N3220521R4207 ARCTIC Solicitation.docx

DOCX document 138 KB Posted

Attached to
USNS ARCTIC REGULAR OVERHAUL DRY DOCKING 2022 Federal contract opportunity
Solicitation number
N3220521R4207
Issued by
Department of the Navy Military Sealift Command

About this file

This document outlines the requirements for a solicitation seeking ship repair services for the USNS ARCTIC regular overhaul and dry docking scheduled for January 2022. The solicitation will be issued by the Department of the Navy's Military Sealift Command for ship repair work to be performed at the contractor's facility. Services required include categories of work items, general services, quality assurance, planning and reporting functions to support the overhaul and dry docking. The period of performance is 118 calendar days from vessel arrival at the contractor's yard. Offerors must have the capabilities and facilities to perform all aspects of ship repair work. The solicitation is targeted for small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to USNS ARCTIC REGULAR OVERHAUL DRY DOCKING 2022, newest first.
File Type Posted
S6161-PQ-FSE-010_3_0.pdf PDF
Machinery Control SystemSSDGLM2500 Sensors.docx DOCX document
Copy of J - 3 Category B Items ARCTIC REV 1.xlsx XLSX spreadsheet
S9555-AR-MMO-010_10_0.pdf PDF
USNS Arctic Master Calibration List.xlsx XLSX spreadsheet
AOE-8 List of Waster Sleeves.xls XLS spreadsheet
Q and A 2.docx DOCX document
0953_A_ANCHORS CHAINS AND LOCKERS 5YR_TAOE_CCSI.docx DOCX document
0966_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS_TAOE_CSI.docx DOCX document
0967_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS 3 AND 4_TAOE_CSI.docx DOCX document
0962_A_CATHODIC PROTECTION (5YR)_TAOE_CCSI_REV 1.docx DOCX document
0968_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS (POST SEA TRIAL)_TAOE_CCSI.docx DOCX document
0155_A_TANK VENT INSPECTION (5YR).docx DOCX document
0959_A_UNDERWATER HULL CLEANING AND PAINTING-NWB(10YR)_TAOE_CCSI_REV 1.docx DOCX document
J - 2 Category A Items ARCTIC REV 1.xlsx XLSX spreadsheet
0656_A_LIFE RAFT CERTIFICATION_REV-A-ARCTIC TAOE CCSI.docx DOCX document
0956_A_OVERHAULING SEA VALVES (5YR)_TAOE_CCSI.docx DOCX document
0955_A_STERN TUBE SEAL ASSEMBLY (5YR)(SCSI)_TAOE_CCSI.docx DOCX document
Q and A 1.docx DOCX document
0957_A_PROPELLER CLEAN AND POLISH_ON DOCK (2.5YR)_TAOE_CCSI.docx DOCX document
J - 3 Category B Items ARCTIC REV 1.xlsx XLSX spreadsheet
Arctic 2022 ROH Index REV 1.docx DOCX document
0963_A_SEA CHEST AND MARINE GROWTH PROTECTION (5YR)_TAOE_CCSI.docx DOCX document
0961_FREEBOARD PRESERVATION (5 YR)_TAOE_CCSI.docx DOCX document
WI 0405 REFERENCE TV-DTS SYSTEM PERFORMANCE SPECIFICATION TEST SHEET.docx DOCX document
J - 11 Dry Dock Evaluation Form.docx DOCX document
J - 9 Disclosure of Lobbying Activities SF-LLL.doc DOC document
J - 7 MSC Ship Repair Facility Survey.doc DOC document
J - 8 Request for Spec Clarification.doc DOC document
J - 12 Past Performance Data.doc DOC document
J - 14 Technical Data Non-Disclosure.docx DOCX document
J - 10 Interport Differential - Arctic Nov MTA 2018.docx DOCX document
J - 4 GFM LIST USNS ARCTIC FY 22 ROHDD.xlsx XLSX spreadsheet
J - 13 PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
J - 2 Category A Items ARCTIC.xls XLS spreadsheet
J - 3 Category B Items ARCTIC.xls XLS spreadsheet
SYNOPSIS N3220521R4207 USNS ARCTIC ROH 2022.docx DOCX document
SOURCES SOUGHT FOR USNS ARCTIC ROHDD 2022.docx DOCX document
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220521R4207

Section B - Supplies or Services and Prices

CLAUSES INCORPORATED BY FULL TEXT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" WIs

