USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 10.pdf

PDF 259 KB Posted

Attached to
USS MUSTIN (DDG 89) FY21 DEPOT MAINTENANCE PERIOD & USS SAN DIEGO (LPD 22) FY21 DOCKING SELECTED RESTRICTED AVAILABILITY
Solicitation number
N00024-21-R-4442
Issued by

About this file

The Naval Sea Systems Command issued Solicitation No. N00024-21-R-4442 for the execution of the USS MUSTIN (DDG 89) FY21 Depot Maintenance Period and USS SAN DIEGO (LPD 22) FY21 Docking Selected Restricted Availability. These availabilities include maintenance, modernization, and repair work and will require contractors with substantial facilities and capabilities. The solicitations are competed on a coast-wide basis and will not be set aside for small business. Interested parties must register in the System for Award Management to participate. Attachments providing pricing workbooks, execution milestones, and compartment closeout requirements will be posted to beta.SAM.gov with restricted access. Work specifications and references will be provided on CDs. All errata and additional references will be transmitted via DOD Safe. The Government anticipates a single award by May 2021. The USS MUSTIN availability will begin in September 2021 and end in July 2023. The USS SAN DIEGO availability will begin in September 2021 and end in December 2022. Place of performance is contractor facilities on the West Coast.

View the file

Other files

File Type Posted
(USS SAN DIEGO) Attachment J-4 Pricing Workbook Rev_2.xlsx XLSX spreadsheet
N00024-21-R-4442_A0009.pdf PDF
N00024-21-R-4442_A0008.pdf PDF
N00024-21-R-4442-A0008 BQ 256-272.xlsx XLSX spreadsheet
MUSTIN ERRATA 12.pdf PDF
N00024-21-R-4442_A0007.pdf PDF
(USS MUSTIN) Attachment J-14 Rev_2.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-13 Rev_2.xlsx XLSX spreadsheet
MUSTIN ERRATA 11.pdf PDF
N00024-21-R-4442-A0007 BQ 210-255.xlsx XLSX spreadsheet
N00024-21-R-4442_A0006.pdf PDF
N00024-21-R-4222_A0006.pdf PDF
N00024-21-R-4442_A0005 BQ 139-209 AMD_0005.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-14 Rev_1.xlsx XLSX spreadsheet
USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 9.pdf PDF
N00024-21-R-4442_A0005.pdf PDF
(USS SAN DIEGO) Attachment J-3 Execution Milestones Rev_1.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-13 Rev_1.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-18 GFM Rev_1.xlsx XLSX spreadsheet
USS MUSTIN ERRATA 9.pdf PDF
USS MUSTIN ERRATA 10.pdf PDF
(USS SAN DIEGO) Attachment J-4 Pricing Workbook Rev_1.xlsx XLSX spreadsheet
N00024-21-R-4442_A0004 BQ 11-138.xlsx XLSX spreadsheet
USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 8.pdf PDF
(USS SAN DIEGO) Attachment J-8 Rev_1 (Errata 8).xlsx XLSX spreadsheet
N00024-21-R-4442_A0004.pdf PDF
N00024-21-R-4442_A0003.pdf PDF
N00024-21-R-4442_A0003 BQ 11-137.xlsx XLSX spreadsheet
N00024-21-R-4442_A0002.pdf PDF
N00024-21-R-4442_A0002 BQ 1-10.xlsx XLSX spreadsheet
N00024-21-R-4442_A0001.pdf PDF
Attachment S-17 (Proposal Assessment).xlsx XLSX spreadsheet
Attachment S-7 (Proposal Assessment).xlsx XLSX spreadsheet
Attachment J-5 (QASP).pdf PDF
Attachment S-3 (PPI Form).xlsx XLSX spreadsheet
Attachment J-15 (QASP).pdf PDF
Attachment J-7 (Schedule Model Review).pdf PDF
Attachment J-8 (GFM List).xlsx XLSX spreadsheet
Attachment J-17 (Schedule Model Review).pdf PDF
N00024-21-R-4442.pdf PDF
CDRLs.zip ZIP file
Attachment S-13 (PPI Form).xlsx XLSX spreadsheet
Attachment J-18 (GFM List).xlsx XLSX spreadsheet
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.

