This document is an Amendment (Amendment 0003) to a federal contract solicitation for a Design-Bid-Build (DBB) project for Energy Campus Infrastructure at the Philadelphia Navy Yard Annex. The amendment includes multiple key updates: revisions to three primary evaluation factors (Corporate Experience, Management Approach & Schedule, and Safety), responses to Pre-Proposal Inquiries (PPIs), and revised attachments and price schedule.
The amendment provides significant clarifications and modifications to the original solicitation, including changes to submittal requirements for project experience documentation, critical path scheduling specifications, and safety reporting requirements. Key schedule details include a total contract duration of 530 calendar days with an interim completion date of 15 November 2026, and a planned contract award date of 30 September 2025. The document contains 36 detailed pre-proposal inquiry responses addressing various technical, logistical, and procedural questions from potential bidders, covering topics such as work restrictions, equipment provisions, safety reporting, and contract experience requirements.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this amendment is to provide the following:
1. Revised Factor 1, Corporate Experience (revisions shown in bold italic text).
2. Revised Factor 2, Management Approach & Schedule (revisions shown in bold italic text).
3. Revised Factor 3, Safety (revisions shown in bold italic text).
4. Responses to Pre-Proposal Inquiries (PPI’s)
5. Revised Attachments
6. Revised ATTACHMENT G - PRICE SCHEDULE.
III. EVALUATION
C. EVALUATION FACTORS FOR AWARD
Factor 1, Corporate Experience:
(i) Solicitation Submittal Requirements:
Delete:
The attached Construction Experience Project Data Sheet is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider submissions via any other medium. Information on additional pages beyond the limit will not be considered when reviewing the project.
Replace with:
The attached Construction Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider this information submitted via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) pages. Information beyond this page limit will not be considered.
III. EVALUATION
C. EVALUATION FACTORS FOR AWARD
Factor 2, Management Approach & Schedule
(i) Solicitation Submittal Requirements:
2. Critical Path Schedule
Add:
The schedule shall include, but not limited to:
a. Provide a detailed Critical Path Method (CPM) construction schedule that illustrates your ability to achieve the schedule and meet all the requirements of the RFP including Milestones identified in Spec 01 14 00 Work Restrictions Section 1.2 Special Scheduling Requirements. The schedule shall demonstrate an understanding of the work to include the base CLIN and all options, a logical sequence of events to accomplish the work, and contain enough information to identify all of the major milestones of the RFP. The schedule shall be based on a contract award date of 30 September 2025. This planned award date is for proposal purposes only and not dispositive of an anticipated/planned award date:
1. Milestone 2 - A total contract duration of 530 calendar days, including 15 days for bond approval.
2. Milestone 1 - An interim completion date of 15 November 2026 for all work within five feet of the AUX and FIT transformer foundations and all work within five feet of the e-house and platform foundations.
III. EVALUATION
C. EVALUATION FACTORS FOR AWARD
Factor 3, Safety
(i) Solicitation Submittal Requirements:
Delete:
(1) DART Rate: Submit five (5) previous complete calendar years’ [CY2023, CY2022, CY2021, CY2020, and CY2019] worth of data (not an overall average). If the offeror has no DART rate, for any year, the offeror must affirmatively state so and explain why. Should a negative trend occur above Moderate Risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
Replace with:
(1) DART Rate: Submit five (5) previous complete calendar years’ [CY2024, CY2023, CY2022, CY2021, and CY2020] worth of data (not an overall average). If the offeror has no DART rate, for any year, the offeror must affirmatively state so and explain why. Should a negative trend occur above Moderate Risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
Pre-Proposal Inquiry Responses:
Question # Reference
Question Government Response Page Section Paragraph
1 205 01 45 00 1.6.1
QC organization personnel requirements lists a Design Quality Engineer to be a member of the QC organization. There are no follow-on references as to what this individual is responsible for nor are qualifications provided. Is this position applicable to this project and if so, please provide a summary of responsibilities and qualifications required for this position.
The referenced paragraph does not mention 'Design Quality Engineer'. The paragraph does mention 'Design Quality Manager' and this position is not defined in the specification. This position is not required for the project.
2 14 01 11 00 1.6
Spec section 01-11-00 page 2 paragraph
1.6 states that one of the required items on the salvage plan is “Light pole and light fixture”. Drawing 3CD101 (site demolition plan) makes note of two light poles, note 11 and note 23. Note 11 states light pole will be “disconnected and removed by utility provider”. Note 23 states to disconnect, remove and demolish light pole and light fixture”.