FFP

Prepare for and accomplish the ROH/DD of the USNS ARCTIC (T-AOE 8) Total Category "A" WIs $_____________

Proposed unit price per KWh of electrical shore power $_____ IAW WI 0011, 7.1.1.4 Proposed unit price per gallon of potable water $______ IAW WI 0011, 7.1.3.2 Proposed unit price per gallon of distilled water $______ IAW WI 0011, 7.1.4.2 Proposed unit price per gallon of bilge water removal $______ IAW WI 0011, 7.1.19.3 Proposed unit price per crane usage $______ IAW WI 0011, 7.9.1 Proposed Hazardous Waste handling fee rate IAW WI 0023, 7.4.3. ______%

CDRLs FOR CLINs INCLUDING OPTION CLINs, IF EXERCISED:

The data to be furnished hereunder shall be prepared and submitted IAW the CDRL, DD Form 1423, Exhibit A, attached hereto. The CDRLs form a part of the schedule of this solicitation.

SEE PARAGRAPH 1.

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR and ODC

AGR

34,000 man-hours @ $________ per man-hour = $_____________

ODC

Base $_____________

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

SEE PARAGRAPH 2, 3, AND 4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

SEE PARAGRAPH 5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 - Continuation of Services

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0951

WI 0930 - Drydocking and Undocking Vessel

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0965

WI 0965 - Steel Renewal

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0969

WI 0969 - Shell Plate Welding and Repair CSI

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0007 $______________

The contractor shall enter the total proposed price of all CLINs.

Section B, Price Schedule, detailed information

1. Attachment J-2, Category “A” WIs, provides a WI breakdown of CLIN 0001 pricing.

2. AGR and ODC

a. This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated during the contract. Changes are inherent to vessel repair contracts and should be expected by Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blastingTank cleaning
WeldingMachinists (inside and outside)
BurningBrazing
CarpentryElectrical work
Electronic workShipfitting
LaggingPainting
BoilermakingPipefitting
Sheetmetal workEngineering
RiggingStaging/scaffolding
General laborFire Watch

b. Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

TestingQuality Assurance
PlanningCleaning (except tank cleaning)
Material handling & warehousingSecurity
SurveyingAdministration
TransportationPurchasing staff
LoftingOther indirect support
Supervision

c. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's FBLR and not separately priced.

d. The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The ACO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

e. The base cost stated in this CLIN does not include profit or G&A rates.

f. This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

3. AGR details.

a. The Government may utilize CLIN 0002 for, and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time as may be granted, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the ACO to take any of the three (3) options set forth in subparagraph “d” below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and for negotiating changes. As part of the contractor’s proposal submission for AGR, the following shall be included:

- FBLR
- Proposed Labor Mix/Categories
- Proposed Man Hours
- Total Proposed AGR

c. Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “d”, below.

d. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

e. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in subparagraphs “d.1” and “d.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

f. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0007 at contract completion shall be de-obligated.

4. ODC details.

a. The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. ODC does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 ODC, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with AGR, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders ODC pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the ODC and will permit the ACO to take any of the three options set forth in subparagraph “e” below. As part of the contractor’s proposal submission for ODCs, the following shall be included:

MaterialEquipment
-Part number- Part number
-Order quantity- Order quantity
-Unit price- Unit price
-Total price- Total price

Other Direct Costs not captured above

- Travel

- Per diem (lodging, M&IE daily rates)

- Subcontractor Proposal Breakdown shall include but not be limited to, Material (Part number, Order Quantity, Unit Price, and Total Price), equipment (Part Number, Order Quantity, Unit Price, and Total Price), labor (FBLR, Proposed Labor Mix/Categories, and Proposed Manhours), and ODC (Travel and Per Diem)

The G&A and profit rates proposed shall be the same as the rates provided under CLIN 0002.

c. The contractor shall demonstrate due diligence in the assessment, evaluation, and determination resulting in the proposed utilization of other than local specialized labor resources. Only with ACO approval to proceed will a contractor, technical representative, or subcontractor be reimbursed for reasonable per diem costs (transportation, travel expenses, lodging, meals, and incidental expenses) required in connection with the associated change order. Per diem costs are considered reasonable, allowable, and reimbursable only to the extent that they do not exceed the allowed per diem rate in effect at the time of travel as set forth in the JTR.

d. Considering G&A and profit rates have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of ODCs proposed to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) the price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “e”, below.

e. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

f. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing this work at the contractor's facility. Furthermore, in cases described in subparagraphs “e.1” and “e.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

g. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for the ODC (CLIN 0002). Settlement of ODC (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0007 at contract completion shall be de-obligated.

