(USS MUSTIN) Attachment J-13 Rev_1.xlsx

XLSX spreadsheet 607 KB Posted

Attached to
USS MUSTIN (DDG 89) FY21 DEPOT MAINTENANCE PERIOD & USS SAN DIEGO (LPD 22) FY21 DOCKING SELECTED RESTRICTED AVAILABILITY
Solicitation number
N00024-21-R-4442
Issued by

About this file

This solicitation seeks proposals for the execution of the USS MUSTIN (DDG 89) FY21 depot maintenance period and the USS SAN DIEGO (LPD 22) FY21 docking selected restricted availability. The Naval Sea Systems Command will conduct maintenance, modernization, and repair of these vessels. Offerors must have substantial facilities including a capable pier, human resources, and the ability to complete, coordinate, and integrate multiple areas of ship maintenance, repair and modernization. The period of performance for the USS MUSTIN availability is from September 2021 to July 2023. The period of performance for the USS SAN DIEGO availability is from September 2021 to December 2022. Interested parties must register in the System for Award Management and monitor the beta.SAM.gov site for solicitation release and amendments. Relevant attachments will be made available on beta.SAM.gov with restricted access. Work specification packages and references will be provided on CDs. The Government anticipates a single award by May 2021.

View the file

Other files

File Type Posted
(USS SAN DIEGO) Attachment J-4 Pricing Workbook Rev_2.xlsx XLSX spreadsheet
N00024-21-R-4442_A0009.pdf PDF
USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 10.pdf PDF
N00024-21-R-4442_A0008.pdf PDF
N00024-21-R-4442-A0008 BQ 256-272.xlsx XLSX spreadsheet
MUSTIN ERRATA 12.pdf PDF
N00024-21-R-4442_A0007.pdf PDF
(USS MUSTIN) Attachment J-14 Rev_2.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-13 Rev_2.xlsx XLSX spreadsheet
MUSTIN ERRATA 11.pdf PDF
N00024-21-R-4442-A0007 BQ 210-255.xlsx XLSX spreadsheet
N00024-21-R-4442_A0006.pdf PDF
N00024-21-R-4222_A0006.pdf PDF
N00024-21-R-4442_A0005 BQ 139-209 AMD_0005.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-14 Rev_1.xlsx XLSX spreadsheet
USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 9.pdf PDF
N00024-21-R-4442_A0005.pdf PDF
(USS SAN DIEGO) Attachment J-3 Execution Milestones Rev_1.xlsx XLSX spreadsheet
(USS MUSTIN) Attachment J-18 GFM Rev_1.xlsx XLSX spreadsheet
USS MUSTIN ERRATA 9.pdf PDF
USS MUSTIN ERRATA 10.pdf PDF
(USS SAN DIEGO) Attachment J-4 Pricing Workbook Rev_1.xlsx XLSX spreadsheet
N00024-21-R-4442_A0004 BQ 11-138.xlsx XLSX spreadsheet
USS San Diego TPPC-LPD22-SWRMC21-CNO1 - ERRATA 8.pdf PDF
(USS SAN DIEGO) Attachment J-8 Rev_1 (Errata 8).xlsx XLSX spreadsheet
N00024-21-R-4442_A0004.pdf PDF
N00024-21-R-4442_A0003.pdf PDF
N00024-21-R-4442_A0003 BQ 11-137.xlsx XLSX spreadsheet
N00024-21-R-4442_A0002.pdf PDF
N00024-21-R-4442_A0002 BQ 1-10.xlsx XLSX spreadsheet
N00024-21-R-4442_A0001.pdf PDF
Attachment S-17 (Proposal Assessment).xlsx XLSX spreadsheet
Attachment S-7 (Proposal Assessment).xlsx XLSX spreadsheet
Attachment J-5 (QASP).pdf PDF
Attachment S-3 (PPI Form).xlsx XLSX spreadsheet
Attachment J-15 (QASP).pdf PDF
Attachment J-7 (Schedule Model Review).pdf PDF
Attachment J-8 (GFM List).xlsx XLSX spreadsheet
Attachment J-17 (Schedule Model Review).pdf PDF
N00024-21-R-4442.pdf PDF
CDRLs.zip ZIP file
Attachment S-13 (PPI Form).xlsx XLSX spreadsheet
Attachment J-18 (GFM List).xlsx XLSX spreadsheet
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exec Milestones (Contractual)

USS MUSTIN (DDG 89) FY21 DMPOfferors are not to propose milestones highlighted in Orange. These milestones are calculated or fixed
Offerors are to propose values highlighted in Blue in accordance with "Notes". Entering values into the blue highlighted cells will allow the milestone spreadsheet to calculated the remaining interim milestones.
SystemMilestones/Key Events (Calculated or Proposed)Notes
Avail Start at MSR FacilityMonday, September 27, 2021
DOCKOfferor to Propose Dock Dates IAW Specification 997-11-001.
Dry Dock Reports Due (No Later Than)Sunday, December 31, 1899Reports due on the date in Column B or, if the date in Column B is on a weekend or Government holiday, due on the next Government business day following the date in Column B
UNDOCK- Offeror to Propose Undock Dates IAW Specification 997-11-001.
20% Open and Inspect CFR DUEThursday, January 13, 2022Reports due on the date in Column B or, if the date in Column B is on a weekend or Government holiday, due on the next Government business day following the date in Column B
25% CONFERENCEWednesday, February 09, 2022Conference to be held on the next Wednesday following the date in Column B
50% CONFERENCEFriday, June 24, 2022Conference to be held on the next Wednesday following the date in Column B
75% CONFERENCEFriday, November 04, 2022Conference to be held on the next Wednesday following the date in Column B
HM&E TURNOVER 1 (MSR TO AIT)Monday, April 25, 2022
HM&E AIT work complete Turnover 1- GEDMS MG and Mesh B (includes cabling) all AITMonday, May 02, 2022
HM&E Turnover 2 (MSR TO AIT)Monday, May 09, 2022
HM&E AIT work complete Turnover 2Monday, May 16, 2022
HM&E Turnover 3 (MSR TO AIT)Monday, May 23, 2022
HM&E AIT work complete Turnover 3Monday, May 30, 2022
HM&E Turnover 4 (MSR TO AIT)Monday, June 06, 2022
HM&E AIT work complete Turnover 4Monday, June 13, 2022
HM&E Turnover 5 (MSR TO AIT)Wednesday, July 06, 2022
HM&E AIT work complete Turnover 5Monday, July 18, 2022
HM&E Turnover 6 (MSR TO AIT)Monday, July 25, 2022
HM&E AIT work complete Turnover 6Wednesday, August 03, 2022
HM&E Turnover 7 (MSR TO AIT)Tuesday, September 06, 2022
HM&E AIT work complete Turnover 7Tuesday, September 13, 2022
Combat Systems Space Turnover 1Thursday, October 06, 2022
Combat Systems Space Turnover 2Thursday, October 13, 2022
Combat Systems Space Turnover 3Thursday, October 20, 2022
Combat Systems Space Turnover 4Thursday, October 27, 2022
Combat Systems Space Turnover 5Thursday, November 03, 2022
PCDTuesday, October 25, 2022
HAB COMPLETEWednesday, November 09, 2022
CREW MOVE ABOARDWednesday, November 09, 2022
AVCERTWednesday, November 09, 2022
C5ILO/ALOTuesday, November 15, 2022
LOATuesday, February 21, 2023
DOCK TRAILS/FAST CRUISEThursday, March 02, 2023
HM&E and TYCOM SEA TRAILSMonday, March 06, 2023
Contract CompleteMonday, March 20, 2023

