Amendment 0005 3G010 - UTILITY COORDINATION AND SEQUENCE OF CONSTRUCTION.pdf

PDF 243 KB Posted

Attached to
N4008525R3500 Design-Bid-Build (DBB), Energy Campus Infrastructure at the Philadelphia Navy Yard Annex (PNYA) in Philadelphia, Pennsylvania
Solicitation number
N4008525R3500
Issued by

About this file

This document is a utility coordination and sequence of construction drawing for a Naval Facilities Engineering Systems Command project at the Philadelphia Navy Yard Annex. The drawing details a phased construction approach for installing a new 20MW electrical feeder bypass, involving complex utility infrastructure modifications. The three-phase construction sequence requires careful coordination with Dominion Energy as a subcontractor, with specific requirements including protecting existing infrastructure, minimizing service interruptions, and precisely managing electrical ductbank and feeder installations.

Key technical requirements include providing a new S101A/B pile-supported concrete vault, establishing new ductbanks, temporarily disconnecting and modifying existing utility feeders, and installing a permanent bypass through multiple electrical manholes and vaults. Critical constraints include limiting CTF 20MW service outages to specific durations (2 calendar days in Phase 1, 5 calendar days in Phase 2), maintaining access to existing switchgear, and ensuring that the permanent CTF 20MW service remains energized throughout the remaining construction period. The utility (Dominion Energy) is required to provide updated record drawings and specific technical submittals upon project completion.

View the file

Other files

File Type Posted
N4008525R35000007CLEAN.pdf PDF
Amendment 0006 Energy Campus Site Photos 3of4.pdf PDF
Amendment 0006 Energy Campus Site Photos 4of4.pdf PDF
Amendment 0006 Energy Campus Site Photos 2of4.pdf PDF
Amendment 0006 Energy Campus Site Photos 1of4.pdf PDF
AMENDMENT 0006.pdf PDF
N4008525R3500 Amendment 0005 final.pdf PDF
Amendment 0005 02 61 13 - EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL.pdf PDF
Amendment 0005 DDG(X) WP3_Dwgs.pdf PDF
Amendment 0005 PS-77-001.0_SD2_PNY B77 POD_Shop Drawing Submittal.pdf PDF
Amendment 0005 CMT Services Group - Navy Yard - Additional Water Results.xlsx XLSX spreadsheet
N4008525R3500 Amendment 0004.pdf PDF
DDG(X) WP3_Amendment 0003_Dwgs_Signed.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 09 96 00.pdf PDF
Amendment 0003 ATTACHMENT G - PRICE SCHEDULE.pdf PDF
DDG(X) WP3_Amendment 0003_Continuation Sheet.pdf PDF
N4008525R3500 Amendment 0003.pdf PDF
Amendment 0003 Attachment 1.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 22 25 00.pdf PDF
DDG(X) WP3_Amendment 0003_Spec Section 02 61 13.pdf PDF
N4008525R3500 Amendment 0002.pdf PDF
Amendment 0002 Site-Visit Sign In Sheets.pdf PDF
Amendment 0001 Site Visit Information.pdf PDF
N4008525R3500 Amendment 0001.pdf PDF
Solicitation - N4008525R3500 (final).pdf PDF
ATTACHMENT C - PAST PERFORMANCE QUESTIONAIRE (PPQ).pdf PDF
N4008525R3500 Specs.pdf PDF
ATTACHMENT H - PIEE VENDOR ACCESS INSTRUCTIONS.pdf PDF
ATTACHMENT A - PRE-PROPOSAL INQUIRY (PPI) LOG.xlsx XLSX spreadsheet
ATTACHMENT D - HISTORICAL SMALL BUSINESS UTILIZATION.pdf PDF
ATTACHMENT F - SMALL BUSINESS SUBCONTRACTING PLAN.pdf PDF
ATTACHMENT B - CONSTRUCTION EXPERIENCE PROJECT DATA SHEET.pdf PDF
N4008525R3500 Drawings.pdf PDF
ATTACHMENT E - SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT (SPCD).pdf PDF
ATTACHMENT G - PRICE SCHEDULE.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D3 3G010

C3 3G010

B3 3G010

EMH-4193

CTF POD

EMH-4185

LBES PODS101A/B

VAULT

D3 3G010

C3 3G010

B3 3G010

EMH-4193

CTF POD

EMH-4185

LBES PODS101A/B

VAULT

Whitman, Requardt & Associates, LLP 801 South Caroline Street, Baltimore, Maryland 21231

PM/DM

BRANCH MANAGER

CHIEF ENG/ARCH

FIRE PROT. ENG.

