/Northwest/TrafficVolume/
Department of Transportation E1 - 5 Contract No.____
SECTION 2. INFRASTRUCTURE, EQUIPMENT, AND SERVICES
WSDOT will provide the infrastructure, equipment, and services described in this Section 2 to enable implementation of the Project. The Vendor shall be responsible for providing all other
Equipment and Services necessary to provide a functioning and compliant System unless overwise noted. Please refer to Attachment 2 of this SOW for Supplemental Information, like As-
Builts, Inspection Reports. Attachment 3 of this SOW illustrates demarcation points among the existing infrastructure. See Appendix 3, Appendix 4, and Appendix 5 for more information.
2.1 Existing Infrastructure
The following existing civil Toll Infrastructure will be available at each toll point:
• Monotube toll gantry(s)
• Roadside cabinets
• AVI reader cabinets
• Electrical service
• Fiber connection to WSDOT’s Northwest Region Transportation Management Center (NWR
TMC) through managed WSDOT Layer 3 network switch
• Conduit system
The Vendor shall be responsible for determining functionality or desired replacement of existing equipment. The Vendor may replace the roadside cabinets and/or reader cabinets at their own expense.
2.2 Existing Equipment
The following equipment will be already in place on the ETL:
• Signage
− TRS
− Illegal to Cross Double Lines
− Vehicles Prohibited from ETL
• WSDOT Layer 3 network switch: Managed by WSDOT to transport data over WSDOT fiber to a regional hub or Traffic Management Center.
• WSDOT portable generators: Intended for power outages on ETL facilities only. Managed and deployed by WSDOT.
2.3 Provided Services
WSDOT will furnish the following services:
Department of Transportation E1 - 6 Contract No.____
• Communications network for data exchange with WSDOT’s BOS/back-office provider and
WSDOT’s Northwest Region Transportation Management Center (NWR TMC)
• Customer Service Center and back office
• Interface documentation for BOS
• FCC License for AVI Equipment, in coordination with the Vendor
SECTION 3. TOLL RATE ASSIGNMENT
Toll rates will be calculated dynamically based on current traffic conditions. Traffic conditions will be monitored by the Washington State TMC, and a WSDOT-generated dynamic pricing algorithm will calculate a variable toll rate. The TMC will monitor and maintain data collection points. Reference Business Rules.
Table 1. Northbound Fare Zone Destinations
Northbound Trips Toll Points
NE 124th St NB01, NB02, NB03, NB04, NB05
SR-522 NB06, NB07, NB08, NB09, NB10
I-5 NB11, NB12, NB13, NB14, NB15, NB16
Table 2. Southbound Fare Zone Destinations
Southbound Trips Toll Points
SR-522 SB01, SB02, SB03, SB04, SB05, SB06
NE 85th St SB07, SB08, SB09, SB10, SB12
Ne 6th St SB11, SB13, SB14, SB15, SB16
SECTION 4. MAINTENANCE OF TRAFFIC ALLOWANCES
The allowable closure hours listed below are typical for projects along the I-405 corridor and are to be used for a general understanding of when lanes can be closed for work. Ultimately, the
Region Traffic Control Office will approve requested closures and hours once MOT plans have been submitted.
Table 3. I-405 Allowable Closures
Closure Type Weekday Weekend
Shoulder Off Peak Off Peak As needed As Needed
Single or dual ETL lane 2100 0500 2100 0500
Single GP lane 2100 0500 2200 0500
Ramp 2200 0500 2200 0500
Full closure 2200 0500 2200 0500
Department of Transportation E1 - 7 Contract No.____
SECTION 5. INSTALLATION AND TESTING PERIOD
The Vendor shall install the Toll Equipment in a way that minimizes disruptions and is in alignment with the MOT Allowances.
The Vendor shall demonstrate through the process of testing that the System provided by the
Vendor complies with the requirements set forth in this Section 5 and its functionality complies with the project requirements and the SDD. Where possible, testing shall be conducted in an
“end-to-end” manner so that results may be tracked through each possible level of the System.
