1-26R1300_Amd0004-Issued.pdf
PDF 659 KB Posted
- Attached to
- WON 1665555, FY24 AJJY183012 (P-012), PDI: NORTH AIRCRAFT PARKING RAMP, ANDERSEN AIR FORCE BASE, GUAM
- Solicitation number
- N62742-26-R-1300
About this file
This is Amendment No. 0004 to Request for Proposal (RFP) N62742-26-R-1300 for the North Aircraft Parking Ramp project at Andersen Air Force Base, Guam. The amendment, effective 22 May 2026, was issued by NAVFAC SYSCOM PACIFIC and is administered by the Naval Facilities Engineering Systems Command. The solicitation number is N6274226R1300, originally dated 11 February 2026. The amendment updates the Solicitation, Offer, and Award (SF 1442) Price Proposal Schedule and replaces multiple specification sections and technical drawings dated 22 May 2026, including revisions to work restrictions, quality control, temporary environmental controls, earthwork, asphalt paving, aviation fuel piping, liquid fuels pipeline coating systems, and telecommunications outside plant specifications.
The project requires firm-fixed-price offers on an "all or none" basis with pricing for 13 line items covering the complete construction project (SLIN 0001AA) and contingent work items including karst feature mitigation using permeable and impermeable infill (9,000 cubic yards each), cultural resources investigations and discovery (ranging from one-day inspections to large site investigations and human skeletal remains recovery), Electrical Resistivity Tomography testing (42,000 linear feet), and disposal of abandoned debris and hazardous materials (concrete debris, waste debris excluding concrete, hazardous waste, hazardous liquid waste in 55-gallon drums, and asbestos-containing waste). Payment for contingent items will be based on actual quantities only, subject to FAR 52.211-18 variation in estimated quantity clause, with equitable adjustment if quantities vary more than 15 percent above or below estimates. Contractors must provide treatment plans, archaeological monitoring plans, and discovery protocols as pre-construction submittals, with all plans and reports subject to Government and Guam State Historic Preservation Office approval.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
Created On:
23 May 2026, 01:55 AM Greenwich Mean Time
N6274226R13000004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE5
SUMMARY OF CHANGES
The following items are applicable to this Amendment:
SOLICITATION, OFFER, AND AWARD (SF1442), PRICE PROPOSAL SCHEDULE
Delete the Solicitation, Offer and Award (Construction, Alteration, or Repair), Standard Form (SF) 1442, Price Proposal Schedule, Page 3 of 6 through Page 6 of 6 (Amendment No. 0002) and replace with the attached revised Solicitation, Offer, and Award (Construction, Alteration, or Repair), SF1442, Price Proposal Schedule, Page 3 of 6 through Page 6 of 6 (Amendment No.
0004).
SPECIFICATIONS
DOCUMENT 00 01 15 – LIST OF DRAWINGS
Remove Replace with
Pages 1 to 10 Page 1 to 10
Amendment No. 0003 Amendment No. 0004
DELETE and REPLACE the following drawings dated 22 May 2026 that accompany this Amendment:
DRAWING
NUMBER
NAVFAC
DRAWING
NUMBER REVISION NUMBER
DRAWING TITLE
G-003 17361626 2 SHEET INDEX
CD107 17361687 2 DEMOLITION PLAN – AREA 6
CS501 17361778 2 SITE DETAILS
CS502 17361779 2 SITE DETAILS
CS503 17361780 1 SITE DETAILS
CG146 17361841 2 KARST FEATURES DETAIL
ES105 17361894 1 ELECTRICAL SITE PLAN 5
ES503 17361898 1 ELECTRICAL SITE DETAILS
ES505 17361900 1 ELECTRICAL SITE DETAILS –
TS104 17361920 2 TELECOMMUNICATIONS
SITE PLAN 4
TS109 17362004 2 TELECOMMUNICATIONS
SITE PLAN 9
TS701 17361924 2 TELECOMMUNICATIONS
INTERBUILDING BACKBONE
RISER
TS702 17362011 1 TELECOMMUNICATIONS
INTERBUILDING BACKBONE
RISER
CF101 17361925 1 OVERALL FUELING PLAN
SECTION 01 14 00 – WORK RESTRICTIONS
Remove Replace with
Pages 1 to 8 Page 1 to 8
Amendment No. 0004
SECTION 01 45 00 – QUALITY CONTROL
Pages 1 to 24 Page 1 to 24
SECTION 01 57 19 – TEMPORARY ENVIRONMENTAL CONTROLS
Pages 1 to 40 Page 1 to 40
SECTION 01 57 19 – ATTACHMENT
Attachment H. Final Record of Decision Site 78 Site-Wide Operable Unit Andersen Air Force Base, Guam
Add
Pages 1 to 77
SECTION 02 82 00 – ASBESTOS REMEDIATION
Pages 1 to 34 Page 1 to 34
SECTION 31 00 00 – EARTHWORK
Pages 1 to 26 Page 1 to 26
SECTION 32 11 20 – BASE COURSE FOR RIGID PAVING
Pages 1 to 10 Page 1 to 10
SECTION 32 12 15.13 – ASPHALT PAVING FOR AIRFIELDS
Pages 1 to 28 Page 1 to 32
SECTION 33 52 43.13 – AVIATION FUEL PIPING
Pages 1 to 20 Page 1 to 22
SECTION 33 52 80 – LIQUID FUELS PIPELINE COATING SYSTEMS
Pages 1 to 32 Page 1 to 34
SECTION 33 82 00 – TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
Pages 1 to 24 Page 1 to 24
--End of Amendment--
SOLICITATION, OFFER AND AWARD (SF 1442), CONTINUED
PRICE PROPOSAL SCHEDULE
FOR
RFP NO. N62742-26-R-1300
WON 1665555, FY24 AJJY183012 (P-012), PDI: NORTH AIRCRAFT PARKING RAMP,
ANDERSEN AIR FORCE BASE, GUAM
RFP N62742-26-R-1300
SF1442 (Continued)
ITEM
NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001AA BASE ITEM
The basis for SLIN 0001AA is the entire work for Project P-012 (WON 1665555) complete in accordance with the drawings and specifications, except the work identified in any other CLIN/SLIN.
Note: Includes the cost for the treatment plans that are to be included in SD-01 Pre- Construction Submittals, Archaeological Monitoring and Discovery Plan.
Project
ESTIMATED
0001AB Permeable Infill Karst Feature Mitigation
The basis for SLIN 0001AB is for mitigation of Karst Features using permeable infill (Zone 2) complete in accordance with drawings and specifications, but not including work specified in any other CLIN/SLINs.
9,000
CY
$_____/CY
0001AC Impermeable Infill Karst Feature Mitigation
The basis for SLIN 0001AC is for mitigation of Karst Features using impermeable infill (Zone
1) complete in accordance with drawings and specifications, but not including work specified in any other CLIN/SLINs.
9,000
CY
$_____/CY
0001AD One-Day Cultural Resources Feature Investigations
The basis for SLIN 0001AD is for One-Day Cultural Resources Feature Investigations for project P-012 in accordance with drawings and specifications, but not including work specified in any other SLINs/CLINs.
See Note 7. below.
EA
$_____/EA
FOR
RFP NO. N62742-26-R-1300
0001AE Cultural Resources Post Review Discovery
(Small Sites)
The basis for SLIN 0001AE are Cultural Resources Post Review Discovery for small sites (equal to or less than 0.5 hectares) for project P-012 in accordance with drawings and specifications, but not including work specified in any other SLINs/CLINs.
See Note 8. below.
0001AF Cultural Resources Post Review Discovery (Large Sites)
The basis for SLIN 0001AF is a Cultural Resources Post Review Discovery for a large site (greater than 0.5 hectares) for project P- 012 in accordance with drawings and specifications, but not including work
See Note 9. below.
0001AG Cultural Resources Post Review Discovery of Human Skeletal Remains
The basis for SLIN 0001AG are Cultural Resources Post Review Discovery of Human Skeletal Remains for project P-012 in accordance with drawings and specifications, but not including work specified in any other SLINs/CLINs.
See Note 10. below.
0001AH Electrical Resistivity Tomography (ERT) Testing
The basis for SLIN 0001AH is to conduct ERT testing in areas approved by the contracting officer, in accordance with drawings and specifications, but not including work specified in any other
42,000
LF
$_____/LF
FOR
RFP NO. N62742-26-R-1300
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AH
(Continued)
Note: ERT testing costs include all geophysicist roles, responsibilities, frequencies, and durations as identified in the specifications
0001AI Abandoned Concrete Debris/Stockpile
The basis of SLIN 0001AI is the price for all labor, temporary stockpiling, material, testing, and equipment for disposal of abandoned waste debris/ stockpiles in accordance with the drawings and specifications, but not including work
See Note 11. below.