SATISFACTORY TO

APPROVED

ACTIVITY

DATE

FOR COMMANDER NAVFAC

SEAL

A/E INFO

A

B

C

D

1 2 3 4 5

1 2 3 4 5

A

B

C

D

SCALE:

CONSTR. CONTR. NO.

SHEET

NAVFAC DRAWING NO.

DES DRW CHK

OF

EPROJECT NO.:

DE

PA

RT

ME

NT

O

F

TH

E

NA

VY

NA

VA

L F

AC

ILI

TI

ES

E

NG

IN

EE

RI

NG

S

YS

TE

MS

C

OM

MA

ND

PH

ILA

DE

LP

HI

A, P

EN

NS

YL

VA

NI

A

PH

ILA

DE

LP

HI

A

NA

VY

Y

AR

D

AN

NE

X

AO

PS

N

OR

TH

NO

RF

OL

K

NA

VA

L S

TA

TI

ON

NO

RF

OL

K, V

IR

GI

NI

A

N

AV

AL

F

AC

IL

IT

IE

S

EN

G

IN

EE

R

IN

G

S

YS

TE

M

S C

O M

M

AN

D

M

ID

-A

TL

AN

TI

C

N4008525R2641

1733372

DD

G(

X)

LB

TS

W

P3 : E

-C

AM

PU

S

AS NOTED

DRAWFORM REVISION: 25 AUGUST 2020

EJA

MRI/PJB

HPN

C te m p Lo c a ls E m b a rn h a rt

(L o c a l) .r vt

MJB KKK CW

3G010

UT

ILI

TY

C

OO

RD

IN

AT

IO

N

AN

D

SE

QU

EN

CE

O F

CO

NS

TR

UC

TI

ON

9A 12922085

DJD

SCALE: 3/32" = 1'-0"C1 PART PLAN AT END OF PHASE 1

GENERAL SHEET NOTES

1. THIS DRAWING SHOWS NEW, EXISTING, AND DEMOLITION WORK TO CONVEY

PHASING AND SEQUENCE OF CONSTRUCTION REQUIREMENTS RELATED TO

THE EXISTING CTF 20MW FEEDER AND NEW BYPASS. REFER TO DISCIPLINE

SPECIFIC DRAWINGS FOR MORE INFORMATION.

2. AS PART OF THIS CONTRACT, THE CONTRACTOR MUST HIRE THE UTILITY

(DOMINION ENERGY) DIRECTLY AS A SUBCONTRACTOR TO PERFORM WORK

ON THE UTILITY OWNED INFRASTRUCTURE AND FEEDERS AS IDENTIFIED IN

NOTES THAT STATE 'UITLITY MUST'.

3. PROTECT EXISTING TO REMAIN INFRASTRUCTURE. SUBMIT A PLAN FOR

REVIEW/APPROVAL BY THE UTILITY WITH MEANS AND METHODS THAT MUST

BE UTILIZED TO PROTECT EXISTING UTILITY-OWNED INFRASTRUCTURE

DURING CONSTRUCTION.

4. THE EXISTING CTF 20MW SERVICE MUST NOT BE INTERRUPTED EXCEPT AS

INDICATED AND ONLY WHEN AUTHORIZED BY THE CONTRACTING OFFICER.

20MW SERVICE OUTAGE MUST BE COORDINATED WITH UTILITY TO MINIMIZE

OUTAGE DURATION MAXIMUM EXTENT PRACTICAL.

5. ALL WORK WITHIN 5FT OF UTILITY-OWNED INFRASTRUCTURE AND/OR

SERVICE MUST BE COORDINATED WITH THE UTILITY A MINIMUM OF 14 DAYS

IN ADVANCE OF WORK TO BE PERFORMED.

6. PRIOR TO THE START OF CONSTRUCTION, COORDINATE WITH THE UTILITY

FOR SCOPING OF THE EXISTING UTILITY OWNED CTF AND LBES DUCTBANKS

SO THE UTILITY CAN DOCUMENT EXISTING CONDITIONS PRIOR TO THE START

OF WORK.

7. DO NOT DISTURB THE EXISTING SUBSURFACE OF THE EXISTING TO REMAIN

DUCTBANKS.