Please clarify which light pole is to be salvaged by contractor.
Neither of the light poles/light fixtures indicated on drawing 3CD101 are required to be salvaged by the Contractor.
3 511 05 12 00 1.2
Spec section 05-12-00 lists the requirement for AISC Structural Steel Erector Quality Certification. Can this certification be waived on this project?
No
4 364 01 91 00.15 1.2 Who is the independent Commissioning Firm that the Government has hired?
The commissioning firm will be determined at a later date.
Please advise if there is any restricted off-hour shift time frames. For example, is any time outside of the normal work hours of 7am - 4:30pm acceptable with approval from the Contracting Officer?
A daily early start time of 0630 would be acceptable with approval from the Contracting Officer. For awareness, the Government operates in the facility 0500- 2000. Tasks that affect Government operations and are required to occur outside of normal business hours shall be planned outside of these hours or coordinated around Government operations (e.g., electrical outages for utility connections). Otherwise, work outside of 7am-4:30pm can be requested and may be supported provided the Government is able to provide a Government presence to oversee the work and escort contract personnel; note that
Government escorts are required for any work outside of 0600-1800 on normal business days. This response does not waive any of the requirements in the Division 01 specifications and is supplemental to information in the specification.
Please advise if any of the HVAC/Plumbing/Controls equipment will be prepurchased by others. If so, please provide the specific equipment.
Otherwise, the assumption is that all MEP equipment will be provided by the Contractor.
Correct, MEP equipment is to be provided by the Contractor unless otherwise noted.
7 1057 31 62 00 1.3 Please provide more details on requirements for the Methane Mitigation Plan for bidding accuracy.
Methane has been encountered within the soil. A mitigation plan is required to be submitted and approved by the government indicating how the Contractor will handle encountering methane.
8 17 01 14 00 1.3.1.1.2
For bidding and schedule purposes, what is the approval time from submission of SECNAV 5512 to NAVFAC until NAVFAC's notification to the ktr of approval?
For bidding purposes, assume approval time of 14 days from submission of SECNAV 5512 to NAVFAC.
9 17 01 14 00 1.3.1.1.2 For bidding and schedule purposes, what are the hours of operation for ktr badge pick up at Security (Building 29)?
Normal hours of operation for contractor badge pick up are 8am-3pm Monday through Friday, excluding Government holidays.
10 2 Solicitation
FAR
52.211-14
Considering that the national supply chain remains strained with lead times for fabrication and delivery of mechanical and electrical equipment and many construction commodities, can the Government consider increasing the DPAS rating of this project from DO-C2 to DX?
No, this project will remain DO-C2 rated.
11 775 23 25 00 3.7.2
The Contractor's Five Year warranty letter states that is is for 5 years, but "10" is also included, Please advise if the "10" can be struck.
Disregard the reference to "10" in the Contractors' Five Year Warranty letter. See Amendment 0003 for revised Spec.
12 3M102
Sheet keynote #8 advises to reference the structural drawing details for a basket strainer support. None of the structural details appear to show or reference a basket strainer support. Please advise.
Provide typical equipment pad. Refer to detail A4/3S005.
Size pad thickness to support approved strainer.
13 364 01 91 00.15 1.4
For commissioning, will the Government Acceptance Representative be a team from NAVFAC Midlant from Norfolk or local NSWCPD/NAVFAC personnel?
NAVFAC ML
14 11 and 26 Solicitation
FAR
52.211-12
Please clarify if Liquidated Damages apply to Milestone 1 or Milestone 2.
Liquidated Damages apply to both milestones. Please see updated FAR Clause 52.211- 12 in Amendment 0003.
The mechanical and electrical schedules (3M701 & 3E701 respectively) list the VFD schedule. The mechanical notes indicate that the VFDs are to be included with the CT package and part of the mechanical package and the electrical notes indicate that the VFDs are included in the division 26 scope of work. Please clarify if the VFDs listed are the same and if the Govt. has a preference as to which divison carries this equipment.
Electrical contractor to provide VFDs for the hydronic pumps per Section 26 29 23.
Cooling tower fan VFDs are to be provided with the cooling tower package.
