1_P012_Specs-Amend0002.pdf

PDF 378 KB Posted

Attached to
WON 1665555, FY24 AJJY183012 (P-012), PDI: NORTH AIRCRAFT PARKING RAMP, ANDERSEN AIR FORCE BASE, GUAM
Solicitation number
N62742-26-R-1300
Issued by

About this file

Summary of FY24 AJJY183012 (P-012) Contract Documents

This document set comprises the List of Drawings (Document 00 01 15), Section 01 57 19 Temporary Environmental Controls specifications, Section 09 96 53.13 Silicone Elastomeric Coatings specifications, and Attachment F Natural Resources Performance Work Statement for the North Aircraft Parking Ramp project at Andersen Air Force Base, Guam. The project involves construction of an aircraft parking ramp with comprehensive environmental protection, resource conservation, and coating system requirements.

Environmental Controls and Specifications: The contractor must implement extensive environmental protection measures including stormwater pollution prevention plans (SWPPP), hazardous waste management, erosion and sediment control, air quality compliance, archaeological monitoring, and natural resources conservation. Key requirements include ECATTS environmental training certification, preparation of an Environmental Protection Plan, monthly solid waste disposal reports, waste determination documentation, and spill prevention control and countermeasure (SPCC) plans. The contractor must obtain all required federal, state, and local permits, including NPDES coverage, GEPA permits for clearing and grubbing, and Class V Underground Injection Control permits for three existing sinkholes. Natural Resources and Construction Requirements: The project requires protection of four endangered plant species (Cycas micronesica, Tabernaemontana rotensis, and three orchid species) and Mariana fruit bats. The contractor must salvage and transplant threatened and endangered species from the construction footprint, conduct archaeological monitoring and data recovery at specified sites, and implement conservation measures at the 151-acre Tarague Forest Enhancement Area including installation of a 2.5-mile ungulate-proof fence and invasive species removal. For the coating system, the contractor must apply two coats of one-component silicone elastomeric coating achieving a minimum 10-mil dry film thickness on concrete surfaces, with a 15-year manufacturer's warranty on materials and workmanship. The contractor must comply with all specified surface preparation requirements and environmental controls during application.

View the file

Other files

File Type Posted
26R1300_Amd0009-Issued.pdf PDF
26R1300_Note11-Issued.pdf PDF
1-26R1300-Amd0008-Issued.pdf PDF
3-P012_Amd0008-Dwgs_09092026_Signed.pdf PDF
26R1300_Note10-Issued.pdf PDF
2-P012-Amd0008-Specs.pdf PDF
26R1300_Note9-Issued.pdf PDF
26R1300_Amd0007-Issued.pdf PDF
26R1300_Amd0006-Issued.pdf PDF
1_N6274226R13000005 SF 30 Issued.pdf PDF
2_013300-A_SubmittalRegister-Amd0005.pdf PDF
3-P012_Amend.0004_Dwgs_Signed.pdf PDF
4-P012_Amend0004_RefDwgs_HS-3_DD35-Pumphouse.pdf PDF
26R1300_Note8.pdf PDF
1-26R1300_Amd0004-Issued.pdf PDF
2-26R1300_Amd0004-Specs.pdf PDF
5-P012_Amend0004_RefDwgsHS-4_DD35-Pumphouse.pdf PDF
26R1300_Note7.pdf PDF
1-N6274226R1300_Amd0003.pdf PDF
2-P012_Amend0003_Specs.pdf PDF
3-P012_Amend0003_Dwgs_Signed.pdf PDF
26R1300_Note6-Final.docx.pdf PDF
0_N6274226R1300_Amd0002.pdf PDF
2_P012_Amend.0002_Dwgs-Signed.pdf PDF
3_P012_NorthAircraftRamp_RefDwgs-Amend0002.pdf PDF
26R1300_Note5.pdf PDF
26R1300_Note4.pdf PDF
N6274226R1300-Amendment 0001.pdf PDF
26R1300_Note3.pdf PDF
26R1300_Note2.pdf PDF
26R1300_Note1.pdf PDF
3-P012_DwgsPt2_BB104-CD107.pdf PDF
6-P012_DwgsPt5_CG141-CF201.pdf PDF
7-P012_DwgsPt6_CF202-EK502.pdf PDF
1-P012_Spec-Final_Signed.pdf PDF
2-P012_DwgsPt1_G001-BB103.pdf PDF
5-P012_DwgsPt4_CS501-CG140.pdf PDF
0-N6274226R1300-FrontEnd.pdf PDF
4-P012_DwgsPt3_CD108-CS312.pdf PDF
P012_Schneider-JA_Redacted.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY24 AJJY183012 (P-012), PDI: North Aircraft Parking Ramp 1665555 Andersen Air Force Base, Guam

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/24

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

DWG NO. NAVFAC DWG

NO.

