This solicitation requests proposals for the USS MUSTIN (DDG 89) FY21 Depot Maintenance Period and USS SAN DIEGO (LPD 22) FY21 Docking Selected Restricted Availability. Offerors must have capable pier and human resources facilities to complete ship maintenance, repair, and modernization work. Proposals are due by May 2021, with the USS MUSTIN availability period starting in September 2021 through July 2023, and the USS SAN DIEGO period beginning in September 2021 through December 2022. The Naval Sea Systems Command will make a single award for contractors to execute required maintenance activities at their West Coast facilities, including coordinating subcontractors, alteration teams, and ship's force personnel. The solicitation attachments include execution milestones, pricing workbooks, and compartment closeout requirements. Interested parties must register in the System for Award Management and request access to restricted attachments on beta.SAM.gov.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J-17 Schedule Model Review
USS MUSTIN
Purpose: At A-30 the Lead Maintenance Activity (LMA) shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day 2 and following is 0800-1130.
1. Required Attendees:
a. LMA management team
b. Government Project Management Team (NSA)
c. Turnkey Subcontractors
d. Alteration Installation Team (AIT) On Site Installation Coordinators (OSIC)
e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable
f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)
2. Agenda:
Day 1 Work Package Execution Review (WPER) (Government Facilitated)
a. Early Start Candidates (LMA)
b. WAF/Tag Out coordination (LMA)
c. Pier Laydown Plan (LMA)
d. First 100 Hour Plan (NSA)
e. Communications Plan (NSA)
f. Process Control Procedures (PCP) (LMA)
g. Access Cuts (LMA)
h. Fire Prevention and Fire Drill (8010) requirements (NSA)
i. Memorandum of Agreement (MOA) – AIT’s only (NSA)
Day 2 - 7
a. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the
LMA, subcontractors, AITs, Ship’s Force, and Intermediate Maintenance Activity (IMA).
3. Deliverables:
a. Updated IPS with all maintenance activities fully integrated. (LMA)
b. Early start candidates submitted and approved by the NSA. (LMA)
c. WAF/Tag Out coordination plan established. (LMA)
d. First 100 Hour Plan established. (NSA)
e. Set schedule for all required meetings. (NSA)
f. Pier Laydown Plan submitted for approval by NSA. (LMA)
g. List of Process Control Procedures with projected due dates. (LMA)
h. List of access cuts (if required). (LMA)
i. Fire drill execution date set. (NSA)
j. Detailed review of critical path and top three controlling path items. (LMA)