For example, the impact of parameter changes observed in the behavior of the lane systems or results of tests that are conducted in the lanes shall be tracked at the Roadside Management
Host. Testing shall only occur when all aspects of the testing environment are stable.
The Vendor shall provide WSDOT access to test data during all testing activity. This may include transaction data, MOMS output, reports, logs, and/or screenshots. This may also include raw and processed transaction data, MOMS outputs, and reports. WSDOT will arrange for reports of any transmitted test data and images to be processed by the CSC and provide to the Vendor.
See Appendix 3, Appendix 4, and Appendix 5 for more information.
SECTION 6. TRANSITION
See Appendix 3, Appendix 4, and Appendix 5 for more information.
SECTION 7. DECOMISSIONING LEGACY EQUIPMENT
There will be 32 existing Toll Points that will be decommissioned. There will be a blend of single and dual gantry configurations and ages of materials.
The Vendor is responsible for removal, inventory, and disposal of legacy toll equipment and materials in the Toll Zone. Raw materials shall be disposed of. Equipment shall initially be taken to Vendor warehouse and inventoried for WSDOT determination of surplus eligibility. Surplus eligible equipment shall be returned to WSDOT in accordance with Appendix 5, Section 5.3.1.
SECTION 8. OPERATIONS AND MAINTENANCE
After a toll point is installed, the Toll Vendor is responsible for maintaining the equipment. Once the Project reaches Substantial Completion, the Operations and Maintenance phase of the project begins.
Department of Transportation E1 - 8 Contract No.____
The Toll Vendor shall comply with all the maintenance and operations requirements called for the Toll System in accordance with this Section 8 and Appendix 3, Appendix 4, and Appendix 5.
SECTION 9. PROJECT DELIVERABLES
The Toll Vendor shall comply with all the project deliverable requirements called for the Toll
System in accordance with Appendix 3, Appendix 4, and Appendix 5.
End of Document
Exhibit E – SOW 5 – Attachment 2
Department of Transportation E2 - 1 Contract KXXX
SECTION 1. I-405 BTL INFRASTRUCTURE BACKGROUND
1.1 Introduction
The existing toll gantries (monotube structures) and associated infrastructure have been reviewed to determine if they can accommodate additional equipment during the transition to a new toll vendor. The new toll vendor will initially collocate new equipment alongside existing equipment and may eventually utilize existing conduits and cabinets as part of their permanent solution implementation.
1.2 Structural Review
The WSDOT Bridge Inspection Team reviewed the following structures:
Gantry ID Structure Type Length / Span Associated Toll Point(s)
405/13.76HOV RAMPS XDAM014 Bridge 78.83' SB10, SB11, NB01, NB02
405/13.77HOV RAMPS XDAM015 Bridge 79.75' SB10, SB11, NB01, NB02
405/15.59SHOV XDAM009 Cantilever 32.5' SB09
405/15.60NSHOV XJAR014 Bridge 122.5' SB09
405/16.71SNHOV XDAM008 Bridge 146.5' NB03
405/16.70NHOV XJAR049 Cantilever 30.67' NB03
405/17.65SHOV XDAM007 Cantilever 35.17' SB08
405/17.66SHOV XDAM006 Cantilever 34.33' SB08
405/19.73NHOV XJAR056 Cantilever 37.58' NB04
405/19.74N HOV XJAR057 Cantilever 37.5' NB04
405/20.47HOV RAMPS XDAM013 Butterfly 50.25' SB07, NB05
405/20.48HOV RAMPS XDAM012 Butterfly 50.42' SB07, NB05
405/20.79HOV RAMPS XDAM011 Butterfly 50.42' NB06, SB06
405/20.80HOV RAMPS XDAM010 Butterfly 50.25' NB06, SB06
405/21.17SHOV XJAR110 Cantilever 39.5' SB05
405/21.18SHOV XJAR109 Cantilever 39.5' SB05
