This is a WebAIM Short Form Task Group Instruction (TGI) for naval ship maintenance work on USS RAFAEL PERALTA (DDG-115). The document details temporary staging and scaffolding installation and removal services required to support Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) maintenance and preservation work on the vessel.
The scope encompasses erecting and removing scaffolding assemblies in two locations: Freeboard Weather between Frames 308 and 338 on the Port side, and the Torpedo Missile and Rocket Magazine (1-304-2-M) on the Main Deck between Frames 308 and 338. Scaffolding work must be performed in accordance with Title 29 CFR Part 1915.71 (Scaffolding or Staging) standards. The contractor work start date is 10/19/2026 with a completion date of 12/13/2026. SRF-JRMC will provide supporting services including crane and crane rigging service, safety inspection for SRF-JRMC employees, and QA inspection for designated symbols. The document references NAVSEA Standard Items (NSI FY-26) and Local Standard Items (LI FY-26) as applicable material standards. The planning point of contact is Code 231B T. Ando (243-4372), and the Work Integration Manager is Code 333 T. Yaginuma (080-6522-9560). The work is classified as non-security sensitive and carries Job Summary ID 120A0001.
View the file
Other files
Show 40 more
Latest 50 of 115 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
29-JAN-2026 0905
20.14.15.2.9333 (September 2024) ICN: 38K6112001 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61 86511
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
CG030737
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
ANDO, TOMOHIKO 231B 3152434372 17-NOV-2025
APPROVED BY: CODE: PHONE: DATE:
TAKEISHI, TAKAYUKI 231B 3152436704 17-NOV-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
CG03-0737
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
SAITO, KAZUNOBU VARIOUS U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
120A0001
1. SCOPE/PURPOSE:
1.1 Title: Scaffolding for Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) Work; install and remove
1.2 Location of Work:
1.2.1 Freeboard Weather, Frames between 308 and 338, Port
1.2.2 Torpedo Missile and Rocket Magazine (1-304-2-M)
1.3 Identification:
1.3.1 Quantity (One Lot), Scaffolding Assembly
Location: 1.2.1 Remarks: Maintenance / Preservation work of blowout hatch will be accomplished by SRF-JRMC.
TGI Short Form
29-JAN-2026 0905
20.14.15.2.9333 (September 2024) (Continued) ICN: 38K6112001 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61 86511
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1.3.2 Quantity (One Lot), Scaffolding Assembly
Location: 1.2.2, Main Deck Frames between 308 and 338 Remarks: Maintenance / Preservation work of blowout hatch will be accomplished by SRF-JRMC.
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. PROCEDURE:
2.1 Erect/hang scaffolding listed in 1.3.1 and 1.3.2 in accordance with Ref. No. 3.
2.2 Remove scaffolding listed in 1.3.1 and 1.3.2 upon completion of the work in accordance with Ref. Ref. No. 3 when requested by SRF-JRMC via Code 333.
2.3 Notes:
2.3.1 Planner: Code 231B T. Ando, 243-4372
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
2.3.3 JCN CG03-0737 is related to this TGI.
2.4 Government Furnished Material (GFM): None.
2.5 SRF-JRMC will provide the following service work: (TGI No. 38K6112001S02)
2.5.1 [C740] Crane and crane rigging service.
2.5.2 [C106.1] Safety inspection for SRF-JRMC employees.
2.5.3 [C133] QA inspection for (G) symbol(s).
Kouichi.Yoshida.ja Typewritten Text 10/19/2026
Kouichi.Yoshida.ja Typewritten Text 12/13/2026
29-JAN-2026 0905
20.14.15.2.9333 (September 2024) (Continued) ICN: 38K6112001 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61 86511
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
3 TM 29 CFR PART
1915.71 Scaffolding or Staging - N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE