N4425523R1503-0001 SF30.pdf
PDF 500 KB Posted
- Solicitation number
- N4425523R1503
About this file
This amendment modifies a solicitation for the MCON P2002 Manchester Tank Farm Improvements project at the Manchester Fuel Depot. The scope of work includes constructing steel tanks 803 and 804, associated concrete foundations and impervious liners, clean water for hydrostatic testing, and other base price items. Optional items include a CCTV system, automatic tank gauging system, and unit prices for testing and disposing of contaminated soils or concrete if encountered. The schedule of prices is replaced to include separate line items for the base price work associated with tanks 803/804 and other items. The representations and certifications are to be provided in Section 00 45 00. The evaluation criteria for experience is modified such that two of five projects demonstrated must be for fuel storage of 50,000 barrels or more, and projects can be up to twelve years old rather than ten. Responses are due by the time and date specified in the solicitation as amended. The Navy is the contracting agency.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
N44255
P2002 BULK FUEL STORAGE TANKS PHASE 2, MANCHESTER FUEL DEPOT, MANCHESTER, WA
See Page 2 for description of amendment.
NAVFAC NORTHWEST
ATTN: EMILY EASTERDAY
1101 TAUTOG CIRCLE, SUITE 316
SILVERDALE, WASHINGTON 98315-1101
See Items 6
J
N44255-23-R-1503
1 6
08/14/2023
07/27/2023
N44255-23-R-1503 Amendment 0001
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0001
1. N4425523R1503 P2002 Solicitation, Section 00 10 00 – Solicitation is hereby revised to replace the schedule of prices as follows.
Remove:
The Schedule of Prices provided by the solicitation is hereby removed in its entirety, and replaced as follows.
Replace:
SCHEDULE OF PRICES
Line
Item Description QTY
UNIT OF
MEASURE
UNIT
COST
SUB-
TOTAL
TOTAL
CLIN
PRICE
BASE PRICE: Total Price
(0001AA through 0001AD) for the entire base work for Project
P2002 Manchester Tank Farm
Improvements Phase 2 in accordance with the drawings and specifications, complete.
1 EA
0001AA-
0001AD
0001AA
Subtotal of Base Price for the entire work for Steel Tanks
803 and 804 complete in accordance with the drawings and specifications, but excluding work provided in another Priced line Item.
2 EA
0001AB
Subtotal of Base Price for concrete foundations, impervious liner, sand fill, cathodic protection, leak detection under steel tanks
803 and 804 complete in accordance with the drawings and specifications, but excluding work provided in another Priced line Item.
2 EA
0001AC
Subtotal of Base Price for clean water including but not limited barge(s) for hydrostatic pressure test for tanks 803 and 804 complete in accordance with the drawings and specifications, but excluding work provided in another Priced line Item.
5,880,000 GAL
Item Description QTY
UNIT OF
MEASURE
UNIT
COST
SUB-
TOTAL
TOTAL
CLIN
PRICE
0001AD
Subtotal of Base Price for All
Other Base Price items complete in accordance with the drawings and specifications, but excluding work provided in another
Subtotal of Base Priced line
Item (0001AA through
0001AC).
OPTION CLINS 0002 -
0005: The Government has the unilateral right to exercise the below Option
CLINs. CLIN 0002 and
0003 can be exercised within 365 days from contract award. CLIN
0004 and 0005 can be exercised within 910 days of contract award in accordance with 52.217-7
OPTION FOR
INCREASED
QUANTITY –
SEPARATELY PRICED
LINE ITEM (MAR 1989),
see Section 00 70 00, Conditions of the Contract.
Options may be awarded at the same time, separately or not at all.
Option
Option Item No. 1: Price for providing all work in connection with the CCTV
System ( cameras, monitor, recorder, programming, and accessories), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
Option
Option Item No. 2: Price for providing all work in connection with the
Automatic Tank Gauging
(ATG) system, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
Item Description QTY
UNIT OF
MEASURE
UNIT
COST
SUB-
TOTAL
TOTAL
CLIN
PRICE
Option
Unit Price is the additional cost associated for testing, removal, and disposal of contaminated stockpiled soils complete in accordance with the drawings, specifications, and actual soil test report, but excluding work provided in another line item. (Non hazardous soil disposal shall be included in the base bid).