ERL

USS MUSTIN (DDG 89) FY21 DMP

Event Readiness List (Work Item Title) Legend: "I" = Open & Inspect (CFR), "P" = Production Complete,

"T" = Testing Complete, "C" = Certification Complete.START OF AVAILDOCKDry Dock Reports DueAVAIL 20% (O&I)UNDOCKPCDHAB COMPLETEC5ILOAVCERTLOADOCK TRAILS/FAST CRUISEHM&E and TYCOM SEA TRAILSCONTRACT COMPLETEAnnotate Critical Path WI, Controlling WI, PCP, RTR…
WORK ITEM NO.WORK ITEM TITLEComments
042-11-001Accountability of Manhour and Material Reservation; accomplishC
042-11-002Work Package Execution Review (WPER); accomplishC
042-11-005Condition Found Report (CFR); provide and manageC
077-11-001Fire Drill Service; provideP/C
110-11-001Underwater Hull; inspect and repairIP/C3.3.1,3.4.1
110-11-002Fairwater Plug; remove and replaceP/C
113-11-001Bilge Drain Well; repair and preserveIP/C3.2.1.1, 3.5.1.1
113-11-002Auxiliary Machinery Room Number One Structural Repair; accomplishP/C
120-11-001Engine Room Number 2; repairP/C
120-11-002Vacuum Collection Holding Tank Room Number One; repairP/C
120-11-004Steering Gear Room Structural Weld; repairP/C
120-11-005Structural; repairP/C
120-11-006Windlass Machinery Room Structural Repair; accomplishIP/C3.1.1
122-20-001Generator Room; repairIP/C3.1.2.1, 3.3.1
122-21-001Auxiliary Machinery Room Number One Transverse Bulkhead; inspect and repairIP/C3.3.1
123-10-001Tank and Void Cleaning and Pumping; accomplishP/CCritical Path, PCP
123-11-001Compensated Fuel Tank Group One; repairIP/C3.1.1.1
123-11-002Compensated Fuel Tank Group 2; repairIP/C3.1.1.1
123-11-003Compensated Fuel Tank Group 3; repairIP/C3.1.1.1
123-11-004Compensated Fuel Tank Group 4; repairIP/C3.1.1.1
123-11-005Compensated Fuel Tank Group 5; repairIP/C3.1.1.1
123-11-006Compensated Fuel Tank Group 6; repairIP/C3.1.1.1
123-11-007Fuel Oil Service and Gravity Head Tank; repairIP/C3.2.1
123-11-008Compensated Fuel Tank Group One; preserveP/CAccess-cut
123-11-009Compensated Fuel Tank Group 2; preserveP/CAccess-cut
123-11-010Compensated Fuel Tank Group 3; preserveP/CAccess-cut
123-11-011Compensated Fuel Tank Group 4; preserveP/CAccess-cut
123-11-012Compensated Fuel Tank Group 5; preserveP/CAccess-cut
123-11-013Compensated Fuel Tank Group 6; preserveP/CAccess-cut
123-11-014Gas Turbine Generator (GTG) Fuel Gravity Feed Tank; preserveP/C
123-11-015Fuel Service Tank; preserveP/CAccess-cut
123-11-016Fuel Oil Tank Equalizing Pipe; repairP/C
123-12-001JP-5 Tank; preserveP/CAccess-cut
123-12-002JP-5 Tank; repairIP/C3.1.1.1
123-14-001Potable Water Tank; repairIP/C3.1.1
123-15-001Lube Oil Tank; repairIP/C3.2.1, PCP
123-17-001Contaminated Oil Tank; preserve (touch up)IP/C3.1.1
123-17-002Contaminated Oil Tank; repairIP/C3.1.1
123-17-003Contaminated Oil Tank; preserveP/CAccess-cut
123-19-001Waste Water Tank; repairIP/C3.1.1.1
123-19-002Waste Water Tank; preserveP/CAccess-cut
123-21-001Forepeak Tank; repairP/C
123-21-002Accessible Void; preserveP/CAccess-cut
123-21-003Accessible Void Base Metal Weld Builup; accomplishIP/C3.1.1.1
123-22-001Chain Locker and Chain Locker Sump; repairIP/C3.1.1
123-22-002Chain Locker and Chain Locker Sump; preserveP/CAccess-cut
130-11-001Aircraft Securing Fitting; replaceP/C
136-11-00101 Level Transverse Bulkhead; repairP/C
137-11-001Davit Arm Stowage Bracket; replaceP/C
150-11-001Deck Edge Coaming; repairP/C
150-11-00202 Level Bulwark; repair and preserveP/C
150-11-00404 Level Port Bridgewing; repairP/C
150-11-00506 Level Platform Deck; repairP/C
150-11-00605 Level Antenna Platform; repairP/C
150-11-00703 Level Deck; repairP/C
150-11-008Close-In Weapons System (CIWS) Mount Number 22 Foundation and Support Structure; replaceP/C
161-11-001Strut; inspect and repairIP/C3.1.1
163-11-001Sea Chest; inspect and repairIP/C3.2.2.1
163-11-002Waster Sleeve; replaceIP/C3.4.7
165-11-001Sonar Dome Rubber Window (SDRW); inspect and repairIP/C3.2.2,3.3.1,3.6.1,3.7.1,3.7, Access-cut
165-80-001ShipAlt DDG51-TY64,188, Sonar Dome Pressurization System, Digital Electronic Pressure Indicator Transducer and Sensing Line Relocation; accomplishP/C
167-11-001Watertight Closure; replaceP/C
167-11-002Bolted Equipment Removal Plate (BERP) Repair; accomplishIP/C3.1.1.1, 3.5.2
167-11-003Lower Sonar Dome Access Scuttle; repairIP/C3.1.1, 3.2.1.4, 3.2.2.1
167-80-001ShipAlt DDG51-76258D, MAFO-Holtkamp Door Installation, (PARTIAL); accomplishP/C
168-12-001Watertight Scuttle; replaceP/C
168-12-002Quick Acting Watertight (QAWTRTT) Door; repairP/C
171-11-001Wiring Trunk; inspect and preserveP/CAccess-cut
181-11-001Auxiliary Machinery Room Number One Foundation; repairP/C
234-10-001Gas Turbine Module (GTM) 1A, 1B, 2A and 2B Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.1.4.1
241-10-001Lube Oil Pump Flexible Hose Assembly; replaceIP/C3.1.4.1
241-11-001Main Reduction Gear (MRG) Number One Flexible Hose Assembly; replaceIP/CPCP, 3.3.4.1
241-12-001Main Reduction Gear (MRG) Number 2 Flexible Hose Assembly; replaceIP/CPCP, 3.3.4.1
243-11-001Starboard Stern Tube Shaft Seal; overhaulIP/C3.2.2.3
243-11-002Starboard Waterborne Propulsion Shafting; inspect and repairIP/C3.1.1, 3.2.5.1, 3.4.1.1, Access Cut, Critical
243-11-003Starboard Waterborne Propulsion Shafting; installIP/C3.1.1, 3.2.7, 3.4.1.1, Access Cut
243-12-001Port Stern Tube Shaft Seal; overhaulIP/C3.2.2.3, 3.3.2
243-12-002Port Waterborne Propulsion Shafting; inspect and repairIP/C3.1.1, 3.2.5.1, 3.4.1.1, Access Cut, Critical
243-12-003Port Waterborne Propulsion Shafting; installIP/C3.1.1, 3.2.5.1, 3.4.1.1, Access Cut
244-10-001Strut Bearing Thru-Hole Plug; installP/C
244-11-001Stern Tube and Strut Bearing Strap; installP/C
244-11-003Starboard Outboard Propulsion Shafting Bearing Clearance Measurement; accomplishIP/C3.1.3.1
244-12-003Port Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplishIP/C3.1.3.1
