This document contains questions and answers related to a solicitation for depot maintenance of two Navy vessels, USS MUSTIN and USS SAN DIEGO. The solicitation seeks maintenance, repair, and modernization services for both ships, to be performed at contractor facilities on the West Coast between September 2021 and July 2023 for USS MUSTIN and December 2022 for USS SAN DIEGO. Questions cover clarification of proposal requirements, availability periods, ship inspections, contract references and specifications, growth work, and identification of errors. The Naval Sea Systems Command issued the solicitation, with proposals due and anticipated award in May 2021. Offerors must register in SAM and contact points of contact to obtain work specifications and references.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Solicitation #: | N00024-21-R-4442 USS SAN DIEGO & USS MUSTIN VG |
| NAVSEA POC: | Stephanie Hoffman, stephanie.l.hoffman@navy.mil, (202) 781-1456 |
| Stephanie Allshouse, stephanie.j.allshous@navy.mil, (202) 781-2383 | |
| Jackie Black, jacqueline.black@navy.mil, (202) 781-1088 |
| Master # | Ship | Question Area | Section / Para # | Contractor Question | Government Response | |
| 1 | N/A | RFP | Section L | Please clarify if contractor may submit a proposal for one vessel only, or if contractor must submit for both vessels in order to be considered responsive. | Please refer to Section L, paragraphs IV and V, which state 'in order to be considered responsive to the solicitation, Offerors must submit proposals to complete ALL of the availabilities supported by the Offeror's available dry dock and pier facilities.' | |
| 2 | MUSTIN | RFP | Section C | Page 123 of 225 Specifications and Standards. C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018) (a) Definitions (i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments). (ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing. (b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below. Bidder's Question; It is the Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references. However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate the reference and only use it to aid in the development of an estimate of references that are to be accomplished. 1) Please concur or advise on this interpretation. | All zero-tier and first-tier references are mandatory for use in accordance with C-211-H016. The contractor is responsible for ensuring compliance with mandatory references. | |
| 3 | N/A | RFP | Section B | Page 103 of 225 NOTE E: SPECIAL AGREEMENT FOR GROWTH WITH A PRICE OF $25,000 OR LESS To make administration of small dollar value growth more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process. Bidder's Question; 1) In NOTE E, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"? | A drawing revision change where no additional work is required is being provided as an example of an administrative change which will follow the change process. In the event a change requires growth (which has an estimated price of $25,000 or less), resolution will follow the Small Dollar Value Growth procedures. The Government will not respond to requests for blanket assertions regarding drawing revisions. | |
| 4 | N/A | RFP | Section L | Page 211 of 225 V. PROPOSAL CONTENT IN ORDER TO BE CONSIDERED RESPONSIVE TO THE SOLICITATION, OFFERORS MUST SUBMIT PROPOSALS TO COMPLETE ALL OF THE AVAILABLITIES SUPPORTED BY THE OFFERORS’ AVAILABLE DRY DOCK AND PIER FACILITIES A. USS MUSTIN Proposal: MUS-1 Price Volume 1. USS MUSTIN Price Proposal: The price proposal shall not contain non-price factor information. The price proposal shall be comprised of the following documentation: g) Completed Proposal Assessment (S-17). Contrator didn't receive the S-17 along with the RFP. Bidder's Question: Will the customer provide the S-17? | Attachment S-17 was provided as a public document dvia beta.SAM.gov on December 22, 2020. | |
| 5 | SAN DIEGO | RFP | Section C | Page 123 of 225 Specifications and Standards. C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018) (a) Definitions (i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments). (ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing. (b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier | ||
| references shall be used for guidance only unless specifically identified below. Bidder's Question; It is the Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references. However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate the reference and only use it to aid in the development of an estimate of references that are to be accomplished. 1) Please concur or advise on this interpretation. | All zero-tier and first-tier references are mandatory for use in accordance with C-211-H016. The contractor is responsible for ensuring compliance with mandatory references. | |||||
| 6 | SAN DIEGO | RFP | Section B | Page 103 of 225 NOTE E: SPECIAL AGREEMENT FOR GROWTH WITH A PRICE OF $25,000 OR LESS To make administration of small dollar value growth more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process. Bidder's Question; In NOTE E, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"? | A drawing revision change where no additional work is required is being provided as an example of an administrative change which will follow the change process. In the event a change requires growth (which has an estimated price of $25,000 or less), resolution will follow the Small Dollar Value Growth procedures. The Government will not respond to requests for blanket assertions regarding drawing revisions. | |