100 CY
Option
Unit Price is the additional cost associated for testing, removal, and disposal of disposal of fuel impacted concrete with volume of concrete in accordance with the drawings, specifications, and actual soil test report, but excluding work provided in another line item. (Non-hazardous concrete disposal shall be included in the base bid).
1,420 CY
Total Proposed Price CLINS 0001-0005
2. N4425523R1503 P2002 Solicitation, Section 00 70 00 – Conditions of the Contract is hereby revised as follows:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within ______. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
Replace with:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within CLIN 0002 and 0003 can be exercised within 365 days from contract award.
CLIN 0004 and 0005 can be exercised within 910 days of contract award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
3. N4425523R1503 P2002 Solicitation Section 00 21 16 - Instructions to Proposers, Proposal Instructions, Basis of
Award and Evaluation Factors, B. Evaluation Factors for Award, paragraph (2)(a)(1)(iv) is hereby revised as follows:
(iv) Completed Representations and Certifications, including the supplemental certifications provided in Section 00600 of the solicitation, are current and posted in SAM;
(iv) Completed Representations and Certifications, including the supplemental certifications provided in Section 00 45 00 of the solicitation, are current and posted in SAM;
4. N4425523R1503 P2002 Solicitation Section 00 21 16 - Instructions to Proposers, Attachments, is hereby revised as follows (attached herein):
Attachment J – Base Access Request Form
Attachment J – SECNAV 5512/1 (MAY 2021)
5. N4425523R1503 P2002 Solicitation Section 00 21 16 - Instructions to Proposers, Proposal Instructions, Basis of
Award and Evaluation Factors, B. Evaluation Factors for Award, paragraph (2)(b)(1)(a), is hereby revised as follows:
The Offeror shall submit the following information:
Submit a minimum of two (2) and a maximum of five (5) construction projects for the Offeror that best demonstrates its experience on relevant projects that are similar in size, scope, and complexity to the RFP. The
Government will only review five (5) construction projects. Any projects submitted in excess of the five (5) will not be considered. Every project shall meet at least one scope element, and the corresponding minimum size of
50,000 barrels of fuel storage. Failure to meet all of the criteria will result in an unacceptable rating.
The Offeror shall submit the following information:
Submit a minimum of two (2) and a maximum of five (5) construction projects for the Offeror that best demonstrates its experience on relevant projects that are similar in size, scope, and complexity to the RFP. The
Government will only review five (5) construction projects. Any projects submitted in excess of the five (5) will not be considered. Every project shall meet at least one scope element. At least two (2) construction projects shall meet the minimum size of 50,000 barrels of fuel storage. Failure to meet all of the criteria will result in an unacceptable rating.
6. N4425523R1503 P2002 Solicitation Section 00 21 16 - Instructions to Proposers, Proposal Instructions, Basis of
Award and Evaluation Factors, B. Evaluation Factors for Award, paragraph (2)(b)(1)(a), Complexity is hereby revised as follows:
Planning and multidisciplinary construction of an above ground storage facility while integrating with an active fuel depot that will remain operational during the construction process. Projects submitted for the Offeror shall be substantially complete (owner can occupy facility) within ten (10) years preceding the original date of issuance of this solicitation.
Replace:
Planning and multidisciplinary construction of an above ground storage facility while integrating with an active fuel depot that will remain operational during the construction process. Projects submitted for the Offeror shall be substantially complete (owner can occupy facility) within twelve (12) years preceding the original date of issuance of this solicitation.
7. This amendment incorporates responses to various Pre-Proposal Inquiries (PPIs), attached herein.
(End Summary of Changes)
Attachments:
PPI Responses
Attachment J – SECNAV 5512/1 (MAY 2021)
File details come from the government source that posted it. Updated .