8. DO NOT INSTALL PILES FOR THE COOLING TOWER OR TRANSFORMER

FOUNDATIONS UNTIL NEW CTF 20MW FEEDER BYPASS IS ESTABLISHED.

9. MAINTAIN OR PROVIDE ACCESS TO THE CTF POD (EMH-4185) SWITCHGEAR,

TO INCLUDE TEMPORARY STAIRS AND WORK PLATFORMS, TO SUPPORT

OPERATION AND INSPECTION OF SWITCHGEAR DURING CONSTRUCTION

OPERATIONS. ACCESS INTERRUPTIONS MUST BE REQUESTED BY THE

CONTRACTOR AND MUST BE APPROVED BY AND COORDINATED WITH THE

GOVERNMENT FIVE WORKING DAYS IN ADVANCE OF THE WORK.

10. AS PART OF THIS CONTRACT, THE UTILITY MUST PROVIDE UPDATED RECORD

DRAWINGS OF THE CTF AND LBES UTILITY SERVICES UPON COMPLETION OF

THE PERMANENT BYPASS.

11. AS PART OF THIS CONTRACT, THE UTILITY MUST PROVIDE (FOR INFORMATION

ONLY) THE FOLLOWING SUBMITTALS TO THE CONTRACTING OFFICER FOR

THEIR DESIGN OF THE PERMANENT BYPASS: FEEDER TYPE, FEEDER LENGTH,

SPLICES, LUGS, HARDWARE, AND TESTING RESULTS.

GRAPHIC SCALE

3/32" = 1'-0"

20'12'4' 8'

SCALE:

1. PROVIDE S101 VAULT. REFER TO C1/3E608 FOR PERMANENT CTF 20MW

BYPASS MEDIUM VOLTAGE FEEDER RACKING AGAINST SOUTH WALL

AND COORDINATE CABLE RACK LOCATION WITH FUTURE DUCT BANK

INTERFACE. REFER TO STRUCTURAL DRAWINGS FOR DETAILS.

2. PROVIDE 24-WAY, (3) 2 BY 4, 6" PVC CONCRETE-ENCASED DUCT BANK.

REFER TO DETAIL A4/3E617.

3. UTILITY MUST PROVIDE 8-WAY, 4 BY 2, 6" PVC CONCRETE-ENCASED

DUCT BANK. REFER TO DETAIL B1/3E606.

4. SOLID FILL HATCH INDICATES PERMANENT CTF 20MW BYPASS MEDIUM

VOLTAGE FEEDER CONDUIT FILL.

5. UTILITY MUST DISCONNECT EXISTING CTF 20MW FEEDERS AT CTF POD.

PROVIDE TERMINATION TO CTF POD VIA PERMANENT CTF 20MW BYPASS

MEDIUM VOLTAGE FEEDER.

6. UTILITY MUST DEMOLISH EXISTING CTF DUCT BANK. CUT DUCT BANK AT

VAULT INTERFACES ON EITHER SIDE. AT THE END OF PHASE 2.

7. EXISTING UTILITY OWNED ELECTRICAL MANHOLE (EMH-4193) WITH TWO

EXISTING 20MW UTILITY SERVICES (CTF SERVICE AND LBES SERVICE).

8. EXISTING NAVY OWNED CTF POD SWITCHGEAR AND VAULT (EMH-4185).

REFER TO A4/3E608 FOR VAULT BUTTERFLY DIAGRAM.

9. EXISTING NAVY OWNED LBES POD SWITCHGEAR AND VAULT. REFER TO

C1/3E617 FOR PERMANENT CTF 20MW BYPASS MEDIUM VOLTAGE

FEEDER RACKING AGAINST SOUTH WALL.

10. EXISTING UTILITY OWNED ELECTRICAL DUCTBANK WITH TWO EXISTING

20MW UTILITY SERVICES (CTF SERVICE AND LBES SERVICE).

11. EXISTING UTILITY OWNED ELECTRICAL DUCTBANK WITH CTF 20MW

UTILITY SERVICE.

12. EXISTING UTILITY OWNED ELECTRICAL DUCTBANK WITH LBES 20MW

UTILITY SERVICE.

13. S101A/B VAULT.

14. EXISTING UTILITY OWNED ELECTRICAL DUCTBANK WITH LBES 20MW

UTILITY SERVICE AND PERMANENT CTF 20MW BYPASS.