5. Attachment J-3, Category “B” WIs, provides a WI breakdown of CLIN 0003 through 0007 pricing.

Section C - Descriptions and Specifications

ACRONYM TABLE

ABIH
American Board of Industrial Hygiene
ABR
Agreement for Boat Repair
ABS
American Bureau of Shipping
ACO
Administrative Contracting Officer
AGR
Additional Government Requirements
AIHA
American Industrial Hygiene Association
ALT
Alternate
AMT
Amount
BLDG
Building
CCO
Contract Change Order
CD
Compact Disc
CDRL
Contract Data Requirements List
CD-ROM
Compact Disc Read-Only Memory
CFM
Contractor Furnished Material
CFP
Contractor Furnished Property
CFR
Condition Found Report
CHENG
Chief Engineer
CFR
Code of Federal Regulations
CIH
Certified Industrial Hygienist
CLIN
Contract Line Item Number

CONUS

CPARS

Contiguous United States Contractor Performance Assessment Reporting System

DBIDS
Defense Biometric Identification Systems
DFARS
Defense Federal Acquisition Regulation Supplement
DOD
Department of Defense
DOD SAFE
Department of Defense Secure Access File Exchange
DON
Department of the Navy
EMAIL
Electronic Mail
ESRS
Electronic Subcontract Report System
FAPIIS
Federal Awardee Performance and Integrity Information System
FAR
Federal Acquisition Regulation
FBLR
Fully-Burdened Labor Rate
F/CC
Fibers Per Cubic Centimeter
FPCON
Force Protection Condition
FTR
Federal Travel Regulations
G&A
General and Administrative
GFI-TD
Government Furnished Information – Technical Data
GFM
Government Furnished Material
GFP
Government Furnished Property
GPE
Governmentwide Point of Entry
IAW
In Accordance With
ID
Identification
ISO
International Organization for Standardization
JTR
Joint Travel Regulations
KO
Contracting Officer
KWh
Kilowatt Hour
LLTM
Long Lead Time Material
LPTA
Lowest Price Technically Acceptable
M&IE
Meals and Incidental Expenses
MSC
Military Sealift Command
MSCREP
Military Sealift Command Representative
MM
Millimeter
MSRA
Master Ship Repair Agreement
MTA
Mid-Term Availability
N/A
Not Applicable
NCACS
Navy Commercial Access Control System
NDA
Non-Disclosure Agreement
NO
Number
NSP
Not Separately Priced
ODC
Other Direct Costs
PAT
Proficiency in Analytical Testing

PDF

PII

Portable Document Format Personally Identifiable Information

PM
Program Manager
PPE
Principle Port Engineer
PRIME
Prime Contractor
QA
Quality Assurance
QC
Quality Control
REV
Revision
RFC
Request for Specification Clarification
RFP
Request for Proposal
ROH/DD
Regular Overhaul/Dry-Docking
SECNAV
Secretary of the Navy
SF
Standard Form
SUB
Subcontractor
TPSN
Time Phased Sequencing Network
TWA
Time-Weighted Average
USC
United States Code
USCG
United States Coast Guard
USNS
United States Naval Ship
VR
Voyage Repair
WAWF
Wide Area Workflow
WI
Work Item

SCOPE OF WORK

1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS ARCTIC (T-AOE 8) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.

2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):

a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.

b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.

c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.

d. Using management procedures and systems to identify behind-schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.

e. Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.

f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.

g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.

h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.

i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.

j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.

k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.

3. Contract work shall be performed by an eligible contractor as defined below.

a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.

b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:

1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.

2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.

3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.

4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.

5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.

6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.

7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.

8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.

9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.

10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:

· Pier, with services in place, accessible to the CLASS size ship for berthing

· Structural Shop

· Machine Shop

· Pipe Shop

· Electrical/Electronic Shop

· Carpentry Shop

· Rigging Equipment

· Dry-dock – when required for docking of vessel in performance of the specification

11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.

c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.

4. Asbestos removal requirements.

a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.

b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.

c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).

d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.

e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.

f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:

1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.

2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.

3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.