SHIP: USS SAN DIEGO (LPD 22)

TPPC-LPD22-SWRMC21-CN01

ERRATA NUMBER:

SPECIFICATION NUMBER:

THE FOLLOWING ITEMS ARE REPLACED:

130-11-001

472-90-001

992-11-008

998-41-001

DATED: 3/2/2021 2:23:52PMPage 1 of 1

SHIP: USS SAN DIEGO (LPD 22) ITEM NO: 130-11-001 (E10)

COAR: 16 PCN: V101-ZA28

CSWT FILE NO: 130-001 (LPD 17) CMP: NONE

REVISED: 18 Sep 2019 PLANNER: GABRIEL, GARRY

FERRER, DANIEL

FLETES, CARLOS

HAMANN, CHRISTOPHER

SSP: TPPC-LPD22-SWRMC21-CN01 1 of 3 ITEM NO: 130-11-001

ERRATA NO. 10

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Aircraft Securing Fitting; replace

1.2 Location of Work:

1.2.1 Flight Deck, Frame 137.5-202, Port to Starboard

1.3 Identification:

1.3.1 Quantity (15 EA), Aircraft Securing Fitting, Deck Socket, PH285 Flush, Type XIV, 7/8 Inch Crossbar, Non-Ballistic Steel Deck, Table 5 of 2.2

2. REFERENCES:

2.1 Standard Items, (FY21)

2.2 803-1916300 Rev P, Hull Standard Drawing Aircraft Securing and Engine Run-Up Fittings

2.3 600-7318156 Rev D, Outfitting Items Structural Unit 3170

2.4 600-7318158 Rev H, Outfitting Items Structural Unit 3172

2.5 600-7318159 Rev G, Outfitting Items-Structural Unit 3173

2.6 600-7318164 Rev D, Outfitting Items-Structural Unit 3270

2.7 600-7318166 Rev F, Outfitting Items Structural Unit 3272

2.8 600-7318167 Rev H, Outfitting Items-Structural Unit 3273

2.9 600-7318172 Rev D, Outfitting Items-Structural Unit 3370

2.10 600-7318174 Rev F, Outfitting Items Structural Unit 3372

2.11 600-7318175 Rev F, Outfitting Items-Structural Unit 3373

2.12 600-7318179 Rev C, Outfitting Items Structural Unit 3470

2.13 600-7318181 Rev G, Outfitting Items Structural Unit 3472

2.14 600-7318182 Rev G, Outfitting Items Structural Unit 3473

3. REQUIREMENTS:

(V)(G) "STRUCTURAL INSPECTION"

3.1 Accomplish an inspection of each aircraft securing fitting for crossbar lashing gear chain hook clearance, structural integrity, deterioration, pitting, cracks and areas of damage or distortion in the location listed in 1.2.

3.1.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 3.1 to the

SSP: TPPC-LPD22-SWRMC21-CN01 2 of 3 ITEM NO: 130-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

SUPERVISOR.

3.2 Remove existing, fit and install up to 15 each new aircraft securing fitting listed in 1.3, provided in 5.1 and located in 1.2, based on report submitted in 3.1.1, in accordance with 2.2, using 2.3 through 2.14 for guidance and as designated by the SUPERVISOR.

(V)(G) "FIT TEST"

3.2.1 Accomplish a Go/No-Go gauge measurement fit test prior to installation of each new aircraft securing fitting crossbar listed in 1.3, using an aircraft lashing gear chain hook, in accordance with Test Note T-1D of 2.2.

3.2.2 Chip and grind each surface flush in way of each repair.

3.2.3 Vee-out and weld a total of 79 linear inches of deteriorated and damaged welds, as designated by SUPERVISOR.

3.2.4 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A and B, Lines One through 7.