15. SHADED FILL HATCH INDICATES EXISTING MEDIUM VOLTAGE FEEDER

CONDUIT FILL.

SHEET KEYNOTES

SCALE: 3/32" = 1'-0"A1 PART PLAN AT END OF PHASE 2

NOT TO SCALESCALE:D3 EXISTING 8-WAY DUCT BANK SECTION

NOT TO SCALESCALE:C3 24-WAY S101 VAULT DUCT BANK SECTION

NOT TO SCALESCALE:B3 8-WAY CTF POD DUCT BANK SECTION

15 (TYP.)

SY

M

DE

SC

RI

PT

IO

N

DA

TE

AP

PR

AM

EN

DM

EN

T

6/1 7/2

W

RA

MI

SC

EL

LA

NE

OU

S

CH

AN

GE

S 7/1

4/2

W

RA

SUGGESTED SEQUENCE OF

CONSTRUCTION

1. ACTIVITIES INDICATED BELOW ARE REQUIRED. THE PHASING AND ORDER OF

ACTIVITIES INCLUDED ARE SUGGESTED.

PHASE 1

1. PROVIDE PROTECTION FOR EXISTING UTILITY INFRASTRUCTURE AND

FEEDERS.

2. PROVIDE S101A/B PILE SUPPORTED CONCRETE VAULT.

3. PROVIDE DUCTBANK BETWEEN EXISTING LBES POD AND S101A/B

VAULT.

4. REMOVE PLATFORM AND FOUNDATION ON NORTH SIDE OF CTF POD

(EMH-4185).

5. COORDINATE A LIMITED OUTAGE (2 CALENDAR DAYS MAXIMUM) OF

CTF POD (EMH-4185) WITH THE UTILITY AND THE CONTRACTING

OFFICER. UTILITY MUST TEMPORARILY DISCONNECT UTILITY FEEDERS

FROM THE PRIMARY SIDE OF CTF POD. UTILITY MUST MODIFY

EXISTING CABLING ARRANGEMENT IN CTF POD TO SAW-CUT OPENING

FOR ENTRANCE OF NEW CTF 20MW FEEDER. UTILITY MUST PROVIDE

OPENING IN CTF POD FOR NEW DUCTBANK AND MUST PROVIDE

DUCTBANK BETWEEN S101A/B VAULT AND EXISTING CTF POD.

PHASE 2

1. COORDINATE A LIMITED OUTAGE (5 CALENDAR DAYS MAXIMUM) OF

THE CTF POD (EMH-4185) WITH THE UTILITY AND THE CONTRACTING

OFFICER FOR PHASE 2 WORK.

2. UTILITY MUST PROVIDE NEW FEEDERS FROM MANHOLE (EMH-4193)

AND SPLICE IF REQUIRED.

3. UTILITY MUST PROVIDE NEW FEEDERS IN PERMANENT BYPASS

THROUGH EXISTING LBES DUCTBANK, EXISTING LBES POD VAULT,

NEW S101A/B VAULT, NEW DUCTBANK AND INTO EXISTING CTF POD

(EMH-4185).

4. UTILITY MUST PULL/REMOVE FEEDERS FROM EXISTING CTF POD

(EMH-4185) THROUGH EXISTING CTF DUCTBANK AND BACK TO

EXISTING UTILITY MANHOLE (EMH-4193).

5. UTILITY MUST DEMOLISH EXISTING CTF DUCTBANK FLUSH WITH

EXISTING CTF POD (EMH-4185) AND MANHOLE AND SEAL/PLUG THE

ABANDONED SLEEVES AT VAULTS.

6. UTILITY MUST PERFORM WORK AND COORDINATE WITH THE

CONTRACTOR TO LIMIT OUTAGE OF THE CTF 20MW SERVICE.

7. RE-INSTALL TEMPORARILY REMOVED PLATFORM.

PHASE 3

1. THE PERMANENT CTF 20MW SERVICE REMAINS ENERGIZED AND

CANNOT ACCOMMODATE ADDITIONAL OUTAGES FOR REMAINING

DURATION OF CONSTRUCTION.

END OF PHASE 1 END OF PHASE 2

END OF PHASE 1 END OF PHASE 2

END OF PHASE 1 END OF PHASE 2

4 (TYP.)

File details come from the government source that posted it. Updated .