TITLE

G-001 17361624 COVER SHEET

G-002 17361625 SHEET INDEX

G-003 17361626 SHEET INDEX

GI001 17361627 LOCATION MAP AND HAUL ROUTE

GI002 17361628 TYPICAL SYMBOLS AND ABBREVIATIONS

GI003 17361629 ABBREVIATIONS CONTINUED

GI108 17361630 PHASING PLAN

GI109 17361631 AIRFIELD PHASING PLAN

V-101 17361632 OVERALL EXISTING CONDITIONS

V-102 17361633 EXISTING CONDITIONS - AREA 1

V-103 17361634 EXISTING CONDITIONS - AREA 2

V-104 17361635 EXISTING CONDITIONS - AREA 3

V-105 17361636 EXISTING CONDITIONS - AREA 4

V-106 17361637 EXISTING CONDITIONS - AREA 5

V-107 17361638 EXISTING CONDITIONS - AREA 6

V-108 17361639 EXISTING CONDITIONS - AREA 7

V-109 17361640 EXISTING CONDITIONS - AREA 8

V-110 17361641 EXISTING CONDITIONS - AREA 9

V-111 17361642 EXISTING CONDITIONS - AREA 10

V-112 17361643 EXISTING CONDITIONS - AREA 11

V-113 17361644 EXISTING CONDITIONS - AREA 12

V-114 17361645 EXISTING CONDITIONS - AREA 13

V-115 17361646 EXISTING CONDITIONS - AREA 14

V-116 17361647 EXISTING CONDITIONS - AREA 15

V-117 17361648 EXISTING CONDITIONS - AREA 16

V-118 17361649 EXISTING CONDITIONS - AREA 17

V-119 17361650 EXISTING CONDITIONS - AREA 18

V-120 17361651 EXISTING CONDITIONS - AREA 19

V-121 17361652 EXISTING CONDITIONS - AREA 20

V-122 17361653 EXISTING CONDITIONS - AREA 21

V-123 17361654 EXISTING CONDITIONS - AREA 22

V-124 17361655 EXISTING CONDITIONS - AREA 23

V-125 17361656 EXISTING CONDITIONS - AREA 24

V-126 17361657 EXISTING CONDITIONS - AREA 25

V-127 17361658 EXISTING CONDITIONS - AREA 26

V-128 17361659 SURVEY CONTROL PLAN

Jacobs D3430603 DOCUMENT 00 01 15 Page 1 10 March 2025 Amendment 0002

BB101 17361660 LIMITED GEOTECHNICAL FIELD WORK PLAN

BB102 17361661 PHASE 2 GEOTECHNICAL FIELD WORK

BB103 17361662 BORING LOGS

BB104 17361663 BORING LOGS

BB105 17361664 BORING LOGS

BB106 17361665 BORING LOGS

BB107 17361666 BORING LOGS

BB108 17361667 BORING LOGS

BB109 17361668 BORING LOGS

BB110 17361669 BORING LOGS

BB111 17361670 BORING LOGS

BB112 17361671 BORING LOGS

BB113 17361672 BORING LOGS

BB114 17361673 BORING LOGS

BB115 17361674 BORING LOGS

BB116 17361675 BORING LOGS

BB117 17361676 BORING LOGS

BB118 17361677 BORING LOGS

BB119 17361678 BORING LOGS

BB120 17361679 BORING LOGS

C-001 17361680 GENERAL NOTES

CD101 17361681 OVERALL DEMOLITION PLAN

CD102 17361682 DEMOLITION PLAN - AREA 1

CD103 17361683 DEMOLITION PLAN - AREA 2

CD104 17361684 DEMOLITION PLAN - AREA 3

CD105 17361685 DEMOLITION PLAN - AREA 4

CD106 17361686 DEMOLITION PLAN - AREA 5

CD107 17361687 DEMOLITION PLAN - AREA 6

CD108 17361688 DEMOLITION PLAN - AREA 7

CD109 17361689 DEMOLITION PLAN - AREA 8

CD110 17361690 DEMOLITION PLAN - AREA 9

CD112 17361691 DEMOLITION PLAN - AREA 11

CD113 17361692 DEMOLITION PLAN - AREA 12

CD114 17361693 DEMOLITION PLAN - AREA 13

CD115 17361694 DEMOLITION PLAN - AREA 14

CD116 17361695 DEMOLITION PLAN - AREA 15

CD117 17361696 DEMOLITION PLAN - AREA 16

CD118 17361697 DEMOLITION PLAN - AREA 17

CD119 17361698 DEMOLITION PLAN - AREA 18

CD120 17361699 DEMOLITION PLAN - AREA 19

CD121 17361700 DEMOLITION PLAN - AREA 20

CD122 17361701 DEMOLITION PLAN - AREA 21

CD123 17361702 DEMOLITION PLAN - AREA 22

CD124 17361703 DEMOLITION PLAN - AREA 23

CD125 17361704 DEMOLITION PLAN - AREA 24

CD126 17361705 DEMOLITION PLAN - AREA 25

CD127 17361706 DEMOLITION PLAN - AREA 26

CD130 17361707 NOT USED

CD131 17361708 NOT USED

CD132 17361709 NOT USED

CD134 17361710 NOT USED

CD135 17361711 NOT USED

CD136 17361712 NOT USED

CD137 17361713 NOT USED

Jacobs D3430603 DOCUMENT 00 01 15 Page 2 10 March 2025

CD138 17361714 NOT USED

CD139 17361715 NOT USED

CS101 17361716 OVERALL SITE & PAVING PLAN

CS102 17361717 SITE & PAVING PLAN - AREA 1

CS103 17361718 SITE & PAVING PLAN - AREA 2

CS104 17361719 SITE & PAVING PLAN - AREA 3

CS105 17361720 SITE & PAVING PLAN - AREA 4

CS106 17361721 SITE & PAVING PLAN - AREA 5

CS107 17361722 SITE & PAVING PLAN - AREA 6

CS108 17361723 SITE & PAVING PLAN - AREA 7

CS109 17361724 SITE & PAVING PLAN - AREA 8

CS110 17361725 SITE & PAVING PLAN - AREA 9

CS111 17361726 SITE & PAVING PLAN - AREA 10

CS112 17361727 SITE & PAVING PLAN - AREA 11

CS113 17361728 SITE & PAVING PLAN - AREA 12

CS114 17361729 SITE & PAVING PLAN - AREA 13

CS115 17361730 SITE & PAVING PLAN - AREA 14

CS120 17361731 SITE & PAVING PLAN - AREA 20

CS121 17361732 SITE & PAVING PLAN - AREA 21

CS122 17361733 SITE & PAVING PLAN - AREA 22

CS123 17361734 SITE & PAVING PLAN - AREA 23

CS124 17361735 SITE & PAVING PLAN - AREA 24

CS125 17361736 SITE & PAVING PLAN - AREA 25

CS126 17361737 SITE & PAVING PLAN - AREA 26

CS130 17361738 OVERALL PAVEMENT MARKING PLAN

CS131 17361739 PAVEMENT MARKING PLAN - AREA 1

CS132 17361740 PAVEMENT MARKING PLAN - AREA 2

CS133 17361741 PAVEMENT MARKING PLAN - AREA 3

CS134 17361742 PAVEMENT MARKING PLAN - AREA 5

CS135 17361743 PAVEMENT MARKING PLAN - AREA 6

CS136 17361744 PAVEMENT MARKING PLAN - AREA 7

CS137 17361745 PAVEMENT MARKING PLAN - AREA 11

CS138 17361746 PAVEMENT MARKING PLAN - AREA 12

CS139 17361747 PAVEMENT MARKING PLAN - AREA 13

CS140 17361748 PAVEMENT MARKING PLAN - AREA 20

CS141 17361749 PAVEMENT MARKING PLAN - AREA 21

CS142 17361750 PAVEMENT MARKING PLAN - AREA 22