3.2.4.1 Accomplish nondestructive testing in accordance with

Line 11 and in accordance with test note 9 of ref 2.2.

3.3 Accomplish the requirements of 009-25 of 2.1 for an air hose test of each new aircraft securing fitting weld seam installed in 3.2. Allowable leakage: None.

(I)(G) "PULL TEST"

3.4 Accomplish the requirements of Test Note T-6 of 2.2 for each new aircraft securing fitting installed in 3.2.

(I)(G) "NONDESTRUCTIVE TESTING"

3.5 Accomplish a nondestructive test on each new aircraft securing fitting installed in 3.2 in accordance with Test Note T-9 of 2.2.

3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

TOTAL

QUANTITY

PROVIDED NAME Of PART

PIECE

NO.

REF

NO.

NATIONAL

STOCK

NO.

REQ

PARA NO.

1. 15 EA

Aircraft Securing Fitting TYPE XIV 2.2

5365-01- 646- 09395365 -01-592- 3.2 (E10)

SSP: TPPC-LPD22-SWRMC21-CN01 3 of 3 ITEM NO: 130-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.

SHIP: USS SAN DIEGO (LPD 22) ITEM NO: 472-90-001 (E10)

COAR: 30 PCN: EXSA-ZBN4

BWST FILE NO: 000-001 CMP: NONE

REVISED: 05 Apr 2019 PLANNER: See Attachment A

SSP: TPPC-LPD22-SWRMC21-CN01 1 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: ShipAlt LPD17-80156K, AN/SLQ-32(V)6 Hardware; accomplish (Option Item)

1.2 Location of Work:

1.2.1 Throughout the Ship

1.3 Identification:

1.3.1 Not Applicable.

1.4 Security Classification of Equipment, Components, Spaces and Documents: The Equipment, Space or Document is classified and subject to the applicable provisions of the National Industrial Security Program Operating Manual, DOD 5220.22M (0584-LP-179-6400).

1.4.1 Spaces:

1.4.1.1 Electronic Warfare Equipment Room (EW) (02-33-0-Q)

(CONFIDENTIAL)

1.4.1.2 Command and Control Center (CCC) (03-34-0-C)

(CONFIDENTIAL)

1.4.1.3 Joint Intel Center (JIC) (02-48-1-Q) (CONFIDENTIAL)

1.4.1.4 Radio Transmitter Room (03-48-2-Q) (CONFIDENTIAL)

1.4.1.5 Combat Information Center Equipment Room (02-39-0-Q)

(CONFIDENTIAL)

1.4.1.6 Radar Room Number One (03-53-1-Q) (CONFIDENTIAL)

1.4.1.7 Radar Room Number 2 (03-101-0-Q) (CONFIDENTIAL)

2. REFERENCES:

2.1 Standard Items, (FY21)

2.2 184-8803054, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Antenna Fdns

(E5)

2.3 184-8803055, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Miscellaneous Fdns

(E5)

2.4 304-8803056, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Mod to Cableways & Cable Rtg List

(E5)

2.5 320-8803057, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Power Distr Mod (E5)

2.6 401-8803058, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Mod to Arr (E5)

2.7 404-8803059, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Waveguide Ripout (E5)

2.8 470-8803062, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Wire Conn List (E5)

SSP: TPPC-LPD22-SWRMC21-CN01 2 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

2.9 470-8803061, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Blk Wrg Diag (E5)

2.10 512-8803064, ShipAlt LPD17-80156K AN/SLQ-32(V)6 HVAC Sys Mod (E5)

2.11 514-8802722, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Chilled Water Sys Mod

(E5)

2.12 532-8803068, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Electronic Cooling Sys Mod

(E5)

2.13 551-8803069, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Ship Service Air Sys Mod

(E5)

2.14 640-8803075, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Furniture

(E5)

2.15 523-8803066, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Wet Sprinkling Sys Mod

(E5)

2.16 523-8803067, ShipAlt LPD17-80156K Countermeasure Washdown Sys Mod (E5)

2.17 432-8803060, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Misc IC Mod (E5)

