About this file

This document is an Amendment (Amendment 0004) to a federal solicitation for a Design-Bid-Build (DBB) contract for Energy Campus Infrastructure at the Philadelphia Navy Yard Annex. The amendment extends the proposal due date to 31 July 2025 by 2:00 PM EST and provides responses to Pre-Proposal Inquiries (PPIs). Key details include:

The amendment addresses multiple technical and procedural questions from potential bidders, covering topics such as site conditions, utility access, demolition requirements, electrical and mechanical systems, soil conditions, and project-specific logistics. Several responses are marked as "PENDING RESPONSE", indicating ongoing clarification. The government anticipates contract award by 30 September 2025, with a 530-calendar day period of performance. The project involves infrastructure work at a Navy facility, with specific considerations around existing site conditions, utility connections, and potential environmental and logistical challenges that bidders must carefully evaluate.

View the file

Other files

File Type Posted
N4008525R35000007CLEAN.pdf PDF
Amendment 0006 Energy Campus Site Photos 2of4.pdf PDF
Amendment 0006 Energy Campus Site Photos 1of4.pdf PDF
AMENDMENT 0006.pdf PDF
Amendment 0006 Energy Campus Site Photos 3of4.pdf PDF
Amendment 0006 Energy Campus Site Photos 4of4.pdf PDF
Amendment 0005 DDG(X) WP3_Dwgs.pdf PDF
Amendment 0005 PS-77-001.0_SD2_PNY B77 POD_Shop Drawing Submittal.pdf PDF
Amendment 0005 CMT Services Group - Navy Yard - Additional Water Results.xlsx XLSX spreadsheet
N4008525R3500 Amendment 0005 final.pdf PDF
Amendment 0005 3G010 - UTILITY COORDINATION AND SEQUENCE OF CONSTRUCTION.pdf PDF
Amendment 0005 02 61 13 - EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL.pdf PDF
N4008525R3500 Amendment 0003.pdf PDF
Amendment 0003 Attachment 1.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 22 25 00.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 02 61 13.pdf PDF
Amendment 0003 ATTACHMENT G - PRICE SCHEDULE.pdf PDF
DDG(X) WP3_Amendment 0003_Dwgs_Signed.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 09 96 00.pdf PDF
DDG(X) WP3_Amendment 0003_Continuation Sheet.pdf PDF
N4008525R3500 Amendment 0002.pdf PDF
Amendment 0002 Site-Visit Sign In Sheets.pdf PDF
Amendment 0001 Site Visit Information.pdf PDF
N4008525R3500 Amendment 0001.pdf PDF
ATTACHMENT G - PRICE SCHEDULE.pdf PDF
ATTACHMENT F - SMALL BUSINESS SUBCONTRACTING PLAN.pdf PDF
ATTACHMENT B - CONSTRUCTION EXPERIENCE PROJECT DATA SHEET.pdf PDF
Solicitation - N4008525R3500 (final).pdf PDF
ATTACHMENT C - PAST PERFORMANCE QUESTIONAIRE (PPQ).pdf PDF
N4008525R3500 Specs.pdf PDF
ATTACHMENT H - PIEE VENDOR ACCESS INSTRUCTIONS.pdf PDF
ATTACHMENT A - PRE-PROPOSAL INQUIRY (PPI) LOG.xlsx XLSX spreadsheet
ATTACHMENT D - HISTORICAL SMALL BUSINESS UTILIZATION.pdf PDF
N4008525R3500 Drawings.pdf PDF
ATTACHMENT E - SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT (SPCD).pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

J 1 2

0004 14 Jul 2025 See Continuation Sheet WON 1808122 N40085

NAVFACSYSCOM MID-ATLANTIC

9324 VIRGINIA AVENUE, NORFOLK VA 23511-0395

NORFOLK, VA 23511-0395

UNITED STATES

MADISON TATEM, Email: madison.e.tatem.civ@us.navy.mil Telephone: 757- 341-0070

SCD: PAS:

N4008525R3500

16 Jun 2025

See Section G - Contract Administration Data

The purpose of this amendment is to provide the following:

1.Extend proposal due date to 31 July 2025 NLT 2:00 PM EST 2.Responses to Pre-Proposal Inquiries (PPI's)

JOHN P. BISHOP

14 Jul 2025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Response Due Date 17 Jul 2025 31 Jul 2025

N4008525R35000004

The purpose of this amendment is to provide the following:

1. Extend proposal due date to 31 July 2025 NLT 2:00 PM EST

2. Responses to Pre-Proposal Inquiries (PPI’s)

Proposal due date extended:

1. Extend proposal due date to 31 July 2025 NLT 2:00 PM EST.

Pre-Proposal Inquiry Responses:

Question # Reference Question Government Response Page Section Paragraph

In order to get access to the B77H high bay pipe chase for the installation of a conduit, there appears to be a lot of material and debris in the way. Will the material and debris be cleared by the building occupants to permit a clear access and work area in the chase?

