TGI_3819P12357_T01_c0v0.pdf

PDF 24 KB Posted

Attached to
USS BLUE RIDGE (LCC-19) 5C1 DSRA TYCOM 1
Solicitation number
N6264925RA021
Issued by

About this file

This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 20-AUG-2024, focusing on a Low Pressure Air System tightness and operational test. The task involves contractor, quality assurance (QA), and ship's force (S/F) work to accomplish and document the test in accordance with reference document TP 55121-3-300KTR. The instruction covers the specific system (55121) for the LCC-19 USS Blue Ridge, with key personnel including Daisuke Saiga as the preparer and John Blewitt as the approver, both from code 246.2. The document provides detailed instructions for performing a comprehensive test of the low and medium pressure air system, with clear delineation of tasks for different work groups.

View the file

Other files

File Type Posted
TGI_3819P59302A01_c1v1.pdf PDF
TGI_3819P14213A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P14206T01_c0v0.pdf PDF
TGI_3819P14206T02_c0v0.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_A01_c2v1.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
2.03 Solicitation N6264925RA0210002.pdf PDF
TGI_3819P14212A01_c0v0.pdf PDF
TGI_3819P14215A01_c0v0.pdf PDF
TGI_3819P51404A01_c0v0.pdf PDF
TGI_3819P14206T03_c0v0.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
TGI_3819P14206A01_c0v2.pdf PDF
TGI_3819P12364A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P12321A01_c1v1.pdf PDF
TGI_3819P12342A01_c0v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12320A01_c0v0.pdf PDF
TGI_3819P12354A01.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
Attachment IV RFI (fillable).pdf PDF
TGI_3819P14211A01_c0v0.pdf PDF
TGI_3819P14214A01_c0v0.pdf PDF
TGI_3819P16729A02_c0v1.pdf PDF
TGI_3819P51405A01_c0v0.pdf PDF
TGI_3819P51401A01_c1v2.pdf PDF
TGI_3819P12388A01_c1v1.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P14203_T01_c0v0.pdf PDF
TGI_3819P12318A01_c2v3.pdf PDF
TGI_3819P12335A01_c1v0.pdf PDF
TGI_3819P12357_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12323A01_c1v1.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
Attachment IV RFI.docx DOCX document
Attachment III TYCOM1_GFP_List_V3.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

20-AUG-2024 1347

20.14.12.0.8874 (April 2024) ICN: 3819P12357 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

ER01ZAL7 * ER01ZAS2 * ER01ZAW2 * ER02ZA02 * ES01NP9R

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

SAIGA, DAISUKE 246.2 3152432271 01-MAY-2024

APPROVED BY: CODE: PHONE: DATE:

BLEWITT, JOHN 246.2 3152438280 15-MAY-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ER01-ZAL7 * ER01-ZAS2 * ER01-ZAW2 * ER02-ZA02 * ES01-NP9R

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A1957

Tightness & Operational Test for Low Pressure Air System - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

20-AUG-2024 1347

20.14.12.0.8874 (April 2024) (Continued) ICN: 3819P12357 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP) - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 55121-3-300KTR LOW AND MEDIUM

PRESSURE AIR (T & OP) -

KTR

LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

/ ES01 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P12357 KEY OP: T01

File details come from the government source that posted it. Updated .