2.18 140-8803053, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Structure

(E5)

2.19 612-8803070, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Liferails

(E5)

2.20 623-8803072, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Ladders

(E5)

2.21 671-8803076, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Stowage

(E5)

2.22 631-8803073, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Paint Schedule

(E5)

2.23 634-8803074, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Deck Covering

(E5)

2.24 472-8803063, ShipAlt LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to Countermeasure

(E5)

2.25 4720-LPD22-FY21, Ship Alteration Material Summary (4720/3) (TBD) (E5)

2.26 622-8803071, SHIPALT LPD17-80156K AN/SLQ-32(V)6 Hardware Mod to False Deck

(E5)

2.27 110-8803052, SHIPALT LPD17-80156K AN/SLQ-32(V)6 Hardware Temporary Access Opening

(E5)

2.28 MIL-STD 2003-5A Rev 5A, Electric Plant Installation Standards for Surface Ships and Submarines

(E8)

2.29 MIL-STD-1310 Rev H, Shipboard Bonding and Grounding and other Techniques for Electromagnetic Compatibility, Electromagnetic Pulse (EMP) Mitigation and Safety

(E8)

2.30 S9086-SD-STM-010/CH-532 Rev 2, Liquid Cooling Systems for (E8)

SSP: TPPC-LPD22-SWRMC21-CN01 3 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

Electronic Cooling, NSTM Chapter 532

2.31 S6430-AE-TED-010 Rev 7, Technical Directive Piping Devices, Flexible Hose Assemblies

(E8)

2.32 SOP-A73-CSA-16-003, Procedure For Surveying Surface Electronic Warfare Improvement Program (SEWIP) Arrays With Lasers Using Spherically Mounted Reflectors (SMR)

(E8)

2.33 SW225-CR-CSA-010/LPD 17 CL Rev 01, Combat Systems Alignment Manual (CSAM) For LPD 17 Class

(E8)

3. REQUIREMENTS:

3.1 Accomplish the requirements of 2.2 through 2.24,27, using material provide in 5.3, include procurement of all material not provided as GFM.

(E5)

3.1.1 Accomplish the requirements of 009-05 of 2.1 (E8)

3.1.1.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A or B, Lines One through 7.

(E8)

3.1.1.2 Accomplish nondestructive testing in accordance with

Line 8, 9, 10 or 11, for each hull material type at location of each access cut.

(E8)

3.1.2 Accomplish the requirements of 009-25 of 2.1 for an air hose test of each new and disturbed watertight/airtight temporary access closure after reinstallation. Allowable leakage: None.

(E8)

3.1.3 Accomplish the requirements of 009-26 of 2.1 for deck covering disturbed as a result of each access cut.

(E8)

3.1.4 Accomplish the requirements of 009-65 of 2.1 for Heating, Ventilation, and Air Conditioning (HVAC) System modification.

(E8)

3.1.5 Cut and fit each raw material to the appropriate size for each install.

(E8)

3.1.6 Chip and grind each surface flush and smooth in way of each removal.

(E8)

3.1.7 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A,B, and D, Lines One through 7.

(E8)

(I)(G) "BONDING AND GROUNDING

3.1.8 Verify bonding and grounding of port and starboard shelter assemblies foundation and HGHS antenna foundation in accordance with of 2.29

(E8)

3.1.9 Alignment and placement of each new shelter assembly

foundation and High Gain High Sensitivity (HGHS)platform and foundation must be located to height, parallel, fore and aft offsets and centerline half-breadth dimensions listed in 2.2 and 2.6, relative to the ships Master Reference Plane (MRP) or Optical Weapon’s Control Reference Plane (OWCRP), using shipboard surveying methods and equipment similar or equal to Laser Tracker devices and techniques described in paragraph 7 of 2.32 and 2.33, performed by

SSP: TPPC-LPD22-SWRMC21-CN01 4 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

qualified personnel.

3.1.9.1 Establish benchmarks at each installation site

transferred directly from the MRP or Optical Weapon’s Control Reference Plane (OWCRP) using qualified operators and precision shipboard surveying equipment equal to that listed in paragraph 7 of reference 2.32 and 2.33. Installing activity must not take measurements from existing bulkheads, decks, platforms or other structures.

(E8)

3.1.9.2 The HGHS foundation may be scribed to the platform deck by removing up to 0.500 inch of foundation leg material without further authorization from the Government.

(E8)

(I)(G) "SHELTER ASSEMBLY FOUNDATION ALIGNMENT/PLACEMENT"

3.1.10 Verify alignment and placement of each new port and starboard antenna shelter assembly foundation using a qualified operator and calibrated equipment, after tack welding in place and prior to production welding, in accordance with 2.2 and 2.6.

(E8)

(I)(G) "HGHS FOUNDATION ALIGNMENT/PLACEMENT"

3.1.11 Verify alignment and placement of new HGHS antenna foundation using a qualified operator and calibrated equipment, after tack welding in place and prior to production welding in accordance with

2.2 and 2.6.

(E8)

(I)(G) "HGHS FOUNDATION LEVEL/FLATNESS"

3.1.11.1 Verify level/flatness of new HGHS antenna foundation, after completion of production welding, in accordance with 2.2.

(E8)

3.1.11.2 Machine new foundation in place to restore flatness. (E8)

3.1.11.3 Foundation top plate minimum thickness of 0.250 inch must be maintained.

(E8)

(I)(G) "SHELTER ASSEMBLY FOUNDATION LEVEL/FLATNESS"

3.1.12 Verify level/flatness of the port and starboard SLQ-32 shelter assembly foundation, after completion of production welding, using qualified operator and calibrated equipment, in accordance with 2.2.

(E8)

3.1.12.1 Machine each foundation in place to restore flatness. (E8)

3.1.12.2 Foundation top plate minimum thickness of 0.750 inch must be maintained.

(E8)

3.1.13 Fabricate and install each new hose assembly in accordance with 2.31.

(V)(G) "HYDROSTATIC TEST"

SSP: TPPC-LPD22-SWRMC21-CN01 5 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

3.1.13.1 Accomplish the requirements of Section 7 of 2.31. (E8)

3.1.13.2 Install a new CRES identification tag on each flexible hose assembly engraved in accordance with Paragraph 7.4 of 2.31.

(E8)

3.2 Provide the following services at the contractor's facility:

Provide a secure lockable office space/area for use by 2 each Government Sponsored Representatives for the entire ship availability. Office space must be furnished with the following for the entire duration of the availability:

Provide 2 each desk with swivel chairs in like new condition.

Provide NMCI Internet access connectivity at each desk.

Provide 2 each parking space adjacent to the office space or at the contractor facility for duration of production.

(E8)

3.3 Accomplish a hammer test the requirements of 009-25 of 2.1 for tightness test and Test Note T-1 of 2.all 19 areas for that each were new affected by bulkhead and deck socket penetrations for from fixed HVAC, Piping, Electrical, and portable structural.lifeline in stanchions accordance with 2.4 and liferail.2.7. Allowable defects: leakage: None.

(E8)

(V)(G) ""LIFERAIL STANCHION PULL TEST""

3.4 Accomplish a visual pull inspection test and of a minimum of 10 percent of the requirements newly installed liferail stanchions. Liferail stanchions shall be tested in place by applying a static concentrated load of Test 300 Note pounds,T-2 minus 0/+ 15 pounds, from the head of 2.the 19 stanchion applied horizontally outboard and perpendicular to the liferail for each a new minimum deck of socket ten miinutes. Inspect for fixed any and permanent portable deformation lifeline or stanchion visual and damage.liferail. Allowable defects: None.

(E8)

3.5 Accomplish a visual inspection and the requirements of Test Note T-2 of 2.19 for each new deck socket for fixed and portable lifeline stanchion and liferail. Allowable defects: None.

(E8)

(V)(G) ""VOLUMETRIC TEST" "

3.6 Accomplish the requirements of Test Note T-1 T-M082 of 2.10.10 of HVAC system.

(E8)

3.6.1 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.6 to the SUPERVISOR.

(E8)

3.7 Remove Accomplish and the dispose requirements of Test Note T-M082 of system 2.fluids.10.

(E8)

3.7.1 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.6 to the SUPERVISOR.

3.8 Remove and dispose of system fluids. (E8)

SSP: TPPC-LPD22-SWRMC21-CN01 6 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

3.9 Restore each piping flange mating surface exposed by disassembly of piping system. Repair by removing each high spot, burr, abrasion, and foreign matter, where removal can be accomplished by a hand tool.

Maintain phonographic finish on each flange that has it.

(E8)

3.10 Accomplish the requirements of 009-12 of 2.1, including Table One, Column A and B, Lines One through 10.

(E8)

3.11 Align each piping to each joint and fitting. Piping must be supported independently and must not impose a strain.

(E8)

3.12 Isolate each component subject to damage and clean the new and modified countermeasure washdown piping system to a cleanliness level that results in the internal surfaces being visually free of grease, oil, flux, scale, dirt, loose particles, and other contamination foreign to the base metal. tap water residues on metals and light superficial rust on carbon steel surfaces, caused by a short time exposure to the atmosphere, are permitted. Light dust on cleaned surfaces is not objectionable, provided that the quantity and size of the particle does not adversely affect system operation.

(E8)

3.13 Accomplish the requirements of Test Note T-1 of 2.11 through 2.13,

2.15 and 2.16, and T-2 of 2.12.

(E8)

3.13.1 Accomplish the requirements of 009-09 of 2.1 for cleaning and flushing for Level II Cleanliness.

(E8)

(V)(G) "ELECTRONIC COOLING WATER CLEANLINESS AND CONDUCTIVITY"

3.13.2 Accomplish the requirements of 009-09 of 2.1 for a Trisodium Phosphate (TSP) and citric acid flush in accordance with paragraphs 532-4.4.2.3.1 and 532-4.4.2.3.2 of 2.30 for each new and disturbed electronic cooling water system piping affected by the work item.

Acceptance Criteria: Filter bag following final flush shall be free of particulate, water conductivity shall be below two micromhos, and internal wall of each pipe shall be as bright as a new copper penny.

(E8)

3.14 Accomplish the requirements of 009-71 of 2.1 for new and disturbed piping.

(E8)

3.14.1 Accomplish a visual inspection and requirements of test Notes of 2.11, 2.15 and 2.16 and of 2.12.

(E8)

3.15 Accomplish Calibrate the requirements of 009-123 of 2.1 and the adjust requirements each of new test gage Note in T-2 accordance with 009-13 of 2.9 1.for each new and disturbed fiber optic cable.

(E8)

3.16 Accomplish the requirements of 009-123 of 2.1 and the requirements of test Note T-2 of 2.9 for each new and disturbed fiber optic cable.

(E8)

3.17 Accomplish an operational test and the requirements of 009-32 Test Note T-E067, and T-1 of 2.5, 2.1 9 in and accordance with 2.22.17.

Allowable defects: None.

(E8)

3.18 Accomplish the requirements of 009-32 of 2.1 in accordance with 2.22.

3.19 Accomplish the requirements of 009-26 of 2.1 in accordance with (E8)

SSP: TPPC-LPD22-SWRMC21-CN01 7 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

2.23.

3.20 Accomplish the requirements of 009-78 of 2.1 in accordance with 2.24.

(E8)

3.20.1 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

(E8)

3.21 Accomplish the requirements of 009-11 of 2.1 for new or disturbed lagging and insulation.

(E8)

3.21.1 Accomplish the requirements of 009-12 of 2.1 for each new fastener (stud) to support insulation and lagging.

(E8)

3.21.2 Accomplish the requirements of 009-32 of 2.1 for each surface to be insulated with the exception of non-ferrous and corrosion resistant steel (CRES) piping, plating, and vent ducting.

