TGI_38K6112320A01_c1v1_REV1.pdf

PDF 2 MB Posted

Attached to
USS RAFAEL PERALTA (DDG-115) FY26 SIA BUNDLE #1
Solicitation number
N6264926RA036
Issued by

About this file

This document is a WebAIM Short Form Task Group Instruction (TGI) for maintenance work on the USS RAFAEL PERALTA (DDG-115) naval vessel. The work involves replacing packing assemblies of stuffing tubes for cable assemblies in the Fuel Tank Level Indicator System for Tank Groups 5 and 6. The task is scheduled to commence on August 3, 2026, and be completed by September 11, 2026.

The scope of work encompasses multiple compartments and spaces throughout the ship, including Crew Living Spaces Nos. 4, 6, and 7; Fuel Receiving Tank Groups 5 and 6; Fuel Tank Groups 5 and 6; an Access Trunk; a Passage; a Generator Room; and an Air Conditioning Machinery and Pump Room. The work requires removal and installation of existing packing assemblies for two stuffing tubes (one for Tank 5-308-1-F and one for Tank 5-354-0-F) with capacities of 30,038 and 38,127 gallons respectively, as well as dewatering of Tank Group 5 (69,695 gallons total) and Tank Group 6 (63,450 gallons total). General cleaning must achieve Level III cleanliness standards. The Government Furnished Material includes four units (2 each) of packing assemblies manufactured per drawing 162160, Revision A, containing washers and bushings. SRF-JRMC will provide supporting services including crane and rigging, electrical utilities, water and air supply, steam supply, safety inspections, and QA inspections for designated items. References include NAVSEA Standard Items, Local Standard Items, MIL-STD-2003 for electrical plant installation, and Tank Level Indicator technical manual SN572-AL-MMA010.

View the file

Other files

File Type Posted
TGI_38K6158301A01_c0v0_REV2.pdf PDF
TGI_38K6112317A01_c0v0_REV2.pdf PDF
TGI_38K6113601A01_c0v0_REV2.pdf PDF
TGI_38K6112305A01_c1v0_REV2.pdf PDF
TGI_38K6169901A01_c0v0_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV2.pdf PDF
TGI_38K6112304A01_c0v0_REV2.pdf PDF
TGI_38K6112325A01_c0v0_REV2.pdf PDF
Solicitation Amendment N6264926RA0360006 SF 30.pdf PDF
TGI_38K6112303A01_c0v0_REV2.pdf PDF
TGI_38K6165401A01_c0v0_REV2.pdf PDF
TGI_38K6113702A01_c0v0_REV2.pdf PDF
TGI_38K6171101A01_c0v0_REV2.pdf PDF
TGI_38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6112321A01_c0v0_REV2.pdf PDF
TGI_38K6112001A01_c0v0_REV2.pdf PDF
TGI_38K6154101A01_c1v1_REV2.pdf PDF
Attachment II Price Proposal Sheet Generator v1.3.xlsx XLSX spreadsheet
TGI_38K6144104A01_c0v0_REV2.pdf PDF
TGI_38K6112301A01_c0v0_REV2.pdf PDF
TGI_38K6112316A01_c0v0_REV2.pdf PDF
TGI_38K6151101A01_c0v0_REV2.pdf PDF
Solicitation Amendment N6264926RA0360005 SF 30.pdf PDF
TGI_38K6112320A01_c1v1_REV2.pdf PDF
TGI_38K6145601A01_c0v0_REV2.pdf PDF
TGI_38K6152101A02_c0v0_REV2.pdf PDF
TGI_38K6113602A01_c0v0_REV2.pdf PDF
TGI_38K6164401A01_c1v2_REV2.pdf PDF
TGI_38K6112306A01_c0v1_REV2.pdf PDF
TGI_38K6154103A02_c0v0_REV2.pdf PDF
TGI_38K6186301A01_c0v0_rev2.pdf PDF
TGI_38K6113801A01_c1v0_REV2.pdf PDF
Attachment I Bundle_1_POP_LIST.xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0360004 SF 30.pdf PDF
Solicitation Amendment N6264926RA0360003 SF 30.pdf PDF
DWG 6218562_53711_-_0001_ R_-_0001.pdf PDF
TGI_38K6112306A01_c0v1_REV1.pdf PDF
TGI_38K6113801A01_c1v0_REV1.pdf PDF
TGI_38K6144104A01_c0v0_REV1.pdf PDF
TGI_38K6145601A01_c0v0_REV1.pdf PDF
38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6158301A01_c0v0_REV1.pdf PDF
TGI 38K6112318A01_c2v2_REV2.pdf PDF
Solicitation Amendment N6264926RA0360002 SF 30.pdf PDF
TGI_38K6113701A01_c0v0_REV1.pdf PDF
TGI_38K6112305A01_c1v0_REV1.pdf PDF
7027318_53711_-_0001_ G_-_0001.pdf PDF
TGI_38K6171101A01_c0v0_REV1.pdf PDF
MP LM19-K6112303-ES01NA54_r3.pdf PDF
TGI_38K6165401A01_c0v0_REV1.pdf PDF
Show 40 more

Latest 50 of 115 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 6

EB140635

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

OGAWA, SHINYA 233 9061708579 27-NOV-2025

APPROVED BY: CODE: PHONE: DATE:

KURIHARA, TAKASHI 233 8093501437 17-JAN-2026

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EB14-0635

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

SAITO, KAZUNOBU

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A1120

1. SCOPE/PURPOSE:

1.1 Title: Packing Assembly of Stuffing Tube for Cable Assembly, Fuel Tank Level Indicator System for Tank Group-5; replace

1.2 Location of Work:

1.2.1 Crew Living Space No. 6 (3-338-3-L)

1.2.2 Fuel Receiving Tank Group 5 (5-308-1-F)

1.2.3 Access Trunk (3-308-2-T)

1.2.4 Fuel Tank Group 5 (5-354-0-F)

1.2.5 Crew Living Space No. 4 (3-300-1-L)

1.2.6 Crew Living Space No. 7 (3-350-2-L)

TGI Short Form

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

FOUO Pg 2 of 6

CU PHASE DESCRIPTION (Cont.)