245-11-001Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Starboard; repairIP/C3.3.2.4, 3.3.4.1,3.4.2.4,3.4.4.1
245-11-002Number One Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box MER One; replaceIP/C3.3.1
245-11-003Propellers and Propulsors Shaft Flexible Hose Assembly; replaceIP/C3.1.4.1
245-11-004Number One Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplishIP/C3.2.2.1, PCP
245-12-001Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Port; repairIP/C3.3.2.4,3.3.4.1,3.4.2.4,3.4.4.1
245-12-002Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box MER 2; replaceIP/C3.3.1
245-12-004Number 2 Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplishIP/C3.2.2.1, PCP
245-80-001DDG51 Class AER 66047, HOPM Bleed Valve and Snubber Install; accomplishP/CPCP
251-30-001Number One Gas Turbine Module (GTM) Clean Air Intake; repair and preserveIP/C3.2.1, 3.5.1, 3.6.1
251-30-002Number 2 Gas Turbine Module (GTM) Clean Air Intake; repairIP/C3.2.1, 3.5.1, 3.6.1
251-30-003Number One Ship Service Gas Turbine Generator (SSGTG) Clean Air Intake; inspect and cleanIP/C3.3.1
251-30-004Number 3 Ship Service Gas Turbine Generator (SSGTG) Clean Air Intake; preserveIP/C3.2.1, 3.4.1
251-31-001Air Intake and Exhaust Louver; clean and preserveIP/C3.3.1.1
251-32-001Propulsion Gas Turbine (GTRB) Intake Number 2 and Ships Service Gas Turbine Generator (SSGTG) Intake Number 2 and 3; repair and preserveIP/C3.2.1, 3.3.1, 3.4.2.1, 3.5.1.1
251-32-002Propulsion Gas Turbine (GTRB) Intake Number One and Ships Service Gas Turbine Generator (SSGTG) Intake Number One; repair and preserveIP/C3.2.1, 3.3.1, 3.4.2.1, 3.5.1.1
256-61-001Seawater Cooling System Butterfly Valve; replaceP/C
256-70-001Centralized Seawater Cooling Pump; overhaulIP/C3.3.1, 3.5.5.1
259-10-001Number 2 Gas Turbine Mixing Room, Uptake and Boundary Layer Infra-Red Suppression System (BLISS); repair and preserveIP/C3.3.3
259-10-002Number One Gas Turbine Mixing Room, Uptake and Boundary Layer Infra-Red Suppression System (BLISS); repair and preserveIP/C3.2.1, 3.4.2
259-10-003Number One Gas Turbine Mixing Room and Intake/Uptake Engine Room One; repairP/C
259-10-004Ship Service Gas Turbine (GTRB) Exhaust Trunk Deck; preserveIP/C3.2.1
259-11-001Gas Turbine (GTRB) Exhaust Duct Collector; repairIP/C3.3.2
261-11-001Fuel Service Pump Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.1.4.1
261-12-0022A Fuel Service Filter Separator; replaceIP/C3.2.3.1
261-21-0011B Fuel Oil Service Pump; overhaul (OPTION ITEM)IP/C3.5.2.1
261-22-0012A Fuel Oil Service Pump; repair (OPTION ITEM)IP/C3.5.2.1
262-11-001Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspectIP/C3.2.3.1, PCP
262-90-001ShipAlt DDG51-76253K, Main Reduction Gear Lube Oil Coalescing Filter Modification; accomplishP/CPCP
264-31-001Lube Oil Purifier Heater Number One; clean and inspectIP/C3.4.5
264-31-002Lube Oil Purifier Heater Number 2; clean and inspectIP/C3.4.5
304-11-001Multicable Transit (MCT) Plate; replaceP/C
311-30-001Ship Service Gas Turbine Generator Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.1.4.1
311-31-001Ship Service Gas Turbine Generator (SSGTG) Number One Lube Oil Cooler; chemically clean and inspectIP/C3.2.2, 3.3.3,1, PCP
311-32-001Ship Service Gas Turbine Generator (SSGTG) Number 2 Lube Oil Cooler; chemically clean and inspectIP/C3.2.2, 3.3.3.2, PCP
311-33-001Ship Service Gas Turbine Generator (SSGTG) Number 3 Lube Oil Cooler; chemically clean and inspectIP/C3.2.2, 3.3.3.2, PCP
311-80-001DDG51 Class AER 66085, Repair Generator Cabling Chafing Modification; accomplishP/C
321-80-002DDG51 Class AER 64201D, Stuffing Tube Replacement (Partial); accomplishP/C
324-80-001DDG51 Class AER 76101D, Replace Dossert Lug Connector (Partial); accomplishP/C
331-80-001DDG51 Class AER 64125, Addition of Launcher Light; accomplishP/C
411-90-001ShipAlt DDG51-89925K, AWS: ACB16/TI16 CIC Display Upgrade; accomplishIP/C3.3.1, Critical Path, PCP, Access Cut
411-90-002ShipAlt DDG51-89804K, AWS: ACB16/TI16 OA Computing Plant; accomplishIP/C3.2.1, Critical Path, PCP, Access Cut
422-11-001Anti Submarine Warfare (ASW) Revolving Light; removeP/C
423-10-001Antenna Group SPY-1 Series Flexible Hose Assembly; replace (OPTION ITEM)P/C
437-90-001ShipAlt DDG51-77829K, Installation of Radar and TDR TLI's for DFM, JP-5 and Potable Water TanksP/CFor tanks that are filled ISO UD, ensure TLI cables are installed and tested prior
438-90-001ShipAlt DDG51-88260K, Enterprise Remote Monitor Hardware Installation; accomplish (OPTION ITEM)IP/C3.1.1, Critcal Path with GEDMS
438-90-002ShipAlt DDG51-71604K, DDG Mod MCS/DCS Upgrades, Single Central Control Station (CCS) Watchstander; accomplishIP/C3.3.2, Controlling Work Item, PCP, Access Cut
438-90-003ShipAlt DDG51-71726K, DDG Mod Full IBS Upgrade, Single Bridge Watchstander; accomplishIP/C3.3.1, Controlling Work Item, PCP, Access Cut
442-10-001TR-232B/WQC-2A and TR-233B/WQC-2A Transducer Cabling; installIP/C3.2.4.1, 3.3.1
442-11-001TR-233B/WQC-2A Transducer; replaceIP/C3.1.4
456-90-001ShipAlt DDG51-89769K, AWS: ACB16/TI16 KAS WDRC Upgrade; accomplishIP/C3.2.1, Critical Path, PCP, Access Cut
456-90-002ShipAlt DDG51-91754K, AWS: ACB16/TI16 MMSP-R Upgrade; accomplishIP/C3.1.1, Critical Path, PCP, Access Cut
462-08-001DT-513/BQA-8 Hydrophone and Cable Assembly; replaceIP/C3.1.2.3, 3.1.3.3, 3.3.1, 3.4.2
463-11-001AN/SQQ-89A (V)15 Transmitter Flexible Hose Assembly; replace (OPTION ITEM)P/C
463-89-001AN/SQQ-89 Sonar Transducer and Stave Cable Connectorized; replaceIP/C3.1.3, 3.2.1
468-90-001ShipAlt DDG51-91580K, AN/SQQ-89A(V)15 Tech Refresh; accomplish (OPTION ITEM)IP/C3.1.1, Critical Path, PCP, Access Cut
472-00-001OrdAlt 80831, Guided Missile Director AS-3444/SPG-62, Passive Countermeasure System (PCMS) Installation; accomplishP/C