2,000
Ton
$_____/Ton
0001AJ Abandoned Waste Debris Stockpile Excluding Concrete Debris
The basis of SLIN 0001AJ is the price for all labor, temporary stockpiling, material, testing, and equipment for disposal of abandoned waste debris stockpiles, excluding concrete debris, in accordance with the drawings and specifications, but not including work specified in any other
See Note 12. below.
0001AK Abandoned Hazardous Waste
The basis of SLIN 0001AK the price for all labor, temporary stockpiling, material, testing, and equipment for disposal of abandoned hazardous waste in accordance with the drawings and specifications, but not including work specified in any other
See Note 13. below.
FOR
RFP NO. N62742-26-R-1300
ESTIMATED
0001AL Abandoned Hazardous Liquid Waste
The basis of SLIN 0001AL is the price for all labor, temporary storage, material, testing, and equipment for disposal of abandoned hazardous liquid waste in accordance with the drawings and specifications, but not including work specified in any other SLINs/CLINs.
See Note 14. below.
55-gal drum
$_____/drum
0001AM Abandoned Asbestos Containing Waste Not Listed In Section 02 82 00
The basis of SLIN 0001AM is the price for all labor, temporary stockpiling, material, testing, and equipment for disposal of abandoned asbestos containing waste that are not listed in Section 02 82 00 ASBESTOS REMEDIATION, Part 1.3.1 Description of Work.
See Note 15. below.
TOTAL CLIN 0001
(includes SLINs 0001AA through 0001AM)
Notes:
1. See Document 00 22 00 for the Price Evaluation.
2. A firm-fixed-price is required for all line items. The following applies:
ALL OR NONE OFFERS - Offers are solicited on an “all or none” basis and FAR 52.215-1, INSTRUCTIONS TO OFFERORS- COMPETITIVE ACQUISITION in Document 00 21 16, is hereby modified. Failure to submit offers for all line items listed shall be cause for rejection of the offer.
3. The Offeror SHALL include a price for ALL CLINs/SLINs.
4. Multiple awards will not be made.
5. In the event there is a difference between a unit price (s) and the extended total(s), the unit price(s) will be held to be the intended offer and the total(s) recomputed accordingly. If an offer provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
FOR
RFP NO. N62742-26-R-1300
6. Payment for SLINs 0001AB through 0001AM shall be for actual quantities only. The unit prices will be used to adjust the contract price for any increase or decrease in the estimated quantities subject to the following clause:
FAR 52.211-18, VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
(End of clause)
7. 0001AD. One-Day Cultural Resources Feature Investigations – The basis for SLIN 0001AD is to inspect suspected archaeological resources, if discovered, to determine the nature, context, and preliminary significance in accordance with SOP #8 Post-Review Discovery of Archaeological Remains, including preparation and implementation of a treatment plan including testing and analysis and preparation of required reports. The data recovery plan attached in Section 01 57 19 provides general archaeological information for the site. Assume the suspected findings are small and the inspection can be completed in one day by a qualified archaeologist. Provide an inspection report including findings, preliminary significance, photographs, and recommendations. (NOTE: The treatment plan is to be included in SD-01 Pre-Construction Submittals, Archaeological Monitoring and Discovery Plan, of Section 01 57 19, and the cost included in SLIN 0001AA.) All plans and reports must be reviewed and approved by the Government and Guam SHPO.
8. 0001AE. Cultural Resources Post Review Discovery (Small Sites) - The basis for SLIN 0001AE is the Cultural Resources Post
Review Discovery located in a small site, which is equal to or less than 0.5 hectares. The data recovery shall be conducted in accordance with the SOP #8 Post-Review Discovery of Archeological Remains, including preparation and implementation of a treatment plan including testing and analysis and preparation of required reports. The data recovery plan attached in Section 01 57 19 provides general archaeological information for the site. Contractors must determine the level of effort, including the anticipated number and size of features. (NOTE: The treatment plan is to be included in SD-01 Pre- Construction Submittals, Archaeological Monitoring and Discovery Plan, of Section 01 57 19, and the cost included in SLIN 0001AA.) All plans and reports must be reviewed and approved by the Government and Guam SHPO.