CS143 17361751 PAVEMENT MARKING PLAN - AREA 23

CS144 17361752 PAVEMENT MARKING PLAN - AREA 24

CS145 17361753 PAVEMENT MARKING PLAN - AREA 25

CS146 17361754 PAVEMENT MARKING PLAN - AREA 26

CS201 17361755 ROADWAY PLAN & PROFILE RW01 STA 0+00-6+25 - AREA 22

CS202 17361756 ROADWAY PLAN & PROFILE RW01 STA 6+25-12+50 - AREA 22 & 23

CS203 17361757 ROADWAY PLAN & PROFILE RW01 STA 12+50-18+75 - AREA 23 & 24

CS204 17361758 ROADWAY PLAN & PROFILE RW01 STA 18+75-25+00 - AREA 24 & 25

CS205 17361759 ROADWAY PLAN & PROFILE RW01 STA 25+00-31+25 - AREA 25 & 26

CS206 17361760 ROADWAY PLAN & PROFILE RW01 STA 31+25-37+50 - AREA 21 & 26

CS207 17361761 ROADWAY PLAN & PROFILE RW01 STA 37+50-44+00 - AREA 21

CS212 17361762 TAXILANE PLAN & PROFILE L2 STA 00+00-06+50

CS213 17361763 TAXILANE PLAN & PROFILE L2 STA 06+50-13+00

CS215 17361764 TAXILANE PLAN & PROFILE L3 STA 00+00-06+50

CS216 17361765 TAXILANE PLAN & PROFILE L3 STA 06+50-13+00

CS301 17361766 ROADWAY SECTIONS - SAMPLE LINE PLAN

Jacobs D3430603 DOCUMENT 00 01 15 Page 3 10 March 2025

CS302 17361767 ROADWAY SECTIONS - RW01

CS303 17361768 ROADWAY SECTIONS - RW01

CS304 17361769 ROADWAY SECTIONS - RW01

CS305 17361770 ROADWAY SECTIONS - RW01

CS306 17361771 ROADWAY SECTIONS - RW01

CS307 17361772 ROADWAY SECTIONS - RW01

CS308 17361773 ROADWAY SECTIONS - RW01

CS309 17361774 ROADWAY SECTIONS - RW01

CS310 17361775 APRON SECTIONS - A01

CS311 17361776 APRON SECTIONS - A02

CS312 17361777 APRON SECTIONS - A03

CS501 17361778 SITE DETAILS

CS502 17361779 SITE DETAILS

CS503 17361780 SITE DETAILS

CS504 17361781 SITE DETAILS

CS505 17361782 SITE DETAILS

CS506 17361783 SITE DETAILS

CS507 17361784 SITE DETAILS

CT101 17361785 OVERALL JOINTING PLAN

CT102 17361786 JOINTING PLAN - AREA 1

CT103 17361787 JOINT ELEVATION PLAN - AREA 1

CT104 17361788 JOINTING PLAN - AREA 2

CT105 17361789 JOINT ELEVATION PLAN - AREA 2

CT106 17361790 JOINTING PLAN - AREA 3

CT107 17361791 JOINT ELEVATION PLAN - AREA 3

CT108 17361792 JOINTING PLAN - AREA 6

CT109 17361793 JOINT ELEVATION PLAN - AREA 6

CT110 17361794 JOINTING PLAN - AREA 7

CT111 17361795 JOINT ELEVATION PLAN - AREA 7

CT112 17361796 JOINTING PLAN - AREA 12

CT113 17361797 JOINT ELEVATION PLAN - AREA 12

CT114 17361798 JOINTING PLAN - AREA 13

CT115 17361799 JOINT ELEVATION PLAN - AREA 13

CG101 17361800 OVERALL GRADING AND DRAINAGE PLAN

CG102 17361801 GRADING AND DRAINAGE PLAN - AREA 1

CG103 17361802 GRADING AND DRAINAGE PLAN - AREA 2

CG104 17361803 GRADING AND DRAINAGE PLAN - AREA 3

CG105 17361804 GRADING AND DRAINAGE PLAN - AREA 4

CG106 17361805 GRADING AND DRAINAGE PLAN - AREA 5

CG107 17361806 GRADING AND DRAINAGE PLAN - AREA 6

CG108 17361807 GRADING AND DRAINAGE PLAN - AREA 7

CG109 17361808 GRADING AND DRAINAGE PLAN - AREA 8

CG110 17361809 GRADING AND DRAINAGE PLAN - AREA 9

CG112 17361810 GRADING AND DRAINAGE PLAN - AREA 11

CG113 17361811 GRADING AND DRAINAGE PLAN - AREA 12

CG114 17361812 GRADING AND DRAINAGE PLAN - AREA 13

CG115 17361813 GRADING AND DRAINAGE PLAN - AREA 14

CG116 17361814 GRADING AND DRAINAGE PLAN - AREA15

CG117 17361815 GRADING AND DRAINAGE PLAN - AREA 16

CG118 17361816 GRADING AND DRAINAGE PLAN - AREA 17

CG119 17361817 GRADING AND DRAINAGE PLAN - AREA 18

CG120 17361818 GRADING AND DRAINAGE PLAN - AREA 19

CG121 17361819 GRADING AND DRAINAGE PLAN - AREA 20

CG122 17361820 GRADING AND DRAINAGE PLAN - AREA 21

Jacobs D3430603 DOCUMENT 00 01 15 Page 4 10 March 2025

CG123 17361821 GRADING AND DRAINAGE PLAN - AREA 22

CG124 17361822 GRADING AND DRAINAGE PLAN - AREA 23

CG125 17361823 GRADING AND DRAINAGE PLAN - AREA 24

CG126 17361824 GRADING AND DRAINAGE PLAN - AREA 25

CG127 17361825 GRADING AND DRAINAGE PLAN - AREA 26

CG130 17361826 NOT USED

CG131 17361827 NOT USED

CG132 17361828 NOT USED

CG134 17361829 NOT USED

CG135 17361830 NOT USED

CG136 17361831 NOT USED

CG137 17361832 NOT USED

CG138 17361833 NOT USED

CG139 17361834 NOT USED

CG140 17361835 LIMITS OF GEOSYNTHETIC CLAY LINER

CG141 17361836 LIMITS OF GEOSYNTHETIC CLAY LINER

CG142 17361837 LAWN RESTORATION PLAN

CG143 17361838 NOT USED

CG144 17361839 KARST FEATURES PLAN

CG145 17361840 NOT USED

CG146 17361841 KARST FEATURES DETAIL

CG147 17361842 TURF REINFORCEMENT PLAN

CG148 17361843 NOT USED

CG201 17361844 DRAINAGE PROFILES

CG202 17361845 DRAINAGE PROFILES

CG203 17361846 DRAINAGE PROFILES

CG204 17361847 DRAINAGE PROFILES

CG205 17361848 DRAINAGE PROFILES

CG206 17361849 DRAINAGE PROFILES

CG207 17361850 DRAINAGE PROFILES

CG208 17361851 DRAINAGE PROFILES

CG209 17361852 DRAINAGE PROFILES

CG210 17361853 DRAINAGE PROFILES

CG211 17361854 DRAINAGE PROFILES

CG212 17361855 DRAINAGE PROFILES

CG501 17361856 DRAINAGE DETAILS

CG502 17361857 DRAINAGE DETAILS

CG503 17361858 DRAINAGE DETAILS

CG504 17361859 DRAINAGE DETAILS

CG505 17361860 DRAINAGE DETAILS

CG506 17361861 DRAINAGE DETAILS

CG507 17361862 SAND FILTER DETAILS

CU101 17361863 OVERALL UTILITY PLAN

CU102 17361864 UTILITY PLAN - AREA 1

CU103 17361865 UTILITY PLAN - AREA 6

CU104 17361866 UTILITY PLAN - AREA 7

CU105 17361867 UTILITY PLAN - AREA 8

CU106 17361868 UTILITY PLAN - AREA 23

CU107 17361869 UTILITY PLAN - AREA 24

CU108 17361870 UTILITY PLAN - AREA 25

CU109 17361871 UTILITY PLAN - AREA 26

CU201 17361872 UTILITY PROFILES

CU202 17361873 UTILITY PROFILES

CU203 17361874 UTILITY PROFILES

Jacobs D3430603 DOCUMENT 00 01 15 Page 5 10 March 2025

CU501 17361875 UTILITY DETAILS

CU502 17361876 UTILITY DETAILS

S-001 17361877 STRUCTURAL GENERAL NOTES

S-002 17361878 STRUCTURAL GENERAL NOTES

S-101 17361879 FOUNDATION PLANS

S-501 17361880 TYPICAL CONCRETE DETAILS

S-502 17361881 TYPICAL CONCRETE DETAILS

S-503 17361882 CONCRETE SECTIONS AND DETAILS

A-001 17361883 GENERAL NOTES, SYMBOLS, AND EXTERIOR PERSPECTIVE VIEWS

A-406 17361884 DETACHED EQUIPMENT YARD

E-001 17361885 ELECTRICAL LEGEND 1 OF 2

E-002 17361886 ELECTRICAL LEGEND 2 OF 2

ED101 17361887 ELECTRICAL DEMOLITION PLAN 1

ED102 17361888 ELECTRICAL DEMOLITION PLAN 2

ED601 17361889 EXISTING DISTRIBUTION ONE LINE DIAGRAM - DEMOLITION PLAN

ES101 17361890 ELECTRICAL SITE PLAN 1

ES102 17361891 ELECTRICAL SITE PLAN 2

ES103 17361892 ELECTRICAL SITE PLAN 3

ES104 17361893 ELECTRICAL SITE PLAN 4

ES105 17361894 ENLARGED ELECTRICAL SITE PLAN

ES201 17361895 EXISTING SWITCHING STATION - 13.8KV SWITCHGEAR ARRANGEMENT

ELEV.ES501 17361896 ELECTRICAL SITE DETAILS

ES502 17361897 ELECTRICAL SITE DETAILS

ES503 17361898 ELECTRICAL SITE DETAILS

ES504 17361899 ELECTRICAL SITE DETAILS

ES505 17361900 ELECTRICAL SITE DETAILS

ES506 17361901 ELECTRICAL SITE DETAILS

ES701 17361902 HIGH MAST LIGHT POLE LOCATIONS

EP601 17361903 EXISTING DISTRUBUTION ONE LINE DIAGRAM - NEW WORK

EP602 17361904 ONE-LINE DIAGRAMS

EP701 17361905 PANELBOARD SCHEDULES

EA101 17361906 AIRFIELD ELECTRICAL PLAN 1

EA102 17361907 AIRFIELD ELECTRICAL PLAN 2

EA501 17361908 AIRFIELD LIGHTING DETAILS

EA502 17361909 AIRFIELD LIGHTING DETAILS

EA503 17361910 AIRFIELD LIGHTING DETAILS

EA504 17361911 AIRFIELD LIGHTING DETAILS

EA701 17361912 AIRFIELD LIGHTING POINTS SCHEDULE

EA702 17361913 AIRFIELD LIGHTING ONE-LINE DIAGRAMS

TS001 17361914 TELECOMMUNICATIONS SITE LEGEND

TD101 17361915 TELECOMMUNICATIONS SITE DEMOLITION PLAN 1

TD102 17361916 TELECOMMUNICATIONS SITE DEMOLITION PLAN 2

TS101 17361917 TELECOMMUNICATIONS SITE PLAN 1

TS102 17361918 TELECOMMUNICATIONS SITE PLAN 2

TS103 17361919 TELECOMMUNICATIONS SITE PLAN 3

TS104 17361920 TELECOMMUNICATIONS SITE PLAN 4

TS105 17361921 TELECOMMUNICATIONS SITE PLAN 5

TS106 17362001 TELECOMMUNICATIONS SITE PLAN 6

TS107 17362002 TELECOMMUNICATIONS SITE PLAN 7

TS108 17362003 TELECOMMUNICATIONS SITE PLAN 8

TS109 17362004 TELECOMMUNICATIONS SITE PLAN 9

TS501 17361922 TELECOMMUNICATIONS SITE DETAILS

TS502 17361923 TELECOMMUNICATIONS SITE DETAILS

TS701 17361924 TELECOMMUNICATIONS INTERBUILDING BACKBONE RISER

Jacobs D3430603 DOCUMENT 00 01 15 Page 6 10 March 2025

CF101 17361925 OVERALL FUELING PLAN

CF102 17361926 OVERALL COMM PLAN

CF201 17361927 FUEL PLAN AND PROFILE - AREA 1

CF202 17361928 FUEL PLAN AND PROFILE - AREA 2

CF203 17361929 FUEL PLAN AND PROFILE - AREA 3

CF204 17361930 FUEL PLAN AND PROFILE - AREA 4

CF205 17361931 FUEL PLAN AND PROFILE - AREA 5

CF206 17361932 FUEL PLAN AND PROFILE - AREA 6

CF207 17361933 FUEL PLAN AND PROFILE - AREA 7

CF208 17361934 FUEL PLAN AND PROFILE - AREA 8

CF209 17361935 FUEL PLAN AND PROFILE - AREA 9

CF210 17361936 FUEL PLAN AND PROFILE - AREA 10

CF211 17361937 FUEL PLAN AND PROFILE - AREA 11

CF212 17361938 FUEL PLAN AND PROFILE - AREA 12

CF221 17361939 COMM PLAN - AREA 1

CF222 17361940 COMM PLAN - AREA 2

CF223 17361941 COMM PLAN - AREA 3

CF224 17361942 COMM PLAN - AREA 4

CF225 17361943 COMM PLAN - AREA 5

CF226 17361944 COMM PLAN - AREA 6

CF227 17361945 COMM PLAN - AREA 7

CF228 17361946 COMM PLAN - AREA 8

CF229 17361947 COMM PLAN - AREA 9

CF230 17361948 COMM PLAN - AREA 10

CF231 17361949 COMM PLAN - AREA 11

CF232 17361950 COMM PLAN - AREA 12

CF233 17361951 COMM PLAN - AREA 13

CF234 17361952 COMM PLAN - AREA 14

CF501 17361953 FUELING DETAILS

CF502 17361954 FUELING DETAILS

SF001 17361955 STRUCTURAL GENERAL NOTES - SHEET 1

SF002 17361956 STRUCTURAL GENERAL NOTES - SHEET 2

SF003 17361957 LEGENDS AND ABBREVIATIONS

SF101 17361958 OVERALL STRUCTURAL LAYOUT

SF111 17361959 ISOLATION VALVE VAULT 1 - PLANS

SF112 17361960 ISOLATION VALVE VAULT 2 - PLANS - SHEET 1

SF113 17361961 ISOLATION VALVE VAULT 2 - PLAN - SHEET 2

SF114 17361962 HYDRANT PIT - PLANS AND SECTIONS

SF115 17361963 HPV PITS - PLANS AND SECTIONS

SF501 17361964 STANDARD STRUCTURAL DETAILS - SHEET 1

SF502 17361965 STANDARD STRUCTURAL DETAILS - SHEET 2

SF511 17361966 ISOLATION VALVE VAULT - SECTIONS - SHEET 1

SF512 17361967 ISOLATION VALVE VAULT - SECTIONS - SHEET 2

SF513 17361968 ISOLATION VALVE VAULT - SECTIONS AND DETAILS

SF521 17361969 ROLLING COVER - SHEET 1

SF522 17361970 ROLLING COVER - SHEET 2

SF523 17361971 ROLLING COVER - SHEET 3

SF524 17361972 ROLLING COVER - SHEET 4

SF525 17361973 ROLLING COVER - SHEET 5

SF551 17361974 PIPE SUPPORT DETAILS

MF001 17361975 FUELING MECHANICAL LEGEND

MF002 17361976 FUELING MECHANICAL GENERAL NOTES

MF011 17361977 FUELING MECHANICAL FLOW DIAGRAM - OVERALL

MF101 17361978 FUELING MECHANICAL OVERALL SITE PLAN

Jacobs D3430603 DOCUMENT 00 01 15 Page 7 10 March 2025

MF501 17361979 FUELING MECHANICAL DETAILS - ISOLATION VALVE VAULT (IVV-1)

MF502 17361980 FUELING MECHANICAL DETAILS - ISOLATION VALVE VAULT (IVV-2)