4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.

g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).

h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.

i. The contractor shall insert this instruction in all subcontracts entered into under this contract.

5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and requires specific approval by the KO.

6. Substitution of key personnel.

a. The contractor agrees to assign to this contract those persons identified as key personnel who are necessary to fulfill the requirements of this contract and whose resumes were submitted with the proposal. No substitution of key personnel shall be made except IAW these instructions.

b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.

c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced. The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.

7. It is anticipated the ship will arrive at the contractor’s yard on or about 17 January 2022. All work shall be completed in no more than 118 calendar days from the actual start date designated by the Government at the time of contract award.

8. The place of performance for this contract shall be the contractor’s facility. Due to operational commitment’s, the location shall be on the East or Gulf Coast.

Table 1: List of WIs:

0001
INTENT, SCOPE, GENERAL REQUIREMENTS, AND DEFINITIONS
0002
TECHNICAL AND MANUFACTURER’S REPRESENTATIVES
0003
APPROACH, BERTH AND MOORING REQUIREMENTS
0004
TESTING AND QUALITY ASSURANCE
0005
ELECTRICAL SAFETY PROCEDURE REQUIREMENTS
0006
HEAVY WEATHER PLAN
0007
COLD WEATHER PLAN
0010
FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM (OMT)
0011
FURNISH GENERAL SERVICES
0012
TELEPHONE SERVICES
0013
PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS
0014
PREPARATION OF WEIGHT AND MOMENT REPORT
0015
INTEGRATED LOGISTICS AND GFM SUPPORT REQUIREMENTS
0016
FIRE PROTECTION AND SHIP’S SAFETY PROGRAM
0017
HANDLING SHIPS STORES
0018
DELIVERY AND REDELIVERY OF THE VESSEL
0019
SHIPBOARD ACCESS AND SECURITY
0020
GAS FREE CERTIFICATES
0021
CLEAN AND GAS FREE TANKS, VOIDS, COFFERDAMS & SPACES
0022
DOCK TRIALS AND SEA TRIALS
0023
HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR’S FACILITY
0024
PHYSICAL SECURITY AT PRIVATE CONTRACTOR FACILITY

100 SERIES

0101
SHIPYARD SUPPORT FOR ABS SPECIAL SURVEY
0103
ABS TANK INSPECTION AND TESTING
0104
KINGPOST SURVEY AND REPAIR
0108
MSD TANK FULL COAT (CSI)
0110
WEATHERDECK HANDRAIL REPAIR (CSI)
0111
WEATHERDECK DRAIN PIPING REPAIR (CSI)
0113
STEERING GEAR ACCESS ALTERATION (TALT 6-18-347)
0114
GAS TURBINE COMBUSTION AIR INTAKE FILTER CAGE (TALT 6-18-388)
0115
REPLACE/REPAIR TOP SIDE STEEL
0155
TANK VENT INSPECTION (ABS) (CSI)
0157
POTABLE WATER TANK PRESERVATION SPOT REPAIR (VR20-0046)
0165
BILGE PRESERVATION (CCSI)
0166
TANK PRESERVATION

200 SERIES

0201
LINE SHAFT BEARINGS OPEN AND INSPECT
0203
FUEL SERVICE SYSTEM RELIEF VALVES AND HOSES - GAS TURBINE MODULE (5 YR) (SCSI)
0204
GAS TURBINE MODULE HOSE REPLACEMENT (5 YR) (CSI)
0205
GAS TURBINE INTAKE REPAIRS (CSI)
0207
REVERSIBLE CONVERTER COUPLING (RCC) LUBE OIL SYSTEM RELIEF VALVES AND HOSES (5 YR) (CSI)
0209
RRG AND RCC TEMPERATURE REGULATING VALVE OVERHAUL (CSI)
0211
BLEED AIR REGULATING VALVES (5 YR) (CSI)

300 SERIES

0301
SSDG CONTROLS - HYDR0MECHANICAL SHUTOFF (HMSO) MAINTENANCE (5 YR) (SCSI)(CCSI)
0307
TEST AND CERTIFY AVIATION ELECTRONICS SYSTEM (2.5 YR) (CSI)
0310
STUFFING TUBE REPLACEMENT
0351
SWITCHBOARD CLEANING (2.5 YR) (CCSI)
0352
LOAD CENTER CLEANING (2.5 YR) (CCSI)