472-90-001ShipAlt DDG51-80156K, AN/SLQ-32 (V)6 Surface Electronic Warfare Improvement Program (SEWIP) Block 2 Upgrade; accomplish (OPTION ITEM)P/CPCP, Access Cut
482-99-001MK 82 Mod 0, Director; replaceP/C
505-11-001Piping Support; repairP/C
506-80-001ShipAlt DDG51-64121D, Relocate Sounding Tube; accomplishP/C
508-12-001Machinery, Pipe, Bulkhead and Ventilation Lagging and Insulation, Inside Machinery Space; replaceP/C
508-12-002Machinery, Pipe Lagging, Bulkhead and Ventilation Insulation, Outside Machinery Space; replaceP/C
512-11-001Ventilation Cleaning; accomplishP/C
512-11-003Supply Ventilation; replaceP/C
512-11-004Ventilation Master Switch Plexiglass Cover; replaceP/C
512-11-005MORPAC Valve Overhaul; accomplishIP/C3.1.2
512-11-006Fan Motor Resilient Mount; replaceP/C
512-80-001DDG-51 Class AER 66113 Hangar Supply System (1S) and Exhaust System (1E) Vent Removal; accomplishP/C
512-90-001ShipAlt DDG51-74012K, VLS Magazine Ventilation Upgrade; accomplishP/CPCP, Access Cut
512-90-002ShipAlt DDG51-71655K, Zone 4 Intake Modification; accomplishP/C
512-90-003ShipAlt DDG51-77419K, DDGM Textile Ducting Installation; accomplishP/C
514-11-001Ventilation Cooling Coil Unit Drain Pan; replaceP/C
514-20-001Air Conditioning Plant Condenser Water Control Valve (CWCV); replaceIP/C3.1.1
514-20-002Air Conditioning Plant Groom and Variable Geometry Diffuser (VGD) Replacement; accomplishIP/C3.2.1, 3.4.1.1
514-21-001Air Conditioning (AC) Plant Condenser; mechanically cleanIP/C3.3.5.1, Critical
514-21-002Air Conditioner Chill Water Pump; overhaulIP/C3.7.1.2
516-11-001Refrigeration System Flexible Hose Assembly; replaceP/CPCP
520-11-001Sea Valve; repair and replaceIP/C3.2.1.1
521-11-001Firemain Valve; replaceIP/C3.2.1
521-11-002Hydraulic Power Unit (HPU) Cascade Orificial Restrictive Device (CORD); installP/C
521-11-003Firemain Valve and Cascade Orificial Restrictive Device (CORD); replaceP/C
521-11-004Firemain Valve; replaceP/C
521-21-001Fire Pump Number 5; overhaulIP/C3.4.3.1, 3.5.3.2
521-21-002Fire Pump Number 2; overhaulIP/C3.4.3.1, 3.5.3.2
522-11-001Deluge Firemain Control Valve; replaceP/C
522-11-003Magazine Sprinkler System Flexible Hose Assembly; replace (OPTION ITEM)P/C
522-11-004Torpedo Magazine Flexible Hose Assembly; replaceP/C
523-11-001Countermeasure Washdown Bulkhead Penetration Sleeve; replaceP/C
523-80-001ShipAlt DDG51-64245D Countermeasure Washdown Bulkhead Penetration Sleeve Installation; accomplishP/C
524-10-001Starboard Shaft Stern Tube Seal Cooling Valve and Piping; replaceP/C
524-10-002Port Shaft Stern Tube Seal Cooling Valve and Piping; replaceP/C
529-11-001Submersible Pump Overboard Discharge Fitting; installP/C
531-11-001Reverse Osmosis Flexible Hose Assembly; replace (OPTION ITEM)P/C
531-51-002Reverse Osmosis High Pressure Pump; replace (OPTION ITEM)P/C
532-10-001Fire Control System Number One, 2 and 3 Flexible Hose Assembly; replace (OPTION ITEM)P/C
532-11-001Cooling Skid, Demineralized Water System Trisodium Phosphate and Citric Acid Flush; accomplishP/CPCP
532-11-002Aegis Cooling Module, HD-1140/SPY-1D Flexible Hose Assembly; replaceP/C
532-11-003AN/SPY-1D S16 Purity Loop Low Flow Switch; replaceP/C
532-11-004Cooling Water Flex Hose Assembly; replaceP/C
533-12-001Potable Water Service Pump Number 2; replace (OPTION ITEM)P/C
541-11-001Fuel Oil Transfer Flexible Hose Assembly; replace (OPTION ITEM)P/C
541-12-001Fueling-at-Sea Station Sampling Valve; replaceP/C
541-21-001Fuel Oil Transfer Pump and Motor; repair (OPTION ITEM)IP/C3.4.2.2
541-22-001Fuel Oil Purifier Class B Overhaul; accomplishP/C3.5.1.1
541-80-001DDG51 ShipAlt 64191D, FAS Transducer Gage Cutout Root Valve; accomplishP/C
541-90-001ShipAlt DDG51-70403K, Digital Fuel Control System Installation; accomplishP/C
551-53-001Number One Low Pressure Air Compressor (LPAC) Class B Overhaul; accomplishIP/C3.3.2, 3.4.1.1
551-53-002Number 2 Low Pressure Air Compressor (LPAC) Class B Overhaul; accomplishIP/C3.3.2, 3.4.1
551-53-003Number 3 Low Pressure Air Compressor (LPAC) Class B Overhaul; accomplishIP/C3.3.2, 3.4.1.1
551-61-001Masker Air Cooler; chemical cleanIP/C3.5, PCP
551-62-001Prairie Air Cooler; chemical cleanP/CPCP
562-10-001Rudder Bearing Seal and Rudderstock Seal; repairIP/C3.3.3.1, ACCECC CUT
562-11-001Starboard Rudder; inspect and repairIP/C3.2.2.1
562-11-002Rudder Stock Bearing; installIP/C3.4.1.1
562-11-003Port Rudder; inspect and repairIP/C3.2.2.1
568-10-001Steering System Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.1.5.1
571-11-001Sliding Padeye, Tilting; overhaul and preserveIP/C3.4.3.1
581-11-001Port and Centerline Anchor Hawse and Chain Pipe; repairIP/C3.2.1, 3.3.1
581-11-002Anchor and Anchor Chain; inspect and preserveIP/C3.1.3.2, 3.3.11
582-11-001Aft Warping Capstan; repairP/C
583-90-001ShipAlt DDG51-83894K, Navy Standard Slewing Arm Davit (SLAD) Installation; accomplishP/CPCP
588-20-001Landing Signal Officer (LSO) Control Station Repair and Heated Window Assembly Replacement; accomplishP/C
588-21-001Flight Deck and Recovery Assist, Securing and Traversing (RAST) System Track and Plate; repair and preserveP/C
588-21-002Helicopter Hangar Door; repairIP/C3.2.1.1, 3.3.3.1
588-21-003Recovery, Assist, Secure and Traverse (RAST) System Flexible Hose Assembly; replace (OPTION ITEM)P/C
588-90-001ShipAlt DDG51-73212K, Helicopter Hanger Door (HHD) Control System Upgrade; accomplishP/C
593-11-001Vacuum, Collection, Holding and Transfer (VCHT) Piping System; chemically cleanP/CPCP
593-11-002Vacuum, Collection, Holding and Transfer (VCHT) Ejector Pump and Motor; replaceP/CPCP
593-11-004Vacuum, Collection, Holding and Transfer (VCHT) System Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.2.5.1, PCP
593-21-001Oily Waste Transfer Pump Flexible Hose Assembly; replace (OPTION ITEM)IP/C3.1.4.1