MF503 17361981 FUELING MECHANICAL DETAILS

MF504 17361982 FUELING MECHANICAL DETAILS

MF505 17361983 FUELING MECHANICAL DETAILS

MF506 17361984 FUELING MECHANICAL DETAILS

MF601 17361985 FUELING MECHANICAL P&ID

EF001 17361986 ELECTRICAL FUELING LEGEND - 1

EF002 17361987 ELECTRICAL FUELING LEGEND - 2

EF011 17361988 OVERALL FUELING HAZARDOUS AREA PLAN

EF101 17361989 OVERALL FUELING ELECTRICAL SITE PLAN

EF401 17361990 ENLARGED PLAN - PUMPHOUSE

EF501 17361991 ELECTRICAL DETAILS - EPDS

EF502 17361992 ELECTRICAL DETAILS - GROUNDING

EF503 17361993 ELECTRICAL SITE DETAILS - HANDHOLES

EF504 17361994 ELECTRICAL SITE DETIALS - DUCT BANKS

EF511 17361995 ELEVATION - PUMP CONTROL PANEL

EF611 17361996 PCP - CONTROL DIAGRAM

EF621 17361997 NORTH APRON EPDS - FRONT LAYOUT

EF622 17361998 NORTH ARON EPDS WIRING - 1

EK501 17361999 CATHODIC PROTECTION DETAILS

EK501 17362000 CATHODIC PROTECTION DETAILS

1.3 REFERENCE DRAWINGS

The following reference drawings are intended only to show the original construction. Drawing are the property of the Government and must not be used for any purpose other than that intended by the contract.

NAVFAC DWG NO. TITLE

3201807 REPAIR/REPLACE OIL/WATER SEPARATORS BUILDING NO. 2550 JET

ENGINE TEST FACILITY

7320181 REPAIR/REPLACE OIL/WATER SEPARATORS BLDG NO. 2550 JET ENGINE

TEST FACILITY

AND-W-122 CONSTRUCT OIL SEPARATOR WET ENGINE TEST STAND (BLG 2550)

Jacobs D3430603 DOCUMENT 00 01 15 Page 8 10 March 2025

NAVFAC DWG NO. TITLE

AND B-230 CONSTRUCT JET TEST STAND READY ROOM

AND-R-60 AIR CONDITIONING SHAW ESTES JET ENGINE TEST CELL CONTROL RM.

BLDG. 2551

-- End of Document --

Jacobs D3430603 DOCUMENT 00 01 15 Page 9 10 March 2025

THIS PAGE INTENTIONALLY LEFT BLANK

Jacobs D3430603 DOCUMENT 00 01 15 Page 10 10 March 2025

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

08/22, CHG 2: 08/25

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA SW-846 (Third Edition; Update VII) Test Methods for Evaluating Solid Waste:

Physical/Chemical Methods

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1053 Respirable Crystalline Silica

29 CFR 1910.1200 Hazard Communication

29 CFR 1926.1153 Respirable Crystalline Silica

40 CFR 50 National Primary and Secondary Ambient Air Quality Standards

40 CFR 60 Standards of Performance for New Stationary Sources

40 CFR 63 National Emission Standards for Hazardous Air Pollutants for Source Categories

40 CFR 64 Compliance Assurance Monitoring

40 CFR 82 Protection of Stratospheric Ozone

40 CFR 112 Oil Pollution Prevention

40 CFR 122.26 Storm Water Discharges (Applicable to State NPDES Programs, see section 123.25)

40 CFR 241 Guidelines for Disposal of Solid Waste

40 CFR 243 Guidelines for the Storage and Collection of Residential, Commercial, and Institutional Solid Waste

40 CFR 258 Subtitle D Landfill Requirements

40 CFR 260 Hazardous Waste Management System: General

40 CFR 261 Identification and Listing of Hazardous Waste

Jacobs D3430603 SECTION 01 57 19 Page 1 10 March 2025

40 CFR 261.7 Residues of Hazardous Waste in Empty Containers

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 262.11 Hazardous Waste Determination and Recordkeeping

40 CFR 263 Standards Applicable to Transporters of Hazardous Waste

40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 273 Standards for Universal Waste Management

40 CFR 279 Standards for the Management of Used Oil

40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan

40 CFR 300.125 National Oil and Hazardous Substances Pollution Contingency Plan - Notification and Communications

40 CFR 355 Emergency Planning and Notification

40 CFR 372 Toxic Chemical Release Reporting

40 CFR 403 General Pretreatment Regulations for Existing and New Sources of Pollution

40 CFR 745 Lead-Based Paint Poisoning Prevention in Certain Residential Structures

40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions

49 CFR 171 General Information, Regulations, and Definitions

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

Jacobs D3430603 SECTION 01 57 19 Page 2 10 March 2025

49 CFR 172.101 Hazardous Material Regulation-Purpose and Use of Hazardous Material Table

49 CFR 173 Shippers - General Requirements for Shipments and Packagings

49 CFR 178 Specifications for Packagings

GUAM CODE ANNOTATED (GCA)

10 GCA CH47 Water Pollution Control

10 GCA CH49 Air Pollution Control Act

10 GCA CH50 Guam Pesticides Act

10 GCA CH51 Solid Waste Management and Litter Control

10 GCA CH76 Storage of Hazardous Materials

22 GCA CH32 Professional Engineers, Architects, and Land Surveyors Law

GUAM ADMINISTRATIVE RULES AND REGULATIONS (GAR)

22 GAR DIV1 CH1 Guam Air Pollution Control Act

22 GAR DIV2 CH5 Guam Water Quality Standards

22 GAR DIV2 CH10 Guam Soil Erosion and Sediment Control Regulations

22 GAR DIV3 CH15 Pesticides

22 GAR DIV4 CH20 Solid Waste Disposal Regulations

22 GAR DIV2 CH30 Hazardous Waste Management

22 GAR DIV9 CH45 Soil Erosion and Sedimentation Control

22 GAR DIV10 CH50 Underground Storage Tanks

Department of the Air Force

Final EIS (2025) Final Environmental Impact Statement for F-15 Beddown and Infrastructure Upgrade at Andersen Air Force Base, Guam

ICRMP (2015) Andersen Air Force Base Integrated Cultural Resources Management Plan

Data Recovery Plan (2025) Data Recovery Plan for Sites 66-07-2113, 66-07-2117, 66-07-2118, and 66-08-2981 (Fafalog), Andersen Air Force Base, Guam

Jacobs D3430603 SECTION 01 57 19 Page 3 10 March 2025

U.S. Fish and Wildlife Service

2025 BO Biological Opinion for Expansions of Aircraft Operations Area at Northwest Field, and Munitions Storage Area (MSA-1), Andersen Air Force Base, Guam, 25 February

HACCP Manual (2019) HACCP Hazard Analysis and Critical Control Point Planning to Prevent the Spread of Invasive Species

1.2 DEFINITIONS

1.2.1 State

"State" when used in reference to states of the United States, also includes the Territory of Guam.

1.2.2 Class I and II Ozone Depleting Substance (ODS)

Class I ODS is defined in Section 602(a) of The Clean Air Act. A list of Class I ODS can be found on the EPA website at the following weblink.

https://www.epa.gov/ozone-layer-protection/ozone-depleting-substances .

Class II ODS is defined in Section 602(s) of The Clean Air Act. A list of Class II ODS can be found on the EPA website at the following weblink.

https://www.epa.gov/ozone-layer-protection/ozone-depleting-substances .

1.2.3 Contractor Generated Hazardous Waste

Contractor generated hazardous waste is materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e., methyl ethyl ketone, toluene), waste thinners, excess paints, excess solvents, waste solvents, excess pesticides, and contaminated pesticide equipment rinse water.

1.2.4 Electronics Waste

Electronics waste is discarded electronic devices intended for salvage, recycling, or disposal.

1.2.5 Environmental Pollution and Damage

Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally or historically.

1.2.6 Environmental Protection

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction.

The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes

Jacobs D3430603 SECTION 01 57 19 Page 4 10 March 2025 management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

1.2.7 Hazardous Debris

As defined in paragraph SOLID WASTE, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) in accordance with 40 CFR 261 . Hazardous debris also includes debris that exhibits a characteristic of hazardous waste in accordance with 40 CFR 261 .

1.2.8 Hazardous Materials

Hazardous material is any material that: Is defined in 49 CFR 171 , listed in 49 CFR 172 , regulated as a hazardous material in accordance with 49 CFR 173 ; or requires a Safety Data Sheet (SDS) in accordance with 29 CFR 1910.1200 ; or during end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, C, or D. Designation of a material by this definition, when separately regulated or controlled by other sections or directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this section for "control" purposes. Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).

1.2.9 Hazardous Waste

Hazardous Waste is any material that meets the definition of a solid waste and exhibits a hazardous characteristic (ignitability, corrosivity, reactivity, or toxicity) as specified in 40 CFR 261 , Subpart C, or contains a listed hazardous waste as identified in 40 CFR 261 , Subpart D, or meets a state, local, or host nation definition of a hazardous waste.

1.2.10 Land Application

Land Application means spreading or spraying discharge water at a rate that allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur.

Comply with federal, state, and local laws and regulations.

1.2.11 Municipal Separate Storm Sewer System (MS4) Permit

MS4 permits are those held by municipalities or installations to obtain NPDES permit coverage for their stormwater discharges.

1.2.12 National Pollutant Discharge Elimination System (NPDES)

The NPDES permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.

1.2.13 Oily Waste

Oily waste are those materials that are, or were, mixed with Petroleum, Jacobs D3430603 SECTION 01 57 19 Page 5 10 March 2025

Oils, and Lubricants (POLs) and have become separated from that POLs.

Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, POLs and may be appropriately tested and discarded in a manner which is in compliance with other state and local requirements.

This definition includes materials such as oily rags, "kitty litter" sorbent clay and organic sorbent material. These materials may be land filled provided that: It is not prohibited in other state regulations or local ordinances; the amount generated is "de minimus" (a small amount);

it is the result of minor leaks or spills resulting from normal process operations; and free-flowing oil has been removed to the practicable extent possible. Large quantities of this material, generated as a result of a major spill or in lieu of proper maintenance of the processing equipment, are a solid waste. As a solid waste, perform a hazardous waste determination prior to disposal. As this can be an expensive process, it is recommended that this type of waste be minimized through good housekeeping practices and employee education.

1.2.14 Regulated Waste

Regulated waste are solid wastes that have specific additional federal, state, or local controls for handling, storage, or disposal.

1.2.15 Sediment

Sediment is soil and other debris that have eroded and have been transported by runoff water or wind.

1.2.16 Solid Waste

Solid waste is a solid, liquid, semi-solid or contained gaseous waste. A solid waste can be a hazardous waste, non-hazardous waste, or non-Resource Conservation and Recovery Act (RCRA) regulated waste. Types of solid waste typically generated at construction sites may include:

1.2.16.1 Debris

Debris is non-hazardous solid material generated during the construction, demolition, or renovation of a structure that exceeds 2.5-inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (for example, cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials may be reinforced with or contain ferrous wire, rods, accessories and weldments. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.

1.2.16.2 Green Waste

Green waste is the vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.

Jacobs D3430603 SECTION 01 57 19 Page 6 10 March 2025

1.2.16.3 Material Not Regulated As Solid Waste

Material not regulated as solid waste is nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended; suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges;

regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.

1.2.16.4 Non-Hazardous Waste

Non-hazardous waste is waste that is excluded from, or does not meet, hazardous waste criteria in accordance with 40 CFR 261 .

1.2.16.5 Recyclables

Recyclables are materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable, wiring, insulated/non-insulated copper wire cable, wire rope, and structural components. It also includes commercial-grade refrigeration equipment with Freon removed, household appliances where the basic material content is metal, clean polyethylene terephthalate bottles, cooking oil, used fuel oil, textiles, high-grade paper products and corrugated cardboard, stackable pallets in good condition, clean crating material, and clean rubber/vehicle tires. Metal meeting the definition of "lead contaminated" or "lead based paint contaminated" may be included as recyclable only if the metal is handled and transported in accordance with regulations, and the facility receiving the material is permitted and authorized to accept and process lead contaminated materials. Paint cans that meet the definition of empty containers in accordance with 40 CFR 261.7 may be included as recyclable if sold to a scrap metal company.

1.2.16.6 Surplus Soil

Surplus soil is existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars, and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included and must be managed in accordance with paragraph HAZARDOUS MATERIAL MANAGEMENT.

1.2.16.7 Scrap Metal

This includes scrap and excess ferrous and non-ferrous metals such as reinforcing steel, structural shapes, pipe, and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.