Material and debris that prohibit contractor access and work will be relocated within five (5) business days once the contractor request is submitted.

There is a large gas main header passing behind the switchgear in B77H. Will this be live during the work activities that will need to be performed in the area?

The gas piping serves the facility boiler and the pipe is generally always energized. However, the boiler is typically only in service from 15 Oct through 15 April each year (heating season). If the line needs to be de-energized and/or purged to support nearby hotwork, work must be planned outside of the heating season or an outage must be planned outside of business hours and completed in a single work shift if performed during heating season; at no point in time shall the facility be subjected to significant freezing risks during any outages on the gas system. Note that the next gas valve upstream from this pipe is the building gas main isolation valve.

There isn't a mention as to where the project laydown area was located. Will there be a laydown area close to the project for contractor and/or CM trailers, lavatories and labor force parking?

Laydown provisions (inclusive of construction trailers) are detailed on Sheet 3G006 General Sheet Note 13 and in Specification Section 01 50 00. Work force lavatories may be located on or adjacent to the construction site and shall be coordinated with the Government through the Construction Site Plan submittal detailed in Section 01 50 00 of the specification. Free public street parking is available in the vicinity of the project site and is available on a first-come first-serve; however, refer to Section 01 50 00 Paragraph 3.1 for additional parking provisions where public street parking is found to be unavailable.

What is the availability for temporary power connecntio(s)?

Will generators need to be provided by the CM?

Power near the construction site will be available as noted in Specification Section 01 50 00. The contractor shall assume that a 480V three-phase three-wire ungrounded source is available inside Bldg 77H and shall provide temporary wiring, material and equipment as necessary to connect to and distribute power for construction site.

New above-grade penetrations through the Bldg 77H building envelope are prohibited without consulting with

NAVFAC.

If there are opportunities to pre-assemble underground conduit banks offsite. Will NAVFAC consider performing assembly inspections at the fabricators facility prior to delivery to permit quicker installation times.

For bidding purposes, assume conduit ductbanks will be required to be assembled and cast on site. After project award, Contractor can submit an RFI detailing the specifics of how pre-assembled ductbanks would be detailed, spliced, transported, and installed on site.

Dwg. 3C104 note #27 shows 15” RCP outlet from the SWM pit. Detail on 3C509 calls for a 12” DIP outlet. Please clarify.

Outlet pipe from SWM facility EC-1 is 12" D.I.P.

27 General

Please confirm the Superintendent can perform the duties of QCM or SSHO concurrently with the duties of Superintendent? Or are there to be three individuals to perform each duty?

There are to be three individuals to perform each duty.

Price Schedul e

Please clarify if the CLIN 0001B pricing for steel piping shall include the helical piles shown on page S-600.

PENDING RESPONSE

32 General Please clarify if there are any overhead restrictions above piles?

There are no existing overhead utilities at the project site. Please note the proximity of Building 77H to the pile foundations along Column Line U1.

33 General Please provide the Geotech report associated with the borings in the documents?

The subsurface information included in the contract documents is provided for bidding. The geotechnical report is not provided to bidders.

34 General Please clarify specifications and security fence requirements. PENDING RESPONSE

37 General

Please advise under which line item the helical piles should be charged. Helical piles are not required.

38 3C104

On Sheet 3C104 Utility Plan Keynotes 29, 49 and 50 all are associated with the same line on the drawing however they reference 2 different size water line (4" and 6"). Please clarify.

Refer to 6" / 4" water service profile A3 on drawing 3C201 for location of 4" x 6" increaser.

39 General

Will spoils remain at the Navy Yard at a location determined by the owner and if so can this location be provided to allow the calculations of trucks required to move spoils?

Excess spoils must be removed from Government property. Temporary stockpile details are shown on drawing 3C105.

40 3E101

On Sheet 3E101 ductbanks are shown extending inside Building 77H, please provide information for existing slab, tie-ins, and required demolition.

The ductbanks inside of the building are being installed as part of a separate project and are noted as existing.

41 3E101

On Sheet 3E101 ductbanks are shown inside Building 77H, these appear to be independent location and not extensions from the outside. Please clarify.

The ductbanks shown inside of the building are being installed under a separate project and are noted as existing.

42 General

Please provide detail to tie new existing ductbanks to existing ductbanks.

Refer to detail B3 on sheet 3E614 for duct bank extension detail.

3CD10

Please confirm no other abatement then what is listed on

3CD102.

Items requiring abatement are identified in the price schedule and on drawing 2CD102 keynote 10.

44 3S405

Detail B1 on page 3S405 does not indicate height of the pedestals.

Please provide location on where height of pedestals is provided.

Top of pedestal elevations are indicated on Drawing 3S403.

3CD10

Note 10 on 3CD102 indicates demolition of the existing steam trench. What is the material and thickness of floor, walls and top slab?

Refer to last bulleted item in keynote 10 on drawing 3CD102. Steam trench material is concrete. For bidding purposes, assume trench walls, floor and top slab are 6 inches thick.

46 General

There will need to be a well point system for groundwater removal?

Is there a preferred location for distribution. PENDING RESPONSE

HVAC/Plumbing equipment schedules and specifications do not provide a basis of design for the manufacturer or model. Who is the basis of design manufacturer/vendor for the scheduled equipment? PENDING RESPONSE

48 3E401

Please clarify the path and method that is to be used to "extend feeder from EX. East Substation to panel MDP-9A location" as stated in note 17 drawing 3E401. If this method is hanging off of trusses please clarify if this design was cross referenced with the existing truss load study performed for the FFG-62 LBES project.

The intent is to support the pull boxes and feeder conduit from the overhead structure. This has not been cross referenced with the FFG-62 study.

Please clarify if a 3D model of the ductbanks' design was created and if so can you please provide the file? PENDING RESPONSE

50 3C104

Please clarify if there is an electrical line to provide power to 4" water meter pit. Drawing 3C104 does not depict an electrical line to the meter pit.

However, Detail 3C506-A3 depicts the existance of a sump pump in the pit. Please provide a BOD for this sump pump. PENDING RESPONSE

Please clarify schedule for "perimeter security improvements" including expected date when encompassed site will be deemed a secure facility. PENDING RESPONSE

Please clarify when and to what extent the mechanical room bump out, located just west of the cooling tower, will be demolished. This bump out was seen on site walk but is not depicted in drawings.

The bump out will be removed entirely as part of a separate project as indicated on Existing Conditions Plan drawing 3C101.

53 3C004

Please clarify if it can be assumed that dewatering can be discharged directly into storm drain without filtration or decontamination.

Drawing 3C004 Note 6 under general sequence of construction notes that water pumped should be treated for "sediment removal" prior to discharging to a surface water. Please provide details on required sediment removal.

Please also provide details on areas deemed "a surface water".

Please clarify if this same process applies to contaminated water, if any other process applies to contaminated water please detail them.

54 3C001

Please clarify applicable area of drawing 3C001 General civil note 5, specifically what is the applicable area of listed "soft digging"? The requirement to use soft-dig equipment as compared to other methods of excavating is important.

The applicable area the Contractor is responsible for identifying existing underground utilities as stated in general note 5 on drawing 3C001 is within the limits of disturbance (LOD) boundary shown on drawing 3C106 Erosion and Sediment Control Plan. The Contractor is responsible for determining means and methods for locating existing underground utilities within areas of excavation and must comply with all federal, state, and local requirements.

Please clarify if the CTF POD must be accessible to non construction personnel during construction project. If access is required please clarify any necessary temporary access measures assuming removal of steps has occured.

See Amendment #3 updated drawings for more prescriptive details. Access must accommodate non-construction personnel and should include temporary access pathways, platforms and stairs to permit Government employees and their contractors to access the switchgear for operation and routine maintenance.

Please provide any and all drawings depiciting anchor bolt layouts for E-house columns.

Refer to Drawings 3S403 and 3S406 for anchor bolt layouts.

57 3E701

The feeder schedule on drawing 3E701 indicates GRS/PVC for some feeders. Please confirm if this is GRS PVC coated.

The feeders indicated with RGS/PVC indicate that the feeder will be run partially in PVC conduit where routed underground and then will transition to RGS when above grade. Refer to drawings for feeder routings for each of these pieces of equipment.

58 3E606

Drawing 3E606, detail A4, 6-way concrete encased duct-bank, please advise if these conduits are PVC schedule 40 or GRS, the

Where these conduits are routed underground, the intent is for concrete encased Schedule 40 PVC. The conduits feeder schedule indicates GRS but the panel schedule indicates

PVC?

are RGS where they transition above grade.