593-21-002Number One Gas Turbine Waste Drain Pump; overhaul (OPTION ITEM)P/C
593-80-001DDG51 Class AER 90419, VCHT System Replacement Controller; accomplishP/C
593-90-001ShipAlt DDG51-73622K, VCHT H2S Detector Installation; accomplishP/C
595-00-001Towed Array Handling and Stowage Flexible Hose Assembly; replace (OPTION ITEM)P/C
611-80-002ShipAlt DDG51-64185D, Anchor Chain Chafing Plate Installation; accomplishP/C
612-21-001Deck Edge Safety Net Load Test; accomplish (OPTION ITEM)P/C
624-11-001Balanced Joiner Door; remove, store and installIP/C3.1.2
625-11-001Pilot House Window; repairP/C
631-11-001Bilge; preserveIP/C3.5.2.1
631-11-002Escape Trunk; preserveP/C
631-11-003Compartment; preserveP/C
631-11-004Crew Washroom, Water Closet and Shower Bulkhead; preserveP/C
631-11-005Supply Department Storeroom; preserveP/C
631-11-006AFFF Station Number One Deck; preserveP/C
631-11-008Fan Room Deck; preserveIP/C3.1.1, 3.2.1.1
631-11-009Interior Compartment Deck; preserveP/C
631-11-010Infrared Suppression (IRS) Eductor Secondary Air Inlet Trunk; preserveP/C
631-12-001Engine Room Number One Deck; preserveIP/C3.1.1, 3.3.1
631-12-003Ships Service Gas Turbine Generator (SSGTG) Exhaust Trunk; preserveIP/C3.2.1, 3.3.1
631-13-001Collective Protection System (CPS) Zone One Fan Room; repair and preserveIP/C3.4.1
631-13-002Collective Protection System (CPS) Zone 2 Fan Room; repair and preserveIP/C3.4.1
631-13-003Collective Protection System (CPS) Zone 3 Fan Room; repair and preserveIP/C3.4.1
631-13-004Interior Compartment Deck; preserveP/C
631-21-001Superstructure; preserveP/C
631-21-002Mast Preservation; accomplishP/CCritical
631-21-004Weatherdeck Nonskid; replaceP/C
631-31-002Underwater Hull Preservation with Paint Company Original Equipment Manufacturers' (OEM) Technical Representative; accomplishIP/C3.1.1, Controlling
631-41-001Freeboard; preserveP/C
633-11-001Transducer Compartment Zinc Anode; installIP/C3.3.3, 3.4.4
633-21-001Impressed Current Cathodic Protection (ICCP) System; inspect and repairIP/C3.2.1, 3.4.3, 3.5.3
633-80-001ShipAlt DDG51-64153D, Zinc Anode Modification; accomplishP/C
634-11-001Trash Disposal Room; repair and preserveP/C
634-11-002Electrical Grade Matting Deck Covering System; replaceP/C
634-11-003Vacuum Collection Holding Tank Room Number One and 2 Chemical Resistant Floor Covering System; installP/C
634-11-0045"/54 Caliber Projectile Magazine Room Latex Concrete Covering; replaceP/C
634-11-005Electrical Grade Matting Deck Covering System; installP/C
634-11-006Solid Vinyl or Vinyl Composition Tile; replaceP/C
634-11-008Weather Deck Nonskid; replaceP/C
634-11-009Bridgewing Deck; repair and preserveP/C
634-11-010Aviation Repair Shop Nonskid; replaceP/C
634-11-011Laundry Room (2-414-0-Q) Chemical Resistant Floor Covering System; installP/C
634-21-001Flight Deck Nonskid; replaceP/C
634-21-003Non-Critical Nonskid; replaceP/C
634-21-004Fueling at Sea (FAS) Station Number 3 and 4 Nonskid; replaceP/C
634-21-005Forecastle Nonskid; replaceP/C
635-11-001Ship Service Gas Turbine Generator (SSGTG) Exhaust Trunk Insulation; replaceP/C
635-11-002Compartment Insulation; installP/C
636-11-001Sonar Dome Hull Damping System; repairIP/C3.1.1, 3.3.1.1
641-11-001Executive Officer Stateroom Desk; replaceP/C
643-11-001Berthing Habitability Project Installation; accomplishP/C
644-11-001Executive Officer Stateroom Head Habitability Overhaul; accomplishP/CPCP
644-11-002Sanitary Habitability Project Installation; accomplishP/CPCP
644-11-00301 Level Officer Washroom, Water Closet and Shower Overhaul; accomplishP/CPCP
644-11-004Female Chief Petty Officer (CPO) Sanitary Space Overhaul; accomplishP/CPCP
644-11-00502 Level Officer Washroom, Water Closet and Shower Overhaul; accomplishP/CPCP
644-11-006Crew Scullery Passing Window; replaceP/C
644-80-001ShipAlt DDG51-64170D, Crew 3 Shower Stall Modification; accomplishP/C
644-90-001ShipAlt DDG51-86821K Women at Sea Berthing Number 2 Crew Living Space Modification; accomplishP/CPCP
651-80-001DDG51 Class AER 66082, Crew Galley Serving Line Modification; accomplishP/C
651-90-001ShipAlt DDG51-71605, DDG Modifications to Galley; accomplishIP/C3.2.1, Controlling Work Item, Access Cut, PCP
661-10-001Chart Table; replaceP/C
711-80-001ShipAlt DDG51-94448D, Install M240 Mount Foundations on DDG51 with SLQ-59; accomplishP/C
721-31-001Vertical Launch System (VLS), MK 41 Launcher Top and Uptake Hatch; preserveP/C3.2.1
721-31-002Vertical Launch System (VLS), MK 41 Launcher Uptake and Cell Hatch; remove and replaceP/C3.3.4.2
721-90-001ShipAlt DDG51-85964K, MK 41 Vertical Launching System (VLS) BLV DDG ShipAlt; accomplishP/C
752-10-001Torpedo Bridge Crane Hoist Flexible Hose Assembly; replaceP/C
763-11-001Ready Service Locker (RSL); repair (OPTION ITEM)P/C
837-90-001Antenna Photograph; provideP/C
857-11-001Personnel Berthing Barge Support; provide (OPTION ITEM; Homeport ONLY)P/CPCP
857-11-003Temporary Duty Section Berthing Off-Ship; provide (OPTION ITEM; Out of Homeport ONLY)P/CPCP
897-11-001Availability Program Management Multi-Cable Transit (MCT) Cableway Integrator; provideP/C** Affects all 3 KEs
980-00-001OrdAlts 85473K, 79024K, and 78778K, AWS: MMSP Transmitter Modifications for DDG and LBTS, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-00-002OrdAlts 85224K and 79353K, MK41 VLS BL BMD 5.1 and Ablative upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-00-003OrdAlt 80817, Air Cooled Solid State Frequency (ACSSFC) Insulated Gate Bipolar Transistor (IGBT) Inverter Module and 28 Volts DC Power Supply, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-00-004OrdAlt 74588, FCS KAS Installation, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-11-002Ship's Force Office Space and Temporary Classroom; provide (OPTION ITEM; Out of Homeport ONLY)P/C