(E8)

3.21.3 Accomplish the requirements of 009-32 of 2.1 for new

insulation, lagging, and reusable covers to match each surrounding area.

(E8)

3.22 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

(E8)

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

TOTAL

QUANTITY

PROVIDED NAME Of PART

PIECE

NO.

REF

NO.

NATIONAL

STOCK

NO.

REQ

PARA NO.

1. 1 KT

Kitted Material for ShipAlt 80156K N/A 2.25 N/A 3.1

SSP: TPPC-LPD22-SWRMC21-CN01 8 of 8 ITEM NO: 472-90-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

Attachment A

Planners

WENCESLAO, JAY

ELECANAL, SEVERO

HAMANN, CHRISTOPHER

MARTIN, ROBERT

TWANO, EUGENE

VEIL, EARL

SHIP: USS SAN DIEGO (LPD 22) ITEM NO: 992-11-008 (E10)

COAR: 16 PCN: EXSY-ZAC8

SWT FILE NO: 992-039 CMP: NONE

REVISED: 18 Sep 2019 PLANNER: DELAPAZ, LYNNNYRD

TRAN, VU

TWANO, EUGENE

SSP: TPPC-LPD22-SWRMC21-CN01 1 of 2 ITEM NO: 992-11-008

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Fuel Assistance and Towboat Service for Fuel Barge; provide (OPTION ITEM, Naval Base Ports Only)

(E10)

1.2 Location of Work:

1.2.1 Not Applicable

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 None.

3. REQUIREMENTS:

3.1 Allow 2 work days (48 hours) for the Government to refuel the ship.

The ship must be refueled prior to machinery space turnover. No hot work will be allowed during this time frame.

3.2 Furnish pilot, towing bridle and towboat service and tow 2 each fuel barges from Fuel Depot to the contractor's plant, adjacent to the ship.

Upon completion of fueling and when directed by the SUPERVISOR, return the fuel barges to their original location.

3.2.1 Navy tugs will be used to get fuel barges from Fuel Depot and turn over fuel barges to Contractors tugs prior to entrance their facility.

3.2.2 Contractors tugs will turn fuel barges over to Navy tugs upon leaving Contractors facility to be returned to the Fuel Depot.

3.3 Maintain each fuel barge in a seaworthy condition during the towing operation.

3.4 Provide mooring lines and secure each barge to the ship at the contractor's plant.

3.4.1 Provide camels between the ship and the barges prior to each barge mooring alongside.

3.5 Remove and reinstall the oil boom when directed by the SUPERVISOR to allow entry and departure of each barge.

4. NOTES:

4.1 None

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

SSP: TPPC-LPD22-SWRMC21-CN01 2 of 2 ITEM NO: 992-11-008

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

5.2 PUSH MATERIAL:

1. None.

SHIP: USS SAN DIEGO (LPD 22) ITEM NO: 998-41-001 (E10)

COAR: 16 PCN: EXSY-ZAE3

SWT FILE NO: 998-002 CMP: NONE

REVISED: 18 Sep 2019 PLANNER: SANCHEZ, CRISTAL

HAMANN, CHRISTOPHER

ROLLINS, KENNETH

SMITH, MICHAEL

TWANO, EUGENE

SSP: TPPC-LPD22-SWRMC21-CN01 1 of 5 ITEM NO: 998-41-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Hazardous Waste Produced on Naval Vessels; control

1.2 Location of Work:

1.2.1 Throughout the Ship

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Resource Conservation and Recovery Act, (RCRA)

2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act

2.3 Applicable Hazardous Waste, Manifest Form

2.4 10 U.S.C., 7311 Repair or Maintenance of Naval Vessels: Handling of Hazardous Waste

3. REQUIREMENTS:

3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.

3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.

3.1.2 Manage and transport for Navy disposal, Navy-generated

hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.

3.1.3 Submit one legible copy, in hard copy or approved

transferrable media, of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.

3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.