Is there additional information in the existing gear that we tie into, specifically as follows:

Manufacturer, Vintage, Nameplate- Voltage, Amperage, pictures, breaker nameplate on a comparable breaker, Cell Provisions? PENDING RESPONSE

3CD10

Please clarify if the metal steps noted in drawing 3CD101 notes 18 -19 are to be reinstalled or recycled.

Metal items noted to be removed in keynotes 18 and 19 on drawing 3CD101 can be recycyled.

Please provide the geotechnical report for the project. See response to PPI #33.

62 26 56 00 2.5.1

Please provide the exterior lighting control strategies as indicated in specification 26 56 00, 2.5.1. There are general strategy notes on 3E604, but want to confirm if there is additional information required to adhere to the specification requirements.

The lighting control for the Exterior Security Lighting and for the Exterior Maintenance lighting are shown at details C1/3E604 and C4/3E604.

The bid documents indicate that ground water can be expected and that dewatering will be necessary.

Drawing 3C004 - Erosion ansd Sediment Control Notes, contains multiple notes (#'s10, 29), indicate that all pumping should be done according to the procedure described within that plan, over undisturbed vegetated areas. During the site visit, it did not appear that there was a nearby vegetated area to pump water to.

Please advise where any water should be pumped to and if any groundwater that is encountered can assumed to be clean or if it is contaminated? If assumed to be contaminated, please provide a test report documenting the contamination so that any filtration processes can be accounted for. It is anticipated that dewatering could be required to be established at the beginning of excavation and pile installation and remain ongoing until construction gets to an elevation above the water level. Is this a realistic assumption?

3.00E+

Drawing 3E204 sheet keynote #8 calls for a control circuit from existing panel TF located in Building 487, this panel is not shown however, where is the panel located in Building 487?

Panel is located on the north wall directly west of the double doors that provide access into Bldg 487. Panel is accessible from the ground.

Drawing 3E204 sheet keynote #10 calls for 4#2, 1#8 for the SA and SB panel feeders. The RTC panel schedule calls for 4#2/0, 1#4, which is correct? PENDING RESPONSE

66 457 03 30 00 1.6.6.1

Please explain the role of the Concrete Quality Control Manager that is required to be a Professional Engineer? Under who's employ is this person required to be?

The Quality Manager's role is to manage the Quality Control Program. As indicated in Paragraph 1.6.6, quality control personnel must be employed by the Contractor.

67 3C104

On Sheet 3C104 Utility Plan Keynotes 29, 49 and 50 all are associated with the same line on the drawing however they reference 2 different size water line (4" and 6"). Please clarify. See response to PPI #38.

68 16 01 14 00 1.2e

Paragraph 1.2e indicates that the Contractor must schedule and reschedule work as needed to allow for testing operations at existing spaces to occur. How much starting and stopping of production should be anticipated?

(1) Generally, work outside of the Government buildings is unaffected by Government operations within the facility. Work within the facility which results in outages on building systems will require advanced coordination with the Government and may need to be rescheduled where outages are not compatible with operations in the facility. (2) Once Milestone 1 in this contract is BOD'd, there will be third-party work occurring to install electrical equipment and a structure within the construction site in parallel with this contract work. There may be periods of time when crane lifts are planned to offload the equipment that require work under the load path to be paused while the load is suspended. Otherwise, work can largely occur in parallel but will require coordination with third-party contractors.

69 285 01 57 19 3.2.5

Has the NPDES Operating Permit for this site been obtained? If not when is it expected?

No. Per "DDG(X) WP3_Amendment 0003_Dwgs_Signed" 3G003, Note #5:

"FOR BIDDING PURPOSES, ASSUME

PERMITS OBTAINED BY THE

GOVERNMENT WILL NOT BE

APPROVED BY PERMITTING

AUTHORITIES UNTIL 15

DECEMBER 2025. CONTRACTOR

WILL NOT BE AUTHORIZED TO

PERFORM WORK INVOLVING

GROUND DISTURBANCE UNTIL

PERMITS ARE APPROVED."

Are landing pads/foundations for exterior stairs required? They are not indicated in the drawings. No

71 23 09 13 3.1.10

Specification 23 09 13 Page 16, Paragraph 3.1.8 Wire and Cable states that wiring external to enclosures must be run in raceways. Please provide further detail regarding control system installation requirements.

Control wiring must be routed in rigid conduit.