980-11-004Light-Off Discrepancy Correction Assistance; provideP/CRTR
980-31-001Regional Maintenance Center (RMC) Office Space; provideP/C
980-90-001ShipAlt 79362K and OrdAlt 79362K, AWS Seawater Flowmeter, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-002ShipAlt 83591K and MachAlt 74904K, Digital Voltage Regulator and FADC Modernization, Alteration Installation Team (AIT) Support Service; provideP/C
980-90-003ShipAlt DDG51-80274K, 76829K, 76869K, 76974K, 82635K, 85964K, 87103K, 90643K, 89769K, 89804K, 89925K, and 91754 NAWCAD Combat Systems Alteration, Alteration Installation Team (AIT) Support Service; provideP/CCritical Path, Controlling Work Item, Access Cut
980-90-004Engineering Change 90119, Navy Cash Equipment Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/CNeeds NIPR. After CANES?
980-90-005ShipAlt DDG-51-96436K, Temporary 30MM Gun Weapon System (GWS), Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/CAffects Intakes/Uptakes
980-90-006Engineering Change 70619, Gas Turbine Module (GTM) Main Engine Digital Fuel Control, Alteration Installation Team (AIT) Support Service; provideP/C
980-90-007ShipAlt DDG51-70403K, 71604K, 71615K, 71726K, 73091K, 77427K, 77829K, 84226K, and 84400 Hull, Mechanical and Electrical (HM and E), Alteration Installation Team (AIT) Support Service; provideP/CControlling Work Item, Access Cut
980-90-008MachAlt DDG-51, 82560K, 82582K, 83082K, and 84127K, DDG Helo Hangar Door Upgrade, Alteration Installation Team (AIT) Support Service; provideP/CSA 732121K Work Item 588-90-001 must complete before this can start
980-90-009ShipAlt DDG51-75360K, CBSP Tier 3, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-010ShipAlt DDG51-84694K, PEOC4I DMR IW and MUOS Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-011ShipAlt DDG51-86033K, MOS Modification, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-012ShipAlt DDG51-91580K and 86222K, SQQ-89/NGF Install, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/CCritical Path, PCP, Access Cut
980-90-014ShipAlt DDG51-87785K, AS-4775 Link 16 Antenna, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-015ShipAlt DDG51-91027K, GPNTS(V)4, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-016ShipAlt DDG51-93987K, SSEE INC AIU Modification, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-017ShipAlt DDG51-88635K, CIWS Block 1B Overhaul, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-018ShipAlt DDG51-83335K, Phase III OPA System Improvement, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-019ShipAlt DDG51-94294K, Canes HW2 Tech Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-020Government Sponsored Representative (NAVSEA SEA21 PMR) Office Space; provideP/C
980-90-021Naval Surface Warfare Center (NSWC) Port Hueneme Detachment (PHD) Project Team Office Space; provideP/C
980-90-022ShipAlt DDG51-85030K, PEOC41 GBS RBM, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-023ShipAlt DDG51-84646K, SSEE Mod SA 555, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-024ShipAlt DDG51-95861K, AN/USQ T-52A(V)1 Training Interface Unit, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-025ShipAlt DDG-51-94692K, N/SPS-73(V)18 Surface Scan Radar, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-026ShipAlt DDG51-94979K, DDG HM&E Condition System Rack, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-028ShipAlt DDG51-85077K, AN/SPQ-9B Production Tech Refresh With PDD On Surface Ship, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/CCritical Path, Controlling Work Item, PCP
980-90-029ShipAlt DDG51-95946K, C2P Tech Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-030Standardized Pierside Maintenance and Repair (SPMR), Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
980-90-031ShipAlt DDG51-90149K, ADNS AN/USQ-144K(V)2 With SP4, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)P/C
982-31-002Machinery Space Production Completion and Requirement for Light-Off Assessment (LOA) (Non-Complex); accomplishP/CRTR
982-31-003Dock Trial, Fast Cruise, and Sea Trial; accomplishP/C
982-32-001Preliminary Light Off Assessment (LOA) Inspection Discrepancy Correction Assistance; provideP/CRTR
992-11-001Temporary Flammable Liquid Hazardous Waste and Hazardous Material Storage for Ship's Force Use at Contractor's Facility; provideP/C
992-11-003Temporary Air Conditioning; provideP/C
992-11-004Transport Control Protocol/Internet Protocol Based T-1 Type Computer Network (T-1 Line) Support Service; provideP/C
992-11-006Fuel Assistance for Fuel Barge; provide (OPTION ITEM; Naval Base Ports Only)P/C
992-11-007Oil Spillage and Floating Sandblasting Debris Boom; installP/C
992-11-008Support Service for Ship's Force Security; provideP/C
992-11-009Temporary Service; provideP/C
992-11-011Ship's Force Parking; provideP/C
992-11-012Pressurized Waveguide and Transmission Line Dry Air Lay-Up; provideP/C
992-11-013Crew Transportation; provideP/C
992-11-015Demineralized Water; provideP/C
992-11-017Barge For Multi-Function Towed Array (MFTA); provideP/C
992-21-001Defuel Ship; accomplish (OPTION ITEM; Non-Naval Base Ports ONLY)P/C
992-31-001Bilge Cleaning and Pumping; accomplishP/C
992-90-001Government Furnished Material Warehouse Storage Space for SEA21 AIT 70,000 Square Feet; provideP/C
993-11-001Ship's Force Warehouse Storage Space; provideP/C
993-11-002Transportation Service; provide (OPTION ITEM)P/C
993-21-001Rigging, Crane and Transportation Service; provideP/C
993-31-001Temporary Main Reduction Gear (MRG) Dehumidifier System; provideP/C
993-31-002Temporary Deck Covering; installP/C
993-31-003AN/SPY-1D Antenna Protective Cover; installP/C
997-11-001Drydocking and Undocking; accomplishP/C
998-41-001Hazardous Waste Produced on Naval Vessels; controlP/C