405/22.12NHOVSHOV XJAR063 Bridge 60' SB04, NB07
405/22.13NSHOV XJAR062 Butterfly 127.5' SB04, NB07
405/25.55SHOV XJAR100 Cantilever 28.33' SB03
405/25.56SHOV XJAR099 Cantilever 26.33' SB03
405/25.92NHOV XJAR072 Cantilever 29.83' NB08
405/25.93NHOV XJAR073 Cantilever 29.75' NB08
405/27.09SHOV XJAR095 Cantilever 26.33' SB02
405/27.10SHOV XJAR094 Cantilever 26.33' SB02
405/28.05NHOV XJAR079 Cantilever 27.5' NB09
Department of Transportation E2 - 2 Contract KXXX
Gantry ID Structure Type Length / Span Associated Toll Point(s)
405/28.06N XJAR080 Bridge 100' NB09
405/28.66SHOV XJAR089 Cantilever 32.33' SB01
405/28.67SHOV XJAR088 Cantilever 32.5' SB01
405/29.18NHOV XJAR083 Cantilever 32.33' NB10
405/29.18SNHOV XJAR086 Bridge 133.17' NB10
The sign bridge inspection reports (dated November 2025) indicate that all structures are in good condition without any notable deterioration or structural concerns identified. Based on the review, all structures appear capable of supporting additional tolling equipment, subject to the following conditions:
• Equipment Size and Weight: The proposed tolling equipment must be similar in size and weight as the existing equipment, and there must be adequate space available to install new equipment.
• Structural Modifications: If there is not enough space on the existing gantry, the toll system vendor may propose adding structural members to support additional equipment. The proposal must include \structural analysis, calculations, and design plans to demonstrate the structural adequacy of both the existing sign bridge and the proposed support system.
• Engineering Requirements: Structural analysis, calculations, and design plans for the proposed tolling support system, including any temporary conditions (e.g. when the new equipment is collocated with the existing one) shall be prepared and stamped by a
Professional Engineer licensed in the State of Washington.
1.3 System Review
Each toll point includes:
• A concrete foundation pad where the toll cabinet and transformer are located.
• Additional reader cabinets attached to the monotube pole.
• Conduit and junction boxes connecting gantries and cabinets as shown in the as-built plans.
Some toll points include additional cabinets for signage systems.
The vendor should protect in place both the toll transformer cabinet and any other cabinets located on the same foundation pad.
The main power supply system (25 kVA transformer) has been inspected by the WSDOT in
November 2025 without significant concerns.
Department of Transportation E2 - 3 Contract KXXX
1.4 Equipment Reuse
Any equipment that has the possibility of reuse will require the new Vendor to inspect and decide if reuse is feasible as part of their solution implementation. The Vendor shall then re-certify the equipment as part of their solution implementation and accept responsibility for integration into their solution.
The following table provides details on the equipment and infrastructure available for the possible reuse or replacement:
Toll Point
MP Toll Cabinet Gantries Gantry type Location of associated cabinets
As-Built ITS Drawings
As-Built Gantry Drawings
SB01 28.51 405tl02868 XJAR089 XJAR088 Cantilever Median TS58 - ST87 ST88
SB02 27.09 405tl02707 XJAR095 XJAR094 Cantilever Median TS52 TSD73 ST77 ST78
SB03 25.48 405tl02551 XJAR100 XJAR099 Cantilever SB, left shldr. TS46 - ST69 ST70
SB04 22.14 405tl02211 XJAR063 XJAR062 Butterfly /
Bridge NB, right shldr. TS33
TSD55
TSD72 ST55 ST56
SB05 21.09 405tl02117 XJAR110 XJAR109 Cantilever SB, left shldr. TS30 - ST45 ST46