1.2.16.8 Wood

Wood is dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included. Treated wood includes, but is not limited to, lumber, utility poles, crossties, and other wood products with chemical treatment.

1.2.17 Surface Discharge

Surface discharge means discharge of water into drainage ditches, storm

Jacobs D3430603 SECTION 01 57 19 Page 7 10 March 2025 sewers, or creeks meeting the definition of "waters of the United States". Surface discharges from construction sites are discrete, identifiable sources and require a permit from the governing agency.

Comply with federal, state, and local laws and regulations.

1.2.18 Wastewater

Wastewater is the aqueous liquid waste generated by a project, to include both domestic wastewater (sewage) and industrial wastewater.

1.2.18.1 Stormwater

Stormwater is any precipitation in an urban or suburban area that does not evaporate or soak into the ground, but instead collects and flows into storm drains, rivers, and streams.

1.2.19 Waters of the United States

Waters of the United States means Federally jurisdictional waters, including wetlands, that are subject to regulation under Section 404 of the Clean Water Act or navigable waters, as defined under the Rivers and Harbors Act.

1.2.20 Wetlands

Wetlands are those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.

1.2.21 Universal Waste

The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (for example, thermostats), and lamps (for example, fluorescent bulbs). The rule is designed to reduce hazardous waste in the municipal solid waste (MSW) stream by making it easier for universal waste handlers to collect these items and send them for recycling or proper disposal. These regulations can be found at 40 CFR 273 . The Guam Environmental Protection Agency (Guam EPA or GEPA) has not adopted the Universal Regulation Rule. Comply with the GEPA regulations and requirements.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Contractor Hazardous Material Inventory Log ; G

Storage Material Inventory

Preconstruction Survey

Regulatory Notifications

Jacobs D3430603 SECTION 01 57 19 Page 8 10 March 2025

Environmental Manager Qualifications

Employee Training Records

Environmental Protection Plan ; G

Dirt and Dust Control Plan

Solid Waste Management Permit

Stormwater Pollution Prevention Plan (SWPPP); G

Stormwater Notice of Intent (for NPDES coverage under the general permit for construction activities)

Spill Prevention Control and Countermeasure (SPCC) Plan ; G

Hazard Analysis and Critical Control Point (HACCP) Plan ; G

GEPA Clearing, Grubbing, Grading, and Stockpiling Permit / General Permit Application ; G

Final Work Plan for Tarague Forest Enhancement Area ; G

Draft Work Plan for Tarague Forest Enhancement Area ; G

Draft Natural Resource Work Plan ; G

Final Natural Resource Work Plan ; G

Natural Resource Field Assessment Report for P-012 Construction Footprint ; G

Natural Resource Field Assessment Report for Tarague Forest Enhancement Area ; G

Archaeological Monitoring and Discovery Plan ; G

SD-02 Shop Drawings

Alignment of Ungulate Fence ; G

SD-06 Test Reports

Monthly Solid Waste Disposal Report ; G

SWPPP Inspection Reports

Laboratory Analysis

SD-07 Certificates

ECATTS Certificate of Completion ; G

Employee Training Records ; G

Erosion and Sediment Control Inspector Qualifications

Jacobs D3430603 SECTION 01 57 19 Page 9 10 March 2025

Qualification of Qualified Biologist(S) ; G

Qualification of Archaeologist(s) ; G

SD-10 Operation and Maintenance Data

Weekly Natural Resources Conservation Status Report ; G

Monthly Natural Resources Conservation Progress Report ; G

Annual Natural Resources Conservation Progress Report ; G

Reports and Submittals required by Data Recovery Plan ; G

End of Field (EOF) Letter for Archaeological Monitoring - Tarague

FEA; G

SD-11 Closeout Submittals

Contractor Hazardous Material Inventory Log ; G

Regulatory Notifications ; G

Assembled Employee Training Records ; G

Solid Waste Management Permit ; G

Stormwater Pollution Prevention Plan Compliance Notebook ; G

Stormwater Notice of Termination (for NPDES coverage under the general permit for construction activities); G

As-Built Topographic Survey

Waste Determination Documentation ; G

Project Solid Waste Disposal Documentation Report ; G

Sales Documentation ; G

Contractor Certification

Hazardous Waste/Debris Management ; G

Disposal Documentation for Hazardous and Regulated Waste ; G

Draft Natural Resources Conservation Report ; G

Final Natural Resources Conservation Report ; G

Weekly archaeological monitoring report-Tarague FEA ; G

Draft Archaeological Monitoring Report-Tarague FEA ; G

Final Archaeological Monitoring Report-Tarague FEA ; G

1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS

Provide and maintain, during the life of the contract, environmental

Jacobs D3430603 SECTION 01 57 19 Page 10 10 March 2025 protection as defined. Plan for and provide environmental protective measures to control pollution that develops during construction practice.

Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.

Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by law, the laboratories must be certified.

1.4.1 Training in Environmental Compliance Assessment Training and Tracking System (ECATTS)

1.4.1.1 Personnel Requirements

The Environmental Manager is responsible for environmental compliance on projects. The Environmental Manager and other environmental staff, must complete applicable ECATTS training modules (installation specific or general) prior to starting respective portions of on-site work under this Contract. If personnel changes occur for any of these positions after starting work, replacement personnel must complete applicable ECATTS training within 14 days of assignment to the project.

1.4.1.2 Certification

Submit an ECATTS certificate of completion for personnel who have completed the required ECATTS training. This training is web-based and can be accessed from any computer with Internet access using the following instructions.

Register for NAVFAC Environmental Compliance Assessment, Training, and Tracking System, by logging on to https://environmentaltraining.ecatts.com/ .

Obtain the password for registration from the Contracting Officer.

1.4.1.3 Refresher Training

This training has been structured to allow contractor personnel to receive credit under this contract and to carry forward credit to future contracts. Ensure the Environmental Manager review their training plans for new modules or updated training requirements prior to beginning work.

Some training modules are tailored for specific state regulatory requirements; therefore, Contractors working in multiple states will be required to retake modules tailored to the state where the contract work is being performed.

1.4.2 Conformance with the Environmental Management System

Perform work under this contract consistent with the policy and objectives identified in the installation's Environmental Management System (EMS).

Perform work in a manner that conforms to objectives and targets of the environmental programs and operational controls identified by the EMS.

Support Government personnel when environmental compliance and EMS audits are conducted by escorting auditors at the Project site, answering

Jacobs D3430603 SECTION 01 57 19 Page 11 10 March 2025 questions, and providing proof of records being maintained. Provide monitoring and measurement information as necessary to address environmental performance relative to environmental, energy, and transportation management goals. In the event an EMS nonconformance or environmental noncompliance associated with the contracted services, tasks, or actions occurs, take corrective and preventative actions. In addition, employees must be aware of their roles and responsibilities under the installation EMS and of how these EMS roles and responsibilities affect work performed under the contract.