72 25 05 11 3.3.6.1.2

In what locations is EMT conduit acceptable for the automation scope of work?

See Section 26 20 00, Paragraph 3.1.2 for conduit installation.

73 25 05 11 3.3.6.1.2

In what locations, if any, is Galvanized Rigid Conduit necessary for the automation scope of work?

See Section 26 20 00, Paragraph 3.1.2 for conduit installation.

74 26 20 00 3 .1.2.8

Please confirm compression fittings are required for all outdoor installation.

PENDING RESPONSE

75 26 08 10 2.1

Are electrical load banks required for any of the electrical testing or system commissioning? If so, who is to provide?

PENDING RESPONSE

Please confirm that all soil on site is regulated nonhazardous soil and that surplus soil is to be removed as such.

Area of regulated nonhazardous soils with contaminants is noted on Drawing 3C105. All other surplus soils are to be handled as regulated nonhazardous soils unless obvious signs of contamination (odor, petroleum sheen, etc) are present, or analytical testing indicates otherwise.

Refer to Section 01 57 19, paragraph 3.7 for waste management and disposal requirements, including sampling and analysis requirements.

77 31 00 00 3.2, 3.4

These paragraphs seem to indicate that any excavated soil taken from this site is not suitable for backfill or bedding material.

Please confirm that all soil material needed must be imported.

Per 3.4, excavated soils meeting the specified requirements may be used for fill and backfill to minimize the need for borrow material. However, per 1.4 e, bids are to be based on suitable soil materials NOT being available at the site.

01 78 .0.00

What aspects of specification 01 78 30.00 20 - GIS Data Deliverables, are applicable to this project?

All aspects of Section 01 78 30.00 20 are applicable to the project.

Does reinstallation of or tie-I to the existing high security fence require any third-party inspections, engineering or recertifications? PENDING RESPONSE

Can a basis of design and/or designer options considered (various acceptables) be provided for the Factory Assembled Cooling Towers? Can it be assumed that the steel supporting structure has been fully coordinated (i.e. dimensions, placement, load capacities, etc.)

with this basis of design and/or other acceptable cooling towers? PENDING RESPONSE

Please advise the closest preferred connection point for the existing Building Automation System for tie-in purposes. The drawings do not indicate. PENDING RESPONSE

3.00E+

Sheet 3E001 Underground/Site Work Legend for Ground Rod with test Well and Ground Rod refers to detail D1/E-609. This drawing does not exist. Can this be provided or the legend amended to reflect detail C3/3E609 & C4/3E609 respectively? PENDING RESPONSE

3E503, 3E504, 3E701

Feeders S2 & S3: The panel schedule on 3E701 does not indicate that these are 15KVA conductors for new MV switchgear S101A & S101B. The one-line diagram on 3E504 indicate that these are the main feeders for these switchgear lineup and are existing. Drawing 3E503, which is stamped as "For Reference Only" show these feeders in bold, which can be intreperted as being new. Pleae advise if feeders S2 & S3 are existing and that they are appropiately sized & rated for the new MV switchgear lineups.

Feeders S2 and S3 are new feeders that are part of this project scope. These medium voltage conductors shall be provided in compliance with spec section 26 05 13.00 10.

84 1 Solicitation

It has been noted by NAVFAC that contract award is anticipated to occur by 30Sep25, however the solicitation document notes that a 120 day price validity period is required. Please clarify.

Per the RFP, offerors pricing shall be valid for 120 days upon receipt of proposals.

Please clarify exactly what temporary utilities the Government is not providing and the Contractor is required to include in the price proposal.

Refer to Section 01 50 00 for temporary utilities.

Page 1 of The Solicitation states "Sealed offers in original and 1 copies…" and Section 4.3 states "Offerors shall only submit electronic proposals (.pdf format) in response to this solicitation."

Are Submissions to be Hand Delivered or uploaded to

SAM.GOV (?)

Refer to 4.2 Proposal Submission Instructions.

Civil drawing 3CD103 note #1 states; Demolish foundations to the extent required. For bidding purposes what dimensions and/or quantities should be used if conflicts are present?

Refer to Price Schedule Contract Line Item No. 0005, Option Item No. 4 for quantity.

Are there asbuilt drawings that can be provided for the structure that occupied the site previously?

Refer to the Reference Drawings included in the RFP Documents (Bookmark 08 in drawings PDF) for drawings of the previous structure.

For this project is the Navy Yard Stockpile being utilized or will excess soils / demolished material need to be disposed offsite.