16 2 Attachment G
CLIN
0002, 0003
Both CLINs 0002 and 0003 indicate that the quantities of contaminated soil and oily water, respectively, are in addition to what is included in the drawings and specifications. Where can this information be found? Please clarify the quantities of each that are supposed to be included with the pricing of CLIN 0001A, if any.
Please see revised
ATTACHMENT G - PRICE
SCHEDULE.
17 3S002
Please confirm that delegated design items are limited to items 1A. - H. of the Delegated Design Notes on dwg 3S002.
If there are additional items not enumerated here please make them known such that they can be evaluated for inclusion.
Delegated design items are inclusive but not limited to the items noted on 3S002.
Will a project labor agreement be required for this project?
No
In order to get access to the B77H high bay pipe chase for the installation of a conduit, there appears to be a lot of material and debris in the way. Will the material and debris be cleared by the
PENDING RESPONSE
building occupants to permit a clear access and work area in the chase?
There is a large gas main header passing behind the switchgear in B77H. Will this be live during the work activities that will need to be performed in the area?
PENDING RESPONSE
There isn't a mention as to where the project laydown area was located. Will there be a laydown area close to the project for contractor and/or CM trailers, lavatories and labor force parking?
PENDING RESPONSE
What is the availability for temporary power connecntio(s)? Will generators need to be provided by the CM?
PENDING RESPONSE
If there are opportunities to pre-assemble underground conduit banks offsite. Will NAVFAC consider performing assembly inspections at the fabricators facility prior to delivery to permit quicker installation times.
PENDING RESPONSE
Work restriction section 01 14 00 Item
1.3.2. states regualr working hours are between 7:00AM and 3:30PM. This time period has the trade subcontractors traveling during high peak rush hours.
Would NAVFAC condier modifing the normal work hours between 6:00AM and 2:30PM to stay away from heavy rush hour traffic?
See response to PPI #5.
Dwg. 3C104 note #27 shows 15” RCP outlet from the SWM pit. Detail on 3C509 calls for a 12” DIP outlet. Please clarify.
PENDING RESPONSE
What are the page limits for Factor 1 Experience if any?
See Amendment 0003 for updated Factor 1.
27 General
Please confirm the Superintendent can perform the duties of QCM or SSHO concurrently with the duties of Superintendent? Or are there to be three individuals to perform each duty?
PENDING RESPONSE
28 General
After award, the Contracting Officer will provide a NTP to the awardee. What is the approximant duration between issuing the award and issuing the NTP?
The award is the Notice to Proceed.
29 General For planning the preliminary project schedule, what is the anticipated award date?
See Amendment 0003.
Price Schedule
Please clarify if the CLIN 0001B pricing for steel piping shall include the helical piles shown on page S-600.
PENDING RESPONSE
31 General
Please extend the bid date two additional weeks due to manufactures and subcontractors bid schedules requiring more time to acquire quotes from vendors.
Proposal due date remains unchanged.
32 General Please clarify if there are any overhead restrictions above piles?
PENDING RESPONSE
33 General Please provide the Geotech report associated with the borings in the documents?
PENDING RESPONSE
34 General Please clarify specifications and security fence requirements.
PENDING RESPONSE
35 General Please clarify what DART rates should be listed in the safety data section, please confirm if 2024 should be listed.
Please see Amendment 0003.
In our last proposal to Navsea we requested a Debriefing and during that debriefing it brought to our attention That my Contract experiences were not accepted because we were a subcontractor, not listed as the prime contractor And we explained that the Navy awards the multibillion dollar contract to the weapons systems (Lockheed) but we are the prime General contractor and only contractors on the project. At that time During the Debriefing, they said that I should have asked at solicitation for acceptance as being listed as a subcontractor Only on these larger Navy Contracts that we are the only contractor performing the construction on a larger Weapons multi Millon dollar projects. With all that being said could you let me know the procedure to apply for this acceptance
Per the RFP: "Subcontractor experience will not be considered. Additionally, experience of the offeror while performing as a subcontractor will not be considered."
Revised Attachments:
Please see the following attachments for revised specifications:
1. DDG(X) WP3_Amendment 0003_Continuation Sheet
2. DDG(X) WP3_Amendment 0003_Dwgs_Signed
3. DDG(X) WP3_Amendment 0003_Dwgs_Signed
4. DDG(X) WP3_Amendment 0003_Spec Section 09 96 00
5. DDG(X) WP3_Amendment 0003_Spec Section 22 25 00
Please see revised ATTACHMENT G - PRICE SCHEDULE.