9. 0001AF. Cultural Resources Post Review Discovery (Large Sites) - The basis for SLIN 0001AF is the Cultural Resources Post
Review Discovery located in a large site, which is greater than 0.5 hectares. The data recovery shall be conducted in accordance with the SOP #8 Post-Review Discovery of Archeological Remains, including preparation and implementation of a treatment plan including testing and analysis and preparation of required reports. The data recovery plan attached in Section 01 57 19 provides general archaeological information for the site. Contractors must determine the level of effort, including the anticipated number and size of features. (NOTE: The treatment plan is to be included in SD-01 Pre- Construction Submittals, Archaeological Monitoring and Discovery Plan, of Section 01 57 19, and the cost included in SLIN 0001AA.) All plans and reports must be reviewed and approved by the Government and Guam SHPO.
10. 0001AG. Cultural Resources Post Review Discovery of Human Skeletal Remains - . The basis for SLIN 0001AG is the price to recover a burial in accordance with the SOP #9 Post-Review Discovery of Human Remains. The Contractor shall prepare and implement a burial treatment plan, including testing and analysis, and preparation of required reports. (NOTE: The treatment plan is to be included in SD-01 Pre-Construction Submittals, Archaeological Monitoring and Discovery Plan, of Section 01 57 19, and the cost included in SLIN 0001AA.) All plans and reports must be reviewed and approved by the Government and Guam SHPO.
FOR
RFP NO. N62742-26-R-1300
11. 0001AI. Abandoned Concrete Debris/Stockpile – The basis for SLIN 0001AI is the price to recycle or dispose of abandoned
Concrete debris/stockpile. The cost must include waste characterization, sampling and analysis, excavation, segregation if required, stockpile management, packaging for shipping and hauling, and transportation. Assume disposal at a permitted recycling or disposal facility in Guam. It is acceptable to reuse onsite after processing concrete debris if the material meets the project requirements.
12. 0001AJ. Abandoned Waste Debris Stockpiles excluding Concrete Debris – The basis for SLIN 0001AJ is the price to dispose of abandoned waste debris stockpiles excluding concrete debris. The cost must include waste characterization, sampling and analysis, excavation, segregation if required, stockpile management, packaging for shipping and hauling, and transportation.
Assume disposal at a permitted disposal facility in Guam. The abandoned waste debris may include, but is not limited to, scrap metal, plastics, and rubber.
13. 0001AK. Abandoned Hazardous Waste – The basis for SLIN 0001AK is the price to dispose of abandoned hazardous waste. The cost must include waste characterization, sampling and analysis, excavation, segregation if required, stockpile management, packaging for shipping and hauling, and transportation. Assume disposal at a permitted hazardous waste disposal facility in the mainland, U.S.
14. 0001AL. Abandoned Hazardous Liquid Waste – The basis for SLIN 0001AL is the price to dispose of abandoned hazardous liquid waste. The cost must include waste characterization, sampling and analysis, excavation, segregation if required, storage, packaging for shipping and hauling, and transportation. Assume disposal at a permitted hazardous waste disposal facility in the mainland, U.S.
15. 0001AM. Abandoned Asbestos Containing Waste Not Listed in Section 02 82 00 – The basis for SLIN 0001AM is the price to dispose of abandoned asbestos containing waste that are not listed in Section 02 82 00 ASBESTOS REMEDIATION, Part
1.3.1 Description of Work. The cost must include worker protection, asbestos removal work, waste characterization, sampling and analysis, excavation, segregation if required, stockpile management, package for shipping and hauling, and transportation. Assume disposal of asbestos-containing waste in a permitted disposal facility in Guam.
16. DFARS 252.247-7023, TRANSPORTATION OF SUPPLIES BY SEA. Within 30 days of each shipment, the Contractor is required to provide an electronic copy of the carrier's bill of lading to the Contracting Officer and to MARAD via e-mail, Attention: Military Team. MARAD email: Cargo.Marad@dot.gov. In addition, the Contractor shall notify the Contracting Officer when oceanic shipments have been initiated within 3 working days of shipment.
| IDCode: J |
| Page: 1 |
| Pages: 5 |
| AmendNo: 0004 |
| EffDate: 22 May 2026 |
| ReqNo: See Continuation Sheet |
| ProjNo: |
| IssCode: N62742 |
| AdmCode: |
| IssuedBy: NAVFACSYSCOM PACIFIC |
258 MAKALAPA DR STE 100, JBPHH HI 96860-3134
JBPHH, HI 96860-3134
UNITED STATES
TREY CAMELLO, Email: trey.m.camello.civ@us.navy.mil Telephone: 8086022282 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: N6274226R1300 |
| SolDate: 11 Feb 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section 00 70 00 - Conditions of the Contract |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: |
| ContDate: |
| CODate: |