DISTRIBUTION STATEMENT D : Distribution authorized to the Department of Defense and U.S. Department of Defense contractors only (administrative use) (27 Sep 16). Other request shall be referred to CNRMC. FOUO

HM&E Turnovers

Critical Path Equipment Cable Turnover, Power-up and Test Requirement Schedule DDG89 FY21 DMP (HM&E Turnovers)
EquipmentA+ SY turnover to AITDateEquipment
MSR Responsible27-Sep-21AIT Responsible
SA 71726- SPS-73 ISEA Disconnect Stand Alone Operating Panel (SAOP) for relocation and engineering/field changes. ISEA to disconnect prior to Contractor rigging.
SA 73091- Remove al FODMS IOUs (29 total) and ship as directed by drawing Ripout 12,13,52,73,81 and 91 foundations.
SA 71604- Start CTM install and Swbd Connections in Swbds, SF Swbds, Load Centers (SA71604) (30 days)
MSR Fuel Bank TurnoverAIT Fuel Bank Turnover
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs6 weeks prior to undockIncludes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs4 weeks prior to undockIncludes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs2 weeks prior to undockIncludes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
MSR Turnover 121025-Apr-22AIT Turnover 1 GEDMS Mesh B and MG
SA 70403- Ripout Fuel Storage & Receiver Tanks Monitor Panel from Oil Lab21025-Apr-22SA 73091K- All Power Sources and Terminal Boxes for Equipment in TO 1, TO 2 and TO 3 to also include new and upgraded sources.*
25-Apr-22SA 73091K-GEDMS Mesh B (BSE B1-B10) and power cables at least one power source has to be available*
25-Apr-22SA 73091K- Install GEDMS Maintenance Group. Removed MG will be shipped as directed by drawing. Install while access cut to Aft IC is open
MSR Turnover 2- Aft Steering, Repair 3 and #3 GTG22409-May-22AIT Turnover 2- Aft Steering, Repair 3 and #3 GTG
SA 71726- Aft Steering Unit (ASU)17509-May-22(Power/Network/Shipside Cabling)
Repair 3 Equipment , Misc Stowages and painted iaw spec 438-90-00217509-May-22SA 71604- RSC Repair 3, C/O SW, Speaker. Hold Keyboard for later installation per SMR direction.
SA 71726- Local Control Steering Units (LCUs 1 - 4)17509-May-22(Power/Network/Shipside Cabling)
SA 71604- Electric Plant DIU 317509-May-22(Power/Network/Shipside Cabling)
All Power Sources & Terminal Boxes for Equipment in TO 4, TO 5 and TO 6 as per SIDs.
FADC #3 (Power/Network/Shipside Cabling)
SA 73091- Install IOUs: 21, 22, 23 and 62. IIUs 122, 162. C-DR 122, 141 and 162. USE-162B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR Turnover 3- CCS and Repair 523823-May-22AIT Turnover 3- CCS and Repair 5
SA 71604-UCCs 1 & 223823-May-22Complete SA 71604 wiring in CCS, including vent control panels, RSC DCC, C/O SW & Speaker. Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction.
SA 77419 Textile Ducting WI 512-90-002 complete23823-May-22S/A 94979 OIP in CCS
CCS and Repair 5 Equipment and Misc Stowages. Painted and deck complete iaw spec 438-90-00223823-May-22SA 71604-RSC Repair 5, UPS, C/O SW and Speaker. Hold Keyboard for later installation per SMR direction.
SA 70403K complete in Oil Lab, includes all cabling, connections for Oil Lab PC
SA 71604- TIWS (CCS) LAN Drop & Power Outlet
SA 73091- Install IOUs 32, 33, 72. IIUs 132, 172 and 173. C-DRs 26,132,172 and 173. USE 132B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR Turnover 4- MER 1, AUX 1 and Repair 225206-Jun-22AIT Turnover 4- MER 1, AUX 1 and Repair 2
SA 71604-Electric Plant DIU 1 AUX 125206-Jun-22(Power/Network/Shipside Cabling)
SA 71604- Propulsion DIU 4 MER 125206-Jun-22(Power/Network/Shipside Cabling)
SA 71604- UCC 3 MER 125206-Jun-22(Power/Network/Shipside Cabling)
SA 71604- ECU 1A and 1B MER 125206-Jun-22(Power/Network/Shipside Cabling)
Repair 2 Equipment, Misc Stowages and painted iaw spec 438-90-00225206-Jun-22S/A 94979 OIC #1/#2/#4/#A1/#A2
F/O, L/O & CRP valves associated with SA71604K in MER1. 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill25206-Jun-22Electrical hook-up of valves associated with SA 71604K in MER 1
FADC #1 (Power/Network/Shipside Cabling)
SA 71605 Galley foundations, piping and electrical complete that impact MER 1 overhead25206-Jun-22SA 71604- RSC Repair 2, C/O SW, Speaker. Hold Keyboard for later installation per SMR direction.
SA 73091- Install IOUs 74, 82, 83 and 84. IIUs 174, 182 and 183. USEs 174B and 183B. C-DRs 8A, 14, 174, 182 and 183. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR Turnover 5- MER 228206-Jul-22AIT Turnover 5- MER 2
SA 71604- Electric Plant DIU 2 MER 228206-Jul-22AIT (Power/Network/Shipside Cabling) S/A 94979 - OIC #3/#5/#B
SA 71604- Propulsion DIU 5 MER 228206-Jul-22AIT (Power/Network/Shipside Cabling)
SA 71604-UCC 4 MER228206-Jul-22AIT (Power/Network/Shipside Cabling)
SA 71604- ECU 2A, 2B MER228206-Jul-22AIT (Power/Network/Shipside Cabling)
F/O, L/O & CRP valves associated with SCD 71604K in MER2. 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill28206-Jul-22AIT (Power/Network/Shipside Cabling)
Install IOU 31, IIU 131 and 134, C-DR 131 and 134, USE 131B.All associated work related to these IOUs/IIUs/USEs/C-DR boxes
FADC # 2 (Power/Network/Shipside Cabling)
SA 71604- ADACS Foundation MER 228206-Jul-22ADACS unit in MER2, including power and all hook-ups
MSR Turnover 6 SA 71604 Potable Water System mods30125-Jul-22AIT Turnover 6
Complete following under SA 71604; Potable Water System, incl Tanks, TBs, MOVs, TLIs & Modified Pump Controllers30125-Jul-22AIT (Power/Network/Shipside Cabling)
GEDMS Mesh A BSEs (A1-A10) and power cables at least one power source has to be available*
Install IOUs 53, 93 and 94. IIU 194. C-DR 5A, 194. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
SA 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) and associated TBs, JP-5, all electrical work complete
MSR Turnover 7 SA70403 DFC, SA77253K Filter Seprator, SA71604 AHSS Vent Mod Complete34406-Sep-22AIT Turnover 7 AHSS, DVSS and Dig Indicators
LO Filter Separator Purifier (SA 76253K) complete34406-Sep-22
AHSS Vent Mod SA 71604 dwg 500-8659958 complete34406-Sep-22AHSS Install Complete
Digital Fuel Control SA 70403 complete34406-Sep-22SA71615 DVSS Complete - ALL VIROEs, CJBs, Cables (*)
SA 77829K 70403K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) and associated TBs, JP-5, all electrical work complete
Digital Indicators SA 77427 complete except CS spaces
SA 71615- Install all DVSS Cameras as directed by SMR (week prior to PCD)
SA 73091-Install IOUs 14, IIUs 114, C-DRs 6, 114. Complete all associated work related to these IOUs/IIUs/USEs/C-DR boxes
HM&E SHIPALT Equipment in Combat Systems MOD Spaces, dates are CS Turnover dates
MSR CompleteA+DateAIT Complete
RADAR 1- SA71726 work complete38820-Oct-22RADAR 1- SA 71726 working complete. IBNS Rack 2 wiring including HS Firewall, UPS & C/O Switches
CIC- SA 71604 work complete38113-Oct-22RADAR 2- SA71726 Trigger/Video Amp installed and wired
CIC- SA71726 work complete38113-Oct-22CIC- SA77427 and SA71726 work complete
Array Room #1- SA71726 mods complete38820-Oct-22Array Room 1- SA71726 work complete
CSMC- SA 71604 work complete37406-Oct-22CSMC- SA73091K (BSE A5), SA 84226K and SA 71604K work complete. Hold Keyboard for later installation per SMR direction.
Pilot House- all SA 71604 mods complete38820-Oct-22Pilot House- all SA71604, SA77427 work complete
Pilot House- SA 71726 SPS-73 SAOP install. (ISEA deliver to SY)38820-Oct-22Pilot House- SA71726, SPS-73 ISEA Connectorize SAOP Ethernet SW, C/O SW & UPS
Pilot House- SA 71726 work complete38820-Oct-22Pilot House- SA71726 work complete. Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction.
Pilot House- SA 77419 Textile ducting work complete38820-Oct-22Pilot House- complete all SA 77427 mods
Pilot House- Painted and deck complete iaw SA 71604 work item38820-Oct-22
Aft IC Gyro 3-300-0-C, SA 73091(IOU41, IIU141, CDR 17/141) and SA77427 complete. SA 94979 OIC #D
Power Supply / Conversion Rm 3-126-2-Q, SA 73091 complete
Fwd IC Gyro 4-94-0-C, SA 73091( IOU51, IIU151, CDR 151) and SA 77427 complete. SA 94979 OIC #C
CSER 1 2-53-1-C, SA 73091(IOU93, CDR4) and SA 77427 complete. SA 94979 - Condition Sys Rack, XFMR, Vent Mod
CSER 3 1-300-0-C, SA 73091 complete (IOU42, IIU142, CDR 24/142)
CSER 2 2-126-2-C, SA 73091 complete (CDR10)
CIC- SA 71604 work complete including RSC, UPS & C/O Switch. Hold Keyboard for later installation per SMR direction.
SONAR Control 2-50-2-C, SA 77427 complete
SONAR 3 3-18-0-Q, SA 73091 complete (IOU92, CDR2)
SONAR 1 1-18-0-Q, SA 73091 complete (BSE A7)
Communications Center 2-126-1-C, SA 73091(IOU71, CDR9) and SA 77427 complete. SA 94979 OIP
CSER 4 03-142-1-C, SA 73091 complete (IOU 11, IIU 111, CDR 29,30, 111)
Chart Room- SA 77427 and SA 71726 complete, IBNS NAV 2 computer
Electric Load Center 03-142-2-Q, SA73091 complete (CDR28)
XO Cabin- SA 77427 complete
CO Cabin- SA 77427, 71726 complete; IBNS NAV 4 computer (CO's Laptop), install prior to HAB Turnover