Coordinate with the installation's EMS coordinator to identify training needs associated with environmental aspects and the EMS, and arrange training or take other action to meet these needs. Provide training documentation to the Contracting Officer. The Installation Environmental Office will retain associated environmental compliance records. Make EMS Awareness training completion certificates available to Government auditors during EMS audits and include the certificates in the Employee Training Records. See paragraph EMPLOYEE TRAINING RECORDS.

1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS

Comply with the special environmental requirements listed here and attached at the end of this section.

Attachment B. Data Recovery Plan for Sites 66-07-2113, 66-07-2117, 66-07-2118, and 66-08-2981 (Fafalog), Andersen Air Force Base, Guam. Conduct data recovery for the archaeological sites that will be impacted/disturbed by the project.

Attachment C. P-012 Permits Record of Decision (PROD): Obtain all required environmental or construction permits and approvals listed in the PROD. Obtain any additional permits or approvals needed but not listed in the PROD at no cost to the Government.

Attachment D. Environmental Mitigations presented in the 2025 Final Environmental Impact Statement ( Final EIS ) for F-15 Beddown and Infrastructure Upgrade at Andersen Air Force Base, Guam. Comply with the environmental mitigation requirements.

Attachment E. Natural Resources Requirements specified in the Biological Opinion ( 2025 BO ) for Expansions of Aircraft Operations Area at Northwest Field, and Munitions Storage Area (MSA-1), Andersen Air Force Base, Guam, 25 February 2025.

Attachment F. Natural Resources Performance Work Statement (PWS)

1.5.1 Abandoned Waste Debris

Refer to the Project Demolition Plan (CD-series). Remove and dispose of stockpiles and waste debris. Refer to the Visual Stockpile Observation Report included in Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL. The site includes abandoned waste debris. Waste debris contains asbestos transite pipes and lead paints. Refer to the Hazardous Material Survey Report for the asbestos transite pipes and lead paints. The report is provided at the end of Section 02 82 00 ASBESTOS

REMEDIATION.

Jacobs D3430603 SECTION 01 57 19 Page 12 10 March 2025

1.5.2 PFAS Contamination and G-RAM/LLRW

Refer to Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL; Attachment A, Soil Management Plan; and Attachment B, G-RAM/LLRW Performance Work Statement.

The project site include PFAS-impacted areas and potential General Radioactive Material (G-RAM)/Low-Level Radioactive Waste (LLRW) Area.

Implement Section 02 61 13 and Section Attachments A and B.

1.5.3 Sinkhole Protection

Sinkholes are present in the vicinity of project sites. Provide the sinkhole mitigation plan and submittals for Government and GEPA review and approval. Obtain Class V Underground Injection Control (UIC) Permits for three exising sinkholes.

1.5.4 Pacific

Comply with the following state, regional and local requirements.

1.5.4.1 Control and Disposal of Ionization Smoke Detectors or Tritium Exit Signs

1.5.4.1.1 Material Bagging

Remove existing ionization smoke detectors and tritium exit signs, and place like types, together (that is same manufacturer and model number) in a plastic bag. Label the bag with the following data:

Manufacturer: Activity:

MODEL No.: Contract No.:

Isotope and Quantity (if known):

1.5.4.1.2 Material Storage

Store plastic bags in 55 gallon covered drum(s). Do not seal the drum(s). Provide a label with a description of the contents and note on the label "TO BE DISPOSED OF BY RASO". Apply the label to the exterior surface of the cover and site of the drum(s). Provide a record copy of the label for each drum storage material inventory to the Contracting Officer, and the RASO.

1.5.4.2 Guam

Comply with all applicable Guam regulations, requirements, and guidance including but are not limited to: HACCP Manual ; 10 GCA CH47 ; 10 GCA CH49 ;

10 GCA CH50 ; 10 GCA CH51 ; 10 GCA CH76 ; 22 GCA CH32 ; 22 GCA CH32 ;

22 GAR DIV1 CH1 ; 22 GAR DIV1 CH1 ; 22 GAR DIV2 CH5 ; 22 GAR DIV2 CH10 ;

22 GAR DIV3 CH15 ; 22 GAR DIV4 CH20 ; 22 GAR DIV2 CH30 ; 22 GAR DIV9 CH45 ;

22 GAR DIV10 CH50 ; and the CNMI and Guam Stormwater Management Manual, prepared by Horsley Witten Group Inc, dated (October 2006, as amended).

1.5.4.2.1 Demarcate Project Limits

Under General Provision section of 22 GCA CH 32 , use a Professional Land Surveyor in order to layout/demarcate the project limits. Demarcate the limits of construction and use a licensed professional land surveyor to delineate project limits. The limits of construction are to be clearly

Jacobs D3430603 SECTION 01 57 19 Page 13 10 March 2025 marked in the field and must be maintained throughout the duration of construction. Use durable, high-visibility tape/rope (unless a physical feature exists at the limit e.g. fence). The marked limits must be on or within the project boundary presented in the project plan.

1.6 QUALITY ASSURANCE

1.6.1 Preconstruction Survey and Protection of Features

This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to start of any onsite construction activities, perform a Preconstruction Survey of the project site with the Contracting Officer, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record. Include in the report a plan describing the features requiring protection under the provisions of the Contract Clauses, which are not specifically identified on the drawings as environmental features requiring protection along with the condition of trees, shrubs and grassed areas immediately adjacent to the site of work and adjacent to the Contractor's assigned storage area and access route(s), as applicable. The Contractor and the Contracting Officer will sign this survey report upon mutual agreement regarding its accuracy and completeness. Protect those environmental features included in the survey report and any indicated on the drawings, regardless of interference that their preservation may cause to the work under the Contract.

1.6.2 Regulatory Notifications

Provide regulatory notification requirements in accordance with federal, state and local regulations. In cases where the Government will also provide public notification (such as stormwater permitting), coordinate with the Contracting Officer. Submit copies of regulatory notifications to the Contracting Officer at least 30 days prior to commencement of work activities. Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).

1.6.3 Environmental Brief

Attend an environmental brief to be included in the preconstruction meeting. Provide the following information: types, quantities, and use of hazardous materials that will be brought onto the installation; and types and quantities of wastes/wastewater that may be generated during the Contract. Discuss the results of the Preconstruction Survey at this time.

Prior to initiating any work on site, meet with the Contracting Officer and installation Environmental Office to discuss the proposed Environmental Protection Plan (EPP) or equipment local requirement.

Develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as mitigation measures), and other measures to be taken.

1.6.4 Environmental Manager

Appoint in writing an Environmental Manager for the project site. The Environmental Manager is directly responsible for coordinating contractor

Jacobs D3430603 SECTION 01 57 19 Page 14 10 March 2025 compliance with federal, state, local, and installation requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements (including hazardous waste handling, storage, manifesting, and disposal); implement the EPP; ensure environmental permits are obtained, maintained, and closed out; ensure compliance with Stormwater Program requirements; ensure compliance with Hazardous Materials (storage, handling, and reporting) requirements; and coordinate any remediation of regulated substances (lead, asbestos, PCB transformers, PFAS-contaminated soil, G-RAM/LLRW).