3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel must only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor must obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared must be presented

SSP: TPPC-LPD22-SWRMC21-CN01 2 of 5 ITEM NO: 998-41-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

to the SUPERVISOR for completion after the hazardous waste has been identified.

3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) must bear a generator identification number issued to the contractor pursuant to applicable law.

Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste must only bear a generator number issued to the contractor.

3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) must bear a generator identification number issued to the contractor pursuant to applicable law and must also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste must bear a generator identification number issued to the contractor and must also cite in the remarks block a generator identification number issued to the Navy. The contractor must sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor must obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Manifests prepared must be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor must notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor must use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.

3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy must notify the contractor within three business days of receipt of notification by the state. The contractor must dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.

3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:

AMOUNT

(E10)

SSP: TPPC-LPD22-SWRMC21-CN01 3 of 5 ITEM NO: 998-41-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

TYPE NAVY CO-GENERATED CONTRACTOR

Acid Solutions (may include 5,000 GAL 3,500 GAL 5,000 GAL spent sulfamic, citric, chromic, nitric, sulfuric, hydrochloric, etc.)

Ethylene Glycol (Antifreeze) 2000 GAL 2000 GAL 2000 GAL

Sodium Hydroxide _____ ____________ __________

Cleaning Solvents 500 GAL ____________ 500 GAL

Sodium Phosphates (Tri, Bi, 5,000 GAL _______ 5,000 GAL or Mono)

Fluorocarbons 500lbs ____________ 500 lbs

Morpholine _____ ____________ __________

Sodium Chromates _____ ____________ __________

Hydrazine _____ ____________ __________

Carbohydrazide _____ ____________ __________

Methyl Ethyl Ketone _____ ____________ __________

Spent Abrasive Blast Material _____ 1,500 lbs 840 Tons

(contaminated with a known hazardous waste)

Trichloroethane _____ ____________

Miscellaneous Chemicals 1500 GAL 1500 GAL 1500 GAL

(Ignitable)

Miscellaneous Chemicals 500 GAL 500 GAL 500 GAL

(Corrosive)

Miscellaneous Chemicals 2000 GAL 2000 GAL 2000 GAL

(TCLP Toxic)

Miscellaneous Chemicals 500 GAL 500 GAL 500 GAL

(Reactive)

Oil (Synthetic) 3,000 GAL 500 GAL 5,000 GAL

Hydraulic Oil 10,000 GAL ________

Fuel OIl 60,000 GAL ________ ________

Paints (Enamel, Latex, 500 GAL 500 GAL 2,500 GAL

Epoxy, thinners, oil based, SSP: TPPC-LPD22-SWRMC21-CN01 4 of 5 ITEM NO: 998-41-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

rubber paint, nonskid, lacquer, remover, varnishes)

Paints (May include lead, 500 GAL 500 GAL 500 GAL cadmium, or chrome)

Paint Strippers (phenols, 500 GAL 500 GAL 500 GAL lead, chromium)

Sludge (Contaminated with 10,000 GAL 10,500 GAL 20,000 GAL a known hazardous waste)

Wool Felt (contaminated _____ ________ __________ with chromium and PCB's)

Ventilation Debris/Residue

(heavy metals, e.g., cadmium, chromium) ______ 6000 lbs ________

Metal (Steel) ______ 25,000 LBS

(Contaminated with a known hazardous waste)

Human Waste _____ ___6000 lbs_____ 5 GAL ___________

Metal (Steel) 10 GAL 2 GAL

Bilge Water _________ 25,10,000 LBS GAL 25,000 GAL

(15,Contaminated 000 with GALa known hazardous waste)

3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.

3.7 Submit one legible copy, in hard copy or approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the SUPERVISOR.

3.7.1 The report must include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.

3.7.1.1 Chemical analysis must be accomplished by laboratories with state or EPA approved quality assurance programs.

3.7.2 The contractor must make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.

3.8 Nothing contained in this Work Item must relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the

SSP: TPPC-LPD22-SWRMC21-CN01 5 of 5 ITEM NO: 998-41-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

performance of this contract.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.