400 SERIES

0403
OE-82 ANTENNA MAINTENANCE (2.5 YR) (CSI)
0404
UHF TRANSCEIVER MAINTENANCE (5 YR) (CSI)
0405
DTS AND DISTRIBUTION GROOM (CSI)
0451
ANNUAL RADAR SERVICE (CCSI)
0452
ANNUAL ECDIS SERVICE (SCSI) (CCSI)
0454
ANNUAL VDR RECERTIFICATION (CCSI)
0455
ANNUAL RADIO COMMUNICATIONS EQUIPMENT RECERTIFICATION (CCSI)
0456
MAGNETIC COMPASS SERVICE (2 YR) (CCSI)
0457
EPIRB SHORE BASED MANAGEMENT SERVICE (CCSI)
0458
ANTENNA MAINTENANCE (5 YR) (CCSI)
0459
ECHO SOUNDER SERVICE (2.5 YR) (CCSI)

500 SERIES

0505
FO PURIFIER HOSE REPLACEMENT (5 YR) (CSI)
0506
LO PURIFIER HOSE REPLACEMENT (5 YR) (CSI)
0508
STEERING GEAR HOSE REPLACEMENT (5 YR) (CSI)
0509
SW SYSTEM HOSE REPLACEMENT (5YR) (CSI)
0513
AUXILIARY BOILER INSPECTION WITH REFT SURVEY
0515
SSDG ENGINE MAJOR OVERHAUL (40K HRS)(SCSI) (CSI)
0517
FIRE AND SMOKE DETECTION SYSTEM INSTALLATION (TALT-6-18-346 & 6-18-350) )
0518
AIR CONDITIONING AND REFRIGERATION COMPRESSOR TEST AND REPAIR
0555
INSPECT, TEST AND CERTIFY MACHINERY SPACE CRANES AND HOISTS (5 YR) (CCSI)
0561
INSTRUMENT CALIBRATION AND REPAIR
0563
SCBA COMPRESSOR AND FILLING STATION INSPECTION AND MAINTENANCE (1YR) (CCSI)
0565
FIXED GAS FIREFIGHTING SYSTEM INSPECTION AND TEST (1 YR) (SCSI) (CCSI)
0567
FIXED FOAM FIREFIGHTING SYSTEM INSPECTION AND TEST (1 YR) (SCSI) 9CCSI)
0568
CARGO HOLD SPRINKLER SYSTEM INSPECTION AND TEST (1 YR) (SCSI)
0569
FIRE AND SMOKE DETECTION AND ALARM SYSTEM (1 YR) (SCSI) (CCSI)
0570
PORTABLE FIRE EXTINGUISHER SYSTEM (1 YR) (CCSI)
0571
FIRE AND SMOKE DAMPER SERVICE (1 YR) (SCSI) (CCSI)
0572
DEEP FAT FRYER AND RANGE HOOD FIRE EXTINGUISHING SYSTEM (1 YR) (SCSI) (CCSI)
0573
FIRE HOSES (1 YR) (CCSI)

600 SERIES

0601
GALLEY AND SCULLERY EQUPMENT INSPECTION AND SERVICE
0602
LAUNDRY EQUIPMENT SERVICE (CSI)
0603
DECK COVERING INSTALLATION AND REPAIR
0606
CERTIFICATION OF SPIDERMAN BASKETS (1 YR) (CSI)
0607
CONVERT CO GALLEY TO EXECUTIVE LAUNDRY (TALT 6-18-333)
0653
ANNUAL RESCUE BOAT AND DAVIT INSPECTION (ABS) (CCSI)
0656
LIFE RAFTS AND EMBARKATION LADDER CERTIFICATION REV-A
0657
ACCOMODATION LADDER INSPECTION (1 YR) (CCSI)
0661
CARPET REPLACEMENT (CCSI)