SB06 20.81 405tl02079 XDAM011 XDAM010 Butterfly SB, right shldr. TS28 TSD54 ST41 ST42
SB07 20.45 405tl02048 XDAM013 XDAM012 Butterfly SB, right shldr. TS27 TSD54 ST39 ST40
SB08 17.83 405tl01765 XDAM007 XDAM006 Cantilever Median
TS16 &
TS17 ST22 ST23
SB09 15.71 405tl01560 XDAM009 XJAR014 Cantilever /
Bridge SB, right shldr. TS9 TSD52 ST8 ST9
SB10 13.85 405tl01379 XDAM014 XDAM015 Bridge
SB I-405 to EB NE 8th Street loop ramp right shldr. TS2 TSD70 ST3 ST4
SB11 13.85 405tl01380 XDAM014 XDAM015 Bridge
SB I-405 to EB NE 8th Street loop ramp right shldr. TS2 TSD70 ST3 ST4
NB01 13.85 405tl01378 XDAM014 XDAM015 Bridge EB NE 8th Street to NB I- 405 loop ramp right shldr. TS2 TSD70 ST3 ST4
NB02 13.85 405tl01377 XDAM014 XDAM015 Bridge EB NE 8th Street to NB I- 405 loop ramp right shldr. TS2 TSD70 ST3 ST4
NB03 16.56 405tl01671 XDAM008 XJAR049 Cantilever /
Bridge SB, right shldr. TS13 TSD71 ST18 ST19
NB04 19.74 405tl01973 XJAR056 XJAR057 Cantilever Median TS24 ST35 ST36A
NB05 20.45 405tl02047 XDAM013 XDAM012 Butterfly SB, right shldr. TS27 TSD54 ST39 ST40
NB06 20.81 405tl02078 XDAM011 XDAM010 Butterfly SB, right shldr. TS28 TSD54 ST41 ST42
NB07 22.14 405tl02210 XJAR063 XJAR062 Butterfly /
Bridge NB, right shldr. TS33
TSD55
TSD72 ST55 ST56
NB08 25.83 405tl02593 XJAR072 XJAR073 Cantilever Median TS48 - ST72 ST73
NB09 28.05 405tl02804 XJAR080 XJAR079 Cantilever /
Bridge NB, left shldr. TS56 - ST84 ST85
NB10 29.23 405tl02919 XJAR083 XJAR086 Cantilever/
Bridge Median TS60 TSD74 ST91 ST92
Department of Transportation E2 - 4 Contract KXXX
In general, for the gantries Vendor needs to inspect and design any mounting assemblies as per their solution in advance of transition and final placement of equipment. For conduits and junction boxes, Vendor needs to inspect and identify fill factor. For toll cabinets, environmental controls may need replacement.
1.5 Reference Documents >link to be provided<
1.6 As-Built Drawings >link to be provided<
1.7 Structural Reports >link to be provided<
1.8 Electrical Report >link to be provided<
Exhibit E – SOW 5 – Attachment 3
Department of Transportation E3 - 1 Contract No.__
ORT RTS Exhibit E, Attachment 3
I-405 BTL RTS TOLL INFRASTRUCTURE DEMARCATION
Exhibit E – SOW 5 – Attachment 3
Department of Transportation E3 - 2 Contract No.__
Exhibit F
Labor Rates
Exhibit F – Labor Rates
Department of Transportation F -1
Contract No.____
SECTION 1. Labor Rates Table
Ref No.
Position Rate, $/Hour Remarks
1 Project Executive $XX
2 Program Manager $XX
3 Project Manager $XX
4 Coordination Manager $XX
5 Program Quality Manager $XX
6 Design Quality Assurance Manager $XX
Construction Quality Assurance Manager
$XX
8 Materials Approval Engineer $XX
9 Installation Manager $XX
10 Environmental Compliance Manager $XX
11 Software Design Manager $XX
12 Software Engineer $XX
13 Business Analyst $XX
14 Systems Engineer $XX
Network Design and Integration Manager
$XX
16 Electrical Systems Engineer $XX
17 Lead Structural Engineer $XX
18 O&M Manager $XX
19 Senior Maintenance Technician $XX
20 Maintenance Technician $XX
Notes:
• All rates will be fully burdened (reflecting the raw rate, overhead, and mark up). That shall reflect the rate intended for invoicing.
• Annual escalation will be applied separately at a CPI-U variable rate not to exceed 5%.
• These Rates will be used to propose Prices for work packages and other directed work.
• Vendor may use different names for Positions in its internal planning and estimating, as may be noted in the Remarks column.