CS Turnovers

USS MUSTIN (DDG 89)SUPPORT SERVICES
SPACE NO.SPACE NAME60 Hz400 HzA/CECWChill WaterFM SWSDry AirHP AirLP AirRelease Date
TURNOVER 1
4-94-0-CIC & Gyro Rm #1YYYYALO -40
3-300-0-CIC & Gyro Rm #2YYYYALO -40
3-126-2-QPower Supply/Conversion RoomYYYYALO -40
3-319-0-QPower Conversion RmYYYYALO -40
4-126-0-EAuxiliary Machinery Rm #1YYYYSWSYALO -40
4-42-0-QSonar Cooling Equip RmYYYYYALO -40
03-142-2-QElectric Load Center #1YYALO -40
01-110-3-QFan Room PZ #1YYALO -40
01-126-3-QFan Room PZ #2YYALO -40
01-158-0-QFan RoomYYALO -40
01-240-01-QFan Room PZ #3YYALO -40
01-300-2-QFan RoomYYALO -40
01-338-3-QFan RoomYYALO -40
01-338-4-QFan RoomYYALO -40
03-142-3-QFan RoomYYALO -40
03-142-4-QFan RoomYYALO -40
1-78-1-QFan RoomYYALO -40
1-78-2-QFan RoomYYALO -40
2-42-2-QFan Room (SNR CONT-CSER1)YYALO -40
3-164-2-QFan RoomYYALO -40
3-362-0-QFan RoomYYALO -40
01-130-0-QCSMCYYYALO -40
TURNOVER 2
05-131-0-QDirector Equip Rm #1YYYYYALO -33
04-272-0-QDirector Equip Rm #2YYYYALO -33
03-282-0-QDirector Equip Rm #3YYYYYALO -33
06-157-0-TMast Access/Wiring TrunkYALO -33
1-126-0-CCICYYYALO -33
1-268-0-CCCS (VLS Alarms)YYALO -33
2-53-1-CCSER #1YYYYALO -33
2-126-2-CCSER #2YYYYALO -33
1-300-0-CCSER #3YYYALO -33
1-314-0-CCSER 3 AnnexYYALO -33
03-142-1-CCSER Rm #4YYYYALO -33
TURNOVER 3
03-128-0-CRadar Rm #1YYYYYYALO -26
03-142-0-CRadar Rm #2YYYYYALO -26
01-274-1-CRadar Rm #3YYYYYALO -26
03-128-1-QArray Rm #1 (Fwd Stbd)YYYYALO -26
03-128-2-QArray Rm #2 (Fwd Port)YYYYALO -26
03-158-3-QArray Rm #3/Elect WS #1AYYYYALO -26
03-158-2-QArray Rm #4/ Elect WS #1BYYYYALO -26
2-126-1-CCommunications CenterYYYALO -26
2-157-1-CRadio Transmitter RoomYYYALO -26
2-220-1-QSnap III Computer RoomYYALO -26

This is the start of the file's text. The full file is on GovTribe.