800 SERIES

0851
ANNUAL GALLEY VENTILATION AND GAYLORD HOOD CLEANING (CCSI)
0852
ANNUAL LAUNDRY VENT CLEANING (CCSI)

900 SERIES

0901
DRY DOCKING AND UNDOCKING VESSEL
0902
SEA SUCTION AND DISCHARGE WASTER PIPING (2.5 YR) (CSI)
0903
PROPULSION SHAFTING INSPECTION AND REMOVAL (5 YR) (CSI)
0904
ZINC RENEWAL (5 YR) (CSI)
0905
SPEED LOG MAINTENANCE (5 YR) (CSI)
0906
ULTRASONIC TESTING
0907
REPLACE PORT AND STBD RUDDER STOCK BEARINGS
0908
BILGE KEEL EXAMINATION
0909
RUDDER AND STERN FRAME EXAMINATION
0953
ANCHORS, CHAINS AND LOCKERS (5 YR) (CCSI)
0955
STERN TUBE SEAL ASSEMBLY (5YR) (SCSI) (CCSI)
0956
OVERHAULING SEA VALVES (5 YR) (CCSI)
0957
PROPELLER CLEAN AND POLISH - ON DOCK (2.5 YR) (CCSI)
0959
UNDERWATER HULL CLEANING AND PAINTING - NEAR WHITE BLAST (10 YR) (CCSI)
0961
FREEBOARD PRESERVATION (5 YR) (CCSI)
0962
CATHODIC PROTECTION (5 YR) (CCSI)
0963
SEA CHEST AND MARINE GROWTH PROTECTION (2.5 YR) (CCSI)
0966
SHAFT ALIGNMENT AND BEARING REACTION CHECKS (SET 1 AND 2) (CCSI)
0967
SHAFT ALIGNMENT AND BEARING REACTION (SETS 3 AND 4) (5 YR) (CCSI)
0968
SHAFT ALIGNMENT AND BEARING REACTION CHECK (POST SEA TRIAL)(CCSI)

1000 SERIES

1001
INSPECT AND TEST UNREP RELIEF VALVES
1002
SADDLE WINCH AND WINCH FOUNDATION REFURBISHMENT
1003
GYPSY WINCH AND WINCH FOUNDATION REFURBISHMENT
1004
STATION SIX WINCH AND SLIDING BLOCK ELECTRIC BRAKE REPLACEMENT AND WIEGHT TEST
1005
SLIDING BLOCK CHAIN REPLACEMENT AND TRANSFER HEAD REFURBISHMENT (STANDARD UNREP STATION)
1006
HEAVY SLIDING BLOCK CHAIN REPLACEMENT AND TRANSFER HEAD REFURBISHMENT

B Items

0025
PHYSICAL SECURITY AT PRIVATE CONTRACTOR FACILITY IN F/P BRAVO - DELTA
0030
CONTINUATION OF SERVICES
0951
DRYDOCKING AND UNDOCKING (CCSI)
0965
STEEL RENEWAL
0969
SHELL PLATE WELDING AND REPAIR (CSI)

Section D - Packaging and Marking

WOOD PACKAGING MATERIAL (WPM) - ADDITIONAL DELIVERY INSTRUCTIONS

In accordance with the requirements of International Standards for Phytosanitary Measures (ISPM) 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM). WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). All materials must include certification markings in accordance with ALSC standards and be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved "DUNNAGE" stamp. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.

(end of instructions)

Section E - Inspection and Acceptance

CLAUSES INCORPORATED BY REFERENCE

252.217-7005
Inspection and Manner of Doing Work
JUL 2009
252.217-7006
Title
DEC 1991
252.217-7013
Guarantees
DEC 1991

Section F - Delivery and Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE
52.242-15
Stop-Work Order
AUG 1989
52.242-17
Government Delay Of Work
APR 1984
52.247-55
F.O.B. Point For Delivery Of Government-Furnished Property
JUN 2003

Section G - Contract Administration data

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the ContractingOfficer.

NOT APPLICABLE

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets therequirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by theContracting Officer.

INVOICE COMBO

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in thecontract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill inapplicable fields in WAWF when creating payment requests and receiving reports in the system.

Field Name in WAWF
Data to be entered in WAWF
Pay Official DoDAAC
N50082

Issue By DoDAAC

Admin DoDAAC**

Inspect By DoDAAC

Ship To Code
N62387

Ship From Code

Mark For Code

Service Approver (DoDAAC)
N62387
Service Acceptor (DoDAAC)
N62387

Accept at Other DoDAAC

LPO DoDAAC
N62387

DCAA Auditor DoDAAC

Other DoDAAC(s)

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

disa.global.servicedesk.mbx.eb-ticket-requests@mail.mil

(2) Contact the WAWF helpdesk at 866-618-5988, 801-605-7095 if assistance is needed.

(End of clause)

MSC SPECIFIC WIDE AREA WORKFLOW (WAWF) INSTRUCTIONS (AUG 2012)

The information contained in this instruction is supplemental to DFARS 252.232-7006.