| 7 | SAN DIEGO | RFP | Section L | Page 209 of 225, III. GENERAL INFORMATION: A. Ship Checks: Item 1 states "The USS SAN DIEGO (LPD 22) will not be available for ship check prior to the proposal submission due date. Potential offerors may inspect a sister ship, the USS ANCHORAGE (LPD 23) in San Diego, CA, from 23 December 2020 to 8 January 2021." Contractor notes the remaining period to perform Ship Checks over the alternate vessel USS ANCHORAGE (LPD 23) is not sufficient to conduct an accurate assessment of the Work Scope in a 312 Work Item Specification package. Bidder's Question; Will the Customer provide a (7) day extension the Ship Check Period or provide another oppertunity to conduct an inspection of the USS ANCHORAGE (LPD 23) or another sister ship and if so will a equal extension day for day PPI Submital date extension be granted inorder to submit question resulting from the Ship Check? | Please refer to Amendment A0001. | |
| 8 | MUSTIN | RFP | Section L | Page 209 of 225, III. GENERAL INFORMATION: A. Ship Checks: Item 2 states "The USS MUSTIN (DDG 89) will not be available for ship check prior to the proposal submission due date. Potential Offerors may inspect sister ships, the USS RAFAEL PERALTA (DDG 115) in San Diego, CA, from 23 December 2020 to 28 December 2020 and the USS SPRUANCE (DDG 111) from 1 January 2021 to 7 January 2021 in San Diego, CA." Contractor notes the remaining period to perform Ship Checks over the alternate vessel USS SPRUANCE (DDG111) is not sufficient to conduct an accurate assessment of the Work Scope in a 323 Work Item Specification package. Bidder's Question; Will the Customer provide a (7) day extension the Ship Check Period or provide another oppertunity to conduct an inspection of the USS SPRUANCE (DDG111) or another sister ship and if so will a equal extension day for day PPI Submital date extension be granted inorder to submit question resulting from the Ship Check? | Please refer to Amendment A0001. | |
| 9 | MUSTIN | RFP | Section C | Section C - Descriptions and Specifications |
CLAUSES INCORPORATED BY FULL TEXT
C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)
(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within 30 days of discovery:
(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,
(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.
(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and Above Work and it provides the process for adjudication.
(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.
(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.
• Contractor has submitted pre-proposal inquiries (PPIs) which have identified disparities in the Specification package and has received subsequent revisions to the specifications through Errata(s) 8. Although the deadline to submit PPIs has passed, the contractor continues to identify anomalies within the specifications and submit PPIs for correction.
Bidder's Question:
Are there any other known errors or omissions to the contract package that the Customer is aware of, as there are no others reasonably apparent to us?
| Pursuant to C-217-H005, 'Growth and New Work' the contractor is under an obligation to address any errors or omissions reasonably apparent to the contractor prior to proposal submission. The ship check deadline was extended through January 15, 2021 (USS MUSTIN/USS SAN DIEGO). The contractor is encouraged to perform its due diligence in submitting its proposal. | ||||
| 10 | SAN DIEGO | RFP | Section C | Section C - Descriptions and Specifications |
CLAUSES INCORPORATED BY FULL TEXT
C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within 30 days of discovery:
(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,
(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.
(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and Above Work and it provides the process for adjudication.
(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.
(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.
• Contractor has submitted pre-proposal inquiries (PPIs) which have identified disparities in the Specification package and has received subsequent revisions to the specifications through Errata(s) 8. Although the deadline to submit PPIs has passed, the contractor continues to identify anomalies within the specifications and submit PPIs for correction.
Bidder's Question:
Are there any other known errors or omissions to the contract package that the Customer is aware of, as there are no others reasonably apparent to us? Pursuant to C-217-H005, 'Growth and New Work' the contractor is under an obligation to address any errors or omissions reasonably apparent to the contractor prior to proposal submission. The ship check deadline was extended through January 15, 2021 (USS MUSTIN/USS SAN DIEGO). The contractor is encouraged to perform its due diligence in submitting its proposal.
image1.jpeg image2.png