1.2.7 Passage (3-338-6-L)

1.2.8 Generator Room (3-370-0-E)

1.2.9 Air Conditioning Machinery and Pump Room (5-300-01-E)

1.3 Identification:

1.3.1 Quantity (One EA), Stuffing Tube for Cable Assembly of Fuel Receiving Tank Level Indicator System for Tank 5-308-1-F Remarks: See Sketch Enclosure-01 for location detail

1.3.2 Quantity (One EA), Stuffing Tube for Cable Assembly of Fuel Stowage Tank Level Indicator System for Tank 5-354-0-F Remarks: See Sketch Enclosure-01 for location detail

1.3.3 Quantity (One EA), Fuel Receiving Tank Group-5

Tank No.: 5-308-1-F Capacity: 30,038 Gallons

1.3.4 Quantity (One EA), Fuel Tank Group-5

Tank No.: 5-354-0-F Capacity: 38,127 Gallons

1.3.5 Quantity (One Lot/3 Tanks), Fuel Tank Group-5

Total Capacity: 69,695 Gallons Required amount of water to dewater: 69,695 Gallons

1.3.5.1 Fuel Receiving Tank Group-5

Tank No.: 5-308-1-F Capacity: 30,038 Gallons

1.3.5.2 Fuel Tank Group-5

Tank No.: 5-354-0-F Capacity: 38,127 Gallons

1.3.5.3 Fuel Expansion Seawater Overflow Tank Group-5

Tank No.: 4-370-3-F Capacity: 1,530 Gallons

1.3.6 Quantity (One Lot/3 Tanks), Fuel Tank Group-6

Total Capacity: 63,450 Gallons Required amount of water to dewater: 63,450 Gallons

1.3.6.1 Fuel Receiving Tank Group-6

Tank No.: 5-308-2-F Capacity: 30,032 Gallons

1.3.6.2 Fuel Tank Group-6

Tank No.: 5-370-0-F

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

FOUO Pg 3 of 6

CU PHASE DESCRIPTION (Cont.)

Capacity: 31,545 Gallons

1.3.6.3 Fuel Expansion Seawater Overflow Tank Group-6

Tank No.: 4-370-4-F Capacity: 1,873 Gallons

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. PROCEDURE:

2.1 Accomplish the requirements of 099-902YO of Ref. No. 2 for each tank listed in 1.3.3 and 1.3.4.

2.1.1 Accomplish the requirements of 099-909YO of Ref. No. 2 for each tank listed in 1.3.5 and 1.3.6.

2.1.1.1 Accomplish the requirements of 009-009 of Ref. No. One

2.1.2 Ensure General Cleaning must be Level III.

2.2 Remove existing and install new packing assembly of the equipment listed in 1.3.1 and 1.3.2 in accordance with Part 3 of Ref. No. 3, using Ref. No. 4 for guidance.

2.3 Notes:

2.3.1 Planner: Code 233 S. Ogawa, 090-6170-8579

Planner: Code 231B A. Suzuki, 243-0968

2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.3.3 JCN EB14-0635 is related to this TGI.

2.4 Government Furnished Material (GFM):

2.4.1 SRF-JRMC will provide GFM listed in Appendix “M”.

2.5 SRF-JRMC will provide the following service work: (TGI No. 38K6112320S01).

2.5.1 [C740] Crane and crane rigging service.

2.5.2 [X99E] Utility service, electrical.

2.5.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.

2.5.4 [C106.1] Safety inspection for SRF-JRMC employees.

Kouichi.Yoshida.ja Typewritten Text 8/3/2026

Kouichi.Yoshida.ja Typewritten Text 9/11/2026

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

FOUO Pg 4 of 6

CU PHASE DESCRIPTION (Cont.)

2.5.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.5.6 [C133] QA inspection for (G) symbol(s).

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

FOUO Pg 5 of 6

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N 3 MIL MIL-STD-2003 Electric Plant Installation

Standard Methods for Surface Ships and Submarines

B N

4 TM SN572-AL-MMA-

Tank Level Indicators 2 N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K6112320 KEY OP: A01

21-JAN-2026 1554

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112320 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: BERTH 6 STFG TUBE AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O – REPL PKG ASSY OF STFG TUBE FOR CBL ASSY, FTK TLI SYS FOR TK GP-5

FOUO Pg 6 of 6

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M PACKING ASSEMBLY,

PACKING ASSEMBLY, FOR

SIZE 4A STUFFING TUBE & 1/4"

DIA CABLE, MFR DWG: 162160,

REV.A,

INCLUDED PARTS NUMBER:

162607(WASHER - 1EA),

149457 (BUSHING - 1EA) &

162157 (WASHER - 2EA),

ORDERED FOR CONTRACTOR

ORIG: CODE 233 S.OGAWA

090-6170-8579

9B 5330 LL4463061 NA 4 N 2/EA

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38K6112320A01-Sketch.pdf 25-NOV-2025 0000

38K6112320A01

SKETCH

ENCLOSURE-01 Sheet 1 of 1

CREW LIVING SPACE NO.6 (3-338-3-L)