The information contained in the table in DFARS 252.232-7006 is for WAWF purposes only. Information included in DFARS 252.232-7006 and this WAWF instruction apply only to WAWF Invoicing and WAWF Receiving Reports. Contradictory information elsewhere in this contract, e.g. Ship to DoDAAC, shall be followed per the terms and conditions of the contract.

When entering the invoice into WAWF, the Contractor shall fill in the DoDAAC fields or DoDAAC extensions exactly as shown in the table in DFARS 252.232-7006. Fields that should not be filled in when entering the invoice into WAWF will be indicated with the direction, “Leave Blank.”

In some situations the WAWF system will pre-populate the “Pay DoDAAC,” “Admin By DoDAAC” and “Issue By DoDAAC.” The Contractor shall verify that those DoDAACs automatically entered by the WAWF system match the information in the table in DFARS 252.232-7006. If these DoDAACs do not match, then the Contractor shall correct the field(s).

If Receiving Reports are required, ensure that the “Inspection” and “Acceptance” defaults of “destination” for both fields are not changed in the WAWF online interface.

The CLINs on the WAWF invoice shall be entered exactly as set forth in the contract document including CLIN number (e.g. 0001), Quantity (may be adjusted for actual quantity or dollar value delivered and invoiced), and Unit Price (e.g. $1.00). The dollar amounts on each CLIN or SubCLIN on the WAWF invoice shall reflect final performance values, but in no instance can the dollar amount for each CLIN or SubCLIN exceed what is specified in the contract document. The Contractor shall bill to the lowest level, e.g., the SubCLIN level. The Quantity and Unit of Measure fields must be filled out exactly as indicated in the CLINs and SubCLINs to reduce the possibility of the invoice being delayed or rejected during processing.

Before closing out of an invoice session in WAWF, but after submitting the document or documents, the Contractor will be given the option to send additional email notifications by clicking on the “Send More Email Notifications” link that appears on the page. The Contractor shall click on this link and add the Technical Point of Contact’s (TPOC) or Contracting Officer’s Representative’s (COR) email address in the first email address block and add any other additional email addresses desired in the following blocks. This additional notification to the Government is important to ensure the acceptor/receiver is aware that the invoice documents have been submitted into the WAWF system.

(End of instructions)

Section I - Contract Clauses

52.202-1
Definitions
JUN 2020
52.203-3
Gratuities
APR 1984
52.203-5
Covenant Against Contingent Fees
MAY 2014
52.203-6
Restrictions On Subcontractor Sales To The Government
JUN 2020
52.203-7
Anti-Kickback Procedures
JUN 2020
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
MAY 2014
52.203-10
Price Or Fee Adjustment For Illegal Or Improper Activity
MAY 2014
52.203-12
Limitation On Payments To Influence Certain Federal Transactions
JUN 2020
52.203-17
Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
JUN 2020
52.203-19
Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-1
Approval of Contract
DEC 1989
52.204-4
Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-10
Reporting Executive Compensation and First-Tier Subcontract Awards
JUN 2020
52.204-13
System for Award Management Maintenance
OCT 2018
52.204-18
Commercial and Government Entity Code Maintenance
AUG 2020
52.204-19
Incorporation by Reference of Representations and Certifications.
DEC 2014
52.204-21
Basic Safeguarding of Covered Contractor Information Systems
JUN 2016
52.204-23
Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.
JUL 2018
52.209-6
Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
JUN 2020
52.209-9
Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10
Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1
Market Research
JUN 2020
52.211-5
Material Requirements
AUG 2000
52.215-2
Audit and Records--Negotiation
JUN 2020
52.215-8
Order of Precedence--Uniform Contract Format
OCT 1997
52.215-10
Price Reduction for Defective Certified Cost or Pricing Data
AUG 2011
52.215-12 (Dev)
Subcontractor Certified Cost or Pricing Data (Deviation 2018-O0015)
JUN 2020
52.215-14
Integrity of Unit Prices
JUN 2020
52.215-17
Waiver of Facilities Capital Cost of Money
OCT 1997
52.215-21
Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data -- Modifications
JUN 2020
52.215-21 Alt IV
Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data -- Modifications (JUN 2020) - Alternate IV
OCT 2010
52.219-6 (Dev)
Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008).
OCT 2020
52.219-8
Utilization of Small Business Concerns
OCT 2018

This is the start of the file's text. The full file is on GovTribe.