0957_A_PROPELLER CLEAN AND POLISH_ON DOCK (2.5YR)_TAOE_CCSI.docx

DOCX document 595 KB Posted

Attached to
USNS ARCTIC REGULAR OVERHAUL DRY DOCKING 2022
Solicitation number
N3220521R4207
Issued by

About this file

This document outlines requirements for cleaning, inspecting, and testing propellers on the USNS ARCTIC during drydocking scheduled for January 2022. The scope of work includes removing marine growth from two 23-foot diameter, six-bladed nickel aluminum bronze propellers; conducting liquid penetrant and visual inspections for cracks, damage, and discontinuities; and restoring painted surfaces. The contractor must comply with all applicable General Technical Requirements and prepare inspection reports using the provided blade and hub forms. The solicitation is being issued by the Department of the Navy Military Sealift Command for the USNS ARCTIC regular overhaul dry docking.

View the file

Other files

File Type Posted
Q and A 2.docx DOCX document
S6161-PQ-FSE-010_3_0.pdf PDF
USNS Arctic Master Calibration List.xlsx XLSX spreadsheet
Copy of J - 3 Category B Items ARCTIC REV 1.xlsx XLSX spreadsheet
Machinery Control SystemSSDGLM2500 Sensors.docx DOCX document
S9555-AR-MMO-010_10_0.pdf PDF
AOE-8 List of Waster Sleeves.xls XLS spreadsheet
0961_FREEBOARD PRESERVATION (5 YR)_TAOE_CCSI.docx DOCX document
J - 2 Category A Items ARCTIC REV 1.xlsx XLSX spreadsheet
0959_A_UNDERWATER HULL CLEANING AND PAINTING-NWB(10YR)_TAOE_CCSI_REV 1.docx DOCX document
0967_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS 3 AND 4_TAOE_CSI.docx DOCX document
WI 0405 REFERENCE TV-DTS SYSTEM PERFORMANCE SPECIFICATION TEST SHEET.docx DOCX document
0956_A_OVERHAULING SEA VALVES (5YR)_TAOE_CCSI.docx DOCX document
0966_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS_TAOE_CSI.docx DOCX document
0968_A_SHAFT ALIGNMENT AND BEARING REACTION CHECKS (POST SEA TRIAL)_TAOE_CCSI.docx DOCX document
0962_A_CATHODIC PROTECTION (5YR)_TAOE_CCSI_REV 1.docx DOCX document
0656_A_LIFE RAFT CERTIFICATION_REV-A-ARCTIC TAOE CCSI.docx DOCX document
0953_A_ANCHORS CHAINS AND LOCKERS 5YR_TAOE_CCSI.docx DOCX document
0955_A_STERN TUBE SEAL ASSEMBLY (5YR)(SCSI)_TAOE_CCSI.docx DOCX document
0155_A_TANK VENT INSPECTION (5YR).docx DOCX document
0963_A_SEA CHEST AND MARINE GROWTH PROTECTION (5YR)_TAOE_CCSI.docx DOCX document
Q and A 1.docx DOCX document
J - 3 Category B Items ARCTIC REV 1.xlsx XLSX spreadsheet
Arctic 2022 ROH Index REV 1.docx DOCX document
J - 12 Past Performance Data.doc DOC document
J - 10 Interport Differential - Arctic Nov MTA 2018.docx DOCX document
J - 8 Request for Spec Clarification.doc DOC document
J - 14 Technical Data Non-Disclosure.docx DOCX document
J - 11 Dry Dock Evaluation Form.docx DOCX document
J - 7 MSC Ship Repair Facility Survey.doc DOC document
J - 9 Disclosure of Lobbying Activities SF-LLL.doc DOC document
J - 4 GFM LIST USNS ARCTIC FY 22 ROHDD.xlsx XLSX spreadsheet
J - 13 PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
J - 3 Category B Items ARCTIC.xls XLS spreadsheet
J - 2 Category A Items ARCTIC.xls XLS spreadsheet
N3220521R4207 ARCTIC Solicitation.docx DOCX document
SYNOPSIS N3220521R4207 USNS ARCTIC ROH 2022.docx DOCX document
SOURCES SOUGHT FOR USNS ARCTIC ROHDD 2022.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT

The purpose of this item is to clean, polish, inspect, and test the propeller on drydock.

REFERENCES/ENCLOSURES

References NAVSEA Drawing No. 801-6360504, USNS ARCTIC (T-AOE 8) Docking Drawing NAVSEA Drawing No. 245-6361975, Propeller NAVSEA Tech Manual S9086-HP-STM-010, NSTM Chapter 245, Propellers and Propulsors Enclosures Blade and Hub Inspection Forms

ITEM LOCATION/DESCRIPTION

Location/Quantity Location: Stern

1.1.1 Quantity: Two (2) Fixed Pitch Propellers

Item Description/Manufacturer’s Data Diameter: 23’-0” Number of Blades: 6 Pitch: 24.43 FT with a ratio of 1.0622 Propeller Material: Nickel Aluminum Bronze Propeller Weight: Approx. 80,000 lbs (each) GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None

NOTES

The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s including but not limited to GTR’s 1 through 7, 22, 23, 24, 28, and 29.