Excess soils/demolished material must be removed and disposed of off Government property as indicated in Section 31 00 00, paragraph 3.9.

Please confirm existing soils are not contaminated and non-hazardous. Any costs associated with contanimated materials will be addressed with the Unit Prices.

Location of contaminated soils have been identified on contract drawing 3C105.

Is there any specific training required for hazardous soil conditions ?

Hazardous soil conditions were not identified at the site. Specific trainings such as a HAZWOPER certification would not be required. NAVFAC COR can provide list of required training if hazardous soils are encountered.

Civil drawing 3CD102 note #10 mentions materials and disposal of a Concrete Steam Trench.

How deep is it from existing grade to the top of the Trench?

Top of existing steam trench is either at grade or just below asphalt pavement.

What is the anticipated NTP for this project?

The award is the NTP. This project is anticipated to be awarded no later than 09/30/2025.

Page 6 of 55 of the Soliciation, Section 1 - General states "The general intent of this solicitation is to award a Fixed Price Construction Contract for Design- Bid-Build (DBB), …" Is the Contractor responsible for any design? See response to PPI #17.

Will there be a bid due date extension?

Proposal due date has been extended to 31 July 2025. See Amendment 0004.

3CD10

1 - 103

Please clarify what work will be completed on the site demolition drawings by Whiting Turner and what items should remain in the GC scope? Please issue a new existing conditions plan depicting what the GC will inherit from whiting turner.

Existing Conditions Plan drawing 3C101 included in the RFP documents depicts the results of the work being done under separate contract. Work required to be done by the General Contractor under this contract (e.g. site demolition) is shown on the drawings included in the RFP documents.

Please provide pictures of the existing site conditions. PENDING RESPONSE

98 Can we schedule a second site visit for any subcontractors that

Per the RFP, only one Government sponsored site visit will be conducted.

were unable to make the site visit on 6/25/25?

Please proivde a unit price each GC should carry per gallon to remove contaminated water

The Navy is unable to provide this estimate based on various options for removal that could be considered.

Is there any specific training required for hazardous soil conditions that we need to cover in the bid? See response to PPI #91.

Please provide a 3 week bid extension to allow for subcontractor and supplier pricing and ensure proper subcontractor and small business coverage on the project. See response to PPI #95.

Leading indicators are showing Long Lead Electrical Equipment may significantly impact the Period of Performance (PoP) NAVFAC has stipulated as 530 calendar days for this project. We request a 3-week extension to the bid date and extension to last day for PPIs to allow more time to evaluate electrical equipment lead times with manufacturers and sequencing of the work and potential impact on the PoP. See response to PPI #95.

Is there a Navy preferred water treatment contractor?

The Navy does not have a preferred water treatment contractor for this installation. The Navy has a water treatment contractor (WTS) currently under contract to maintain the current systems; however, they are not necessarily the contractor that is required to perform the work associated with this contract.

104 23 65 00 3.2.2

The specification reads that any vibration isolation is to be determined by the cooling tower manufacturer. Please confirm that there are no additional vibration isolation requirements for the cooling towers.

There are no additional vibration isolation requirements specifically for the cooling towers.

23 05 15 What is the difference between the Agency water treatment contractor of record and the water

Agency water treatment contractor is the Navy’s current contractor which at this time is WTS; this entity is separate from treatment contractor? This is not defined within the specification.

the water treatment company identified in Section 23 25 00. The role of the Agency water treatment contractor is limited to the functions and responsibilities noted in Section 23 05 15.

10 Solicitation (1) Factor 1 Experience

The last sentence at the top of page numbered 10 of the solicitation says "Information on additional pages beyond the limit will not be considered when reviewing the project." There is no where in the solicitation that indicates the page limit for Technical Factor 1, Attachment B, which has expandable blocks.

Request the page count be limited to 3 pages per Attachment B.

See Amendment 0003.

A4/3S0

The Typical detail for the top of pile anchorage shows 4 bent bars, but the table seems to note that 6 bars are required for most piles.

Please confirm the number of bent bars and advise the orientation of these bars.

Provide the number of bars as indicated in the detail and table.

S600 Sheet S600 indicates (8) helical piles for the B77 POD switchgear vault; however, the size and length of the piles are not specified. Please provide the design loads and any additional specifications required for sizing and installation.

PENDING RESPONSE

1 13 a We respectfully request a bid extension of 2 weeks 7/31/2025.

See response to PPI #95.

N4008525R3500 Amendment 0004 1
Amendment 0004 Text