Exhibit G
Preliminary Coordination for Future Systems
Statement of Work XX
Exhibit G – Preliminary Coordination for Future Systems
Department of Transportation G-1 Contract No.____
STATEMENT OF WORK NO. #
for
Preliminary Coordination for Future Systems
This Statement of Work No. # (SOW) for the Roadway Toll System is made and entered into by and between the Washington State Department of Transportation, an agency of the State of
Washington (WSDOT), and Toll Vendor, licensed to do business in the State of Washington
(Vendor).
SECTION 1. RECITALS
1.1 WSDOT and Vendor are parties to Contract No.____ dated Month Day, Year, for
Roadway Toll Systems Supply, Installation, and Maintenance (Contract).
1.2 The Contract allows WSDOT, at its discretion, to issue Statements of Work under which
Vendor shall supply, install and maintain a Roadway Toll System on a specified roadway.
NOW, THEREFORE, Vendor and WSDOT agree to the following SOW for the Roadway Toll
System:
SECTION 2. DEFINITIONS; PURPOSE; TERM AND CONDITIONS
2.1 Definitions.
All capitalized terms used herein but not defined herein have the respective meanings set forth in the Contract Documents or, if not defined in the Contract Documents or in this SOW, have their ordinary and usual meaning. All section and exhibit references herein are to the sections and exhibits of the Contract, unless otherwise stated.
2.2 Purpose.
The purpose of this SOW No. # is to direct Vendor to conduct preliminary coordination for future systems for the Roadway Toll System (RTS).
2.3 Terms and Conditions.
The terms and conditions applicable to the Work performed under this SOW are set forth in the
Contract Documents and this SOW. In the event of a conflict in the provisions of the Contract
Documents and this SOW, the conflict will be resolved in accordance with the Order of
Precedence as set forth in Contract Section 21.13.
Department of Transportation G-2 Contract No.____
SECTION 3. TERM AND EXTENSIONS
3.1 The term of this SOW shall commence upon signature and end when the contract is terminated.
3.2 Vendor shall not commence Work on the Preliminary Coordination for Future Systems until WSDOT has issued a written Notice to Proceed to Vendor.
3.3 In no event shall the term of this SOW exceed the term of the Contract, or any extensions thereto.
3.4 This SOW may be terminated in accordance with the termination provisions of the
Contract or as mutually agreed in writing between the parties. In any event, this SOW shall terminate concurrently with the termination of the Contract.
SECTION 4. SCOPE OF WORK
4.1 Deliverables
4.1.1 Vendor shall perform preliminary coordination and furnish deliverables as described below, upon WSDOT request, for future roadside toll systems.
4.1.2 Deliverables specifications may be included in the individual Notice to Proceed for each individual Work Package. Deliverables may include, but not limited to, the following:
• Attend meetings/workshops with WSDOT and representatives of the Future Systems projects. Vendor attendance may be in person or on the phone, as approved by WSDOT.
Provide meeting notes with action items identified.
• Conceptual design plans and calculations.
• White papers to evaluate approaches to the system operation, equipment selection, or installation approach.
• Infrastructure requirements for Future Systems (power, comm, conduit, equipment weight, and other factors).
• Provide review comments for meeting notes, reports, plans, or other project related documents provided by others. Including a summary of what aspects were reviewed by each resource (MOT tables, power, conduit, etc.).
4.1.3 Vendor shall provide monthly progress reports to include:
• Summary description of work completed, work planned, and budget remaining.
Department of Transportation G-3 Contract No.____
4.1.4 In addition to the itemized invoice described in Contract Section 4.3.3, Vendor shall provide:
• Description of and supporting documentation, including timesheets, for any work on a time and materials basis.
4.2 Staff Availability
4.2.1 Vendor shall make staff available to perform work directed by this SOW without compromising staff availability required on other SOW’s under this contract.
SECTION 5. COORDINATION
Vendor acknowledges that WSDOT has contractors working on the Preliminary Coordination and Vendor agrees to coordinate and cooperate with WSDOT, WSDOT contractors, consultants, and other vendors, if any, in performing the Work under this SOW and attempt to see that the Work is properly performed on schedule in accordance with Appendix 3.