The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, including but not limited to Work Items 023, 901 and XXX to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

QUALITY ASSURANCE REQUIREMENTS: None additional

STATEMENT OF WORK REQUIRED

Clean, polish, inspect, and test the propellers identified in section 3.0, using References 2.1.1 through 2.1.3 and Enclosure 2.2.1 as guidance. Accomplish all tasks using IMO, SOLAS, and the Manufacturer’s requirements as guidance.

With the assistance of ship’s force, tag-out all required systems and equipment.

Clean and polish the propeller to meet the manufacturer’s design, installation, maintenance instructions, and service bulletin requirements using References 2.1.1 through 2.1.3 as guidance. Perform the following:

1.1.2 Remove all sea growth from the propeller, including, but not limited to: calcium deposits, sea grass, and barnacles. Cleaning must not result in damage to the propeller or the removal of propeller material. Utilize the following approved cleaning methods:

a. Hydro-blasting (High Pressure Water Jet Cleaning) may be used on all propellers and fairwater surfaces. Perform hydro-blasting immediately upon drydocking and before marine growth has dried. Hydro-blasting on unpainted propeller surfaces must not exceed 10,000 psi. Hydro-blasting on painted propeller surfaces must not exceed 2,000 psi.

b. Hand-cleaning methods such as scraping, and the use of brushes and pads. Plastic or hardwood scrapers, nylon, and polypropylene brushes such as A-1 and A-2, and hand-held plastic conditioning pads such as Scotch-Brite “Green” are acceptable for cleaning all propeller surfaces. It is preferred that the final cleaning operation of propeller blade edges (within 3 inches) be cleaned by hand with plastic surface conditioning pads. Do not attempt to round the edges of the blades with brushes and discs.

c. Powered cleaning processes. Only nylon and polypropylene brushes such as A-1 and A-2, and non-abrasive plastic surface conditioning discs such as Scotch-Brite “Green” may be used with power tools on less sensitive areas of painted propellers. Do not remove markings. Powered cleaning methods are not to be used within three (3) inches of blade edges, tips, cusps, fillets (excluding hub to blade interface), areas of high curvature, or other sensitive areas of the propeller(s). When cleaning the outer periphery of the blades, the brushes and discs must be kept flat on the blade surface.

1.2 Conduct an inspection of the propeller to meet the manufacturer’s design, installation, maintenance instructions and service bulletin requirements. Use References 2.1.1 through 2.1.3 and Enclosure 2.2.1 as guidance. Perform the following:

1.2.1 Examine all visible parts of the propeller. Inspect the hub, blades, and blade edges for cracks, curling, porosity, cavitation erosion, nicks, dents, bends, cable marks, flat spots, ridges, punch marks, and gouges. Verify that the propeller is free of conditions that may cause the propeller to become out of balance.

1.2.2 Photograph and record all markings.

1.3 Coordinate and conduct testing of the propeller to meet the manufacturer’s design, installation, maintenance instructions and service bulletin requirements. Conduct testing in the presence of the OMT REP and ABS Surveyor using References 2.1.1 through 2.1.3 as guidance. The testing includes/verifies:

1.3.1 Accomplish liquid penetrant NDT inspection of the entire propeller (blades and hub) as an aid in locating discontinuities.

1.4 Maintain workspaces in a clean condition during and upon completion of the work requirements. Prevent contamination of any adjacent equipment and spaces.

1.5 Upon completion of all inspections, tests and repairs, return the propeller to a ready for service condition.

1.6 With the assistance of ship’s force, tag-in all required systems and equipment.

1.7 Reports

1.7.1 Prepare and submit Enclosure 2.2.1 document any damage and/or discontinuities found during inspection and NDT. Submit one (1) electronic copy in Portable Document Format (PDF) to the OMT REP and one (1) electronic copy in Portable Document Format (PDF) to the ABS Surveyor.

1.7.2 When inspections, maintenance, servicing and testing reveal any deficiency, a condition report is to be submitted to the OMT REP with recommended repairs and parts required. Submit one (1) electronic copy in Portable Document Format (PDF).

1.7.3 Upon completion of all inspections, maintenance, servicing, and testing, prepare and submit a typewritten Service Report documenting the final “as released” condition of propeller(s) affirming they are safe for use. Submit one (1) electronic copy in Portable Document Format (PDF) of the report.

1.7.4 All reports and checklists are to be completed and signed by the person who carried out the inspections, maintenance, servicing, and testing and are to be countersigned by the Company's representative.

1.8 Painting/Lagging

1.8.1 Mechanically clean, prepare, prime, paint and restore all new, soiled, and disturbed surfaces to match surrounding surfaces.

1.9 Manufacturer’s Representative: None

USNS ARCTIC

(T-AOE 8)

DRYDOCKING AND UNDOCKINGRFP. NO. N32205-21-R-4207
4 May 2021
ITEM NO. 957Category “A”MSC/N756/CCSI

PROPELLER CLEAN AND POLISH – ON DOCK (2.5 YR)

2.0 GENERAL REQUIREMENTS: None additional

957-1

ENCLOSURE 2.2.1 BLADE AND HUB INSPECTION FORMS

image1.emf image2.emf image3.emf image4.emf image5.emf image6.emf