SECTION 6. INSURANCE
6.1 Vendor shall maintain in full force and effect the insurance required in Contract Section
17.2 for the RTS covered by this SOW.
SECTION 7. PRICE AND PAYMENT TERMS
7.1 Work under this SOW shall not exceed the Price amount of one million dollars and no cents ($1,000,000.00).
7.2 WSDOT shall pay Vendor as identified herein for the Work actually performed by Vendor and for which WSDOT has Approved.
7.3 WSDOT shall pay Vendor for costs incurred for the Preliminary Coordination for Future
Systems in accordance with the unit pricing provided in Exhibit F, Pricing Table for Hourly
Rates, and not to exceed Effort Estimates associated with each Notice to Proceed. The unit pricing in effect at the time the Work Package is issued will remain effective for that Work
Package. Vendor invoices will include broken-down cost detail, separately for individual Notices to Proceed. WSDOT will notify Vendor in writing in advance of Work with a limited Notice to
Proceed associated with each package of upcoming coordination needs. Payment of invoices will indicate successful completion and WSDOT acceptance of deliverables for each Work
Package.
Department of Transportation G-4 Contract No.____
In Witness Whereof, the parties hereto, having read this Contract in its entirety, including all attachments, do agree in each and every particular and have thus set their hands hereunto.
Attachment 1 – Sample Notice to Proceed Letter
Department of Transportation G1-1 Contract No.____
ATTACHMENT 1 – SAMPLE NOTICE TO PROCEED
Vendor Name
Attn: Vendor Staff Name
Vendor Address
RE: Roadway Toll System
WSDOT Contract No. ____
Notice to Proceed – Future Systems Preliminary Coordination Package 1, System X
This letter is Vendor Name official notice to proceed on Contract No.___, the Future
Systems Preliminary Coordination Package 1, System X Work for the Roadway Toll
System, effective Month Day, Year.
The total not-to-exceed amount authorized for the Future Systems Preliminary Coordination Package 1, System X Work is $X,XXX, as detailed in the attached Effort Estimate.
Deliverables specification (Section 4. Deliverables of Exhibit G, Statement of Work No. # –
Future Systems Preliminary Coordination)
Vendor will attend 1-day meeting in-person on Month Day, Year to discuss __________.
Deliverables required for payment of costs incurred for this work include:
• Meeting notes with action items identified
• Draft conceptual designs and calculations
• Monthly Progress reports
• Monthly Invoices
We look forward to working with Vendor Name on this very important Project for Washington
State. Please feel free to contact me at melissa.garr@wsdot.wa.gov if you have any questions or concerns.
Sincerely, Melissa Garr, P.E.
Toll Systems Development Manager Washington State Department of Transportation mailto:melissa.garr@wsdot.wa.gov
Department of Transportation G1-2 Contract No.____
Vendor Name Acknowledgment
Signature Date
(The person signing to acknowledge this letter has accepted responsibility for completion of the work described herein and has the authority to do so.)
MG; mg
CC: Contract No.____
WSDOT Roadway Toll System Preliminary Coordination for Future Systems - NTP Effort Estimate
SAMPLE
Task No. Description Qty Unit
Hourly Rate
Price Subtotal
1-Day Meeting and Meeting Minutes
Project Manager X Hrs $XX $XX
Systems Engineer X Hrs $XX $XX
Software Engineer X Hrs $XX $XX
Conceptual Design and Calcs
Project Manager X Hrs $XX $XX
Invoice and Progress Report
Taxes $XX
Total $XX
Exhibit H
Hypothetical Future Systems
Exhibit H – Hypothetical Future Systems
Department of Transportation H - 1 Contract No.____
Hypothetical Future Systems
SECTION 1. OVERVIEW
Future Systems may later be added to the Project based on future legislative direction and WSDOT toll program development. The Contract will be amended if future Systems are added to the Project.
Vendors agrees to install, operate and maintain RTS on future Toll facilities at Prices determined in negotiation with WSDOT based on this exhibit. If future Systems are added to the Project, the price provided by the Vendor in response to this RFP will be considered a price proposal for purposes to support…